HomeMy WebLinkAboutstudio2G_ParkingStructureSafety_RFP_Proposalstudio 2G Architects, LLP. 811 Palm St. San Luis Obispo, CA 93405 pursuits@studio-2g.com www.studio-2g.com Federal Tax ID Number: 20-2906907 Limited Liability Partnership 20+ Years in Business RFP: Parking Structure Safety Element Research and Design studio 2G Architects, LLP Main Office Downtown 811 Palm Street, SLO 2S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Cover Letter Ashley Mayou, Partner 805.594.0771 x117 ashley@studio-2g.com studio 2G Architects, LLP. 811 Palm St. San Luis Obispo, CA 93401 STUDIO 2G ARCHITECTS | COVER LETTER Dear Mr. Swartz, studio 2G Architects is pleased to submit our proposal for the Parking Structure Safety Element Research and Design project for the City of San Luis Obispo. We are a woman-owned (WOSB), LEED-certified architecture firm based on California’s Central Coast, dedicated to delivering sustainable, cost-effective design solutions for complex public projects that require careful coordination, technical rigor, and sensitivity to community context. As a fully local firm, our entire team is based here in San Luis Obispo, with our office located downtown just steps from the Palm Street parking structures. Our architects and staff use these structures regularly as part of our daily work, giving us a direct, personal understanding of their existing conditions, user experience, and safety concerns. This proximity and familiarity uniquely position us to approach this project with both technical expertise and a genuine investment in creating meaningful, lasting improvements for the community. We understand that the City is seeking to enhance safety at three downtown parking structures through the evaluation and implementation of perimeter barrier systems and security camera infrastructure. These structures are highly visible, heavily utilized public assets, and improvements must balance safety, constructability, and aesthetics while maintaining uninterrupted operations. Our team brings a strong understanding of these challenges, particularly in working with existing structures, post-tensioned systems, and phased construction in active facilities. Our approach is grounded in proactive project management, early coordination, and clear communication. studio 2G will lead a collaborative team of trusted subconsultants with whom we have longstanding working relationships. We will manage the project through all phases, from Alternatives Analysis through Construction Support, with a focus on maintaining schedule, controlling scope, and providing consistent, well-documented deliverables aligned with the City’s expectations for PS&E development . Our project manager will serve as a single point of contact and will actively coordinate meetings, track decisions, and ensure alignment across disciplines. During the Alternatives Analysis phase, we will evaluate multiple barrier system approaches, including parapet-mounted and surface-mounted options, while integrating CPTED principles, structural feasibility, and constructability considerations. We will work closely with the City to align on safety priorities and camera coverage strategies early in the process, ensuring that subsequent design phases proceed efficiently and with clear direction. RFP: Parking Structure Safety Element Research and Design City of San Luis Obispo ATTN: Michael Swartz Project Manager III mswartz@slocity.org 3S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Cover Letter signature of date of 4/17/2026 Ashley Mayou | Principal Architect, NCIDQ | studio 2G Architects, LLP. STUDIO 2G ARCHITECTS | COVER LETTER As the project advances into structural analysis and design, our team will carefully evaluate existing conditions, particularly the constraints associated with post-tensioned concrete construction. We will incorporate non- destructive investigation methods such as x-ray scanning to identify safe anchorage locations and avoid impacts to existing structural systems. Our electrical and security design partners will develop coordinated camera layouts and data pathways that optimize coverage at key areas such as entries, corners, and elevated levels. studio 2G places strong emphasis on quality assurance and quality control. We allocate dedicated time within our schedule for internal QA/QC reviews, including interdisciplinary page-turn sessions and the use of structured checklists for all consultants. This process ensures that documents are coordinated, code- compliant, and ready for efficient plan check review. We also take an active role in managing the permitting process by coordinating responses to City comments and maintaining momentum through each review cycle. Cost control and risk management are integral to our approach. Our cost estimator is engaged from the outset to establish baseline assumptions, identify potential risks, and inform early decision-making. At each phase, the design will be evaluated against budget, with clear feedback provided to the team and the City. This iterative process allows us to proactively address unknowns and maintain alignment with project goals. We are enthusiastic about the opportunity to support the City of San Luis Obispo in improving safety at these important downtown facilities. As a local firm whose staff actively uses these structures, we are personally invested in delivering thoughtful, buildable solutions that enhance safety while respecting the character and functionality of these essential public assets. Thank you for your consideration. We look forward to the opportunity to work with the City on this important project. CONTENTS Understanding of the Project and Technical Approach 04 Relevant Experience 09 Qualifications of the Proposed Project Team 13 Proposed Project Schedule 15 Detailed Fee Proposal By Task Historic Federal Courthouse Building Security Fencing studio 2G Architects, LLP UNDERSTANDING OF THE PROJECT AND TECHNICAL APPROACH » 6S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff UNDERSTANDING OF THE PROJECT AND TECHNICAL APPROACH The City of San Luis Obispo is seeking to enhance safety at three downtown parking structures through the integration of perimeter fencing and security camera systems, with a focus on evaluating the elevated parking deck perimeters for three potential mounting options; surface-mounted, parapet- mounted, and recessed. The project requires a balanced approach that improves safety while maintaining structural integrity, minimizing operational disruptions, and delivering construction-ready documents suitable for permitting and implementation. Our team understands that the primary challenge of this project lies in integrating new systems into three distinct existing structures with varying age, geometry, structural systems, limited documentation, and active daily use. In response, our approach emphasizes early validation of existing conditions, disciplined scope control, and coordinated design across structural and electrical systems to reduce risk and deliver a practical, buildable solution. Project Management and Early Validation We will provide disciplined and proactive project management to maintain alignment with the City’s goals for safety, constructability, schedule, and cost control across all three parking structures. Our approach recognizes that the success of this project depends on early identification and resolution of unknown existing conditions, particularly given the age of the facilities and the likelihood of incomplete or outdated documentation. A central component of our methodology is early field validation paired with critical review of available record drawings. studio 2G will conduct site observations alongside our structural subconsultant, FTF Structural, to verify as-built conditions. We will compare these findings against existing documentation to identify discrepancies that could impact design, constructability, or cost. This includes confirmation of parapet configurations, edge conditions, structural constraints, and the presence of embedded elements that may affect anchorage or routing. By grounding the design in verified field conditions rather than assumptions, we reduce the risk of unforeseen conflicts during later design phases or construction. In parallel, we will coordinate closely with our electrical subconsultant to validate existing infrastructure systems, including electrical capacity, data pathways, and potential equipment locations. This early effort will also identify constraints related to post-tensioned construction, access limitations, and operational considerations within active parking environments. Recognizing that these structures are in continuous use, our validation process will be carefully planned to minimize disruption while still capturing the level of detail required to support design decisions. Where necessary, we will recommend targeted non-destructive investigation methods to supplement visual observations and confirm critical conditions. This early validation phase establishes a reliable technical baseline for the project, allowing the team to refine design assumptions, support accurate cost estimating, and avoid rework. It also enables informed decision-making during alternatives analysis by ensuring that proposed solutions are grounded in the realities of each structure. Through this structured and field-informed approach, we reduce uncertainty, improve coordination across disciplines, and position the project for efficient progression into design and implementation. Alternatives Analysis and System Definition Our Alternatives Analysis Report will include a structured comparison matrix evaluating each mounting strategy (surface, parapet, recessed) across structural feasibility, constructability, CPTED effectiveness, visual impact, cost, and operational disruption. This will be supplemented by representative photo simulations and conceptual details to support City decision- making. A key aspect of this phase is the definition of the CCTV system, as current requirements are not fully established. We will work closely with the City to determine system expectations, including camera coverage, system architecture, and integration with existing infrastructure. This includes evaluating centralized versus distributed headend configurations, confirming storage requirements, and identifying whether new equipment such as servers, licensing, and software will be required. We will also verify the availability and responsibility of network infrastructure within each structure, including IDF capacity and network switching. Early coordination of these elements is essential to avoid downstream conflicts and cost escalation. In addition, we will perform a high-level review of electrical and life safety considerations, including lighting and emergency lighting requirements that may be impacted by the proposed improvements. Understanding of the Project and Technical Approach 7S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff UNDERSTANDING OF THE PROJECT AND TECHNICAL APPROACH In addition, we will perform a high level review of electrical and life safety considerations, including lighting and emergency lighting requirements that may be impacted by the proposed improvements. This review will also evaluate the potential impacts of proposed fencing systems on means of egress, occupant safety at elevated levels, and emergency responder access to ensure that all design options maintain compliance with applicable fire and life safety codes. Future system considerations, such as photovoltaic (PV) solar and battery energy storage systems (BESS), will also be documented to ensure compatibility with long-term City objectives, although these systems are not included in the base scope. Targeted Structural Analysis and System Integration Following selection of a preferred alternative, our team will perform a focused structural analysis limited to the parapet edges and localized attachment zones required for fencing and camera systems including wind load analysis and seismic anchorage in accordance with the current California Building Code. This targeted approach ensures that the analysis remains aligned with the project scope while avoiding unnecessary expansion into full structural rehabilitation. Because the parking structures are constructed with post- tensioned concrete, special care will be taken to avoid conflicts with existing tendons. All proposed penetrations for CCTV raceways and anchorage points for fencing will require non- destructive investigation, such as x-ray scanning, to verify the installation will not affect the structural integrity of the existing garages. In parallel, we will advance camera layouts, electrical routing, and system coordination. This includes confirming power availability, data pathways, and equipment locations, as well as identifying any infrastructure limitations that may impact implementation. Consistent with the City’s direction, this phase will also identify any existing conditions that would prevent implementation of the proposed improvements. Where necessary, we will define enabling work required to support installation, including structural, electrical, or code-related upgrades. Understanding of the Project and Technical Approach Local Presence and Proximity to Project Sites studio 2G Architects’ downtown San Luis Obispo office at 811 Palm Street places our team in immediate proximity to all three project sites, allowing for a highly responsive and informed approach to this work. We are located directly across the street from the 842 Palm Street parking structure, within a three minute walk of the 919 Palm Street structure, and approximately a five minute walk to the 871 Marsh Street structure. 8S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff UNDERSTANDING OF THE PROJECT AND TECHNICAL APPROACH Design Development and Construction Sequencing As Architect of Record, studio 2G Architects will lead the advancement of the design through Design Development and Construction Documents, ensuring that all disciplines remain coordinated, aligned, and responsive to the City’s goals. Our role extends beyond document production to active design leadership, maintaining continuity between the selected alternative and a fully coordinated, constructable solution. We will facilitate internal pull planning sessions with the full consultant team to proactively manage design progression, identify dependencies, and resolve issues early. This collaborative approach keeps structural, electrical, and system design efforts aligned and allows the team to maintain momentum through each phase while avoiding late-stage conflicts. These working sessions are complemented by regular coordination meetings with the City, ensuring that decisions are confirmed in real time and that the design continues to reflect City priorities as it evolves. Throughout this phase, studio 2G will implement our SmartSheet weekly tracking system, which is distributed each Friday to the full team and City stakeholders. This report provides a clear summary of progress, including completed tasks, upcoming work, key decisions, and any items requiring input or action. This level of transparency supports accountability across the team and allows for timely resolution of issues before they impact schedule or budget. As the design is refined, we will develop detailed fencing layouts, structural attachment details, camera placements, and coordinated electrical and data pathways, with a strong emphasis on constructability. We recognize that installing new safety railings and camera systems in active parking structures presents significant logistical challenges. Our approach will evaluate phased installation strategies by level or zone, allowing portions of each structure to remain operational while work progresses. We will incorporate the use of temporary barriers and safety measures to maintain public safety during construction and carefully coordinate work areas to minimize disruption. In addition, we will evaluate the use of prefabricated railing systems and efficient installation methods to reduce construction duration, limit on-site labor, and improve overall safety. These strategies will be coordinated with both the structural and electrical design to ensure that installation sequencing is feasible and aligned with real-world constraints. Coordination between disciplines will remain a priority during this phase, particularly where installation sequencing, temporary conditions, or access constraints influence design decisions. Where necessary, we will work with the City to define acceptable operational impacts and develop solutions that balance safety, efficiency, and user experience. Through strong leadership as AOR, structured coordination, and clear communication tools, studio 2G will guide the project through design development and documentation in a manner that is organized, transparent, and focused on successful implementation. Understanding of the Project and Technical Approach “OUR EXPERIENCES THUS FAR WITH STUDIO 2G HAVE BEEN VERY POSITIVE. I PERSONALLY HAVE APPRECIATED THE HONESTY, INTEGRITY AND PROFESSIONALISM THEY HAVE EXHIBITED IN THE PROJECTS WE’VE WORKED ON.” - JASON LAL, DIRECTOR OF FACILITIES, COMMUNITY ACTION PARTNERSHIP OF SAN LUIS OBISPO 9S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff UNDERSTANDING OF THE PROJECT AND TECHNICAL APPROACH Permitting, Final Design, and Implementation Support As the project advances into final design and permitting, studio 2G Architects will continue to lead as Architect of Record, ensuring that the construction documents are complete, coordinated, and responsive to agency requirements. Our focus during this phase is to deliver a high-quality PS&E package that supports an efficient plan check process and minimizes the risk of delays. A key component of our approach is a structured and intentional QA/QC process, with dedicated time built into the project schedule specifically for detailed internal review. studio 2G will lead a comprehensive quality control effort that includes discipline-specific QA/QC checklists for each consultant, ensuring that structural, electrical, and system components are reviewed for completeness, coordination, and code compliance prior to submittal. In addition, we will conduct a formal QA/QC page turn review, bringing the full team together to review the documents sheet-by-sheet. This process allows for real-time identification of coordination gaps, constructability concerns, and inconsistencies across disciplines, significantly reducing the likelihood of plan check comments and rework. We will actively manage the plan review and permitting process in coordination with the City and the consultant team. This includes early alignment with applicable codes and permitting requirements, internal quality control reviews prior to submittal, and clear documentation of design decisions to support agency review. By maintaining consistency between earlier design phases and final documents, we reduce the likelihood of major comments or redesign during plan check. studio 2G will lead the response to plan check comments, coordinating with all disciplines to provide timely, complete, and well-integrated responses. We will track all comments, assign responsibility, and verify that each response is fully incorporated into the documents prior to resubmittal, maintaining control of the review cycle and avoiding delays. This effort is strengthened by our established working relationships with our consultant team, many of whom we have partnered with over multiple projects. This familiarity allows for efficient communication, clear accountability, and rapid resolution of issues during critical review periods. Throughout permitting and final design, we will continue to apply our proven project management approach, including pull planning sessions, regular coordination meetings with the City, and our SmartSheet weekly tracking system. These tools provide transparency into progress, highlight outstanding items, and ensure alignment across all stakeholders. Following permit approval, we will support the City during bidding and construction by responding to contractor questions, reviewing submittals and shop drawings, and conducting site visits at key milestones to ensure that the design intent is maintained. Through strong leadership, disciplined QA/QC, and a coordinated team with a proven history of collaboration, studio 2G will guide the project through permitting and implementation with a focus on efficiency, clarity, and successful delivery. Understanding of the Project and Technical Approach QA/QC Process: 10S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff UNDERSTANDING OF THE PROJECT AND TECHNICAL APPROACH Cost Approach and Risk Management Our cost approach is grounded in an understanding of the complexities associated with working within three existing parking structures with varying and partially unknown conditions. We recognize that key variables such as structural constraints, electrical infrastructure capacity, and final CCTV system requirements have the potential to significantly influence project cost if not addressed early and proactively. To manage this, our cost estimator is engaged as an active member of the team from the outset of the project, not only at defined submittal milestones. At the beginning of the project, the estimator will review available information and develop an initial assessment of potential cost drivers, risks, and unknowns. This early evaluation informs a set of targeted questions and assumptions that will be coordinated with the City during the initial phases, helping to clarify scope and reduce uncertainty before design progresses. As the design advances, the cost estimator will continuously review evolving drawings and system decisions, providing real- time feedback to the team on cost impacts, constructability considerations, and potential budget risks. This allows the team to make informed decisions during alternatives analysis and design development, rather than reacting to cost issues later in the process. Formal cost estimates will be prepared at each required phase, including Alternatives Analysis, 50%, 90%, and final PS&E, with clearly documented assumptions and contingencies. Each estimate will reflect the current level of design development while also identifying remaining risks, including unknown existing conditions, infrastructure limitations, and scope elements that may require further definition. Our approach also incorporates early field validation and coordination across disciplines to reduce uncertainty related to structural conditions, electrical capacity, and system integration. By aligning cost estimating with verified field conditions and coordinated design decisions, we improve the reliability of cost projections and reduce the likelihood of unexpected changes during construction. Key cost drivers for this project include fencing and safety improvements, CCTV system scope and configuration, electrical and data infrastructure upgrades, and any enabling work required to support installation. These elements will be continuously evaluated and communicated to the City throughout the project. Through early estimator involvement, continuous cost feedback, and clear documentation of risks and assumptions, studio 2G provides a proactive and transparent cost management approach that supports informed decision- making and alignment with the City’s budget objectives. Summary studio 2G Architects brings a clear and disciplined approach to the Parking Structure Safety Element project, grounded in a strong understanding of the technical challenges, risks, and operational constraints associated with working in active, existing parking structures. Our approach is defined by early validation of as-built conditions, ensuring that design decisions are based on verified field information rather than assumptions. This reduces uncertainty, supports accurate cost estimating, and minimizes the risk of redesign during later phases. As Architect of Record, we provide consistent leadership from project initiation through construction, maintaining alignment across all disciplines and guiding the project toward a coordinated, buildable solution. We are supported by a well-integrated consultant team with an established history of collaboration, enabling efficient coordination, clear communication, and rapid resolution of issues. Our process is reinforced by structured project management tools, including pull planning sessions, weekly SmartSheet reporting, and ongoing engagement with the City to maintain transparency and momentum. Quality and risk management are embedded throughout our workflow. Through dedicated QA/QC processes, including consultant checklists and full team page turn reviews, we ensure that documents are complete, coordinated, and ready for efficient plan check review. In parallel, our cost estimator is engaged from the outset, providing continuous feedback on cost drivers, risks, and design decisions to support alignment with the City’s budget objectives. Finally, we place strong emphasis on constructability and implementation, developing phased construction strategies that maintain parking operations while prioritizing public safety. From early analysis through final design and construction support, our focus remains on delivering practical, efficient solutions that can be successfully built. Through this comprehensive and coordinated approach, studio 2G Architects will deliver a design that enhances safety, minimizes disruption, and supports the City’s goals for long- term performance and reliability. Understanding of the Project and Technical Approach RELEVANT EXPERIENCE » San Francisco Federal Building Childcare Security Fencing studio 2G Architects, LLP 12S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff RELEVANT EXPERIENCE Toyota Walnut Creek Dealership (FTF Structural) RELEVANCE • Structural Analysis • Evaluation of Existing Parapets and Edge Conditions • Identification of Anchorage Locations • Wind Load Analysis and Seismic Anchorage Review • Preliminary Structural Feasibility • Conceptual Layouts • Representative Mounting and Attachment Details • Construction Phasing Plan Minimizing Parking Disruptions • Project Management and Coordination • Plans, Specifications, and Estimates (PS&E) FTF Engineering provided structural engineering services for the new two-story Toyota Walnut Creek dealership, a 240,000-square-foot state-of-the-art automotive facility. The building features a ground-floor sales showroom and service reception area, a second-floor service shop with training rooms, office space, and a parts warehouse, along with 163,000 square feet of open parking distributed across the ground, second, and rooftop levels. A significant component of the project was the design and coordination of the multi-level parking areas, including the ground, second, and rooftop parking decks. These elevated parking levels required careful structural planning to accommodate vehicle loads, circulation patterns, and long-span requirements while maintaining alignment with the program above and below. The use of post-tensioned concrete systems allowed for efficient spans and minimized column intrusion, maximizing parking efficiency and user circulation. Coordination of structural elements with access ramps, guardrails, and perimeter conditions was critical to ensure safety, durability, and constructability, while supporting the overall performance of the parking structure. The structure is primarily cast-in-place concrete construction, utilizing reinforced concrete columns, shear walls, and slabs. Post-tensioned girders were incorporated to achieve long spans and wide bays, optimizing the layout to align the architectural parking requirements with the service bays above. The foundation system consists of economical shallow foundations, including spread footings, grade beams, and a heavily reinforced mat slab. This approach was selected to accommodate the variable subsurface conditions, with bedrock encountered at depths ranging from the finished floor level to approximately 30 feet below grade. TOYOTA WALNUT CREEK DEALERSHIP WALNUT CREEK, CA PROJECT DESCRIPTION FTF Engineering provided structural engineering services for the new two-story Toyota Walnut Creek dealership, a 240,000-square-foot state-of-the-art automotive facility. The building features a ground- floor sales showroom and service reception area, a second-floor service shop with training rooms, office space, and a parts warehouse, along with 163,000 square feet of open parking distributed across the ground, second, and rooftop levels. The structure is primarily cast-in- place concrete construction, utilizing reinforced concrete columns, shear walls, and slabs. Post-tensioned girders were incorporated to achieve long spans and wide bays, optimizing the layout to align the architectural parking requirements with the service bays above. The foundation system consists of economical shallow foundations, including spread footings, grade beams, and a heavily reinforced mat slab. This approach was selected to accommodate the variable subsurface conditions, with bedrock encountered at depths ranging from the finished floor level to approximately 30 feet below grade. GROSS SQUARE FOOTAGE 240,000 sf CONSTRUCTION COST Confidential CONSTRUCTION TYPE Type I-B DATE CONSTRUCTION COMPLETED Expected 2027 PROJECT TEAM Gensler [Architect] McDevitt Construction [General Contractor] Image Courtesy of Gensler Image Courtesy of Gensler Location: Walnut Creek, CA | Construction Cost: N/A | Size: 240,000 SF | Completed: est. 2027 13S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff RELEVANT EXPERIENCE RELEVANCE • Perimeter Fencing / Barrier Systems • Evaluation of Mounting Approaches • Conceptual Fence Layouts • Representative Mounting and Attachment Details • Preliminary Structural Feasibility • CPTED and Aesthetic Considerations • Building, Accessibility, and Fire/Life Safety Code Impacts • Identification of Anchorage Locations • Construction Phasing Plan Minimizing Disruptions • Project Management and Coordination studio 2G Architects has delivered multiple projects focused on perimeter security enhancements for sensitive and high-profile facilities, including both historic and federal buildings. Through careful evaluation of mounting strategies, coordination with existing structures, and attention to constructability and operations, our team has developed secure, durable, and context-sensitive solutions for public agencies. Historic Federal Courthouse Fencing: Location: Oakland, CA | Construction Cost: $303K | Size: 1,320 SF | Completed: 2026 studio 2G Architects provided design and project management services for a design-build project involving the addition of a security fence at a historic courthouse facility. The project required a careful balance between improving site security and preserving the historic character of the building and surrounding landscape. The project included the design and installation of a perimeter security fence with three secure access gates. The layout and detailing were carefully developed to provide the required level of security while remaining visually compatible with the historic setting. Material selection, proportions, and placement were all considered to ensure the fence complemented the historic architecture rather than detracting from it. The result is a secure and functional solution that meets safety needs while respecting the historic significance of the courthouse. San Francisco Federal Building Childcare Fencing: General Service Administration (GSA) Security Fencing Location: San Francisco, CA | Construction Cost: $190K | Size: 2,100 SF | Completed: 2023 studio 2G Architects designed perimeter security improvements for the childcare area at the San Francisco Federal Building, focusing on creating a safe and controlled outdoor environment. The project included a continuous security fence system integrated with existing concrete planter walls and the building’s sunscreen structure to establish a secure boundary without disrupting the overall design. Mesh fencing was added above the planters to prevent unauthorized access while maintaining visibility into and out of the space. A double-door emergency exit gate was included to meet life safety requirements, allowing for secure egress while maintaining controlled access. The result is a well-defined and secure perimeter that prioritizes safety while remaining compatible with the building’s architecture. Historic Federal Courthouse Federal Building Childcare 14S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff RELEVANT EXPERIENCE USDA OIG Tenant Improvement studio 2G Architects served as the prime contract holder, providing project management, architectural design, interior design, and construction administration services for a 7,600 SF tenant improvement for the relocation and consolidation of the United States Department of Agriculture, Office of the Inspector General. A key component of the project was the integration of enhanced security measures throughout the space. The design incorporated secure wall assemblies to protect sensitive areas and support controlled access, along with strategically placed security cameras to provide full coverage of entry points, circulation paths, and critical work zones. These systems were carefully coordinated with the overall layout to maintain both security and functionality without compromising the user experience. The project included full demolition of existing walls, ceilings, and furnishings, allowing the team to reconfigure the space to meet program and security requirements. studio 2G worked closely with USDA leadership to develop a layout that balanced operational needs, visibility, and control. Interior design features incorporated USDA branding, using logo colors and biophilic elements to create a modern and welcoming environment. Open office areas were arranged at slight angles to preserve key views while maintaining clear sightlines, which also supported passive supervision and security awareness. The project was delivered within budget, and the end users are highly satisfied with a secure, efficient, and modernized workspace. RELEVANCE • Security Camera Infrastructure • Site Assessment for Security Camera Placement • Camera Layout Plans • Refined Camera Placements and Coverage • Electrical and Data Routing Concepts • Building and Fire/Life Safety Code Impacts • Project Management and Coordination • Construction Support Services • Preparation of Plans, Specifications, and Estimates (PS&E) • Working within Existing Conditions • ADA Upgrades Location: Oakland, CA | Construction Cost: $3.2M | Size: 7,500 SF | Completed: 2022 15S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff RELEVANT EXPERIENCE RELEVANCE • Security Camera Infrastructure • Site Assessment for Camera Placement • Camera Layout Plans • Electrical and Data Routing Concepts • Refined Camera Placements and Coverage Diagrams • Electrical and Data Pathway Design • Structural Analysis and Anchorage Coordination • Alternatives Analysis and Feasibility Evaluation studio 2G Architects completed the design for a tenant improvement of a municipal police facility serving multiple City departments, with a strong focus on enhancing site and building security. The project required careful coordination to improve safety while working within existing building and code constraints. A key component of the Cherry Hills project was the integration of a comprehensive security camera system to support a secure perimeter and controlled monitoring of the facility. The project included a defined number of new cameras, requiring the team to evaluate and prioritize placement to achieve the most effective coverage. studio 2G analyzed building geometry, circulation paths, and points of vulnerability to determine optimal camera locations. The design also considered mounting conditions, coordination with existing structures, and integration with other security elements to maintain both performance and constructability. The team also conducted detailed code analysis to ensure that the security improvements could be implemented without triggering major building upgrades, allowing the project to remain efficient and cost-effective. This project demonstrates studio 2G’s ability to plan and design effective security systems within existing facilities, using a strategic and analytical approach to maximize coverage, enhance safety, and support long-term operations. City of Menifee Police Department Renovation Location: Meniffee, CA | Construction Cost: $2M | Size: 2,500 SF | Completed: 2026 RELEVANCE • Alternatives Analysis • Evaluation of Existing Conditions • Structural Analysis • Identification of Anchorage Locations • Building, Accessibility, and Fire/Life Safety Code Impacts • Identification of Permits and Approval Requirements • Project Management and Coordination • Conceptual Layouts • Structural Feasibility studio 2G Architects completed a feasibility study for improvements to an existing pedestrian bridge spanning Broadway Street (HWY 135) in the City of Santa Maria. The study focused on evaluating existing structural and access conditions and developing strategies to improve safety, accessibility, and long- term functionality of the crossing. A key component of the work included assessment of the existing stair and elevator systems, as well as exploration of a new elevator and stair connection on the east side of the bridge to replace the existing connection to the mall’s second level. The team conducted a detailed review of existing conditions to identify constraints, code deficiencies, and opportunities for improvement, including required upgrades to meet current accessibility and life safety standards. Multiple design options were analyzed to determine feasible approaches for integrating new vertical circulation elements with the existing structure while minimizing impacts to ongoing use and adjacent properties. The project also required coordination with Caltrans due to the bridge’s location over a state highway, including consideration of right-of-way limitations and permitting requirements. The result was a set of clear recommendations and conceptual approaches to guide future design, permitting, and implementation. Santa Maria Broadway Bridge Feasability Study Location: Santa Maria, CA | Construction Cost ext. $2M | Completed: 2026 QUALIFICATIONS OF THE PROPOSED PROJECT TEAM » Santa Maria Broadway Bridge Feasability Study studio 2G Architects, LLP 17S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES Organizational Chart ROLES OF OUR MANAGEMENT TEAM AND FIRM SIZE Project Architect • Primary person of contact for client. • Maintains regular communication with client and the team. • Contract administration and management. Project Manager • Manages schedule compliance and budget control. • Provides direction to personnel. • Day-to-day tasks project completion. • Communication with the end user. • Attends project meetings Quality Manager • Prepares contract specific QA/QC plan. • Implements all quality tasks. • Coordinates with PMs for consistency in quality process across project. studio 2G Archtects, LLP • Our firm is made up of three (3) partners, six (6) support staffi, one (1) technical support staffi, and one (1) administrative staffi. • Our firm has remained stable at this size for the past 5 years. PROJECT MANAGER Serena Kacheros-Warren, NCARB Licensure Candidate (studio 2G Architects) QUALITY MANAGER Heidi Gibson, AIA, LEED BD+C, NCARB (studio 2G Architects) PROJECT ARCHITECT Ashley Mayou, RA, NCIDQ (studio 2G Architects) KEY DISCIPLINES STRUCTURAL ENGINEERING Jillian van Enckevort, PE (FTF Engineering) ELECTRICAL ENGINEERING John Maloney (JMPE Engineering) FIRE PROTECTION & LIFE SAFETY Al Yakel, PE (Collings & Associates) COST ESTIMATING John Moreno, CCP, LCPE (Sierra West) 18S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES EDUCATION Bachelor of Architecture California Polytechnic State University San Luis Obispo, CA AFFILIATIONS City of San Luis Obispo Architectural Review Commission Chair (2022-2024) Vice Chair (2021-2022; 2024-Present) Commissioner (2020-2021) SELECT EXPERIENCE GSA, USDA OIG Tenant Improvement | Oakland, CA Construction Cost: $3.2M | Size: 7,500 SF | Completed: 2022 Acting as Project Manager for this Design-Bid-Build tenant improvement of the 15th floor of the Dellums Federal Building to include new private offices, open office workstations, conference rooms, break room, IT, and storage rooms for the the United States Department of Agriculture. Project featured security camera infrastructure, site assessment for security camera placement. GSA, SFFB Childcare Fencing | San Francisco, CA Construction Cost: $190K | Size: 2,100 SF | Completed: 2023 Acting as Project Architect / Manager for perimeter security improvements at the San Francisco Federal Building childcare area, overseeing design and coordination to create a safe and controlled outdoor environment. Led integration of a continuous security fence system with existing planter walls and building elements, maintaining visibility, security, and architectural compatibility. Coordinated life safety requirements, including a double-door emergency egress gate, delivering a secure and code-compliant solution. County of Santa Barbara BeWell Facility | Santa Barbara, CA Construction Cost: $ 1.4 M | Size: 2,804 SF Acting as Project Manager / Architect for a residential wellness facility with a strong focus on accessibility compliance. Scope included interior renovation of a board and care facility. Work included design and implementation of exterior ADA-compliant path of travel, accessible parking improvements, and coordinated ADA signage to ensure full site accessibility and code compliance. SLO City Hall Finance / IT Tenant Improvement | San Luis Obispo, CA Construction Cost: $1.24M | Size: 7,500 SF Acting as Project Manager / Architect for tenant improvements to the City Hall Finance and Information Technology Offices, with an emphasis on delivering ADA upgrades within an occupied, locally serving civic facility. Scope included reconfiguration of interior spaces to improve accessibility, including an upgraded accessible path of travel to the primary stair, and strategic modifications within existing structural constraints. Ashley Mayou, Licensed Architect C-27830, Licensed Interior Designer NCIDQ #421364 Partner, studio 2G Architects | Architect | 7+ with studio 2G | 9 yrs of experience Ashley Mayou will be the Project Architect for this City project. Mayou has received a reputation in the industry for being a swift communicator and providing thorough coordination of the design team documents throughout a project. Mayou has extensive experience working with public/government clients. She is currently the Project Manager and Interior Designer on active projects with the County of Santa Barbara, the City of San Luis Obispo, and the City of Menifee. Below you will find her experience working with government clients and projects of a similar size. 19S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES Serena Kacharos-Warren, NCARB studio 2G Architects | Project Manager | 2+ with studio 2G | 8 yrs of experience Serena Kacharos-Warren will serve as Project Manager on this City Project. Kacharos-Warren has experience overseeing a wide range of architectural projects, including civic, federal, commercial, hospitality, and mixed-use projects. She specializes in coordinating design teams, facilitating clear communication with clients, and managing project schedules to ensure successful delivery from concept through construction. Serena will serve as the central point of coordination between clients, consultants, and contractors. She has successfully coordinated across disciplines on several projects that required complex integration of building systems with architectural design. Below you will find her experience working with government clients and projects of a similar size. SELECT EXPERIENCE Santa Maria Broadway Bridge Feasability Study | Santa Maria, CA Construction Cost est. $2M | Size: N/A Acting as Project Manager for a feasibility study evaluating improvements to an existing pedestrian bridge spanning Broadway (Hwy 135) in the City of Santa Maria. The study evaluated adding a new elevator and stair tower on the east side of Broadway, and assessing code compliance to the existing elevator and stair systems, while coordinating with Caltrans and overseeing supporting studies including topographic survey and hazardous materials testing. Camp Roberts Remodel | San Miguel, CA Construction Cost: $1.1M | Size: 1,591 SF Acting as Project Manager for federal office facility renovation. Attended site visits and meetings with the client. Created and updated project narrative throughout project. Scope included interior renovation to update the existing condition of the building. Interior finishes, restrooms, mechanical systems, electrical, plumbing, ADA, windows & doors, exterior siding, and sitework were all evaluated and assessed for removal and replacement. Included structural retrofit and abatement. Woodland Business Park | Nipomo, CA Construction Cost: $4M | Size: 10,000 SF Acting as Project Manager for the new build of two shell commercial buildings designed to provide flexible spaces to accomodate various potential occupants. Point of contact with the client and consultants. Auxiliary Office Addition | Paso Robles, CA Construction Cost: $897,000 | Size: 2,700 SF Acting as Project Manager for addition to a wine production facility that added new office space and updated ADA bathrooms for staff. Coordinated throughout the project with client, consultants, and jurisdiction. EDUCATION Bachelor of Architecture Minor in Business & Economics University of Oregon Eugene, OR AFFILIATIONS Vice President S&T Water Board June 2025 - Current AIA Board - Associates Director 2020-2022 20S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES Heidi Gibson, AIA, NCARB, LEED BD+C, Licensed Architect C-27830 Partner, studio 2G Architects | Architect | 20+ with studio 2G | 32 yrs of experience Heidi Gibson, AIA, LEED AP BD+C certified, will be the QA/QC Manager for this City Project. Gibson has extensive experience with renovation work with public clients. Gibson has received a reputation in the industry for going beyond the status quo and she strives to take clients on a journey by giving them insights on how their project can create a healthy environment, conserve resources, and be dramatically unique. Gibson’s projects have received numerous awards from the AIA and local award platforms. Heidi leads studio 2G’s Hospitality and Federal POD, overseeing a diverse portfolio of projects for both public and private clients. Below you will find her experience working with government clients and projects of a similar size. SELECT EXPERIENCE GSA, USDA OIG Office TI | Oakland, CA Construction Cost: $3.1 M | Size: 7,485 SF Acting as Project Architect for this Design-Bid-Build tenant improvement of the 15th floor of the Dellums Federal Building to include new private offices, open office workstations, conference rooms, break room, IT and storage rooms for the the United States Department of Agriculture. SLO City Hall Finance and IT Office TI | San Luis Obispo, CA Construction Cost: $430,000 | Size: 7,500 SF Tenant improvement to the City Hall Finance and Information Technology offices to remove walls and incorporate glass material to accentuate natural light along with new work station furniture. Upgrades were required in the break room and restrooms to bring the facility into ADA compliance. GSA, Health and Human Services Office TI | San Francisco, CA Construction Cost: $9.9 M | Size: 56,000 SF Acting as Project Architect for this tenant improvement which encompasses five (5) floors of the San Francisco Federal Building to consolidate the HHS offices and create shared working spaces. GSA, Historic Federal Courthouse Fencing | Oakland, CA Construction Cost: $303K | Size: 1,320 SF | Completed: 2026 Served as Project Architect for an Historic Federal Courthouse fencing project in Oakland, leading design development and detailing for a perimeter security system within a sensitive historic context. Developed fence layout, gate locations, and material selections to achieve required security while maintaining compatibility with the courthouse architecture and surrounding landscape. Coordinated with the design-build team to deliver a secure, code-compliant solution for this historic site. EDUCATION Bachelor of ArchitectureCalifornia Polytechnic State University San Luis Obispo, CA Associate of Arts Degree in Interior DesignFashion Institute of Design and Merchandising, Los Angeles AFFILIATIONS American Institute of Architects Central Coast Chapter Past President (2010-2013) CA Director (2014-2016) Member of the National Council of Architect Registration Board US Green Build Council California Air Guard, Retired Lieutenant Colonel 21S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES Jillian van Enckevort, S.E. Principal California SE # 5394 / California CE # 67784 Utah SE # 11283864-2203 Nevada SE # 027347 Oregon SE # 100531 Missouri PE # 2026014473 Experience: 24 years Jillian joined FTF Engineering in 2015 with over thirteen years of structural engineering experience. The breadth of her work encompasses residential, commercial and hospitality projects and numerous industrial and military base projects, including commercial launch facilities, satellite processing facilities and large antenna foundations. Jillian has performed numerous foundation repairs, bluff stabilizations and seismic retrofits in wood, steel and concrete as well as the creation of computer models for the development of structural damper systems. She has also implemented a wide range of design software and drawing tools and is an experienced project manager. Jillian serves as the leader of the San Luis Obispo office of FTF Engineering, managing multiple projects and multiple engineers across California and the United States. Education B.S. in Architectural Engineering, California Polytechnic State University, San Luis Obispo, CA, June 2002 Professional Affiliations Structural Engineering Association of Southern California (SEAOSC) American Society of Civil Engineers (ASCE) Central Coast International Code Council (ICC) Project Experience Toyota Automotive Facility, Walnut Creek, CA Engineer of Record for 240,000 square foot state of the art automotive facility with 163,000 square feet of parking on the ground, second floor, and roof top. Scope of work included design and detailing of safety elements including bollards, parapets, and traffic guardrails. GSA Security Upgrades, San Francisco and Sacramento, CA Engineer of Record for security upgrades at numerous GSA facilities including fencing and hardening elements with review and coordination of anchorage to existing structural elements. Walmart Headquarters Security Upgrade, San Bruno, CA Anchorage of entryway security upgrades on an existing six-story concrete office complex over two stories of parking. Included review and coordination for attachments to existing post-tensioned concrete slabs. ReSource Recovery Project, Tajiguas Landfill, Santa Barbara County, CA California Seismic Engineer for the design of equipment supports, anchorage of the processing equipment, and cast-in-place concrete percolate tanks at the Santa Barbara County ReSource Center, which is a state-of-the-art material recycling facility and anaerobic digester. San Francisco Airport International Terminal Building Phase 2 Renovation, San Francisco, CA Provided engineering oversight and internal QA/QC for the ITB Phase 2 Renovation Design-Build Project which involves the centralization of US Customs Secondary Operations to the central Second Floor. FTF’s scope includes all structural design for new metal stud framing, blast-resistant rooms, designing penetrations in floors, and designing structural support for architectural features. Foundation and Anchorage at Test Pad 01, Vandenberg Air Force Base, CA Design of concrete foundations for the support of scaffolding anchorage loads during the processing phase, upgrading an existing launch support pad to support a new steel pedestal and launch vehicle. 22S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES John Maloney, PE Principal/Engineer Licenses California #E13083 Colorado #26463 Oregon #71274PE Arkansas #11196 Louisiana #32751 Nevada #019896 Alabama #32073-E Since 1982, John Maloney has been committed to creating the most cost-effective, energy-efficient electrical and lighting design solutions for government, commercial, and residential projects. In 1994, Maloney formed JMPE, his own electrical engineering and lighting design business headquartered in Santa Barbara, California. In 2002 he opened a branch office in Bakersfield with a staff of four that has grown to fifteen. In 2014 John opened a third office in Orcutt. Maloney's areas of expertise include electrical design of power, lighting, and signal systems; distribution system design, short circuit analysis, coordination studies and Title 24 Lighting Calculations; as well as interior and exterior lighting design for retail stores, offices, and residences. Professional Experience: Santa Barbara Electrical Design Group, Inc., Partner 1987-1994 JMPE Electrical Engineering & Lighting Design, Owner 1994-Present JMPE is a full-spectrum electrical engineering and lighting design firm with offices in:  Bakersfield, CA 5500 Ming Ave. Suite 251 (661) 831-7851  Santa Barbara, CA 146 East Carrillo Street (805) 569-9216  Santa Maria, CA 2880 Santa Maria Way, Suite D4 Suite 204 (805) 886-1390 John’s areas of expertise include, but are not limited to:  Interior and exterior lighting design for retail stores, offices and residences.  Electrical design of power, lighting, and communication systems for schools, hospitals, commercial and government entities.  Distribution system design.  Fire alarm system design.  Short circuit analyses.  Arc Flash Analyses  Coordination studies.  Title 24 lighting calculations.  Detailed electrical cost estimating.  Industrial power and control systems, commercial and institutional power, lighting, and communication systems.  Data network cabling designs. 23S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES John Maloney, PE Page 2 Organizations:  Former Vice Chair of the Department of the State Architect Green Committee. 2009  Named Chairperson of the prestigious State of California Electrical Engineering Technical Advisory Committee. 1997  Served on the State of California Electrical Engineering Advisory Council 1998 - 2007  Appointed to the Division of State Architect Advisory Board. 2006  Member of OSHPD SNF Ad Hoc Committee 2008 – 2009  Member of Fire and Code Board, City of Santa Barbara 2017 - Present Professional Memberships:  IEEE (Institute of Electrical & Electronic Engineers-former Section Chair)  IESNA (Illuminating Engineering Society of North America former Section Chairman)  California Society of Professional Engineers (former Chapter President)  MathCounts Chairperson  Member of the U.S. Green Building Council.  Member (and past secretary) of ACEC (American Council of Engineering Companies) Kern County Chapter. Awards: 1995 - American Institute of Architects - San Luis Obispo Chapter Award (Palm Street Offices) 1995 - Applee Award - Honorable Mention (Crossroads Restaurant in Santa Barbara interior lighting) 1994 - Santa Barbara Beautiful Award (Crossroads Restaurant in Santa Barbara) 1994 - Illuminating Engineering Society's Paul Waterbury Award (Santa Barbara City College's Parking Structure Lighting) Three-time winner of the Southern California Edison Design for Excellence Award 1993 - Oxnard Post Office Remodel 1992 - Lost Arrow/Patagonia Office Remodel 1991 - Emilie Ritchen Elementary School Oxnard 2000 - Named Engineer of the Year for 2000 for Ventura and Santa Barbara Counties. 2002 - Received the California State AIA Award of Merit for Energy Savings at the South Coast Watershed Resource Center 2002 - Citation of Merit for California Savings By Design Energy Efficiency Integration Award 2005 - Savings By Design Energy Efficiency Integration Award of High Honor for Casa Nueva, Santa Barbara County Office Building 2009 - California Community Colleges Chancellor’s Award for most Innovative Energy Design 2010 - Energy Efficiency Green Award for UCSB Tipton Meeting House 2013 - Habitat for Humanity, Canon Perdido St., Santa Barbara. Passive House Certified. 2017 - Museum of Exploration & Innovation (MOXI), 125 State St., Santa Barbara; President's Award 2023 - Preservation Design Award, Hart Park Adobe House Rehabilitation 24S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMES Al Yakel, SET, CFPS Principal-In-Charge, Collings & Associates | Director of Fire and Life Safety | 32 yrs of experience Al brings more than 32 years of experience in numerous fire protection arenas, including system design, code consulting, egress modeling, and as a former Authority Having Jurisdiction with the University of California as a Designated Campus Fire Marshal. Mr. Yakel has extensive experience in the application of the Building and Fire Codes and the requirements of California Title 19 and 24. He has been involved in a wide variety of fire and life safety projects, including the review and approval of plans and specifications for new construction and tenant improvements. Our firm has recently completed several library specific projects which have included all levels of fire protection including fire alarm, fire suppression, life safety and code consulting. We are well versed in the code requirements and needs of the fire service to provide a comprehensive fire protection solution. SELECT EXPERIENCE Mesa Parking Structure Bldg. 18 | UCSB Campus, CA Development of installation level (Shop Drawing’s) fire alarm system design documents, to include automatic detection coverage throughout all elevator landings as required per the provisions of 2022 CFC, 2022 NFPA 72 and the Designated Campus Fire Marshal for a fully approved elevator recall system submittal. V22-020 SLC3 PLARB Bldg. Expansion | Vandenberg SFB, CA | Diatri Building Corp. Installed missing pipe hangers. Provided As-Built Drawings to support field change for the point of connection with the existing 4-inch mail. Completed the Fire Sprinkler System installation in the Control Room and provided updated as-built drawings to show changes as discussed in the field. Completed the GN2 connection to the Fire Sprinkler System riser and test the system both hydrostatically and with air as required by NFPA. Moorpark College Gymnasium Renovation Coordinated underground fire service piping supply routes, pipe sizes and materials, backflow assembly, sprinkler system riser location, fire department connection, and related installation requirements, with Amador Whittle Architects. Provided a complete engineering design of the required fire sprinkler systems for submittal and review by DSA; incorporate DSA plan review comments. Provided a detailed fire sprinkler system installation and performance specification, to accompany construction documents. Galveston (GDSCC) Fire Alarm Replacement | Jet Propulsion Laboratory/Deep Blue Integration, Inc. EDUCATION BSB Business Administration, University of Phoenix, Phoenix, AZ AS Fire Technology, Oxnard College, Oxnard, CA Firefighter I, Allan Hancock College, Santa Maria, CA AFFILIATIONS • National Institute for Certification in Engineering Technologies (NICET) Fire Alarm Systems Level IV, No. 142617 • International Code Council (ICC) Building Inspector No. 0881772- 60 • International Code Council (ICC) Building Inspector No. 0881772- 10 • National Fire Protection Association (NFPA) Professional Member No. 2915186 • International Code Council (ICC) Professional Member • Certified Fire Protection Specialist (CFPS), Certification No. 1140199 2026 BILLING RATES Principal Engineer: $235.00 per hour Senior Engineer: $205.00 per hour Staff Engineer: $175.00 per hour CAD/Drafting Services: $130.00 per hour Administration/Clerical: $99.00 per hour Other: Reproduction: Cost Special Travel & Subsistence: Cost Automobile Mileage: Current IRS Standard Effective January 1, 2026 260 Maple Court, Suite 241 Ventura, California 93003 (805) 658-0003 25S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN Resumes STUDIO 2G ARCHITECTS ff ORGINIZATIONAL CHART & RESUMESSTUDIO 2G ARCHITECTS | MANAGEMENT, TEAM MEMBERS & SUBCONSULTANTS 17S2G | CITY OF SANTA MARIA: ON-CALL DESIGN SERVICES 9700 Business Park Drive #102 Sacramento, CA 95827 JOHN MORENO Vice President and Chief Estimator (916) 925-4000, ext. 102 jlmoreno@sierrawestgroup.com EDUCATION • AA Construction — Butte Community College, Chico, CA • RS Means — Electrical Estimating • RS Means — Mechanical Estimating • CSUS & ARC — Estimating & Construction Management AFFILIATIONS • Association of Professional Estimators — (ASPE) • Construction Specifications Institute — (CSI) • Association of General Contractors — (AGC PROFILE Mr. Moreno offers a diverse range of construction expertise. He brings with him over 26 years of experience in construction and estimating. Specializing in mechanical and electrical work, his participation ranges from the conceptual planning phase through design and final construction. With an extensive knowledge base, Mr. Moreno has a proven record and is known for his ability to work with clients to produce quality results. PROJECT ROLE John Moreno leads the cost estimating efforts for Sierra West Consulting Group, Inc. He works closely with the entire team through each phase of the project to provide a series of successively refined estimates as the project scope is clarified to assure that the project remains within the budget parameters. RELEVANT EXPERIENCE ● Santa Clara County, Civic Parking Garage ADA Improvements, On-Call, San Francisco, CA ● Santa Clara County, Department of Revenue Credit Union, On-Call, San Francisco, CA ● Santa Clara County- Vector Control, On-Call, San Francisco, CA ● County of Sacramento, RCCC Campus Expansion and infrastructure improvements, On-Call, Sacramento, CA ● Stanislaus County, Alternate Emergency Operations Center, On-Call, Modesto, CA ● County of Sacramento, ADA Path of Travel, On-Call, Sacramento, CA ● County of Sacramento, Masterplan update, On-Call, Sacramento, Ca ● County of Sacramento, 700 H Street Bullet Resistant Upgrades, On-Call, Sacramento, CA ● County of Sacramento, Ecology Lane ADA Path of Travel, On-Call, Sacramento, CA ● County of Sacramento, ADA Path of Travel Restroom Upgrades, On-Call, Sacramento, CA ● Napa County, Building site A&B investigation, On-Call Napa, CA ● Stanislaus County, Community Service Facility Life Energy Analysis, On-Call, Modesto, CA ● County of Kern, Animal Services Facility, On-Call, Bakersfield, CA Subconsultants San Luis Obispo City Hall Finance and IT Tenant Improvement Security and ADA Upgrades studio 2G Architects, LLP PROPOSED PROJECT SCHEDULE » 22662255 SSCCPPGG SSLLOO CCiittyy PPaarrkkiinngg GGaarraaggee Page 1 of 2 Page 2 of 2 Proposed Project Schedule studio 2G Architects proposes a structured and efficient schedule that aligns with the City’s anticipated review durations and supports timely decision making at each phase. Our approach is designed to maintain momentum while allowing adequate time for City review and coordination. We will initiate the project immediately upon notice to proceed with a focused kickoff meeting to confirm scope, schedule, communication protocols, and site access. Following kickoff, the work will proceed through the defined phases as outlined in the attached Gantt Chart. Estimated Overall Duration Based on the durations above and inclusion of City review periods, the total project timeline from notice to proceed through completion of bidding is estimated at approximately 9 to 10 months. We estimated construction duration to be approximately 90 days due to phased construction to maintain parking operations, limited work hours, multiple structures (3 sites) and electrical / data complexity. Schedule Approach Our team will actively manage the schedule through regular updates, early identification of potential constraints, and close coordination with the City. We will prioritize timely submittals and clear documentation to support efficient reviews and approvals. This approach ensures a predictable project timeline while maintaining the flexibility needed to respond to project complexities and stakeholder input. Under Construction SLO Parking Structure Task 6 - Construction Support PS&E and Permitting Support PS&E and Permitting Support USDA OIG Tenant Improvement Security and ADA Upgrades studio 2G Architects, LLP DETAILED FEE PROPOSAL BY TASK » 29S2G | PARKING STRUCTURE SAFETY ELEMENT RESEARCH AND DESIGN STUDIO 2G ARCHITECTS ff DETAILED FEE PROPOSAL BY TASK PROFESSIONAL SERVICES FOR PARKING STRUCTURE SAFETY ELEMENTS RESEARCH AND DESIGN DESIGN TEAM COSTS OVERVIEW HOURLY BREAKDOWNS WERE NOT REQUIRED PER THIS RFP, BUT HOURLY BREAKDOWNS CAN BE PROVIDED UPON REQUEST. Conpany and Discipline Task 0 – Project Management Task 1 – Alternatives Analysis Task 2 – 50% PS&E Task 3 – 90% PS&E Task 4 – 100% PS&E + Permitting Task 5 – Final PS&E + Bidding Task 6 – Construction Support Totals studio 2G - Architecture, Project Management $15,931.80 $15,326.26 $14,815.66 $15,730.56 $12,185.50 $4,826.74 $9,517.96 $88,334.48 FTF - Structural -$8,600.00 $14,580.00 $7,640.00 $5,600.00 $2,340.00 $6,540.00 $45,300.00 JMPE - Electrical ---$4,800.00 $3,800.00 $800.00 $1,800.00 $11,200.00 Sierra West - Cost Estimating -$1,500.00 $6,000.00 $4,500.00 $3,000.00 $2,000.00 -$17,000.00 Collings - Fire $840.00 $420.00 $1,005.00 $780.00 $840.00 $225.00 $585.00 $4,695.00 Totals (Not Including Bid Alternates):$16,771.80 $25,846.26 $36,400.66 $33,450.56 $25,425.50 $10,191.74 $18,442.96 $166,529.48 Compliance with On-Call Agreement studio 2G Architects confirms that this proposal complies with the terms and conditions of the executed On-Call Professional Services Agreement with the City of San Luis Obispo. Services are proposed on a lump sum (fixed fee) basis by task, consistent with the scope defined in this specific RFP. Billing rates and detailed hourly breakdowns are readily available and can be provided upon request. Assumptions 1. One contractor will be selected for all three parking structures. 2. Work will be performed concurrently across all three structures; deliverables may be packaged but analyzed individually. 3. Construction duration is assumed to be approximately 16 weeks. 4. Scope is limited to safety improvements at the three identified parking structures. 5. No comprehensive ADA upgrades are included beyond those directly impacted by the proposed safety improvements. 6. Design will be based on available existing documentation and limited field verification. 7. Site visits are limited to approximately 3–4 key milestone visits per structure. 8. Post-tension scanning (e.g., GPR/X-ray) will be provided by others; anchor design is dependent on results. 9. Design assumes no major structural deficiencies requiring significant repair or strengthening beyond localized improvements necessary to support new safety elements. 10. Alternative analysis is limited to the three options identified in the RFP (surface-mounted, parapet-mounted, recessed-mounted). 11. Camera system design will follow precedent established in the Cultural Arts District. 12. Integration of existing camera systems is limited to pay station areas only. 13. No centralized monitoring system is included in the base scope. 14. Existing power and network infrastructure are assumed to have adequate capacity for proposed improvements. 15. Phased construction is assumed to maintain ongoing parking operations. 16. Design is based on a total project construction budget of approximately $1.5 million. 17. Cost estimates are opinions of probable construction cost only. 18. Deliverables are limited to those identified in RFP Section 5 (PS&E, reports, cost estimates, etc.). 19. One formal review cycle per phase is assumed. 20. If unforeseen conditions or regulatory requirements necessitate additional scope, such services will be treated as additional services. Exclusions 1. Structural repairs beyond those required to support new safety systems. 2. Full structural retrofit or seismic upgrades. 3. Hazardous materials investigation, testing, or abatement (e.g., asbestos, lead). 4. Destructive testing, coring, or intrusive investigation. 5. Detailed IT/network design beyond a diagrammatic or performance-based level. 6. Procurement, installation, or commissioning of camera/security systems. 7. Software, monitoring systems, or data storage design. 8. Utility upgrades, including new electrical service, transformers, or major infrastructure improvements. 9. Full-time construction observation or inspection. 10. Construction means, methods, techniques, sequencing, or safety. 11. Contractor schedule control, delays, or claims. 12. Permit, plan check, or agency fees. 13. Redesign or additional documentation resulting from agency or client changes beyond the assumed single review cycle. 14. Environmental review or documentation (e.g., CEQA), if triggered. 15. Public outreach, stakeholder engagement, or community meetings beyond those specifically identified in the scope. 16. Grant applications, funding assistance, or financial procurement services. 17. Design for future system expansion beyond what is required for the current project scope.