HomeMy WebLinkAboutWO 117738Work Order ID # 117738
Work Order Category
Corrective
Work Order Description
RECONSTRUCT SIDEWALK
Work Order Priority
Medium (2 to 5 days)
Supervisor
KEAVNEY, GARY J
Projected Start Date
5/20/2014 2:26:23 PM
Projected Finish Date
Actual Start Date
Actual Finish Date
5/21/2014 3:36:18 PM
Work Order X Coordinate
5764470.642
Work Order Y Coordinate
2304383.347
Work Order Z Coordinate
Facility Id
Shop Field Value
STREETS
Work Order Initiated By Name
KLINE, JEFFERY J
Work Order Requested By Name
Date & Time Work Order Initiated
5/20/2014 2:26:23 PM
O Cancelled?
O Cancelled By
O Cancel Reason
O Cancel Date
Source Work Order ID #
Work Order Repeat Cycle Type
NEVER
Work Order Repeat Cycle #
6
Work Order Repeat Cycle Unit
M
Cycle Schedule Date
Work Order Cycle From Date
Total Work Order Cost
$4,649.96
Total Of Work Order Labor Costs
$2,991.77
Total Of Work Order Material Costs
$290.00
Total Of Work Order Equipment Costs
$1,368.19
General Work Order Account Number
Work Order General Location
228 n chorro
,Work Order Address
204 N CHORRO
[Work Order Comments
By KLINE, JEFFERY J: 5/20/2014 2:33:16 PM
19/14 marked in white paint (usa) ticket# 106568
KLINE, JEFFERY J: 5/20/2014 2:35:35 PM
16/14 saw cut both locations.
KLINE, JEFFERY J: 5/20/2014 2:37:59 PM
19/14 tore out concrete grubbed, formed and based at
KLINE, JEFFERY J: 5/20/2014 2:40:34 PM
4 poured back concrete at both locations.
By KLINE, JEFFERY J: 5/21/2014 3:34:30 PM
05/21/14 stripped forms and back filled at both locations.
Work Order Instructions
Employee Name That Closed Work Order
KLINE, JEFFERY J
Date Work Order Was Printed
6/15/2026 12:34:04 PM
Employee Name From Submit To
KLINE, JEFFERY J
Date Work Order Was Submitted
5/20/2014 2:28:41 PM
Work Order Status Value
Closed
Work Completed By Employee Name
Date Work Order Closed
5/21/2014 3:36:27 PM
otal Entities on Work Order
11