HomeMy WebLinkAboutItem 7d - South & King Crossing ModificationCity Council Meeting
Tuesday, June 16, 2026
South Street and King Court/Street Crossing
Project Modification
Luke Schwartz, Transportation Manager
Public Works Department
Recommendations:
1.Approve a modification to the South Street and King Court Crossing
Project (Specification No. 2001059), authorizing installation of a
standard traffic signal in lieu of a pedestrian hybrid beacon; and,
2.Authorize the City Engineer to approve modifications to project plans
and specifications and approve associated construction Contract
Change Orders as needed to facilitate project modifications up to the
available project budget and consistent with California Public Contract
Code, including any amendments authorized by the City Manager.
Project History
•2021 – ATP Adopted, Recommends Crossing Improvement at South & King
•2023 - Phase 1 Crossing Upgrades (RRFBs) Installed
•2023-25 – $500k SLOCOG Grant Obtained, Crossing Upgrade Fully Funded in CIP,
Planning/Engineering/Design Advanced
•Warrants met for full signal or PHB
•Initial concerns from Emergency Response, favored PHB with future for full
signal
•Plans & Specs for PHB approved by Council late 2025
•2026
•EVP equipment upgraded funded for SLO Fire and SLO PD
•Construction initiated on PHB, growing concerns from King Court drivers, full signal
OK’d by Emergency Response
Proposed Project Modifications
•Seeking Council input on potential to modify project design from
PHB to full traffic signal
•Could be advanced within existing budget (+$20k -$40k), without
significant delays or risk to $500k in grant funding
•Noticing:
•Post cards mailed within 1,000-foot radius
•News release
•Sandwich boards at South/King and South/Exposition
•Email to ATC and residents who previously contacted City
Pedestrian Hybrid Beacon (PHB) Design
Potential Traffic Signal Design
Advantages of Full Traffic Signal vs. PHB
•Improves access for King Court/Street drivers crossing South Street
•Provides signalized crossing of South Street for pedestrians and
bicyclists
•Less potential for driver confusion or compliance issues with full signal
vs. hybrid beacon
•Relatively minor change to project designs, scope of work, cost
•Pedestrian delay crossing South St. similar to PHB
Disadvantages of Full Traffic Signal vs. PHB
•More frequent stops and delays to traffic on South Street
(including autos, peds, bikes, emergency vehicles)
•Some conflicts with turning vehicles from King Street/Court
during pedestrian crossings compared to PHB—conflicts can be
managed with design strategies, but not fully removed
•Some added cost and schedule delay
Potential for Cut-Through via Exposition Drive
Speed Humps Planned with
Higuera Complete Street
Options and Next Steps
A.Approve Project Modification to Full Traffic Signal (Staff
Recommendation)
B.Retain PHB as Originally Planned*
•*Staff recommends minor modification
C.Conduct More Detailed Analysis & Engagement on Various
Alternatives
•If Council selects this option, staff suggests proceeding with PHB as currently planned
(*with minor modification) to retain $500k grant funding, and pursue further study with
FY2027-29 Financial Plan
Suggested Modification to PHB
Original Design
Suggested Modification to PHB
Suggested Modification to Illuminated Blank-Out Signs
Questions?