SUBJECT: California Conservation Corps
CAO RECOMMENDATION:
By motion,
1) Direct staff to use California Conservation Corps (CCC) labor
for 11 City projects with a total estimated value of $112, 100
(an estimated $45,700 would go to the CCC for labor)
2) Authorize the Mayor to send a letter of commitment to the CCC
pledging use of CCC labor on the it designated projects
DISCUSSION:
Background.. The California Conservation Corps (CCC) is facing a
50 percent reduction in its budget, a cut which threatens to close
the local CCC Center which serves the Central Coast. (See Exhibit
1, California Conservation Corps 50 Percent Budget Reduction. )
Since its inception in 1976, the CCC has established a tremendous
record of community and environmental service. Perhaps more
important, this program has provided training, education, social
graces and confidence to young people. In turn, it has developed
productive, hardworking individuals who may not have had an
opportunity for advancement in society except through their
experiences in the CCC.
A -local task force, led by County Supervisor Ruth Brackett, has
been established to gather support for the CCC. On June 26, 1992,
Assemblywoman Andrea Seastrand convened a meeting of representa-
tives from all Central Coast cities, the County, the State, the SLO
Land Conservancy, the Private Industry Council, PG&E, Unocal,
Southern California Gas Company, ECOSLO, Cal Poly State University
and Cuesta College. These representatives formed a local task
force, with County Supervisor Ruth Brackett presiding, to gather
support for the CCC.
At this meeting, CCC Director Dick Bernheimer explained the CCC's
plight and described what the CCC would need to survive and keep
the CCC Center at Camp San Luis open. (See Exhibit 2, Bernheimer
Speech. ) Keeping the CCC Center at Camp San Luis open with a
minimal force will require firm commitments for a total of $550. 000
from various local public agencies and private companies. Such a
commitment would pay for a basic CCC contingent of three working
crews with supervisors, one cook, one secretary, and one manager.
Over the last 16 years, the City has used CCC services extensively.
The attached matrix describes the work completed from 1981 through
0-a-�
���n�►�►►i�iilllll�p ���lll city of san tins oBispo
Nii% COUNCIL AGENDA REPORT
California Conservation Corps
Page 2
1991. (See Exhibit 3, Matrix of Public Conservation Work. )
CCC officials estimate for every $1. 00 paid to the CCC $1.73 of
value is returned to the community.
Proposed City Commitment. Staff has assembled the following list
of it City projects which would be appropriate for the CCC.
Typical procedure calls for the City to furnish materials and pay
the CCC for its labor only.
LABOR MAT'L TOTAL
PROJECT COST COST COST
Parking Lot Landscaping $ 11000 41000 51000
M. Plaza W'way Brick Replacement (*) 81000 21000 10, 000
Rec Center Landscaping 31000 12, 000 15, 000
Tree Replacement (Parks) 21000 51000 71000
Tree Replacement (Streets) 51000 15, 000 20,000
Sinsheimer Concession Stand Renovation 61000 2, 000 8,000
Mission Plaza Fixtures Repainting (*) 21000 1,000 3 , 000
Meadow Park Bldg Exterior Restaining 31000 400 3 ,400
Restroom Partition Replacement 41000 4, 000 81000
Pool Bathhouse Exterior Repainting 1,700 1, 000 21700
S. Rosa Med. Island Landscaping (*) 10. 000 20. 000 30. 000
TOTALS $45,700 $66,400 $112, 100
(Projects marked with an asterisk (*) are new projects or projects
where financing has lapsed) .
The next meeting of the task force is scheduled for July 31st, when
agencies will review the total commitments to the CCC. (See
Exhibit 4, letter from Assemblywoman Seastrand) . The commitments
must be made by August 1, 1992. Therefore, Council action on July
21 is essential. A formal letter of commitment to be executed by
the Mayor is provided as Exhibit 5.
FISCAL IMPACT:
All projects not marked with an asterisk are fully budgeted through
operating budget appropriations or capital improvement plan
designations. Money for the Mission Plaza projects would come from
the CIP allocation for Mission Plaza Improvements (200,000
available) . Money for the Santa Rosa Street Median Island
Landscaping would come from the CIP allocation for the Corporation
Yard Landscaping ($30, 000) , which is on hold pending completion of
the master plan for that area.
ii�tl���►►►�►IIIIII�I�° ��B�N city 0� SmI Luis ogispo
UNGS COUNCIL AGENDA REPORT
California Conservation Corps
Page 3
Attacbments:
Exhibit 1 - CCC 50 Percent Budget Reduction
Exhibit 2 - Bernheimer Speech
Exhibit 3 - Matrix of Public Service Conservation Work
Exhibit 4 - Seastrand Letter
Exhibit 5 - Mayor's Letter
I
c8�
EXHIBIT 1 California Conservation Cc 3 MYkX
EXHIBITrI
50 Percent Budget Reduction
Overview.
The latest figures from the Department of Finance estimate a $4 billion or more
shortfall; the official 'May revise' projection is expected within a few weeks. .The state
budget crisis is very real, and from all indications, worsening.
The Resources Agency's share of the shortfall, at thi§ time, comes to $76 million. The
state's top priorities are health and safety and the Governor's prevention initiatives.
Each Cabinet Secretary must find the required savings from departments, boards, and
commissions within their own agencies.
The CCC has been asked to reduce its General Fund expenditures by 50 percent,
resulting in a $16 million cut for the 1992-93 fiscal year. In order to realize savings
beginning this July, we will begin the implementation of this.cut immediately.
CCC cuts in Governor's budget $ 3.4 million
50% reduction of $32 million General Fund
appropriation $16. million
Loss of reimbursement $$$ (less crews) 2. million
General Fund Reduction, Lost Reimb. _ $18. million $18. million
i
. Total reduction $21.4 million .
Center Closures & Headquarters Cuts
To meet this level of reduction, the CCC's only alternative was to cut centers and
satellites and reduce headquarters. This means staff and corpsmember positions will
be lost To achieve this level of reduction, we had only difficult choices to make, as
each of the centers can make a strong case for remaining open. The major criteria
considered were geographic coverage of the state, ability to generate reimbursement
dollars, maintaining our commitments to special funding, and maintaining a presence
in resource-rich areas.
Overall, we must close the following.seven centers, and the training Academy, to
achieve.a budget reduction of this magnitude.
* Bay Area
* Camanllo
* Central Coast
* Delta
' Inland Empire
* Mendocino
* Sisklyou
C-8�
Satellites
We will be eliminating 11 satellite crews and closing most satellites of the closed
centers. Fourteen satellites will remain, including most in the major metropolitan
areas. The Leggett and Hayfork satellites will be the only residential satellites in
operation.
The net corpsmember satellite population reduction is 109. The corpsmember
population at the remaining satellites will be 267 (excluding the Salmon Restoration
ProjecVs,46 corpsmembers).
Bea quarters Impar
Headquarters would take a total reduction of$705,102. This brings the total of
headquarters reductions to 16 positions.
Reduction in Cornsmember Strength
With the seven center closures, our total budgeted corpsrrember strength, including
local corps, will drop from 1746 to 1090, a loss of 656 corpsmembers. The proportion
of residential corpsmembers would increase. Of the 1090 corpsmembers, the CCC .
would be authorized 1035 and 55 would be allocated to the local corps.
j The impact on the local corps programs will be a drop from funding 76 to 55
corpsmembers, a loss of 21 corpsmembers.
What's Ahead
The Governor and the Legislature will have the ultimate say as to the CCC's final
budget. However, we must begin implementing these cuts now, to even come close
to meeting the projected full-year savings. 'If not, the shortfall will grow worse.
We want the CCC to survive as a program and a department dedicated to young
people and the environment. The next few months may be the toughest in the CCUs
history — let us work together to implement this plan, and hope that as the economy
improves, the Corps will once again be able to grow. ,
i
s _
California '
I .
- Conservation
Ste: � '
Dal Nona : . Corps
JT
Centers
Humboldt
r•
a..w Placer =RPA l=tx►v d t J\
MendocinoTahoe-Sierra
t M.. .
` ..�. m
Delta
Say AreaAkw
,-Ar0
Oti WYiO
1d0
Santa Clara x
w to .
w
Sequoia
%a Lee oso tw .
r `
Central Coast ''•'•'••�
ACBdertly La&a.
5
Camarillo' ...e,
Pomona
; ::.. Inland Empire
I .; San Diego
I
�,QW�.C�7,AW,G C2�ev'•S ,
Califo*ia Conservation. corps
Central Coast Service District May 21 , 1992
CCC Agrees to:
* Pay all Worker's Compensation Costs
* Cover all administrative overhead
1 Provide radio communication with base station
* Provide vehicle transportation
* Provide all hand tools
* Provide chainsaws/fuel
I
* Provide safety gear
EXHIBIT 2 �EXBI$IT_A2
.,UL- .2-92 THU 3 :4S :C HOS EXECUTIVE P. 02
ti
THANK YOU ASSEMBLYWOMAN SEASTRAND;
AND - THANK YOU LADIES AND GENTLEMEN FOR .
COMING HERE TODAY TO EXPRESS YOUR
CONCERN FOR THE FUTURE OF THE CCC AND TO
SHARE YOUR IDEAS FOR MAINTAINING A
CONTINUING PRESENCE FOR THE CCC IN THE
SAN LUIS AREA,
I DO NOT WANT TO DWELL TOO LONG ON HOW
AND WHY WE GOT TO THIS SORRY SITUATION
BECAUSE I AM SURE YOU ARE ALL TOO AWARE
OF THE STATES BUDGET CRISIS, DUE TO THE
$10 MILLION +OR- REVENUE GAP THE STATE
GENERAL FUND AGENCIES WILL SUSTAIN AN
ESTIMATED ACROSS THE BOARD CUT OF 15 TO 20
%. UNFORTUNATELY, CUTS ARE NOT TRULY
ACROSS THE BOARD, THEY ARE ONLY AVERAGE
CUTS WITH SOME DEPARTMENTS RECEIVING
HIGHER AND SOME LOWER CUTS THAN THE
AVERAGE. IN THE CASE OF THE CCC, WE HAVE
THE MISFORTUNE, IN TERMS OF THE BUDGET, OF
BEING IN THE RESOURCES AGENCY ALONG WITH
THE CALIFORNIA DEPARTMENT OF FORESTRY,
CDF HAS 65% OF THE ENTIRE GENERAL FUND
BUDGET FOR ALL DEPARTMENTS IN THE
RESOURCES AGENCY. BECAUSE REDUCTIONS IN
THE CDF BUDGET DIRECTLY RELATE TO FIRE
FIGHTING CAPACITY AND PUBLIC HEALTH AND
SAFETY DEEP CUTS IN THAT BUDGET TRANSLATE
C-8 8
-JUL-- 2-92 THU 3 :49 C HQs EXECUTIVE 1 P. 03
INTO CLOSING FIRE CENTERS AND AIR TANKER
BASES. IT IS A VERY TOUGH PRACTICAL AND
POLITICAL DECISION TO KEEP A CCC CENTER
AND CLOSE A FIRE CENTER, IF YOU GUESS
WRONG AND CLOSE THE WRONG FIRE CENTER I
DON'T HAVE TO TELL YOU THE CONSEQUENCES.
THE RESULT OF THIS CATCH 22 IS THAT CDF WILL
TAKE A LESSER CUT, AND, a THE REMAINING
DEPARTMENTS IN THE AGENCY WILL TAKE A
GREATER CUT. THE CUT FOR THE CCC HAS BEEN
SET AT 50% BELOW THE AMOUNT IN THE
GOVERNORS BUDGET PRESENTED IN JANUARY,
WHICH WAS ALREADY 6 To 7% BELOW THE
CURRENT YEAR BUDGET,
AS YOU MAY NOT KNOW HOWEVER, STATE
PROGRAMS CANNOT BE CUT INSTANTLY. THE
LAWS AND RULES GOVERNING SENIORITY AND
LAYOFF ARE CUMBERSOME AND TIME
CONSUMING. FOUR TO EIGHT MONTH IS TO BE
EXPECTED. THEREFORE IF CUTS CAN NOT BE
PUT INTO EFFECT AT THE START OF THE FISCAL
YEAR TO GENERATE A FULL 12 MONTH SAVING,
EVER INCREASING LEVEL OF CUTS MUST BE
MADE TO COVER THE PERIOD OF DELAY,
WHILE THE BUDGET IS NOT YET FINAL, THE
AGENCY AND THE CCC, BASED ON THE
ANTICIPATED LEVEL OF CUTS, HAVE . INITIATED
THE DOWNSIZING PROCESS AS EARLY AS
a '
. JUL_ 2-92 THU 3 :511 :C HQs EXECUTIVE P. 04
POSSIBLE TO ACHIEVE AS NEARLY AS POSSIBLE
THE FULL 12 MONTHS SAVING FOR THE ACTIONS
TAKEN, EVEN WITH THE HEAD START WE HAVE
TAKEN, MOST OF OUR PERSONNEL REDUCTIONS
WILL NET ONLY 10 TO 10 & 1/2 MONTHS SAVINGS.
WE ARE FACED WITH AN OVER ALL EUDGET
REDUCTION OF APPROXIMATELY $20 MILLION
FROM A CURRENT BUDGET OF APPROXIMATELY
$52 MILLION.
TO ACCOMPLISH THIS WE HAVE MADE CUTS IN
ALL AREAS OF THE CCC INCLUDING A 15 to 18%
REDUCTION IN HEADQUARTERS STAFFING,
REDUCTIONS IN FIELD MANAGEMENT POSITIONS,
REDUCTIONS IN CORPSMEM.BER BENEFITS,
CLOSURE OF 7 BASE CENTERS AND THE.
TRAINING ACADEMY AND THE REDUCTION OF OUR
CORPSMEMBER POPULATION FROM 1746 TO 1090.
IN ALL HONESTY, SELECTING A CENTER TO
CLOSE IN NOT A CLEAR CUT CHOICE AS IT ONCE
WAS. WHEN FACED WITH LESSER CUTS IN THE
PAST WE HAVE ADOPTED CRITERIA FOR CENTER
CLOSURE WHICH, WHEN .APPLIED YIELDED A
CLEAR CHOICE. BUT NOW THAT THESE WEAK
CENTERS HAVE BEEN CLOSED NEARLY ALL THE
REMAINING CENTERS ARE. MORE NEARLY EQUAL
AND HAVE STRENGTHS TO OFFSET THE
WEAKNESS, OUR CHOICES WERE BASED MORE
ON THE PAST RECORD OF REVENUE GENERATION
C-8-10
JUL— 2-92 THU 3 :51 r^C Hos EXECUTIVE 1 F P. 05
AND ON GEOGRAPHIC COVERAGE OF THE STATE,
THE CHOICES ARE NOT EASY ONES.
HAVING SAID ALL THAT WHICH IS PURE AND
UNADULTERATED GLOOM, I WOULD LIKE TO END
ON A MORE POSITIVE AND OPTIMISTIC NOTE,
IMMEDIATELY AFTER ANNOUNCING THE CENTERS
FOR CLOSURE, LOCAL SUPPORT BEGAN TO FORM
IN ALMOST ALL AREAS. I BEGAN TO GET
INQUIRIES AS TO "WHAT WOULD IT TAKE IN THE
WAY OF LOCAL FINANCIAL COMMITMENTS TO
. KEEP SOME LEVEL OF CCC OPERATION HERE
UNTIL THINGS GET BETTER?". IN RESPONSE, I
PREPARED A CONCEPT PAPER THAT PROPOSED A
STRUCTURE AND BUDGET WHICH, IF WORK
CONTRACTS COULD BE COMMITTED, WE WOULD
AUGMENT IN ORDER TO SAVE THE FACILITY AND
MAINTAIN A PRESENCE IN A GIVEN AREA,
SEVERAL COMMUNITIES ARE ACTIVELY PURSUING
THIS STRATEGY. OF EVEN GREATER
SIGNIFICANCE, IF YOU ARE WILLING TO BE
OPTIMISTIC IN THIS OTHERWISE GLOOMY BUDGET
SCENARIO, IS SOMETHING THAT OCCURRED IN
THE LAST FEW DAYS. THE CCC WAS REQUESTED
A FEW DAYS AGO TO PREPARE AN ALTERNATIVE
BUDGET WITH A 40% RATHER THAN A 50%
REDUCTION WHICH, I SPECULATE WITH SOME
CONFIDENCE, MAY BE- INCORPORATED INTO THE
GOVERNORS REVISED STATE BUDGET HE IS
SUBMITTING TO THE LEGISLATIVE LEADERSHIP.
C�'lI
JUL-_ 2-92 THU 3 :51 C HQs EXECUTIVE P. 96
IF IN FACT OUR CUT IS REDUCED TO THIS LEVEL
WE WILL SERIOUSLY CONSIDER PROVIDING A
GREATER SUBSIDY TO EACH OF THE CENTERS
PROPOSED FOR CLOSURE WHERE A HIGH LEVEL
OF COMMUNITY SUPPORT IS EVIDENT. THIS
WOULD BE IN LIEU OF REOPENING ONE CENTER,
IF IN FACT, THIS LESSER CUT IS ADOPTED WE
CERTAINLY WOULD BE IN A POSITION TO WORK
WITH YOU TO SAVE JOBS FOR YOUTH, SAVE THE
FACILITIES FOR FUTURE REESTABLISHMENT OF A
BASE CENTER, SAVE SOME OF THE JOBS FOR
STAFF THAT WOULD OTHERWISE BE DISPLACED
AND CONTRIBUTE WORKERS FOR LOCAL
PROJECTS AND $S TO THE LOCAL ECONOMY,
I AM MOST ANXIOUS TO HERE WHAT YOU HAVE
BEEN DOING LOCALLY AND WHAT YOU HAVE TO
SUGGEST. THANK YOU FOR THIS OPPORTUNITY
TO MEET WITH YOU IN SUPPORT OF THE CCC.
F.BHIBIT 3
E%HIBIT 3-7
California Conservation Corps MATRIX OF PUBLIC SERVICE CONSERVATION IARC
San Luis Obispo Center
P.O. Box 1380
San Luis Obispo, California 93406 York Sponsor_ City of San Luis Obispo
(805) 549-3561
Tear Project Project Date
Number Title York Completed I Cowl. JBaursJ Value
YEAR OF 19881
1981 81-1199 Whale Rork Reservoir Cleared out logs, brush, and other debris from 2-15-82 994 10,784.90
Flood Control, around reservoir banks.
Cayucos
1981 81-613 Great California Re- Worked at recycling yard and cleaned up litter. 4-15-82 72 782.20
source Rally
TEAR OF 1982
1982 82-1150 Fire Station 04 Put in low maintenance vegetation; installed irrigation 1 9-29-821 479 1 5,197.15
Landscaping, Los Osos system.
Valley 8 Madonna
Roads
TEAR OF 1983
1983 83-413 San Luis Creek Storm Placed ten (10) gabions (wire cages filled with rocks) 2-16-83 152 1,649.20
Damage Erosion Con- along eroded creek bank containing outfall line. 3-4-83
trot - Sewer Farm
(Emergency Project)
1983 83-526 San Luis Creek Placed thirty (30) more gabions along right creek bank 3-4-83 S10 5,533.50
Erosion Control-- (25' x 10' high area) to prevent further erosion and to
Phase I further protect outfaLL line; built 56 gabions for
stockpiling.
1983 83-640 Madonna Road Land- Trimmed two (2) 1800' hedges used as a meridian barrier; 4-22-83 236 2,560.60
scaping trimmed and replanted iceplant areas; Loaded clippings
and debris into trucks for hauling.
1983 83-638 Whale Rock Debris Clear shorelines from Cottontail and Old Creek to fish 4-29-83 936 10,155.60
Clearance--Cayucoa traps of logs, brush, and debris; burn same.
1983 83-1427 Model Fire Protection Cut approximately one (1) acre of fire breaks at three 7-27-83 104 677.04
Program locations.
1983 83-779 Sinsheimer Park Acid wash, patch holes, and seal coat six (6) tennis 7-29-83 466 3,033.66
Tennis Court Refurb. courts.
C-8-!3
Forma Conservation Corps MATRIX OF PUBLIC SERVICE CO11SERVATION WORK
Luis Obispo Center
P.O. Box 1380
San Luis Obispo, California 93406 York Sponsor: City of San Luis Obispo
(805) 549-3561
Year Project Project Date
Number Title York Coupleted Cowl. Hours value
1983 83-1428 City of SLO Creek Cleaned out all creeks within city limits of San Luis 9-8-83 2,614 17,017.14
Clearance Obispo.
1983 83-639 City of SLO Tree Planted trees in tree wells along several downtown 8-26-83 1,143 7,440.93
Planting streets.
1983 83-1589 San Luis Creek Soil Constructed and installed gabions along banks of San Thru 12- 1,950 12,694.50
Erosion Control-- Luis Obispo Creek at Sewer Fars to prevent erosion of 83 and
Phase II outfall line. continuing.
1983 83-1590 Jack House Well Demolished damaged walls and readied for replastering 9-16-83 104 677.04
Demolition and restoration.
1983 83-1594 Grand Avenue Removed approximately ten (10) cubic yards of weeds and 9-21-83 103 670.53
Landscaping debris and replanted Grand Avenue meridian strip.
1983 83-1696 Jack House Lard- Weeded and replanted Jack House grounds. 9-23-83 120 781.20
seeping
1983 83-1649 Old Garden Creek Construct and install gabions to prevent erosion. Thru 12- 342 2,226.42
Erosion Control 83 and
continuing.
-i 83-1969 San Luis Obispo Creek Building retaining wall to prevent erosion. Thru 12-I 40 260.40
Nipomo Street Retain- 83 and
ing Wall continuing.
1983 83-1989 Sinsheimer Park Constructing and installing approximately 30 gabions to 12-16-83 448 2,916.48
Gabios prevent further erosion of a creek bank which is one full
side of a bell field.
YEAR OF 1984
1984 83-1990 Mission Plaza Cleared out overgrown shrubs and ground cover. Replanted 1-13-84 343 3,722.00
Landscaping area as necessary.
1984 83-1649 Old Garden Creek Install stacked concrete rip-rap on banks. Planted pine 2-16-64 136 1,476
Erosion Control trees, install gabions.
1984 83-1589 Laguna Lake Eros. CtL Construct gabion retaining wall in park roadside. 3-16-84 1,518 14,821.00
1984 84-3093 Interns -Tree Care and Interns assigned to tree crew. There have been sixteen 6/87 5,824 558,240
presentation. corpsman rs assigned to tree crew during this time.
This project lasted through years 1984-87.
2
Califo rnia Camervation Corps MATRIX OF PUBLIC SERVICE CONSERVATION YORK
Sen Luis Obispo Center
P.O. Boot 1380
San Luis Obispo, California 934% Work Sponsor: City of San Luis Obispo
(805) 549-3561
Year Project Project Date
number Title work Completed CORA. Honors value
1984 83-1589 San Luis Creek Soil Extensive gabion wall to protect and control erosion 3-16-84 1,518 14,821.00
Erosion Construction around sewer outfall line.
1984 83-1647 Brook Street Erosion Install gabion wall and revetment on San Luis Creek at 4-20-84 1,720 20,000.00
Control--Phase I Brook Street.
YEAR OF 1985
1985 84-3088 Erosion Control-- Installation of gabion walls at Perfuno Creek (auto 10-25-85 6,820 70,000.00
Gabios--184 - 185 parkway); San Luis Creek and Santa Rosa Street. Replan-
ted 600 trees and shrubs.
1985 84-3084 Street Tree and Side- Inspection and corrective action regarding sidewalk 04/85 2,714 20,960.00
walk Preservation upheaval from tree roots in downtown San Luis Obispo.
1985 84-3108 Creek 8 Drainage Cleared approximately 700 linear feet of stream in SLO. 9-16-85 152 2,787.68
Cleaning
1985 84-3109 Parks 8 Building Performed a large amount of work in various parks and 5-30-86 7,914 36,000.00
Project 185 buildings throughout the City, Mission Plaza Land-
seeping, Meadow Park, Jack House, Santa Rosa Land-
scaping, and Parking Lot irrigation.
1985 84-3083 SLO City Creek 8 Clean City drainage systems of debris, unwanted vege- 12-13-85 4,859 49,000.00
Drainage Clearance- tation and silting. spray vegetation where warranted.
1984 Flush drain pipes. Zone 9 creeks.
YEAR OF 1986
1986 86-3104 Tree planting, Planted approximately 40 trees throughout the City of 4-8-86 1,389 19,417.00
Downtown SLO S.L.O. Cleaned out tree sidewalk area, pruned approx-
mately 35 trees.
1986 86-3055 Erosion control 8 This project involved the installation of gabions at 11/86 1,575 8,700.00
Creek Maintenance Broad Street and the annual clean-up of brush and litter
of the SLO City creeks.
1
3
J
^-rifornia Conservation Corps MATRIX OF P16LIC SERVICE CONSERVATION YORK
Luis Obispo Center
. Box 1380
San Luis Obispo, California 93406 York Sponsor: City of San Luis Obispo
(805) 549-3561
Year Project Project Date
Number Title York Completed Conpl. Nouns Value
YEAR OF 1987
1987 87-2473 Gabions: Yearly Major gabion construction at two sites: 1/88 8025 580,250.
Creek Cleaning 1) San Luis Creek at Los Osos Valley Rd, overpass.
2) San Luis Creek behind biofiltration plant (by
84 Umber).
Also, yearly clean-up of streets.
1987 87-2471 SLO City Tree Planting Planted 72 trees within the city. 7/87 288 52,880.
YEAR OF 1988
1988 88-1228 Mitchell Park- Removal Removal of a brick wail that was constructed as a
of War Memorial Wall World War II Memorial. The wall was dismantled and 10/88 1800 57,000.
the bricks cleaned to be reused on a new memorial
entry plaza in the same location.
1988 87-2470 SLOCity Tree Intern Original project number for City tree intern positions - 6/88 6122 530,304
Plant and maintain trees; install irrigation, planter and
root containment boxes; operate chipper, chain saw, grinder
and serial lift; traffic control.
4
California Conservation Corps MATRIX OF PLR(LIC SERVICE CONSERVATION WOW
San Luis Obispo Canter
P.O. Boo[ 13'80
San Luis Obispo, California 93106 York Sponsor: City of Sen Luis Obispo
(805) 549-3361
Year Project Project Date
number Title York Completed CampL. Bar Value
YEAR OF 1989
89 89-4633 Laguna Lake Commera-
tive Grove Irrigation. Install approx. 8485 linear feet of underground 6/89 240 $2,400.
PVC irrigation system (Drip) around the
Comierative Tree Grove at Laguna Lake.
YEAR OF 1990
1990 90-3624 Mission Plaza Restor- Restain all rood railings and pedestrian bridge in 7/90 464 4640
ation. mission plaza area.
1990 90-3647 Bill Street Chipping Brush out and chip various debris at the top of Bill Street 11/90 64 640
YEAR OF 1991
1991 91-1729 San Luis Creek Erosion control, reed abatement, rip rap installed, re- 10/91 1133 11330
Restoration etation.
_ 5
C-8-17
EXHIBIT 4
❑ CAPITOL OFFICE COMMITTEES,
STATE CAPITOL
AGRICULTURE
SACRAMENTO,CA 951114 Q» �
EDUCATION
(916(445.7795 9 G
GOVERNMENTAL EFFICIENCY.
• • • CONSUMER PROTECTION AND
�tt�Yrittt � YSX�#urs NEW TECHNOLOGY
HOUSING AND COMMUNITY
DEVELOPMENT
❑ D6iTRICT OFFICE
ANDREA SEASTRAND MEMBER
523 HIGUERA STREET ASSEMBLYWOMAN,TWENTY-NINTH DISTRICT RURAL CAUCUS
SAN LUIS 0&SPO,CA 9341 SELECT COMMITTEE ON
(8051549.3381 MARINE RESOURCES
ON WINE
July 7, 1992 SELECT R OURCESITTEE NA D ECONOMY
SsaTF
Lane Wilson
City of SLO e
25 Prado Road
San Luis Obispo,. CA 93401 0•?`''a~0S
Dear Lane,
As you are aware, state government is facing the biggest fiscal crisis in
recent years with the reality of having to issue I .O.U.s to pay its
bills. The gravity of such a monumental budget crises dictates that cuts
are inevitable in all programs, even successful ones such as the
California Conservation Corps (CCC) . However, realizing the importance
of the CCC and all that it offers the many young men and women who
participate in it, the question remains, what can we do which will be
constructive when these cuts are implemented?
Your attendance at the recent meeting I hosted with CCC Director Dick
Bernheimer indicates that you are committed to efforts which will answer
the above question. As a result, Supervisor Ruth Brackett and I are
inviting you to participate on the task force designed to develop
shared-cost methods of off-setting the proposed cuts. Our next meeting
is scheduled for Friday, July 31 , 1992, at the Embassy Suites .Hotel in
San Luis Obispo. The meeting will be from 12 :00 to 2 : 00 and lunch will
be served. It is hoped that this notice is early enough to give local
organizations and governments the proper time to put together their firm
commitments to utilize the CCC through the coming year. I am sure this
meeting will be productive in providing Mr. Bernheimer with the necessary
local-dollar threshold to prevent our CCC camp from closing altogether.
Please contact Vicki Fisher in Supervisor Ruth Brackett's office at (805)
549-5457 if you are planning on attending this important meeting.
Sincerely,
a*wt"l
ANDREA SEASTRAND
AS :ed
C-B-IV
Orinluii nn Dn.wN�l Dann.
\'L y O� EXHIBIT 5
444 * Cl of sAn tuffs oaspo
f OFFICE OF THE MAYOR •990 PALM STREET
?/ S O Post Office Box 8100• San Luis Obispo,CA 93403-8100 • 805/549.7111
July 22, 1992
Mr. Dick Bernheimer, Director
California Conservation Corps
1530 Capitol Avenue
Sacramento, CA 95814
Dear Mr. Bernheimer:
I am pleased to inform you that on July 21, 1992 the San Luis
Obispo City Council directed City staff to use California Conserva-
tion Corps (CCC) labor for 11 City projects in 1992-93 with a total
estimated value of $112, 100. Of this total, an estimated $45,700
will go to the CCC in support of labor costs. This letter and the
attached list of projects serves as the City's formal commitment
to use CCC services for these projects during 1992-93.
On behalf of the City Council, I would like to thank you for your
efforts to keep the CCC Center at Camp San Luis open and operating.
Over the last 16 years we here in San Luis Obispo have benefitted
greatly from the cost-effective service provided by the CCC.
During that time we have watched with gratification as CCC training
and labor have transformed young men and women into confident,
productive, hardworking adults.
We hope the City's commitment helps the CCC survive, because it is
certainly a .worthy organization that has been of great benefit to
San Luis Obispo over the years.
Sincerely,
RON DUNIN
Mayor
RD:mc
Attachment
C. City Council
Assemblywoman Seastrand
Senator Maddy
Supervisor Ruth Brackett
MEETING '"FNDA
DATE Z-J/44- #
two
BOARD OF SUPERVISORS
COUNTY GOVERNMENT CENTER• SAN LUIS OBISPO, CALIFO NIA 93408 • 805-549-5450
COPMS❑ De n�
d`amCH ° CDDDUL
ACRO a FIN.MX
CHIEF RUTH E. BRACKETT
July 16, 1992 anwORIC u�� DISTRICT FOUR
MCMI.TEAM ❑ REC DIB.
❑ READFILE 13UnLDIR.
John Dunn, City Administrative Officer �T
City of San Luis Obispo
P.O. Box 8100 .•JJ
San Luis Obispo, CA 93403-8100
Dear Mr. Dunn:
Assemblywoman Andrea Seastrand recently sent you a letter with an invitation to attend a
luncheon in support of the California Conservation Corps (CCC) on Friday, July 31, 19920
from 12:00-2:00 p.m., at the Embassy Suites Hotel in San Luis Obispo. The purpose of the
meeting is to enlarge the efforts of a local task force formed to offer immediate and long-term
support for the CCC in our area.
The short-term goal is to obtain signed commitments in the form of contracts, such as the
one agreed to by Cal-Trans for$125,000. Our target is to obtain$500,000 in locally financed
projects by August 31, 1992. Our long-term goals will be discussed further at the upcoming
luncheon.
Assemblywoman Seastrand and I are encouraged by the support and enthusiasm received
so far. In a short period of time, the task force has identified many agencies and projects
that can help us reach our stated target.
We look forward to seeing you at the luncheon,and we appreciate your ongoing commitment
to preserving the California Conservation Corps on the Central Coast. Please R.S.V.P.to my
Field Representative, Vicki Fisher, at 549-5450.
Sincerely,
7 • - ��N s�aealsNlWad
RUTH BRACKETT E C E § V E v'
Supervisor, District Four 2661
JUL 2 0 1992 131n,�'J��
f perr6\tzCfiVW .(1 CITY CLERK
SAN LUIS CBIEPO,CA