HomeMy WebLinkAboutItem 6f - Authorization to apply for Grant Funding through Caltrans For Preparation of a Citywide Sae Routes to Schools Plan Item 6f
Department: Public Works
Cost Center: 5010
For Agenda of: 10/6/2026
Placement: Consent
Estimated Time: N/A
FROM: Aaron Floyd, Public Works & Utilities Director
Prepared By: Jennifer Rice, Active Transportation Manager
SUBJECT: AUTHORIZATION TO APPLY FOR GRANT FUNDING THROUGH THE
CALTRANS SUSTAINABLE COMMUNITIES PLANNING GRANT
PROGRAM FOR PREPARATION OF A CITYWIDE SAFE ROUTES TO
SCHOOL PLAN
RECOMMENDATION
1. Authorize staff to prepare and submit an application for the Caltrans Sustainable
Communities grant program, including a request of up to $300,000 to fund
preparation of a Citywide Safe Routes to School Plan; and,
2. Approve the use of up to $50,000 in Active Transportation Plan Implementation
capital project account (Specification No. 2000608) funding as the required local
match funds for this grant pursuit; and,
3. Authorize the Finance Director to appropriate grant funds and approve a budget
amendment to reflect received grant funds, if awarded;
4. Authorize the City Manager and City Attorney, or their respective designees, to act
as agents to conduct all negotiations, execute and submit all grant documents
including, but not limited to, applications, agreements, and payment requests
which may be necessary for the completion of the aforementioned project; and,
5. Adopt a Draft Resolution entitled, “A Resolution of the City Council of San Luis
Obispo, California, approving the application for grant funding through the Caltrans
Sustainable Communities Grant Program to fund preparation of a Citywide Safe
Routes to School Plan.”
REPORT-IN-BRIEF
In September 2025, the Active Transportation Committee (ATC) established a Safe
Routes to School (SRTS) subcommittee tasked with providing updates and
recommendations to the ATC on SRTS planning, funding, and outreach ahead of the
ATC’s review and recommended prioritization of projects and programs for the 2027 –29
Financial Plan. The committee has expressed a clear intent to identify preparation of a
Citywide SRTS Plan as a high-priority recommendation for funding.
In parallel, staff continually monitor upcoming grant opportunities to identify funding
sources that may align with current or future projects and planning efforts. Recently,
Caltrans released the FY 2027-28 Sustainable Transportation Planning Grant application,
Page 89 of 274
Item 6f
which includes Sustainable Communities Grants. This program presents a strong
opportunity to secure funding to support preparation of a Citywide SRTS Plan ; therefore,
staff are recommending Council approval for the City to submit an application seeking up
to $300,000 in grant funding. Staff are requesting authorization for up to $50,000 to
provide flexibility to meet the final local match requirement, which will depend on the final
grant award amount. The minimum match required for the full $300,000 grant request is
$34,410. Staff estimate a total budget of up to $350,000 would be appropriate and
sufficient to fund the full scope of work with a minor contingency.
Caltrans’ announcement of grant awards is anticipated to occur during this current fiscal
year, in the spring of 2027 with project activities beginning in the summer. If the grant is
awarded, this effort will be formally incorporated into the 2027–29 Financial Plan work
program, including the allocation of staff resources to manage the project. Budget to fund
the $50,000 local match is identified in the current fiscal year, as the grants are anticipated
to be awarded this spring. There is currently available in the Active Transportation Plan
Implementation capital project account (No. 2000608), and in addition, the Capital
Improvement Plan identifies a potential future annual allocation in out-years 2027-29.
If secured, funding would allow staff to hire a professional transportation
planning/engineering consultant via a Request for Proposals (RFP) to lead planning
activities including community and stakeholder engagement and collaboration, compiling
background information, conducting walk and bike audits, identifying safety and
accessibility barriers, mapping and prioritizing these improvement opportunities. The
planned scope of work will include all K-12 public schools within the City limits as well as
Los Ranchos Elementary.
POLICY CONTEXT
The Active Transportation Plan (ATP) includes a goal1 to develop a focused Safe Routes
to School Improvement Plan for all K-12 schools in San Luis Obispo to reduce safety and
mobility barriers for walking and biking to school. Additionally, the Vision Zero Safe
Streets Action Plan reinforces this goal, including it as a Safer Streets (Engineering)
Proactive Safety Recommendation.2
In 2017, the City Council adopted the Bishop’s Peak and Pacheco Elementary Schools
Safe Routes to School Plan which include a needs assessment and transportation
improvement and enforcement recommendations. The City has no other adopted single
or citywide school safe routes to school plans.
1 Goal 2.5 on page 25 of the Active Transportation Plan: Safe Routes to School. Develop a focused Safe
Routes to School Improvement Plan for all K-12 schools in San Luis Obispo to reduce safety and mobility
barriers to walking and biking to school.
2 Safer Streets (Engineering) Proactive Safety Recommendation 7 on page 128 of the Visi on Zero Safe
Streets Action Plan: Safe Routes to Schools Planning: As recommended in the City’s Active Transportation
Plan, prepare a focused Safe Routes to School Improvement Plan for each K-12 school within the city
limits, focusing on strategies that im prove safety for vulnerable road users and reduce barriers to walking
and biking to school.
Page 90 of 274
Item 6f
Per Section 740 of the City’s Financial Management Manual, staff is required to obtain
Council approval prior to applying for grant applications over $5,000.
DISCUSSION
Background
Consistent with the goals of the Active Transportation Plan (ATP), the ATC has identified
preparation of a Citywide SRTS Plan as a priority. However, due to other projects and
programs also identified as high priorities during development of the current Financial
Plan, funding for an SRTS planning effort was not included in the current 2025 -27 budget.
Further staff did not have sufficient capacity during this current work program to begin this
planning work in-house. In response to these constraints, community members and ATC
members expressed interest in contributing their own time to advance preliminary tasks
to lay the groundwork for a future SRTS planning effort, including conducting research,
early public engagement, and identifying potential future funding opportunities. This
interest showed that the community wants this important work to continue and led the
ATC to consider forming a subcommittee to help move it forward.
At the September 18, 2025 ATC meeting, the committee established a SRTS
subcommittee consisting of three members with staff providing support. The
subcommittee was tasked with providing updates and recommendations to the ATC on
SRTS planning, funding, and outreach. Its work is scheduled to conclude at the end of
November 2026, ahead of the ATC’s review and prioritization of projects and programs
for the 2027–29 Financial Plan. Since the fall, the ATC has informally expressed an co
intent to identify preparation of a Citywide SRTS Plan as a high -priority recommendation
for funding.
Since forming in September 2025, the subcommittee, with support from community
volunteers, including the Cal Poly Urbanists Club, has made substantial progress,
including:
Safe Routes to School and Active Transportation Plan Review: Research
Report: Under the guidance of the subcommittee with staff support, the Cal Poly
Urbanists Club prepared a research report comparing SRTS plans from mid -sized
California cities and other notable examples to help identify a suitable format for a
citywide SRTS approach. After review and as recommended by the subcommittee,
at the July 16, 2026 meeting, the ATC expressed consensus during their
deliberation that the City of Davis model could be a strong fit for San Luis Obispo.
Rather than producing a standalone SRTS Plan, Davis includes a Safe Routes to
School Bicycling and Walking Audit Report as an appendix to its bicycle action
plan. Each chapter focuses on an individual elementary or junior high school and
includes review of existing conditions, a prioritized list of recommended
improvement projects, and maps of existing and planned improvements, such as
suggested walking and biking routes and bicycle parking.
CL Smith Elementary Preliminary SRTS Audit and Findings: To test an
approach similar to Davis, the subcommittee, alongside staff and community
Page 91 of 274
Item 6f
volunteers, developed a draft SRTS audit and findings report for C L Smith
Elementary School. This effort involved coordinating with school and community
stakeholders, gathering background and site information, completing an in-person
walking and biking audit, and mapping existing and planned improvements. The
resulting materials mirror the type of content compiled for each school in the Davis
report.
Again, during the July 16, 2026 meeting, the ATC shared consensus during deliberation
for this approach as piloted at CL Smith Elementary and expressed support for continuing
citywide SRTS planning efforts as capacity allows, with ongoing involvement from
volunteers and interested community members.
Caltrans Sustainable Communities Grant
Caltrans has released the FY 2027-28 Sustainable Transportation Planning Grant
Application Guide and Call for Applications, which includes Sustainable Communities
Grants (approximately $30.4 million) to encourage local and regional planning that
supports State goals, implements Regional Transportation Plan (RTP) Sustainable
Communities Strategies (SCS) (where applicable), and ultimately achieves the State’s
greenhouse gas (GHG) reduction target of 40 and 85 percent below 1990 levels by 2030
and 2045, respectively. The program requires a minimum of 11.47% match of local funds.
This program presents a strong opportunity to secure funding to support preparation of a
Citywide SRTS Plan and therefore staff are recommending Council approval to submit an
application seeking up to $300,000 in grant funding.
The Sustainable Transportation Planning Grant opportunity allows the City to advance a
priority identified by the ATC while leveraging outside funding and minimizing the amount
of local funding needed to complete the planning effort. It should be noted that typically,
staff recommends pursuing grant opportunities for projects already included in the City
Council–approved work plan. However, the timing of this grant application aligns well with
the proposed planning effort, should it be prioritized and incorporated into the work
program, and would allow staff to continue making progress on this initiative.
If secured, this funding would allow staff to hire a professional transportation
planning/engineering consultant to lead this planning effort in FY2027-29, with continued
collaboration from staff, the ATC, school representatives, and community members.
Award of the grant is anticipated to be announced in the spring of 2027, during this current
fiscal year, while planning activities would begin in the summer.
Planning activities would include community and stakeholder engagement and
collaboration, compiling background and layout information, conducting walk and bike
field assessments to identify walking and bicycling condit ions, identifying safety and
accessibility barriers, mapping and prioritizing these improvement opportunities. The
planned scope of work will include all K-12 public schools3 within the City limits as well as
3 Schools planned to be included are: Bishop Peak Elementary, Hawthorne Elementary, Los Ranchos
Elementary, Pacheco Elementary, Sinsheimer Elementary, CL Smith Elem entary, Teach Elementary,
Laguna Middle School, San Luis High School, and Pacific Beach High School
Page 92 of 274
Item 6f
Los Ranchos Elementary4.
The project’s anticipated timeframe is as follows:
Task Anticipated Schedule
Submit Sustainable Communities Grant Application By October 9, 2026
Grant Award and Contract Administration Spring 2027
Request for Proposals (RFP) for Consultant
Services Summer 2027
Begin Planning and Public Outreach Fall 2027
Final Citywide Safe Routes to School Plan Winter 2029
The schedule above is preliminary and dependent on grant administration requirements
and resources. Per the grant application guidelines, awarded funding must b e spent by
June 30, 2030.
Previous Council or Advisory Body Action
September 18, 2025, Active Transportation Committee (ATC) meeting: ATC established
a three-member Safe Routes to School (SRTS) subcommittee.
July 16, 2026, Active Transportation Committee (ATC) meeting: SRTS subcommittee
presented an update to the broader ATC and received support on initial progress and
approach.
September 17, 2026, Active Transportation Committee: ATC supported and
recommended Council’s consideration of applying for a Caltrans Sustainable
Communities Grant.
Public Engagement
SRTS subcommittee members have engaged with various community volunteers to
support early planning activities, particularly parents and staff of the CL Smith Elementary
School.
If the project receives funding, future planning will build on these established stakeholder
partnerships and include multiple opportunities for close coordination with local school
representatives and the public, such as walk and bike audits for each school and surveys
of key walking and biking barriers and opportunities for improvement.
CONCURRENCE
The Public Works Department, Finance Department, and City Administration have
reviewed this staff report and concur with its contents.
4 While outside the City Limits, Los Ranchos Elementary attendance boundaries include several
neighborhoods within the City, including Avila Ranch, Righetti Ranch, and the Arbor neighborhoods.
Page 93 of 274
Item 6f
ENVIRONMENTAL REVIEW
There is no environmental review required for grant submittals. The California
Environmental Quality Act (CEQA) does not apply to the recommended action in this
report because the action does not constitute a “Pro ject” under CEQA Guidelines Sec.
15378. The appropriate level of CEQA review will be prepared for the recommendations
and actions that are ultimately identified in a forthcoming SRTS Plan.
FISCAL IMPACT
Budgeted: Yes Budget Year: 2027-28
Funding Identified: Yes
Fiscal Analysis:
Based on a proposed grant request for up to $300,000, staff is proposing to earmark up
to $50,000 in local funds to meet the local match requirement for this grant program. The
grant requires a minimum local match of 11.47%, ($34,410). Staff estimate a total budget
of up to $350,000 would be appropriate and sufficient to fund the full scope of work with
a minor contingency.
Because the grant is expected to be announced in the spring of 2027, staff are requesting
allocation of funds from this current fiscal year to be earmarked for the match requirement.
Funding is available in the Active Transportation Plan Implementation capital project
account (No. 2000608) to fund this local match of up to $50,000. There is currently
$100,000 available from the CIP Capital Outlay – Local Revenue Measure (LRM) funding
source and the 10-year Capital Improvement Plan identifies a potential future annual
allocation of another $200,000 per year in out-years 2027-29.
If the grant is awarded, the funds from this current fiscal year will be added to a new task
within the Active Transportation Plan Implementation capital project account (No.
2000608). Additionally, this work effort will be incorporated into the recommended 2027–
29 Financial Plan, including the allocation of staff resources to manage the project and
oversee the consultant.
Upon completion of the SRTS Plan, projects would likely be implemented through a
combination of approaches. Smaller improvements could be incorporated into ann ual
paving projects or funded as standalone projects through the Active Transportation Plan
Implementation or Vision Zero accounts. Larger projects would need to be considered
through future budgeting and Capital Improvement Planning processes or potential future
grant opportunities.
Funding Sources Total Budget
Available
Total Budget
Available Total Balance
Page 94 of 274
Item 6f
(Active
Transportation Plan
Implementation)
(NEW Task 05 –
Safe Routes to
School Plan)
CIP – Capital Outlay Fund
- LRM
$100,000 $0 $100,000
State: Sustainable
Communities Grant*
$0 $300,000* $300,000
Current Funding Request ($50,000) $50,000 $0
Total $50,000 $350,000* $400,000
*If grant application is successful.
ALTERNATIVES
Deny authorization to apply for grant funding. The City Council could decide not to
authorize staff to apply for the Caltrans Sustainable Communities Grant at this time.
Under this scenario, staff would likely request local funding to support this SRTS planning
effort as part of the FY 2027-29 Financial Plan, assuming the ATC identifies preparation
of a Citywide SRTS Plan as one of the committee’s top priority recommendations for the
2027–29 Financial Plan (the ATC will meet to identify budget priorities in November
2026). Council could then consider the funding request within the broader context of all
other proposed budget priorities and capital projects in the next financial plan.
Alternatively, if the City Council does not authorize staff to pursue this grant funding, and
local funding for SRTS planning is ultimately not approved as part of the 2027–29
Financial Plan, preparation of a full Citywide SRTS plan would not be feasible at this time.
If SRTS planning remains a high priority based on ATC and community input, but no
funding for outside consultant support is available, it is possible that focused SRTS plans
could be prepared incrementally using a combination of in -house staff and volunteer
support. However, under this approach, it would take several years to complete this
planning, as staffing resources can likely support planning for only one-to-two schools
each year.
The City’s Active Transportation Plan (ATP) is also approaching an appropriate timeframe
for an update, and staff are targeting the 2029 –31 work program. If funding and staffing
resources cannot support SRTS planning as part of the 2027 -29 work program, the 2029-
31 Financial Plan may present another opportunity to pursue funding for this effort. Under
this scenario, there may be additional opportunities to pursue outside grant funding in the
coming years.
ATTACHMENTS
A - Draft Resolution Approving the Application for Caltrans Sustainable Transportation
Planning Grant Program
Page 95 of 274
Page 96 of 274
R ______
RESOLUTION NO. _____ (2026 SERIES)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN LUIS
OBISPO, CALIFORNIA, APPROVING THE APPLICATION FOR GRANT
FUNDING THROUGH THE CALTRANS SUSTAINABLE COMMUNITIES
GRANT PROGRAM TO FUND PREPARATION OF A CITYWIDE SAFE
ROUTES TO SCHOOL PLAN
WHEREAS, Caltrans released the FY 2027-28 Sustainable Transportation
Planning Grant Application Guide and Call for Applications includ ing Sustainable
Communities Grants with approximately $30.4 million; and
WHEREAS, the Sustainable Transportation Planning Grant program encourages
local and regional planning that supports state goals, implements Regional Transportation
Plan (RTP) Sustainable Communities Strategies (SCS) (where applicable), and to
ultimately achieve the State’s greenhouse gas (GHG) reduction target of 40 and 85
percent below 1990 levels by 2030 and 2045, respectively; and
WHEREAS, the City of San Luis Obispo 2021 Active Transportation Plan (ATP)
includes a goal to develop a focused Safe Routes to School Improvement Plan for all K -
12 schools in San Luis Obispo to reduce safety and mobility barriers to walking and biking
to school; and
WHEREAS, the 2026 Vision Zero, San Luis Obispo’s Safe Streets Action Plan
includes the Safer Streets (Engineering) Proactive Safety Recommendation to prepare a
focused Safe Routes to School Improvement Plan for each K -12 school within the city
limits, focusing on strategies that improve safety for vulnerable road users and reduce
barriers to walking and biking to school; and
WHEREAS, the Sustainable Communities Grant requires an 11.7% match of local
funds.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of San Luis
Obispo as follows:
SECTION 1. Authorizes staff to prepare and submit an application for the
Sustainable Communities Grant of up to $300,000 for preparation of a Citywide Safe
Routes to School Plan.
SECTION 2. Approves the use of up to $ 50,000 in local Active Transportation
Plan Implementation Project Account funding as matching funds for this grant, if awarded.
SECTION 3. Authorizes the Finance Director to appropriate grant funds and
approve a budget amendment to reflect received grant funds, if awarded.
Page 97 of 274
Resolution No. _____ (2026 Series) Page 2
R ______
SECTION 4. Authorizes the City Manager and City Attorney, or their respective
designees, to act as agents to conduct all negotiations, execute and submit all grant
documents including, but not limited to, applications, agreements, and payment requests
which may be necessary for the completion of the aforementioned project.
Upon motion of Council Member ___________, seconded by Council Member
___________, and on the following roll call vote:
AYES:
NOES:
ABSENT:
The foregoing resolution was adopted this _____ day of _______________ 20 26.
___________________________
Mayor Erica A. Stewart
ATTEST:
______________________
Teresa Purrington
City Clerk
APPROVED AS TO FORM:
______________________
J. Christine Dietrick
City Attorney
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the
City of San Luis Obispo, California, on ______________________.
___________________________
Teresa Purrington
City Clerk