HomeMy WebLinkAbout_2025-04-25-04.25.2025 Enclave L24-Plan Review Responses_v1 (1)
3590 Broad Street, Suite 130 San Luis Obispo, CA 93401 vellumdesignbuild.com P / 805.784.0487 F / 805.784.0488
community | innovation | value | integrity
Page 1 of 5
s:\sales\client_folders\construction\enclave at righetti ranch\lot 24\design documents enclave lot 24\permits - applications\construction - building\sub2\00 enclave l24 - plan
review responses\04.xx.2025 enclave l24-plan review responses.docx
vellum
DESIGN BUILD
residential ● commercial
DATE: April 25, 2025
PERMIT CORRECTION RESPONSES
PERMIT NUMBER: BLDG-0438-2025
PARCEL NUMBER: 004-719-024
PROJECT ADDRESS: ENLCAVE LOT 24 - 1424 HANSEN LANE, SAN LUIS OBISPO, CA 93401
REVIEW ITEM STATUS REVIEWER
Addressing v.1 Ready for Action Vanessa Nichols Ph: 8057817588
General – Addressing email: vnichols@slocity.org
REVIEW ITEM STATUS REVIEWER
Building v.1 Needs Resubmit Vanessa Nichols Ph: 8057817588
BUILDING DEPARTMENT email: vnichols@slocity.org
Comments: #1 Please note the water meter as "New" in Water Key Note #2, Sheet C4.0.
RESPONSE: See WALSH’s Civil works responses.
Comments: #2 Final fees pending response to comments and other department reviews.
RESPONSE: Noted.
REVIEW ITEM STATUS REVIEWER
Planning v.1 Read for Action Walter Oetzell Ph: (805) 781-7593
General Planning email: woetzell@slocity.org
REVIEW ITEM STATUS REVIEWER
Private Sewer Lateral v.1 Not Required
Private Sewer Lateral Inspection requirements (per Muni Code section 13.08.395)
REVIEW ITEM STATUS REVIEWER
Public Works Permit Review v.1 Needs Resubmit Melissa Savage Ph: 8057817206
General – Public Works email: msavage@slocity.org
Comments: 1) On the coversheet, please reference the City permit/application numbers associated with
this project for reference:
ARCH-0457-2024 Architectural Review – Lots 23, 24 & 34 Enclave at Righetti single family dwellings
FMAP-1955-2018 Tract 3063 Phase 3 - On-Site & Improvement Plans & revisions
RESPONSE: Amended. See T1.1, under Permit History.
Comments: 2) Verify that the following Public Works Notes are included (or revised) on the cover sheet of
the building plans:
a. All work located within the public right-of-way or within the jurisdiction of the Utilities and Public
Works Departments shall comply with the most current edition of the Engineering Standards and
Standard Specifications dated August 2020.
RESPONSE: Amended. See T1.1, under Public Works Notes, updated version to “August 2020”.
community | innovation | value | integrity
Page 2 of 5
s:\sales\client_folders\construction\enclave at righetti ranch\lot 24\design documents enclave lot 24\permits - applications\construction - building\sub2\00 enclave l24 - plan
review responses\04.xx.2025 enclave l24-plan review responses.docx
vellum
DESIGN BUILD
residential ● commercial
b. Contact the Public Works inspection hotline at 781-7554 with at least a 48-hour notice prior to
starting work in the right-of-way and for any required encroachment permit inspection or final
inspection.
RESPONSE: See T1.1 sheet, under Public Works Notes, item #B. No amendment to be made.
c. The public improvements shall be substantially complete to the satisfaction of the Public Works
Director prior to final inspection approvals and/or occupancy of any building.
RESPONSE: See T1.1 sheet, under Public Works Notes, item #D. No amendment to be made.
d. Any existing survey monuments shall be protected in place or shall be tied out by a licensed land
surveyor prior to disturbance and then replaced prior to occupancy in accordance with Section
8771 of the California Business and Professions Code.
RESPONSE: Amended. See T1.1 sheet, under Public Works Notes, item #L.
Comments: 3) Provide a Water Pollution Control Plan (WPCP) in the format provided by the Building
Division for minor projects less than 1 acre. Contact the Building Division at (805) 781-7180 for questions on
any additional plan requirements and for a copy of the form. Otherwise, the form
may be found at http://www.slocity.org/home/showdocument?id=7147
RESPONSE: See WALSH’s Civil works responses.
Comments: 4) Provide bearings and distances for all property lines in accordance with the Tract 3063
Phase 3 map.
RESPONSE: For Arch, no amendment to be made. See WALSH’s Civil works responses.
Comments: 5) Please refer to the Tract 3063 Phase 3 Improvement Plans. Tract plans indicate wrought iron
boundary fencing and interior privacy fencing are to be installed by homebuilder. Clarify locations and
types of fencing in this plan set. Clarify and coordinate locations and types of fencing on the Grading
and Arch plans. Verify which fence details are used where.
RESPONSE: Amended. See A1.0, under Site Plan Keynotes, items #22-25. See WALSH’s Civil works responses.
Comments: 6) Show pad elevations on the grading plan for lot 24 per tract 3063 Phase 3 Improvement
Plans.
RESPONSE: See WALSH’s Civil works responses.
Comments: 7) Show and label all existing easements on plans. Include the private sewer easement on
the northeastern corner of the property per Tract Map No. 3063 Phase 3. Show proposed building outside
of all easements.
RESPONSE: Annotated. See A1.0, under Site Plan Keynotes, items #34. This is a new community
development per Tract Map #3063 Phase 3. See WALSH’s Civil works responses.
Comments: 8) Show on plans the existing stormwater and sanitary sewer mains and laterals serving lots 24
and 22 per 3063 Phase 3 Improvement Plans. Include invert elevations.
RESPONSE: For Arch, no amendment to be made. See WALSH’s Civil works responses.
Comments: 9) If existing utilities are proposed to be moved, show on plans as proposed utility locations
and clarify who is proposing to move or relocate the existing utilities. Provide invert elevations, and
horizontal and vertical controls for proposed utilities.
RESPONSE: See WALSH’s Civil works responses.
community | innovation | value | integrity
Page 3 of 5
s:\sales\client_folders\construction\enclave at righetti ranch\lot 24\design documents enclave lot 24\permits - applications\construction - building\sub2\00 enclave l24 - plan
review responses\04.xx.2025 enclave l24-plan review responses.docx
vellum
DESIGN BUILD
residential ● commercial
Comments: 10) Plans show a proposed retaining wall within the private storm drain and sewer easement
at the northeast corner of the property. Revise the retaining wall to be outside of the easement or provide
details showing how existing utilities will remain accessible to the neighboring property (lot 22).
RESPONSE: See WALSH’s Civil works responses.
Comments: 11) Plans show a proposed retaining wall within the 14’ public utility and public pedestrian
access easement on the southwestern edge of the property. Show the retaining wall outside of the
easement.
RESPONSE: Amended. See A1.0 – Site Plan. Garden wall removed. See WALSH’s Civil works responses.
Comments: 12) Verify that the retaining wall footing/heel (and/or the 12” wide gravel drains) based on
detail 2/C6.0 does not cross over the property line on the easterly side of the property. Show the dimension
of the wall to the property line.
RESPONSE: See WALSH’s Civil works / FTF’s Structural calculations responses.
Comments: 13) Show and label new ADA compliant driveway approach. See city standard #2116 for
reference.
RESPONSE: Not required as per email confirmation from msavage@slocity.org last Friday, April 4, 2025 @
3:45PM.
Comments: 14) Per stormwater control plan for the tract, roof drains are to be disconnected and drain in
a non-erosive manner to vegetated areas. Revise compliance strategy if roof drains are to be hard tied
into storm drains as proposed in detail 7 on sheet C6.0 and note 4 on sheet C4.0. Complete and submit
the PCR checklist available at the following link: http://www.slocity.org/home/showdocument?id=5190
RESPONSE: See WALSH’s Civil works responses.
Comments: 15) Provide a Stormwater Compliance/Special Inspection Block on the title sheet that
identifies Performance Requirement (PR) and Stormwater Control Measures (SCMs) used for compliance
consistent with plans. Fill in the blanks with the measure used for compliance such as, disconnecting roof
drains, etc. For PR1 projects use the following block. Insert on the title Sheet T1.1: (Also verify method of
compliance agrees with submitted SWCP which states compliance via “directing roof run off to
vegetated areas.”)
STORMWATER COMPLIANCE SUMMARY:
The Project is subject to the following Performance Requirements (PR) of Regional Water Quality Control
Board Resolution R3-2013-0032 “Post Construction Stormwater Management Requirements for
Development Projects in the Central Coast Region”: ☒ PR 1 Site Design/Runoff Reduction through use of (fill in the blank). Sheet ______
Stormwater Control Plan by__________________ dated___________________
City Field Verification. Prior to final acceptance, contact the City for field verification of installed Structural
Control Measures (SCMs) and/or other required elements as proposed in the project Stormwater Control
Plan.
RESPONSE: See T1.1, under STORMWATER COMPLIANCE SUMMARY. Detached supporting documents
submitted, see Doc_Enclave Lot 24_SWCP from Walsh Engineering.
Comments: 16) Add note to plans: Stormwater and drainage system certification is required from the
engineer of record prior to final inspection approvals. The engineer shall certify that the drainage and
stormwater system components have been inspected and are in general conformance with the
drainage report, system design, and the approved plans, including all final elevations, component sizing,
level spreaders, drainage piping, inlets, weir elevations, and orifices.
RESPONSE: Added. See T1.1, under SPECIAL REPORTS, FORMS, PERMITS AND CERTIFICATIONS. See also,
WALSH’s Civil works responses.
community | innovation | value | integrity
Page 4 of 5
s:\sales\client_folders\construction\enclave at righetti ranch\lot 24\design documents enclave lot 24\permits - applications\construction - building\sub2\00 enclave l24 - plan
review responses\04.xx.2025 enclave l24-plan review responses.docx
vellum
DESIGN BUILD
residential ● commercial
Comments: 17) A CAL-OSHA permit is required for excavations or trenching greater than 5 feet in depth.
A copy of the annual, provisional, or temporary permit shall be provided to the Building Division prior to
building, utility, and/or grading permit issuance if applicable. CA Health and Safety Code Section 17922.5
RESPONSE: ADDED. See T1.1, under SPECIAL INSPECTION, REPORTS, PERMITS AND REQUIREMENTS.
Comments: 18) Show the location of the existing street trees on the site plan for reference. Include the
tree diameter, species, and show the tree canopy to scale for reference. Clarify whether the proposed
construction, construction staging, scaffolding, etc. will require safety pruning of the existing tree. Note on
the plans to contact the City Arborist at 781-7578 to review and approve any required or proposed
pruning of street trees.
RESPONSE: See L1.0, indicates the shaded area and street trees are by tract developer per tract map,
shown for reference only. Not in scope and no amendments to be made.
Comments: 19) Tree protection measures for existing street trees shall be implemented to the satisfaction
of the City Arborist. The City Arborist shall review and approve the proposed tree protection measures to
be incorporated into the building plans. Contact the City Arborist at (805) 781-7578 to schedule a site visit.
Tentative plans shall be provided to the arborist for review either prior to or at the time of the field
investigation.
RESPONSE: See L1.0, indicates the shaded area and street trees are by tract developer per tract map,
shown for reference only. Not in scope and no amendments to be made.
Comments: 20) Please revise vicinity map on sheet T1.1 to better reflect project location.
RESPONSE: Amended. See T1.1. Vicinity Map.
Comments: 21) Revise sheets C3.0 and C4.0 to show proposed walkway to not overlapping with existing
sidewalk.
RESPONSE: See WALSH’s Civil works responses.
Comments: 22) Show and label existing sidewalk underdrains.
RESPONSE: See WALSH’s Civil works responses.
Comments: 23) Provide reference(s) in place of “by others” (typical). See sheet C4.0 sanitary sewer
keynote 4, sheet C5.0 redline, and sheet C6.0 detail 2 for examples.
RESPONSE: See WALSH’s Civil works / FTF’s Structural calculations responses.
Comments: 24) Show existing utility locations and elevations on sheet RW1.0. Include sanitary sewer and
storm drain mains and laterals, if applicable.
RESPONSE: See WALSH’s Civil works responses.
Comments: 25) Show backflow preventer location on plans. Provide reference to standard 6550 on sheet
L3.0.
RESPONSE: Amended. See Sheet L2.0 IRRIGATION KEYNOTES & IRRIGATION SYMBOL LEGEND.
Comments: 26) Show distance from footing to property line on detail 16, sheet S-400.
RESPONSE: See FTF’s Structural calculations response.
community | innovation | value | integrity
Page 5 of 5
s:\sales\client_folders\construction\enclave at righetti ranch\lot 24\design documents enclave lot 24\permits - applications\construction - building\sub2\00 enclave l24 - plan
review responses\04.xx.2025 enclave l24-plan review responses.docx
vellum
DESIGN BUILD
residential ● commercial
REVIEW ITEM STATUS REVIEWER
Recylcing v.1 Needs Resubmit Rachelle Paris
General - Recycling email: rparis@slocity.org
Comments: Please submit your project's Recycle Plan online at
https://forms.slocity.org/Forms/recyclingplan
RESPONSE: Submitted.
REVIEW ITEM STATUS REVIEWER
Site Grading / PW v.1 Needs Resubmit Melissa Savage
General – Site Grading/PW email: msavage@slocity.org
Comments: See Public Works Permit Review comments.
RESPONSE: See WALSH’s Civil works responses.
REVIEW ITEM STATUS REVIEWER
Stormwater (Engineering-CDD) v.1 Needs Resubmit Melissa Savage
General – Stormwater/PW email: msavage@slocity.org
Comments: See Public Works Permit Review comments.
RESPONSE: See WALSH’s Civil works responses.
REVIEW ITEM STATUS REVIEWER
Utilities (Consultant) v.1 Not Required Geraldine Seng
email: gseng@slocity.org
REVIEW ITEM STATUS REVIEWER
Wastewater Offset v.1 Not Required Geraldine Seng
Wastewater Offset email: gseng@slocity.org
REVIEW ITEM STATUS REVIEWER
Water (Building) v.1 Needs Resubmit Vanessa Nichols Ph: 8057817588
General - Water email: vnichols@slocity.org
RESPONSE: As per email conversation dated Friday, April 4, 2025 @ 11:07AM – “No Action Required”
Vellum Inc.
Paul J. Abbott
President
April 25, 2025