HomeMy WebLinkAboutItem 7d - South St and King Ct Crossing Project Modification SPEC No. 2001059 Item 7d
Department: Public Works
Cost Center: 9501
For Agenda of: 6/16/2025
Placement: Business
Estimated Time: 30 Minutes
FROM: Aaron Floyd, Public Works & Utilities Director
Prepared By: Luke Schwartz, Transportation Manager
SUBJECT: SOUTH STREET AND KING COURT CROSSING PROJECT
MODIFICATION, SPECIFICATION NO. 2001059
RECOMMENDATION
1. Approve a modification to the South Street and King Court Crossing Project
(Specification No. 2001059), authorizing installation of a standard traffic signal in lieu
of a pedestrian hybrid beacon; and,
2. Authorize the City Engineer to approve modifications to project plans and
specifications and approve associated construction Contract Change Orders as
needed to facilitate project modifications up to the available project budget and
consistent with California Public Contract Code, including any amendments
authorized by the City Manager.
REPORT-IN-BRIEF
The South Street and King Court Crossing Project is currently in early phases of
construction and includes installation of a new controlled crossing at the intersection of
South Street and King Street/Court. Construction activities are currently on pause
pending PG&E electrical work and delivery of materials. During the original planning and
design process, both a pedestrian hybrid beacon and a full traffic signal were evaluated
for this location. While a fully signalized intersection was identified as the preferred long-
term configuration due to its ability to improve both pedestrian safety and vehicle access,
the project advanced with a pedestrian hybrid beacon due to concerns regarding
emergency response operations along South Street.
To preserve future flexibility, the hybrid beacon project was intentionally designed to
incorporate much of the infrastructure necessary to support a future traffic signal, allowing
for a relatively straightforward conversion should conditions warrant. However, following
recent implementation of upgraded emergency vehicle pre-emption technology and
renewed coordination with City emergency service providers, staff have confirmed that
those emergency response concerns can now be effectively addressed. As construction
is currently paused awaiting utility work and equipment delivery, staff is recommending
modification of the project to install a full traffic signal in lieu of the previously approved
pedestrian hybrid beacon. Because the project was designed with future signalization in
Page 471 of 476
Item 7d
mind, staff anticipates limited schedule impacts and modest additional costs that can be
accommodated within the existing project budget.
The proposed modification does not represent a change in the overall purpose or vision
of the project; rather, it advances a traffic control alternative that was evaluated during
the original design process and intentionally accommodated within the project design.
The purpose of this item is to provide an opportunity for community members to provide
input on this proposed project modification, and for the Council to take formal action to
approve this proposal, if supported.
POLICY CONTEXT
The City’s 2021 Active Transportation Plan (ATP) recommends installation of pedestrian
crossing improvements at the intersection of South Street and King Court as a Tier 1
(highest-priority) project. Installation of this crossing also supports the City’s overarching
Vision Zero objective to improve traffic safety and eliminate traffic fatalities, as well as the
specific recommendation to upgrade and modernize emergency vehicle pre -emption
(EVP) equipment for the San Luis Obispo Fire (SLO Fire) and Police (SLO PD)
Departments, as identified in City’s 2026 Vision Zero Action Plan (See Post-Crash Care
Recommended Action #1).
DISCUSSION
Background
On October 7, 2025, the City Council approved plans and specifications, and authorized
staff to advertise the South Street & King Court Crossing (Project) for construction bids.
On January 13, 2026, the City Council approved award of the construction contract to JJ
Fisher Construction Inc. This action also authorized purchase and installati on of
new/upgraded emergency vehicle preemption equipment for the City Police and Fire
Department vehicles, which has since been completed.
Since January 2026, the construction contract has been awarded and work has begun,
including procurement of traffic signal poles and installation of a new electrical meter box
for the beacon/signal system. The City is currently awaiting installation of electrical
service by PG&E (expected summer 2026), and delivery of traffic signal poles (expected
delivery late August 2026) before commencing with remaining phases of construction in
the fall.
Pedestrian Hybrid Beacon Crossing vs. Full Traffic Signal
As currently approved, the Project includes installation of a new pedestrian hybrid beacon
(PHB) crossing at the intersection of South Street and King Street/Court, with the primary
purpose of improving pedestrian safety on a safe route to school. As discussed in the
October 7, 2025 staff report, a full traffic signal was also explored as a design alternative
earlier in project development, as a signal would improve access and safety for both
pedestrians/cyclists and drivers navigating this intersection. Drivers attempting to make
left turns from King Court onto South Street currently experience lengthy de lays during
Page 472 of 476
Item 7d
peak traffic periods, with the northbound left-turn movement operating at level of service
(LOS) F during the AM commute period.
While the South & King intersection currently meets warrants for both signalization and/or
installation of a pedestrian hybrid beacon per the design guidance in the California
Manual on Uniform Traffic Control Devices (CAMUTCD), a traffic signal was not
recommended when this project was initially designed due to concerns from the City Fire
Department that a full signal may increase delays for emergency response along South
Street, a primary response route near Fire Station #1. Thus, a pedestrian hybrid beacon
was advanced as the preferred near-term solution at that time. However, because a fully
signalized intersection was viewed as a desirable long-term configuration, the project was
intentionally designed to incorporate much of the infrastructure necessary to support
future signalization. Signal foundations, conduit, electrical infrastructure, and other
intersection improvements were designed to accommodate either treatment, allowing the
intersection to be converted to a full traffic signal in the future with minimal redesign,
limited additional construction, and comparatively low cost .
Proposed Project Modifications
Since project approval, the City has received significant correspondence from residents
regarding the proposed pedestrian hybrid beacon, particularly concerning vehicle access
and delays experienced by drivers exiting King Court onto South Stre et. While vehicle
access concerns were considered during the original project development process, the
recent volume of community feedback highlighted the importance of revisiting whether
the original emergency response concerns that drove the project reco mmendation could
now be addressed.
During the original evaluation of alternatives, emergency response considerations were
the primary factor that led staff to recommend a pedestrian hybrid beacon rather than a
fully signalized intersection. Since that time, upgraded emergency vehicle preemption
equipment has been installed for City Fire and Police Department vehicles, providing
enhanced capability for emergency vehicles to communicate with traffic signals and clear
intersections more efficiently during emergency response.
Based on renewed coordination with City emergency service providers, consideration of
the operational benefits provided by the upgraded emergency vehicle preemption
technology, and recognition of the access concerns raised by nearby re sidents,
emergency service representatives have indicated support for installation of a full traffic
signal at this location. Staff is now requesting Council approval to proceed with a
modification to this project to advance construction of a traffic signal in lieu of a pedestrian
hybrid beacon.
Impacts on Project Schedule, Costs, and Gran t Funding
Because the project was intentionally designed to accommodate future signalization and
construction is already underway, this may be an appropriate opportunity to advance the
full traffic signal alternative that was previously evaluated during project development.
The proposed modification would improve pedestrian and bicycle safety, address vehicle
Page 473 of 476
Item 7d
access concerns at the intersection, and can be accomplished with limited additional cost
and minimal impact to the overall project schedule.
The proposed design modifications do not represent a substantial change or expansion
in project scope or type of construction activities. The vast majority of the construction
tasks and equipment (i.e. new signal poles, conduits, electrical wiring, signal cabinet,
lighting, sign and striping work) remain the same with a signal or pedestrian hybrid
beacon. Modifications primarily include minor revisions to signage and striping and minor
adjustments to some signal equipment, such as use of standard signal heads instead of
hybrid beacon indicators.
While construction has already begun, work is currently on pause as the contractor awaits
PG&E scheduling and delivery of traffic signal poles (6-8 month typical lead time between
order and delivery). Therefore, the proposed modification can be accommodated with
relatively minor delays to the overall project schedule. Currently, construction is expected
to resume this fall and a target completion date of late 2026 may still be possible if the
project modification to a full signal is advanced.
The majority of the Project funding ($500,000) is provided via a grant secured by the San
Luis Obispo Council of Governments—these funds must be expended by end of the 2026
to receive full reimbursement. Staff have determined that the proposed modification to
the project may be advanced within this time frame, without risking forfeiture of grant
funding.
Previous Council or Advisory Body Action
On October 7, 2025, the City Council authorized staff to advertise for construction bids
for the South Street and King Court Crossing Project. On January 13, 2026, the City
Council approved award of the Project construction contract.
The City Active Transportation Committee (ATC) has received updates on the Project in
numerous meetings over the past several years. The Project was identified as a high
priority in the ATC’s 2025-27 budget priority recommendations (approved November 21,
2024), and discussed again during the ATC’s September 18, 2025, meeting. The
Committee consistently expressed support for improving safety and accessibility at this
crossing location, and no concerns were raised regarding future signalization of the
intersection.
While there was not an opportunity to schedule a focused agenda item with the ATC
regarding the proposed modification from a hybrid beacon to full traffic signal at the South
& King intersection prior to this City Council meeting without risking fu rther delays (and
grant funding)—during previous staff updates to the ATC during Project planning and
design, there were discussions on potential for a full traffic signal in lieu of a hybrid beacon
and there were no specific concerns or objections raised by the committee on this
alternative. It is staff’s opinion that the modified project—a full traffic signal—provides
equivalent benefit to pedestrian and bicycle crossing access and safety as the pedestrian
hybrid beacon design and may provide superior benefits to overall road user safety and
Page 474 of 476
Item 7d
user understanding/compliance. Members of the ATC have received notification of this
proposed modification. While no concerns have been reported by members following this
notification, they will have the opportunity to comment on this agenda item as individuals.
For a detailed summary on previous City Council and Advisory Body actions related to
the Project, see the October 7, 2025 Council Agenda Report.
Public Engagement
A detailed summary of public outreach and engagement activities conducted to date on
the Project prior to construction advertisement is provided in the October 7, 2025 Council
Agenda Report.
To provide additional notice to community members ahead of this hearing on the
proposed Project modification, staff provided advanced notification to representatives of
the home owners associations for the two residential communities located on King Court
(Parkside and The Villages), direct email notice to residents who recently contacted City
staff and Council expressing concerns for the previous project designs, sent post cards
via mail to all properties within 1,000 feet of the project location, and placed notices on
sandwich boards at the South & King intersection the week prior to this meeting date.
Both this current agenda item and the previous Council Agenda items on the Project
followed all required postings and notifications, and the public has had an opportunity to
comment on this topic at or before these meetings.
CONCURRENCE
The proposed Project modification and staff report have been reviewed and have
concurrence from the City Public Works Department, Fire Department, Police
Department, City Attorney’s Office, and City Administration.
ENVIRONMENTAL REVIEW
The Project qualifies for an Exemption to the California Environmental Quality Act (CEQA)
pursuant to State CEQA Guidelines Section 15301 Class 1 (Existing Facilities) and 15302
Class 2 (Replacement or Reconstruction). A Notice of Exemption has been filed through
the Community Development Department with the County Clerk-Recorder for the
previous project design (pedestrian hybrid beacon) and the proposed design
modifications do not present any material changes that would affect this CEQA
determination.
FISCAL IMPACT
Budgeted: Yes Budget Year: 2025-26
Funding Identified: Yes
Page 475 of 476
Item 7d
Fiscal Analysis:
Funding Sources
(Project Account 2001059)
Total Budget
Remaining
Unencumbered
Current
Funding
Request
Remaining
Balance
SLOCOG Grant (State REAP Funds)* $0 $0 $0
General Fund - Capital Outlay LRM* $3,357 $0 $3,357
General Fund - Capital Outlay LRM* $149,999 $0 $149,999
Total $153,356 $0 $153,356
*Above totals reflect remaining funding in the South & King Crossing Project account, which has already
been approved for the project. Totals exclude $632,816 in project funds that have already been
encumbered in a purchase order for the project construction contract, including $500,000 in SLOCOG grant
funds.
Prior to start of construction, approximately $970,000 was appropriated to the Project
account (No. 2001059), comprised of $500,000 in State REAP grant funding administered
by SLOCOG, and local general funds. This total included funding for construction of the
Project, purchase and installation of emergency vehicle preemption equipment for the
City Fire and Police Departments, and contingencies.
To date, $632,816 has been encumbered for the construction contract and all emergency
vehicle preemption expenditures have been completed, leaving $153,356 in remaining
funds in the project account for construction contingencies. This remaining funding is
sufficient to accommodate the potential cost increases related to the proposed Project
modifications (estimated at an approximately $35,000 in additional costs), while retaining
sufficient contingency funds through the remainder of project construction.
ALTERNATIVES
Deny the request to modify the project. City Council could deny the request to modify
the Project designs to advance a traffic signal in lieu of a pedestrian hybrid beacon. Under
this alternative, staff would move forward with plans as previously approved to install a
pedestrian hybrid beacon, while conversion to a full traffic signal or other intersection
modifications to address vehicle access concerns could be pursued at a later date when
prioritized for funding and approved by Council through a separate budget action.
Page 476 of 476