HomeMy WebLinkAboutCPUC Resolution T-17852 (Adopted)Resolution T-17852 Date of Issuance: October 21, 2024
CD/CJ2
544078450 1
PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Communications Division RESOLUTION T-17852
Broadband Regional Initiatives Branch October 17, 2024
R E S O L U T I O N
RESOLUTION T-17852: Approves seven applications for grants for up to $18,011,261
from the Last Mile Federal Funding Account in San Luis Obispo County, providing
service to 2,754 unserved locations.
I. SUMMARY
This Resolution recommends approval of seven Last Mile Federal Funding Account
grants in the amount of up to $18,011,261.
This Resolution is part of the seventh package of Resolutions approving grants to
Federal Funding Account applicants for broadband infrastructure projects serving
unserved areas in California. Subsequent Resolutions will be presented for Commission
vote as Communications Division Staff completes its analyses of applications.
The seven projects in this Resolution propose to make investments bringing the social,
economic, civic, and public safety benefits of high-speed broadband to 2,754 unserved
locations and an estimated unserved population of 8,641 in San Luis Obispo County. An
estimated total population of 23,514 people will benefit from these investments as
households and businesses that already have service in these communities will benefit
from greater customer choice in the broadband market. The last mile connections
funded by these grants build upon the state-owned open-access Middle-Mile
Broadband Initiative.
Staff recommends grant awards to three entities (listed in the order in which they
appear in this Resolution): Astound, the California Broadband Alliance, and the City of
San Luis Obispo.
Astound is an independent telecommunications company offering service in multiple
California counties. The California Broadband Alliance is a 501(c)3 non-profit
organization working on broadband access in the Central Coast that has partnered with
the independent telecommunications company Surfnet Communications to apply to the
Resolution T-17852
CD/CJ2
2
Federal Funding Account. The City of San Luis Obispo is an incorporated city located in
San Luis Obispo County.
Staff recommends the following seven grant applications for Commission approval as
shown in Table 1 below. Maps and summaries associated with each project are in the
appendices.
Table 1: Summary of Grant Funding
Applicant Project Name
Estimated
Unserved
Locations
Estimated
Unserved
Units
Estimated
Unserved
Population
Estimated
Benefitting
Population
Awarded
Amount
San Luis Obispo
Astound Atascadero –
Paso Robles 201 252 800 2,498 $6,794,215
Surfnet Branch 856 844 2,087 2,087 $2,093,539
Surfnet Corbett
Canyon 273 443 989 2,168 $1,280,937
Surfnet Old Oak Park 370 482 1,143 1,688 $1,550,572
City of San
Luis Obispo
San Luis
Obispo
Affordable
Broadband
Network
490 966 2,011 13,423 $4,863,799
Surfnet Shandon 443 424 1,281 1,318 $722,821
Surfnet Whitley
Gardens 121 131 330 332 $705,378
Total 2,754 3,542 8,641 23,514 $18,011,261
II. BACKGROUND
California’s multi-year broadband investment package established the last mile Federal
Funding Account as part of the Budget Act of 2021 and Senate Bill 1561 and invested
$2 billion in the program over multiple years. The Federal Funding Account funds the
construction of last mile broadband infrastructure projects in unserved areas of
California. The Federal Funding Account encourages the deployment of broadband
throughout the State to enable the public to access internet-based safety applications,
telehealth services, emergency services, and to allow first responders to communicate
with each other and collaborate during emergencies.
1 Statute 2021, Chapters 84 and 112.
Resolution T-17852
CD/CJ2
3
On April 21, 2022, the Commission issued Decision (D.) 22-04-055, Decision Adopting
Federal Funding Account Rules. The rules and guidelines adopted in that decision
included, among other items, the following: rules about projects to benefit
Environmental and Social Justice Communities, affordable offers, five and ten-year
price commitments, low-cost plans, project eligibility, application requirements,
application objections, implementation of Public Utilities Code section 281(n) allocating
funding between “rural counties” and “urban counties,” a process to reimburse
grantees, a ministerial review process whereby Communications Division Staff may
approve certain projects, and minimum performance standards for grantees.
The Federal Funding Account D. 22-04-055 includes requirements and preference for a
number of affordability requirements including:
• Participation in the Affordable Connectivity Program or access to a “broad-
based affordability program.” Given that the Affordable Connectivity Program
has lapsed grantees must participate in a successor program when identified by
the Commission.
• A five-year price commitment, and preference for a ten-year commitment.
• Preference for a low-cost plan that is $40/month or less and provides speeds of
at least 50 Megabits per second (Mbps) down and 20 Megabits per second up.
• Preference for participation in the California and/or federal Lifeline programs
(which may include bundled voice and broadband offerings).
Applications that committed to provide voice service and participate in LifeLine,
consistent with the requirement to serve customers in the project area at prices not
exceeding those in the application for five years after project completion, must provide
voice service and participate in LifeLine for five years after project completion. In
providing grant funding to projects the Commission is validating the need for and the
state’s investment in the provision of communications service, including voice and
programs supporting affordability like LifeLine, for the life of the infrastructure.
The Federal Funding Account Decision and Appendix specify additional consideration
for disadvantaged communities or Environmental and Social Justice communities.2 The
Commission made available on the Federal Funding Account Public Map,3 the
2 The Commission Environmental and Social Justice Action plan includes definitions and data indicators
for disadvantaged or Environmental and Social Justice communities including Disadvantaged
Communities defined by the California Environmental Protection Agency (CalEPA) and low-income
households defined as household incomes below 80 percent of the area median income. The
Commission’s Environmental and Social Justice Action Plan 2.0 is available at:
https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/news-and-outreach/documents/news-
office/key-issues/esj/esj-action-plan-v2jw.pdf
3 The Federal Funding Account Public Map is available at: https://federalfundingaccountmap.vetro.io/
Resolution T-17852
CD/CJ2
4
Applicant Tool,4 and data downloads locations and census blocks meeting these
definitions.5 A grant application window was opened on June 30, 2023, and closed at
4 p.m. on September 29, 2023; 484 applications were submitted. Application summaries
were posted on October 23, 2023, and a 28-day objection period closed on
November 20, 2023. Responses to objections were received until December 20, 2023.
Applications were holistically evaluated: required and supporting documentation and
the merits of the applications were compared and assessed on a county basis. Following
an initial analysis, Staff sent a data request to applicants and requested additional
information. Staff’s holistic evaluation included project engineering, technical feasibility
and design, financial viability, cost, applicant capacity, and community need, among
other factors. Staff assessed how to manage overlapping applications and applications
planning to include some already-served areas in their project area.6
Staff also evaluated how applications and groups of applications compared to
competing applications in the same county.
The specific locations to be provided service for a given project will be updated and
reconciled with the Broadband Serviceable Location Fabric after detailed engineering
and project design, and the grant amount may be reduced consistent with a reduction in
the number of locations. The Federal Funding Account award will not fund locations
supported by a federal broadband program with Capital Project Fund monies.7
4 Registration for the Federal Funding Account Applicant Tool is available at: FFA Applicant Tool
Registration
5 Disadvantaged or Environmental and Social Justice communities and individual locations, for purposes
of the Federal Funding Account, include those in Disadvantaged Communities census tracts as defined
by CalEPA and low-income areas in which the census block group median household income is less than
or equal to 80 percent of the higher of the county or state average. This data is available for download on
the Federal Funding Account Public Map page (visited June 13, 2024),
https://www.cpuc.ca.gov/industries-and-topics/internet-and-phone/broadband-implementation-for-
california/last-mile-federal-funding-account/ffa-public-map and the Federal Funding Account
Application Resources Page (visited June 13, 2024), https://www.cpuc.ca.gov/industries-and-
topics/internet-and-phone/broadband-implementation-for-california/last-mile-federal-funding-
account/ffa-application-resources-page .
6 D.22-04-055 states that “households and businesses with an identified need for additional broadband
infrastructure do not have to be the only ones in the service area served by an eligible broadband
infrastructure project. Indeed, serving these households and businesses may require a holistic approach
that provides service to a wider area, for example, in order to make ongoing service of certain households
or businesses within the service area economical.”
7 Federal broadband programs include the Connect America Fund II (CAFII), Community Connects Grant Program
(CCGP), Enhanced Alternative Connect America Cost Model (EACACM), Rural Digital Opportunity Fund
(RDOF), Rural E-Connectivity Program (REP), Tribal Broadband Connectivity Program (TBCP), and Telephone
Loan Program (TLP).
Resolution T-17852
CD/CJ2
5
III. APPLICATION SUMMARIES, DISCUSSION, AND RECOMMENDATIONS
San Luis Obispo Summary
The allocation for projects in San Luis Obispo County in D. 22-04-005 is $22,346,936.
This Resolution recommends awarding five grants to the California Broadband
Alliance, which has partnered with the applicant Surfnet Communications, one grant to
Astound, and one grant to City of San Luis Obispo for projects in San Luis Obispo
County. The recommended grant amount for projects in San Luis Obispo County is
$18,011,261, which leaves a remainder of $4,335,675 of the allocation for San Luis
Obispo County.
San Luis Obispo County Awards
1. Astound, Atascadero-Paso Robles
Staff recommends the Commission approve Astound’s application for a grant of up to
$6,794,215 for the Atascadero-Paso Robles project.
The Atascadero-Paso Robles project proposes to serve an estimated 201 unserved
locations based on a March 2024 supplemental application filing. There are
approximately 252 unserved units in the project area. An estimated unserved
population of 800 would be offered service. An estimated total population of 2,498 will
benefit from these investments in the communities of City of Atascadero and City of
Paso Robles. The last-mile fiber project will provide up to 2,000/2,000 Mbps service to
consumers.
Astound will deploy approximately 33 miles of last-mile fiber. The network
infrastructure will be 16 percent underground.
The Atascadero-Paso Robles project will benefit disadvantaged or Environmental and
Social Justice communities; 49 percent of the unserved locations are in low-income
communities. Astound will provide a low-cost plan that meets the requirements in D.
22-04-055, Section 3, and has committed to maintaining the price of that plan for at least
ten years.
The proposed project will cost an estimated $6,794,215, of which the Federal Funding
Account will fund approximately 100 percent of costs.
Staff determined that the applicant and the project are financially viable, and the
applicant’s engineering meets the program standards. The applicant demonstrated the
Resolution T-17852
CD/CJ2
6
administrative, technical, and operational capacity to provide broadband service at the
scale of this project.
This application received one objection. Staff verified that the application seeks funding
only for unserved locations within the project area and that partial funding for fixed
infrastructure through served areas is necessary to reach the unserved locations. The
project area of Atascadero-Paso Robles was not modified in response to objections; the
Federal Final Rule8 and D.22-04-0559 allow projects serving unserved locations to
include served locations to make the project viable.
No Federal Funding Account Public Map comments were submitted in San Luis Obispo
County.10 Atascadero-Paso Robles project area’s unserved locations were evaluated in
light of the updated Federal Communications Commission and Federal Funding
Account unserved data (as of June 30, 2023). In response to objections and this data, the
number of unserved locations is unchanged at 201, the project area is unchanged, and
the total grant amount is unchanged. The specific locations to be provided service will
be updated and reconciled with the Broadband Serviceable Location Fabric after
detailed engineering and project design, and the grant amount may be reduced
consistent with a reduction in the number of locations.
The following submitted letters of support for this application: City of Atascadero, City
of Paso Robles, Broadband Consortium of the Pacific Coast, Atascadero Chamber of
Commerce, REACH the Regional Economic Action Coalition.
The proposed project provides the public safety benefits of reliable broadband
infrastructure. This project will connect to Astound’s middle mile infrastructure.
Based on the information received, the Commission’s Energy Division has determined
that this project has not met the requirements for a CEQA categorial exemption at this
time. Astound must comply with the CEQA requirements discussed in the appendices.
If Astound provides additional documentation sufficient to justify a staff determination
of CEQA exemption, then the project can be exempted by letter from the
Communications Division Director or the director’s delegate or designee.
Astound and the Atascadero-Paso Robles project comply with all requirements for
approval in D. 22-04-055. The Communications Division recommends that the
8 Department of the Treasury, Final Rule, Coronavirus State and Local Fiscal Recovery Funds, 31 C.F.R.
Part 35, 87 FR 4338-4454 (January 27, 2022) (Final Rule), available at:
https://www.federalregister.gov/documents/2022/01/27/2022-00292/coronavirus-state-and-local-
fiscal-recovery-funds.
9 D.22-04-055, Appendix A, Section 2, p. A-5.
10 See Federal Funding Account Public Map, https://federalfundingaccountmap.vetro.io/ (visited
August 19, 2024).
Resolution T-17852
CD/CJ2
7
Commission approve the application of Astound for a grant of up to $6,794,215 for the
Atascadero-Paso Robles project.
2. Surfnet Communications, Branch
Staff recommends the Commission approve Surfnet Communications’ application for a
grant of up to $2,093,539 to the California Broadband Alliance for the Branch project.
The Branch project proposes to serve an estimated 856 unserved locations based on a
March 2024 supplemental application filing. There are approximately 844 unserved
units in the project area. An estimated unserved population of 2,087 would be offered
service. An estimated total population of 2,087 will benefit from these investments in
the community of Branch. The last-mile fiber project will provide up to 1000 Mbps/1000
Mbps service to consumers.
The California Broadband Alliance will be the grant recipient and owner of the project
infrastructure. The California Broadband Alliance will enter into an agreement with the
applicant, Surfnet Communications, who will manage the project construction. After
the project is complete, Surfnet Communications will lease access to the infrastructure
from the California Broadband Alliance.
Surfnet Communications will deploy approximately two miles of last-mile fiber and 25
of middle mile and backhaul fiber. The network infrastructure will be 5 percent
underground.
Surfnet Communications will provide a low-cost plan that meets the requirements in D.
22-04-055, Section 3, and has committed to maintaining the price of that plan for at least
ten years.
The proposed project will cost an estimated $2,093,539 of which the Federal Funding
Account will fund approximately 100 percent of costs.
Staff determined that the applicant and the project are financially viable, and the
applicant’s engineering meets the program standards. The applicant demonstrated the
administrative, technical, and operational capacity to provide broadband service at the
scale of this project.
This application received no objections.
Resolution T-17852
CD/CJ2
8
No Federal Funding Account Public Map comments were submitted in San Luis Obispo
County.11 The Branch project area’s unserved locations were evaluated in light of the
updated Federal Communications Commission and Federal Funding Account unserved
data (as of June 30, 2023). In response to this data, the number of unserved locations is
unchanged at 856, the project area is unchanged, and the total grant amount is
unchanged. The specific locations to be provided service will be updated and reconciled
with the Broadband Serviceable Location Fabric after detailed engineering and project
design, and the grant amount may be reduced consistent with a reduction in the
number of locations.
One letter of support was submitted for this application from the Broadband
Consortium of the Pacific Coast.
The proposed project provides the public safety benefits of reliable broadband
infrastructure. This project will connect to the open-access Middle-Mile Broadband
Initiative. This project includes approximately 25 miles of open-access middle-mile fiber
and backhaul fiber, and to connect them to the Middle-Mile Broadband Initiative.
Based on the information received, the Commission’s Energy Division has determined
that this project has not met the requirements for a CEQA categorial exemption at this
time. Surfnet Communications and the California Broadband Alliance must comply
with the CEQA requirements discussed in the appendices. If Surfnet Communications
or the California Broadband Alliance provides additional documentation sufficient to
justify a staff determination of CEQA exemption, then the project can be exempted by
letter from the Communications Division Director or the director’s delegate or designee.
The California Broadband Alliance, Surfnet Communications, and the Branch project
comply with all requirements for approval in D. 22-04-055. The Communications
Division recommends that the Commission approve the application of Surfnet
Communications for a grant of up to $2,093,539 to the California Broadband Alliance for
the Branch project.
3. Surfnet Communications, Corbett Canyon
Staff recommends the Commission approve Surfnet Communications’ application for a
grant of up to $1,280,937 to the California Broadband Alliance for the Corbett Canyon
project.
11 See Federal Funding Account Public Map, https://federalfundingaccountmap.vetro.io/ (visited
August 19, 2024).
Resolution T-17852
CD/CJ2
9
The Corbett Canyon project proposes to serve an estimated 273 unserved locations
based on a March 2024 supplemental application filing. There are approximately 443
unserved units in the project area. An estimated unserved population of 989 would be
offered service. An estimated total population of 2,168 will benefit from these
investments in the community of Corbett Canyon. The last-mile fiber project will
provide up to 1000 Mbps/1000 Mbps per second service to consumers.
The California Broadband Alliance will be the grant recipient and owner of the project
infrastructure. The California Broadband Alliance will enter into an agreement with the
applicant, Surfnet Communications, who will manage the project construction. After
the project is complete, Surfnet Communications will lease access to the infrastructure
from the California Broadband Alliance.
Surfnet Communications will deploy approximately 18 miles of last-mile fiber. The
network will be 5 percent underground.
Surfnet Communications will provide a low-cost plan that meets the requirements in D.
22-04-055, Section 3, and has committed to maintaining the price of that plan for at least
ten years.
The proposed project will cost an estimated $1,280,937, of which the Federal Funding
Account will fund approximately 100 percent of costs.
Staff determined that the applicant and the project are financially viable, and the
applicant’s engineering meets the program standards. The applicant demonstrated the
administrative, technical, and operational capacity to provide broadband service at the
scale of this project.
This application received one objection. Staff determined that the objector did not
provide sufficient documentation to substantiate a claim that it would serve the project
area. The project area of Corbett Canyon was not modified in response to objections.
No Federal Funding Account Public Map comments were submitted in San Luis Obispo
County.12 Corbett Canyon project area’s unserved locations were evaluated in light of
the updated Federal Communications Commission and Federal Funding Account
unserved data (as of June 30, 2023). In response to objections and this data, the number
of unserved locations is unchanged at 273, the project area is unchanged, and the total
grant amount is unchanged. The specific locations to be provided service will be
updated and reconciled with the Broadband Serviceable Location Fabric after detailed
12 See Federal Funding Account Public Map, https://federalfundingaccountmap.vetro.io/ (visited
August 19, 2024).
Resolution T-17852
CD/CJ2
10
engineering and project design, and the grant amount may be reduced consistent with a
reduction in the number of locations.
One letter of support was submitted for this application from the Broadband
Consortium of the Pacific Coast.
The proposed project provides the public safety benefits of reliable broadband
infrastructure and will benefit households located in High Fire Threat District 2. This
project will connect to the open-access Middle-Mile Broadband Initiative.
Based on the information received, the Commission’s Energy Division has determined
that this project has not met the requirements for a CEQA categorial exemption at this
time. Surfnet Communications and the California Broadband Alliance must comply
with the CEQA requirements discussed in the appendices. If Surfnet Communications
or the California Broadband Alliance provides additional documentation sufficient to
justify a staff determination of CEQA exemption, then the project can be exempted by
letter from the Communications Division Director or the director’s delegate or designee.
Surfnet Communications, the California Broadband Alliance, and the Corbett Canyon
project comply with all requirements for approval in D. 22-04-055. The Communications
Division recommends that the Commission approve the application of Surfnet
Communications for a grant of up to $1,280,937 to the California Broadband Alliance for
the Corbett Canyon project.
4. Surfnet Communications, Old Oak Park
Staff recommends the Commission approve Surfnet Communications’ application for a
grant of up to $1,550,572 to the California Broadband Alliance for the Old Oak Park
project.
The Old Oak Park project proposes to serve an estimated 370 unserved locations based
on a March 2024 supplemental application filing as modified by a subsequent objection.
There are approximately 482 unserved units in the project area. An estimated unserved
population of 1,143 would be offered service. An estimated total population of 1,688
will benefit from these investments in the community of Old Oak Park. The last-mile
fiber project will provide up to 1000 Mbps/1000 Mbps service to consumers.
The California Broadband Alliance will be the grant recipient and owner of the project
infrastructure. The California Broadband Alliance will enter into an agreement with the
applicant, Surfnet Communications, who will manage the project construction. After
the project is complete, Surfnet Communications will lease access to the infrastructure
from the California Broadband Alliance.
Resolution T-17852
CD/CJ2
11
Surfnet Communications will deploy approximately three miles of last-mile fiber and 15
miles of middle mile and backhaul fiber. The network will be 5 percent underground.
Surfnet Communications will provide a low-cost plan that meets the requirements in D.
22-04-055, Section 3, and has committed to maintaining the price of that plan for at least
ten years.
The proposed project will cost an estimated $1,550,572, of which the Federal Funding
Account will fund approximately 100 percent of costs.
Staff determined that the applicant and the project are financially viable, and the
applicant’s engineering meets the program standards. The applicant demonstrated the
administrative, technical, and operational capacity to provide broadband service at the
scale of this project.
This application received one objection. Staff removed nine locations from the project
that were determined to be served and reduced the proposed award to reflect fewer
locations.
No Federal Funding Account Public Map comments were submitted in San Luis Obispo
County.13 Old Oak Park project area’s unserved locations were evaluated in light of the
updated Federal Communications Commission and Federal Funding Account unserved
data (as of June 30, 2023). In response to objections and this data, the number of
unserved locations was reduced to 370, and the total grant amount was reduced to
$1,550,572. The specific locations to be provided service will be updated and reconciled
with the Broadband Serviceable Location Fabric after detailed engineering and project
design, and the grant amount may be reduced consistent with a reduction in the
number of locations.
One letter of support was submitted for this application from the Broadband
Consortium of the Pacific Coast.
The proposed project provides the public safety benefits of reliable broadband
infrastructure and will benefit households located in High Fire Threat District 2. This
project will connect to the open-access Middle-Mile Broadband Initiative.
Based on the information received, the Commission’s Energy Division has determined
that this project has not met the requirements for a CEQA categorial exemption at this
time. Surfnet Communications and the California Broadband Alliance must comply
with the CEQA requirements discussed in the appendices. If Surfnet Communications
13 See Federal Funding Account Public Map, https://federalfundingaccountmap.vetro.io/ (visited
August 19, 2024).
Resolution T-17852
CD/CJ2
12
or the California Broadband Alliance provides additional documentation sufficient to
justify a staff determination of CEQA exemption, then the project can be exempted by
letter from the Communications Division Director or the director’s delegate or designee.
Surfnet Communications, the California Broadband Alliance and the Old Oak Park
project comply with all requirements for approval in D. 22-04-055. The Communications
Division recommends that the Commission approve the application of Surfnet
Communications for a grant of up to $1,550,572 to the California Broadband Alliance for
the Old Oak Park project.
5. City of San Luis Obispo, San Luis Obispo Affordable Broadband Network
Staff recommends the Commission approve the City of San Luis Obispo’s application
for a grant of up to $4,863,799 for the San Luis Obispo Affordable Broadband Network
project.
The San Luis Obispo Affordable Broadband Network project proposes to serve an
estimated 490 unserved locations based on a March 2024 supplemental application
filing. There are approximately 966 unserved units in the project area. An estimated
unserved population of 2,011 would be offered service. An estimated total population
of 13,423 will benefit from these investments in the community of San Luis Obispo. The
last-mile fiber project will provide up to 1000/1000 Mbps service to consumers.
The City of San Luis Obispo will deploy approximately 5 miles of last-mile fiber. The
network will be 32 percent underground.
The City of San Luis Obispo is the applicant and awardee. The City of San Luis Obispo
will retain ownership and anticipates entering into an agreement with Astound to
provide last mil service. This recommended award is conditioned on City of San Luis
Obispo last-mile agreements that are consistent with the program requirements.
The San Luis Obispo Affordable Broadband Network project will benefit disadvantaged
or Environmental and Social Justice communities; 78 percent of the unserved locations
are in low-income communities. Through its contracted operator of Astound, the City of
San Luis Obispo will provide a low-cost plan that meets the requirements in D. 22-04-
055, Section 3, and has committed to maintaining the price of that plan for at least ten
years.
The proposed project will cost an estimated $6,074,810 of which the Federal Funding
Account will fund approximately 80 percent of costs.
Resolution T-17852
CD/CJ2
13
Staff determined that the applicant and the project are financially viable, and the
applicant’s engineering meets the program standards. The applicant demonstrated the
administrative, technical, and operational capacity to provide broadband service at the
scale of this project.
This application received two objections. Staff determined that fragmenting the
applicant’s served areas is likely to threaten the fiscal and technical viability of the
award. Therefore, the proposed project area remains unchanged. The Federal Final Rule
and D.22-04-055 allow projects serving unserved locations to include served locations to
make the project viable.
No Federal Funding Account Public Map comments were submitted in San Luis Obispo
County.14 San Luis Obispo Affordable Broadband Network project area’s unserved
locations were evaluated in light of the updated Federal Communications Commission
and Federal Funding Account unserved data (as of June 30, 2023). In response to
objections and this data, the number of unserved locations is unchanged at 490, the
project area is unchanged, and the total grant amount is unchanged. The specific
locations to be provided service will be updated and reconciled with the Broadband
Serviceable Location Fabric after detailed engineering and project design, and the grant
amount may be reduced consistent with a reduction in the number of locations.
The following submitted letters of support for this application: San Luis Coastal Unified
School District, California Polytechnic State University – San Luis Obispo, Community
Action Partnership of San Luis Obispo, People’s Self-Help Housing, REACH the
Regional Economic Action Coalition, Broadband Consortium of the Pacific Coast, San
Luis Obispo Council of Governments, and the San Luis Obispo Chamber of Commerce.
The proposed project provides the public safety benefits of reliable broadband
infrastructure and will benefit households located in High Fire Threat District 2. This
project will connect to the open-access Middle-Mile Broadband Initiative.
Based on the information received, the Commission’s Energy Division has determined
that this project has not met the requirements for a CEQA categorial exemption at this
time. The City of San Luis Obispo must comply with the CEQA requirements discussed
in the appendices. If the City of San Luis Obispo provides additional documentation
sufficient to justify a staff determination of CEQA exemption, then the project can be
exempted by letter from the Communications Division Director or the director’s
delegate or designee.
14 See Federal Funding Account Public Map, https://federalfundingaccountmap.vetro.io/ (visited
August 19, 2024).
Resolution T-17852
CD/CJ2
14
City of San Luis Obispo and the San Luis Obispo Affordable Broadband Network
project comply with all requirements for approval in D. 22-04-055. The Communications
Division recommends that the Commission approve the application of City of San Luis
Obispo for a grant of up to $4,863,799 for the San Luis Obispo Affordable Broadband
Network project.
6. Surfnet Communications, Shandon
Staff recommends the Commission approve Surfnet Communications’ application for a
grant of up to $722,821 to the California Broadband Alliance for the Shandon project.
The Shandon project proposes to serve an estimated 443 unserved locations based on a
March 2024 supplemental application filing. There are approximately 424 unserved
units in the project area. An estimated unserved population of 1,281 would be offered
service. An estimated total population of 1,318 will benefit from these investments in
the community of Shandon. The last-mile fiber project will provide up to 1000
Mbps/1000 Mbps per second service to consumers.
The California Broadband Alliance will be the grant recipient and owner of the project
infrastructure. The California Broadband Alliance will enter into an agreement with the
applicant, Surfnet Communications, who will manage the project construction. After
the project is complete, Surfnet Communications will lease access to the infrastructure
from the California Broadband Alliance.
Surfnet Communications will deploy approximately 6 miles of last-mile fiber. The
network will be 5 percent underground.
Seven percent of the unserved locations in the Shandon project are in low-income
communities. Surfnet Communications will provide a low-cost plan that meets the
requirements in D. 22-04-055, Section 3, and has committed to maintaining the price of
that plan for at least ten years.
The proposed project will cost an estimated $722,821, of which the Federal Funding
Account will fund approximately 100 percent of costs.
Staff determined that the applicant and the project are financially viable, and the
applicant’s engineering meets the program standards. The applicant demonstrated the
administrative, technical, and operational capacity to provide broadband service at the
scale of this project.
This application received no objections.
Resolution T-17852
CD/CJ2
15
No Federal Funding Account Public Map comments were submitted in San Luis Obispo
County.15 The Shandon project area’s unserved locations were evaluated in light of the
updated Federal Communications Commission and Federal Funding Account unserved
data (as of June 30, 2023). In response to this data, the number of unserved locations is
unchanged at 443, the project area is unchanged, and the total grant amount is
unchanged. The specific locations to be provided service will be updated and reconciled
with the Broadband Serviceable Location Fabric after detailed engineering and project
design, and the grant amount may be reduced consistent with a reduction in the
number of locations.
One letter of support was submitted for this application from the Broadband
Consortium of the Pacific Coast.
The proposed project provides the public safety benefits of reliable broadband
infrastructure. This project will connect to the open-access Middle-Mile Broadband
Initiative.
Based on information that Surfnet Communications provided, the Commission’s
Energy Division has confirmed that the project meets the criteria for the California
Environmental Quality Act (CEQA) categorical exemptions under 14 California Code of
Regulations (C.C.R.) Section 15301 (Existing Facilities), 14 C.C.R Section 15303 (New
Construction or Conversion of Small Structures), and 14 C.C.R Section 15304 (Minor
Alterations to Land). Thus, the Shandon project is categorically exempt from CEQA
review and the CPUC may authorize funds for construction activities.
Surfnet Communications, the California Broadband Alliance, and the Shandon project
comply with all requirements for approval in D. 22-04-055. The Communications
Division recommends that the Commission approve the application of Surfnet
Communications for a grant of up to $722,821 to the California Broadband Alliance for
the Shandon project.
7. Surfnet Communications, Whitley Gardens
Staff recommends the Commission approve Surfnet Communications’ application for a
grant of up to $705,378 to the California Broadband Alliance for the Whitley Gardens
project.
The Whitley Gardens project proposes to serve an estimated 121 unserved locations
based on a March 2024 supplemental application filing. There are approximately 131
unserved units in the project area. An estimated unserved population of 330 would be
15 See Federal Funding Account Public Map, https://federalfundingaccountmap.vetro.io/ (visited
August 19, 2024).
Resolution T-17852
CD/CJ2
16
offered service. An estimated total population of 332 will benefit from these investments
in the community of Whitley Gardens. The last-mile fiber project will provide up to
1000 Mbps/1000 Mbps per second service to consumers.
The California Broadband Alliance will be the grant recipient and owner of the project
infrastructure. The California Broadband Alliance will enter into an agreement with the
applicant, Surfnet Communications, who will manage the project construction. After
the project is complete, Surfnet Communications will lease access to the infrastructure
from the California Broadband Alliance.
Surfnet Communications will deploy approximately two miles of last-mile fiber and
one mile of middle mile fiber. The network will be 5 percent underground.
Fifteen percent of the unserved locations in the Whitley Gardens project in low-income
communities. Surfnet Communications will provide a low-cost plan that meets the
requirements in D. 22-04-055, Section 3, and has committed to maintaining the price of
that plan for at least ten years.
The proposed project will cost an estimated $705,378, of which the Federal Funding
Account will fund approximately 100 percent of costs.
Staff determined that the applicant and the project are financially viable, and the
applicant’s engineering meets the program standards. The applicant demonstrated the
administrative, technical, and operational capacity to provide broadband service at the
scale of this project.
This application received no objections.
No Federal Funding Account Public Map comments were submitted in San Luis Obispo
County.16 Whitley Gardens project area’s unserved locations were evaluated in light of
the updated Federal Communications Commission and Federal Funding Account
unserved data (as of June 30, 2023). In response to this data, the number of unserved
locations is unchanged at 121, the project area is unchanged, and the total grant amount
is unchanged. The specific locations to be provided service will be updated and
reconciled with the Broadband Serviceable Location Fabric after detailed engineering
and project design, and the grant amount may be reduced consistent with a reduction in
the number of locations.
One letter of support was submitted for this application from the Broadband
Consortium of the Pacific Coast.
16 See Federal Funding Account Public Map, https://federalfundingaccountmap.vetro.io/ (visited
August 19, 2024).
Resolution T-17852
CD/CJ2
17
The proposed project provides the public safety benefits of reliable broadband
infrastructure. This project will connect to the open-access Middle-Mile Broadband
Initiative.
Based on the information received, the Commission’s Energy Division has determined
that this project has not met the requirements for a CEQA categorial exemption at this
time. Surfnet Communications and the California Broadband Alliance must comply
with the CEQA requirements discussed in the appendices. If Surfnet Communications
or the California Broadband Alliance provides additional documentation sufficient to
justify a staff determination of CEQA exemption, then the project can be exempted by
letter from the Communications Division Director or the director’s delegate or designee.
Surfnet Communications, the California Broadband Alliance, and the Whitley Gardens
project comply with all requirements for approval in D. 22-04-055. The Communications
Division recommends that the Commission approve the application of Surfnet
Communications for a grant of up to $705,378 to the California Broadband Alliance for
the Whitley Gardens project.
Comments
In compliance with Public Utilities Code Section 311(g)(1), a Notice of Availability of
this draft resolution was e-mailed on September 12, 2024, informing all parties on the
CASF Distribution List and the R. 20-09-001 Service List of the availability of the draft of
this Resolution, and of the opportunity to comment, at the Commission’s website at
http://www.cpuc.ca.gov/.
Resolution comments were submitted on October 2, 2024, by Charter.
Charter’s Comments
Charter requests the removal of locations which Staff acknowledge are currently served.
They state that they believe this to be approximately 85 percent of locations in the
project area, and that there is no evidence that proves building to the currently served
locations is essential for the rest of the project. Charter requests substantial evidence
that proves how deploying to served locations is essential for the viability of the project,
and states that, if the Commission cannot prove that the served locations are necessary,
then they should be removed.
Staff Response to Comments
With regards to Charter’s comments, all entities were given an opportunity to object to
proposed applications and provide detailed data under the program rules. Charter’s
comments to this resolution reiterated the objections that Charter submitted during the
Resolution T-17852
CD/CJ2
18
28-day objection period that lasted from October 23, 2023 to November 20, 2023. The
comments do not present new or updated information. The City of San Luis Obispo
submitted a thorough response to Charter’s objection on December 6, 2023, that
analyzed residents’ inequitable access to broadband, showed that some neighborhoods
are unserved, and argued that Charter does not provide reliable and affordable service
at the locations that are considered served. In response to Charter’s objections, Staff
reexamined Charter’s contentions that it already provides reliable high-speed
broadband service to the locations where Charter submitted objections, and determined
that the San Luis Obispo Affordable Broadband Network project could not feasibly
serve the unserved locations in the project area without including the disputed
locations. Furthermore, the San Luis Obispo Affordable Broadband Network project
will provide reliable, low-cost broadband service in a disadvantaged community,
benefitting served and unserved households alike. Staff has not modified the San Luis
Obispo Affordable Broadband Network project area, grant amount, or locations in
response to comments on the Resolution.
Nonetheless, Staff will confer with the City of San Luis Obispo regarding the specific
locations to be provided service for the San Luis Obispo Affordable Broadband
Network, which will be updated and reconciled with the Broadband Serviceable
Location Fabric after detailed engineering and project design, and the grant amount
may be reduced consistent with a reduction in the number of locations.
IV. COMPLIANCE REQUIREMENTS
Awardees are required to comply with all the guidelines, requirements, and conditions
associated with the grant of Federal Funding Account awards as specified in D.22-04-
055. All Awardees are also required to sign a consent form agreeing to the terms and
conditions of the Federal Funding Account. Such compliance includes, but is not limited
to, the items noted below.
A. Deployment Schedule: All CEQA-exempt projects must be completed within 18
months, and all other projects shall be completed within 24 months after receiving
authorization to construct.
B. Pricing: By accepting these awards, the Awardees commit to serve customers in the
project area at prices not exceeding those provided in the application for five years after
project completion. Awardees who committed not to increase prices for a period of ten
years in their application commit to serve customers in the project area for ten years
after project completion. Should the need arise for grant recipients to adjust prices due
to externalities outside their control (e.g. inflation), grant recipients may file and serve,
on the R. 20-09-001 proceeding service list, a request to modify this requirement with
the Communications Division.
Resolution T-17852
CD/CJ2
19
C. Speed and Latency: All households in the proposed project areas must be offered a
broadband internet service plan with speeds of at least 100 megabits per second
megabits per second download and 100 megabits per second upload, with not more
than 100 milliseconds of latency.
D. Affordability: All projects shall participate in the Affordable Connectivity Program
or otherwise provide access to a broad-based affordability program to low-income
customers in the proposed service area of the broadband infrastructure that provides
benefits to households commensurate with those provided under the Affordable
Connectivity Program. Should the Affordable Connectivity Program end, the
Commission will identify a successor low-income subsidy program in which
participants must participate. Awardees must participate in a successor to the
Affordable Connectivity Program identified after the grant is awarded.
E. Project Audit: The Commission has the right to conduct any necessary audit,
verification, and discovery during project implementation/construction to ensure that
Federal Funding Account funds are spent in accordance with Commission approval. All
recipients of federally funded grants exceeding $750,000 will need to include a budget
for a federal audit.17
F. Reporting Requirements: Numerous post-award reports are required. In summary,
these include monthly contractor reports (if applicable), quarterly progress reports, and
a final completion report.18
G. Prevailing Wage: Section 1720 of the California Labor Code requires Federal Funding
Account projects be subject to prevailing wage requirements.19 Applicants accepting
Federal Funding Account awards are committing to follow state prevailing wage
requirements with regards to their projects.
H. Payments to Federal Funding Account Recipients: The Commission may reimburse
Awardees’ expenses in accordance with Public Utilities Code Section 281(n)(2), D.22-04-
055, and the Appendix. Requests for payments may be submitted as the project is
progressively deployed. The prerequisite for first payment is the submittal of a progress
report to the Commission showing that a minimum of ten percent of the project (as
determined by budget spent) has been completed. Subsequent payments may be made
17 Treasury, Compliance and Reporting Guidance State and Local Fiscal Recovery Funds (November 15,
2021 Version 2.1), available at https://home.treasury.gov/system/files/136/SLFRF-Compliance-and-
Reporting-Guidance.pdf.
18 D. 22-04-055, Appendix A, Section 14.
19 D.22-054-055, Section 13.2, page 57.
Resolution T-17852
CD/CJ2
20
upon at least 25 percent intervals, with the final 15 percent payment request (from 85 to
100 percent) not eligible for payment without an approved completion report. Payments
are based on submitted receipts, invoices and other supporting documentation showing
expenditures incurred for the project in accordance with the approved Federal Funding
Account budget included in the awardee’s application.
FINDINGS OF FACT
1. California’s multi-year broadband infrastructure investments in the Budget Act of
2021 and Senate Bill 156 (Statutes 2021, Chapters 84 and 112) provided $2 billion
over multiple years to the Last Mile Federal Funding Account to facilitate, via
reimbursement, construction of last mile broadband infrastructure projects to
connect unserved Californians.
2. On April 21, 2022, the Commission approved Decision 22-04-055, which along with
the Federal Final Rule, established the Last Mile Federal Funding Account and set
program rules.
3. The Communications Division opened an application window for the Federal
Funding Account on June 30, 2023, and closed it on September 29, 2023. Applicants
submitted 484 applications before the deadline. Application summaries were posted
on October 23, 2023, and a 28-day objection window closed on November 20, 2023.
Responses to objections were received until December 20, 2023.
4. Astound submitted an application for the Atascadero – Paso Robles project on
September 29, 2023.
5. Surfnet Communications submitted applications for the Branch, Corbett Canyon,
Old Oak Park, Shandon, and Whitley Gardens projects on September 29, 2023.
6. The City of San Luis Obispo submitted an application for the project on September
29, 2023.
7. Applicants responded to a supplemental data request that was due on March 12,
2024, providing information on project route miles, poles, unserved locations,
middle-mile connectivity, and other updated project specific information.
8. The Commission has determined that Surfnet Communications’ Shandon project is
categorically exempt from California Environmental Quality Act (CEQA) review
pursuant to CEQA Guidelines at 14 California Code of Regulations (C.C.R.) Section
15301 regarding exemption for existing facilities, 14 C.C.R. Section 15303 regarding
new construction or conversion of small structures, and 14 C.C.R. Section 15304,
Resolution T-17852
CD/CJ2
21
which consists of minor public or private alterations in the condition of land.
9. The Commission has determined that Astound’s Atascadero - Paso Robles project is
not categorically exempt from California Environmental Quality Act review at this
time.
10. The Commission has determined that Surfnet Communications’ Branch, Corbett
Canyon, Old Oak Park, Shandon, and Whitley Gardens projects are not categorically
exempt from California Environmental Quality Act review at this time.
11. The Commission has determined that the City of San Luis Obispo’s San Luis Obispo
Affordable Broadband Network project is not categorically exempt from California
Environmental Quality Act review at this time.
12. Communications Division staff analyzed the applications for compliance with
Commission and Federal rules, reviewed local feedback, and conducted fiscal and
technical analysis.
13. All applications listed above met minimum eligibility requirements provided in
Decision 22-04-055.
14. Staff recommends approval of the applications in this resolution, as they comply
with program rules as stated and contribute to the Federal Funding Account’s goal
of building broadband internet infrastructure to communities without access to
internet service at sufficient and reliable speeds.
15. Draft Resolution T-17852 was emailed to the CASF Distribution List and the R. 20-
09-001 Service List on September 12, 2024, in compliance with Public Utilities Code
Section 311(g)(1).
THERFORE, IT IS ORDERED that:
1. The Commission shall award up to $6,794,215 in Federal Funding Account funds to
Astound in order to complete the Atascadero – Paso Robles project, as described in
the appendices. The specific locations to be provided service will be updated and
reconciled with the Broadband Serviceable Location Fabric after detailed
engineering and project design, and the grant amount may be reduced consistent
with a reduction in the number of locations.
2. The Commission shall award up to $2,093,539 in Federal Funding Account funds to
the California Broadband Alliance in order to complete the Branch project, as
Resolution T-17852
CD/CJ2
22
described in the appendices. The specific locations to be provided service will be
updated and reconciled with the Broadband Serviceable Location Fabric after
detailed engineering and project design, and the grant amount may be reduced
consistent with a reduction in the number of locations.
3. The Commission shall award up to $1,280,937 in Federal Funding Account funds to
the California Broadband Alliance in order to complete the Corbett Canyon project,
as described in the appendices. The specific locations to be provided service will be
updated and reconciled with the Broadband Serviceable Location Fabric after
detailed engineering and project design, and the grant amount may be reduced
consistent with a reduction in the number of locations.
4. The Commission shall award up to $1,550,572 in Federal Funding Account funds to
the California Broadband Alliance in order to complete the Old Oak Park project, as
described in the appendices. The specific locations to be provided service will be
updated and reconciled with the Broadband Serviceable Location Fabric after
detailed engineering and project design, and the grant amount may be reduced
consistent with a reduction in the number of locations.
5. The Commission shall award up to $4,863,799 in Federal Funding Account funds to
the City of San Luis Obispo in order to complete the San Luis Obispo Affordable
Broadband Network project, as described in the appendices. The specific locations to
be provided service will be updated and reconciled with the Broadband Serviceable
Location Fabric after detailed engineering and project design, and the grant amount
may be reduced consistent with a reduction in the number of locations.
6. The Commission shall award up to $722,821 in Federal Funding Account funds to
the California Broadband Alliance in order to complete the Shandon project, as
described in the appendices. The specific locations to be provided service will be
updated and reconciled with the Broadband Serviceable Location Fabric after
detailed engineering and project design, and the grant amount may be reduced
consistent with a reduction in the number of locations.
7. The Commission shall award up to $705,378 in Federal Funding Account funds to
the California Broadband Alliance in order to complete the Whitley Gardens project,
as described in the appendices. The specific locations to be provided service will be
updated and reconciled with the Broadband Serviceable Location Fabric after
detailed engineering and project design, and the grant amount may be reduced
consistent with a reduction in the number of locations.
Resolution T-17852
CD/CJ2
23
8. To ensure compliance with all program rules and guidelines, the Commission will
not release funds to an applicant, including but not limited to the California
Broadband Alliance and the City of San Luis Obispo, proposing to enter into
agreement(s) with a third party or third parties for the ownership, operation, and/or
leasing of the proposed infrastructure or network until the applicant provides the
Commission with an advanced copy of the agreement document(s) as well as any
signed agreements.
9. Applicants that committed to provide voice and/or Lifeline service must provide
voice service and participate in LifeLine for five years after project completion in
Federal Funding Account project areas.
10. For those projects not determined to be categorically exempt, the Commission
cannot release funds for construction activities until California Environmental
Quality Act (CEQA) review is complete. The awardees must comply with the
requirements set forth in the CEQA Section of the Resolution. The awardees must
provide their Proponent’s Environmental Assessment for each project prior to the
first payment.
11. Awardee(s) shall comply with all guidelines, requirements, and conditions set forth
in this resolution.
12. When a successor to the Affordable Connectivity Program is identified by the
Commission, all awardees shall participate in that program.
13. All construction covered by the grant must be completed within the applicable 18-
month or 24-month time frame. In the event of extenuating circumstances
jeopardizing this timeline, the Awardee(s) must notify the Communications
Division’s Director as soon as they become aware of any delay. If such notice is not
provided, staff can take corrective actions including reducing payment for failure to
satisfy this requirement.
14. If the awardee(s) fail to complete the project(s) in accordance with the terms
outlined in Decision 22-04-055 and with the terms of the Commission’s approval, as
set forth in this resolution, awardees must reimburse some or all the Federal
Funding Account grants received or take other corrective action.
15. If staff evaluation finds any of the projects can be exempt from the California
Environmental Quality Act, then the project can be exempted by letter from the
Communications Division Director or the director’s delegate or designee.
16. The effective date of each award and encumbrance of funds is to be set, in
consultation with the Applicant, by letter from the Communications Division
Resolution T-17852
CD/CJ2
24
Director or the director’s delegate or designee. All awards are contingent on
available state budget appropriations funding.
This resolution is effective today.
I certify that the foregoing resolution was duly introduced, passed, and adopted at a
conference of the Public Utilities Commission of the State of California held on October
17, 2024, the following Commissioners voting favorable thereon:
/s/ RACHEL PETERSON
Rachel Peterson
Executive Director
ALICE REYNOLDS
President
DARCIE L. HOUCK
JOHN REYNOLDS
KAREN DOUGLAS
MATTHEW BAKER
Commissioners
Resolution T-17852
CD/CJ2
A-1
APPENDIX A
California Broadband Alliance and Surfnet Communications California
Environmental Quality Act Compliance Requirements
The following Surfnet Communications project is categorically exempt from California
Environmental Quality Act (CEQA) review:
- Shandon
For the Shandon project located in unincorporated San Luis Obispo County, the CPUC
was provided with project plans to construct six miles of fiber optic cable. The project
includes 95 percent aerial installation on existing poles, and five percent underground.
Underground installation will be located in existing rights-of-way and utility easements
and will avoid previously undisturbed ground. Aerial installation will occur on existing
support structures and in compliance with CPUC GO 95 loading requirements.
Based on information that Surfnet Communications provided, the CPUC’s Energy
Division has confirmed that the project meets the criteria for the CEQA categorical
exemptions under 14 C.C.R Section 15301 (Existing Facilities), 14 C.C.R Section 15303
(New Construction or Conversion of Small Structures), and 14 C.C.R Section 15304
(Minor Alterations to Land). Thus, the Shandon project is categorically exempt from
CEQA review and the CPUC may authorize funds for construction activities.
Resolution T-17852
CD/CJ2
B-1
APPENDIX B
Astound California Environmental Quality Act Compliance Requirements
The following Astound project is subject to California Environmental Quality Act
(CEQA) review:
Atascadero – Paso Robles
The Commission must complete CEQA review prior to disbursing Federal Funding
Account funds for construction activities. The initial funding granted in this Resolution
may be used for project development and other Astound activities that do not involve
construction or any activities that would have any direct or indirect effect on the
physical environment.
Prior to any construction activity for the project, Astound is required to seek further
authority from the Commission for such activity by filing a Proponent’s Environmental
Assessment (PEA) pursuant to Commission Rule of Practice and Procedure 2.4; and
must undergo an environmental review pursuant to CEQA (California Public Resources
Code § 21000 et seq.).
Astound should contact the Supervisor of the Commission’s Energy Division CEQA
Unit well in advance of a contemplated filing to (a) consult with staff regarding the
process of developing and filing a PEA; (b) provide for cost recovery per Rule of
Practice and Procedure 2.5; and (c) enter into a Memorandum of Understanding to
allow the Energy Division to initiate the retention of an environmental contractor to
perform the environmental review.
Astound must provide a PEA prior to the first payment. The Commission cannot
release funds for the construction phase of this project until the Commission has
completed CEQA review.
Resolution T-17852
CD/CJ2
C-1
APPENDIX C
California Broadband Alliance and Surfnet Communications California
Environmental Quality Act Compliance Requirements
The following Surfnet Communications projects are subject to California Environmental
Quality Act (CEQA) review:
Branch
Corbett Canyon
Old Oak Park
Whitley Gardens
The Commission must complete CEQA review prior to disbursing Federal Funding
Account funds for construction activities. The initial funding granted in this Resolution
may be used for project development and other Surfnet Communications or California
Broadband Alliance activities that do not involve construction or any activities that
would have any direct or indirect effect on the physical environment.
Prior to any construction activity for the project, Surfnet Communications and the
California Broadband Alliance are required to seek further authority from the
Commission for such activity by filing a Proponent’s Environmental Assessment (PEA)
pursuant to Commission Rule of Practice and Procedure 2.4; and must undergo an
environmental review pursuant to CEQA (California Public Resources Code § 21000 et
seq.).
The California Broadband Alliance and Surfnet Communications should contact the
Supervisor of the Commission’s Energy Division CEQA Unit well in advance of a
contemplated filing to (a) consult with staff regarding the process of developing and
filing a PEA; (b) provide for cost recovery per Rule of Practice and Procedure 2.5; and
(c) enter into a Memorandum of Understanding to allow the Energy Division to initiate
the retention of an environmental contractor to perform the environmental review.
The California Broadband Alliance and Surfnet Communications must provide a PEA
prior to the first payment. The Commission cannot release funds for the construction
phase of this project until the Commission has completed CEQA review.
Resolution T-17852
CD/CJ2
D-1
APPENDIX D
City of San Luis Obispo California Environmental Quality Act Compliance
Requirements
The following City of San Luis Obispo project is subject to California Environmental
Quality Act (CEQA) review:
San Luis Obispo Affordable Broadband Network
The Commission must complete CEQA review prior to disbursing Federal Funding
Account funds for construction activities. The initial funding granted in this Resolution
may be used for project development and other City of San Luis Obispo activities that
do not involve construction or any activities that would have any direct or indirect
effect on the physical environment.
Prior to any construction activity for the project, the City of San Luis Obispo is required
to seek further authority from the Commission for such activity by filing a Proponent’s
Environmental Assessment (PEA) pursuant to Commission Rule of Practice and
Procedure 2.4; and must undergo an environmental review pursuant to CEQA
(California Public Resources Code § 21000 et seq.).
The City of San Luis Obispo should contact the Supervisor of the Commission’s Energy
Division CEQA Unit well in advance of a contemplated filing to (a) consult with staff
regarding the process of developing and filing a PEA; (b) provide for cost recovery per
Rule of Practice and Procedure 2.5; and (c) enter into a Memorandum of Understanding
to allow the Energy Division to initiate the retention of an environmental contractor to
perform the environmental review.
The City of San Luis Obispo must provide a PEA prior to the first payment. The
Commission cannot release funds for the construction phase of this project until the
Commission has completed CEQA review.
Resolution T-17852
CD/CJ2
E-1
APPENDIX E
Astound Service Plans
As a condition of the grant awards in this Resolution, Astound is obligated to offer
service to customers in the project areas of the listed projects at no less than the speeds
in the Table below, no more than 100 milliseconds of latency, and no more than the
prices20 in the Table below, including installation, for at least ten years following project
completion:
Atascadero – Paso Robles
Plan Speed Price in 2024
Dollars
Notes
Internet
First
50/50 Mbps $10/month Customers must provide
documentation showing
eligibility for a qualifying
program.21
Low-Cost
Plan
100/100 Mbps $40/month -
1 Gig
Internet
1,000/1,000 Mbps $80/month -
2 Gig
Internet
2,000/2,000 Mbps $129.95/month -
As a condition of the grant awards in this Resolution, Astound has committed to
provide LifeLine-discounted voice service in the project area listed.
20 Prices may increase at no more than the rate of inflation, defined by the Consumer Price Index.
21 Qualifying programs/income thresholds include: Medicaid; Public Housing Assistance; Unemployment;
Supplemental Nutrition Assistance Program; Temporary Assistance for Needy Families; Supplemental Security
Income; National School Lunch Program or Head Start; Low Income Home Energy Assistance Program; the Special
Supplemental Nutrition Program for Women, Infants and Children; Federal Pell Grants; Veterans Administration
Pensions; Tribal Assistance, including Tribal Temporary Assistance to Needy Families and Food Distribution
Program on Indian Reservations.
Resolution T-17852
CD/CJ2
F-1
APPENDIX F
California Broadband Alliance and Surfnet Communications Service Plans
As a condition of the grant awards in this Resolution, the California Broadband Alliance
and Surfnet Communications are obligated to offer service to customers in the project
areas of the listed projects at no less than the speeds in the Table below, no more than
100 milliseconds of latency, and no more than the prices22 in the Table below, including
installation, for at least ten years following project completion.
Branch
Corbett Canyon
Old Oak Park
Shandon
Whitley Gardens
Plan Speed Price in 2024 Dollars Notes
Low-Cost
Plan
50/20 Mbps $40/month -
Standard
Plan
200/200 Mbps $90/month -
Premium
Plan
1,000/1,000
Mbps
$150/month -
22 Prices may increase at no more than the rate of inflation, defined by the Consumer Price Index.
Resolution T-17852
CD/CJ2
G-1
APPENDIX G
City of San Luis Obispo Service Plans
As a condition of the grant awards in this Resolution, the City of San Luis Obispo is
obligated to offer service to customers in the project areas of the listed projects at no less
than the speeds in the Table below, no more than 100 milliseconds of latency, and no
more than the prices23 in the Table below, including installation, for at least ten years
following project completion.
San Luis Obispo Affordable Broadband Network
Plan Speed Price in 2024
Dollars
Notes
Internet First 50/50
Mbps
$9.99/month Customers must provide
documentation showing
eligibility for a qualifying
program.24
Low-Cost Plan 100/100
Mbps
$40/month -
1 Gig Internet 1/1 Gbps $80/month -
23 Prices may increase at no more than the rate of inflation, defined by the Consumer Price Index.
24 Qualifying programs/income thresholds include: Medicaid; Public Housing Assistance; Unemployment;
Supplemental Nutrition Assistance Program; Temporary Assistance for Needy Families; Supplemental Security
Income; National School Lunch Program or Head Start; Low Income Home Energy Assistance Program; the Special
Supplemental Nutrition Program for Women, Infants and Children; Federal Pell Grants; Veterans Administration
Pensions; Tribal Assistance, including Tribal Temporary Assistance to Needy Families and Food Distribution
Program on Indian Reservations.
Resolution T-17852
CD/CJ2
H-1
APPENDIX H
Atascadero – Paso Robles Project
Key Information
Project Name Atascadero-Paso Robles
Applicant Name Astound Broadband, LLC
Community Names City of Atascadero, City of El Paso de Robles
County San Luis Obispo County
County Allocation $22,346,936
Project Size (in square miles) 9
Maximum Download/Upload speed 2000 Mbps/2000 Mbps
Lowest cost plan (non-income qualified) $40 for 100/100 Mbps
Low-income plan $10 for 50/50 Mbps
Low-cost plan $40 for 50/20 Mbps minimum
LifeLine Participation Yes
Percent Disadvantaged Communities 0 percent
Percent Low-Income Areas 49 percent
Median Household Income (weighted) $53,730
Area Households 767
Area Population 2498
Estimated locations within 1000 feet of the
project area (location passings) 2511
Estimated units within 1000 feet of the project
area (unit passings) 3775
Unserved locations proposed to be served by
the project 201
Unserved locations in the project area 192
Unserved units in the project area 252
Estimated unserved population in the project
area 800
Resolution T-17852
CD/CJ2
H-2
Estimated unserved Multiple Dwelling Unit
(MDU) locations in the project area 26
Estimated unserved Multiple Dwelling Unit
(MDU) location units in the project area 86
Community Anchor Institutions benefitting
from the project 7
Public safety locations benefitting from the
project 1
Does the project connect to public open
access middle mile? No
Distance of middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project
0
Grant costs for middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project
$0
Grant costs for last-mile delivery $6,794,215
Deployment Schedule 15 Months
Total Project Cost $6,794,215
Amount of FFA grant funds requested $6,794,215
Applicant funded $0
Grant (excluding middle mile) per unserved
unit in the project area $26,961
Grant (excluding middle mile) per unit passing $1,800
Resolution T-17852
CD/CJ2
H-3
Map of Atascadero – Paso Robles
Resolution T-17852
CD/CJ2
I-1
APPENDIX I
Branch Project
Key Information
Project Name Branch
Applicant Name Surfnet Communications, Inc.
Community Names Branch
County San Luis Obispo
County Allocation $22,346,936
Project Size (in square miles) 5
Maximum Download/Upload speed 1000 Mbps/ 1000 Mbps
Lowest cost plan (non-income qualified) $40 for 50/20 Mbps minimum
Low-income plan $15 for 200/200 Mbps
Low-cost plan $40 for 50/20 Mbps minimum
LifeLine Participation No
Percent Disadvantaged Communities 0 percent
Percent Low-Income Areas 0 percent
Median Household Income (weighted) $106,050
Area Households 799
Area Population 2087
Estimated locations within 1000 feet of the
project area (location passings) 869
Estimated units within 1000 feet of the project
area (unit passings) 888
Unserved locations proposed to be served by
the project 856
Unserved locations in the project area 827
Unserved units in the project area 844
Estimated unserved population in the project
area 2087
Resolution T-17852
CD/CJ2
I-2
Estimated unserved Multiple Dwelling Unit
(MDU) locations in the project area 17
Estimated unserved Multiple Dwelling Unit
(MDU) location units in the project area 34
Community Anchor Institutions benefitting
from the project 2
Public safety locations benefitting from the
project 0
Does the project connect to public open
access middle mile? Yes
Distance of middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project 24.8
Grant costs for middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project $0
Grant costs for last-mile delivery $2,093,539
Deployment Schedule 18 Months
Total Project Cost $2,093,539
Amount of FFA grant funds requested $2,093,539
Applicant funded $0
Grant (excluding middle mile) per unserved
unit in the project area $2,480
Grant (excluding middle mile) per unit passing $2,358
Resolution T-17852
CD/CJ2
I-3
Map of Branch
Resolution T-17852
CD/CJ2
J-1
APPENDIX J
Corbett Canyon Project
Key Information
Project Name Corbett Canyon
Applicant Name Surfnet Communications, Inc.
Community Names Corbett Canyon
County San Luis Obispo
County Allocation $22,346,936
Project Size (in square miles) 5
Maximum Download/Upload speed 1000 Mbps/ 1000 Mbps
Lowest cost plan (non-income qualified) $40 for 50/20 Mbps minimum
Low-income plan $15 for 200/200 Mbps
Low-cost plan $40 for 50/20 Mbps minimum
LifeLine Participation No
Percent Disadvantaged Communities 0 percent
Percent Low-Income Areas 0 percent
Median Household Income (weighted) $89,567
Area Households 788
Area Population 2168
Estimated locations within 1000 feet of the
project area (location passings) 1307
Estimated units within 1000 feet of the project
area (unit passings) 1771
Unserved locations proposed to be served by
the project 273
Unserved locations in the project area 317
Unserved units in the project area 443
Estimated unserved population in the project
area 989
Resolution T-17852
CD/CJ2
J-2
Estimated unserved Multiple Dwelling Unit
(MDU) locations in the project area 68
Estimated unserved Multiple Dwelling Unit
(MDU) location units in the project area 194
Community Anchor Institutions benefitting
from the project 2
Public safety locations benefitting from the
project 0
Does the project connect to public open
access middle mile? Yes
Distance of middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project 18
Grant costs for middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project $0
Grant costs for last-mile delivery $1,280,937
Deployment Schedule 18 Months
Total Project Cost $1,280,937
Amount of FFA grant funds requested $1,280,937
Applicant funded $0
Grant (excluding middle mile) per unserved
unit in the project area $2,892
Grant (excluding middle mile) per unit passing $723
Resolution T-17852
CD/CJ2
J-3
Map of Corbett Canyon
Resolution T-17852
CD/CJ2
K-1
APPENDIX K
Old Oak Park Project
Key Information
Project Name Old Oak Park
Applicant Name Surfnet Communications, Inc.
Community Names Old Oak Park
County San Luis Obispo
County Allocation $22,346,936
Project Size (in square miles) 5
Maximum Download/Upload speed 1000 Mbps/ 1000 Mbps
Lowest cost plan (non-income qualified) $40 for 50/20 Mbps minimum
Low-income plan $15 for 200/200 Mbps
Low-cost plan $40 for 50/20 Mbps minimum
LifeLine Participation No
Percent Disadvantaged Communities 0 percent
Percent Low-Income Areas 0 percent
Median Household Income (weighted) $89,567
Area Households 689
Area Population 1688
Estimated locations within 1000 feet of the
project area (location passings) 1073
Estimated units within 1000 feet of the project
area (unit passings) 1329
Unserved locations proposed to be served by
the project 370
Unserved locations in the project area 362
Unserved units in the project area 482
Estimated unserved population in the project
area 1143
Resolution T-17852
CD/CJ2
K-2
Estimated unserved Multiple Dwelling Unit
(MDU) locations in the project area 68
Estimated unserved Multiple Dwelling Unit
(MDU) location units in the project area 188
Community Anchor Institutions benefitting
from the project 6
Public safety locations benefitting from the
project 0
Does the project connect to public open
access middle mile? Yes
Distance of middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project 14.82
Grant costs for middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project $0
Grant costs for last-mile delivery $1,550,572
Deployment Schedule 18 Months
Total Project Cost $1,550,572
Amount of FFA grant funds requested $1,550,572
Applicant funded $0
Grant (excluding middle mile) per unserved
unit in the project area $3,217
Grant (excluding middle mile) per unit passing $1,167
Resolution T-17852
CD/CJ2
K-3
Map of Old Oak Park Project
Resolution T-17852
CD/CJ2
L-1
APPENDIX L
San Luis Obispo Affordable Broadband Network Project
Key Information
Project Name
San Luis Obispo Affordable Broadband
Network
Applicant Name City of San Luis Obispo
Community Names San Luis Obispo
County San Luis Obispo
County Allocation $22,346,936
Project Size (in square miles) 3
Maximum Download/Upload speed 1000 Mbps/ 1000 Mbps
Lowest cost plan (non-income qualified) $40 for 100/100 Mbps
Low-income plan $9.99 for 50/50 Mbps
Low-cost plan $40 for 50/20 Mbps Minimum
LifeLine Participation No
Percent Disadvantaged Communities 0 percent
Percent Low-Income Areas 78 percent
Median Household Income (weighted) $56,866
Area Households 4566
Area Population 13423
Estimated locations within 1000 feet of the
project area (location passings) 7968
Estimated units within 1000 feet of the project
area (unit passings) 16205
Unserved locations proposed to be served by
the project 490
Unserved locations in the project area 487
Unserved units in the project area 966
Resolution T-17852
CD/CJ2
L-2
Estimated unserved population in the project
area 2011
Estimated unserved Multiple Dwelling Unit
(MDU) locations in the project area 184
Estimated unserved Multiple Dwelling Unit
(MDU) location units in the project area 663
Community Anchor Institutions benefitting
from the project 37
Public safety locations benefitting from the
project 4
Does the project connect to public open
access middle mile? Yes
Distance of middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project
0
Grant costs for middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project
$0
Grant costs for last-mile delivery $4,863,799
Deployment Schedule 18 Months
Total Project Cost $6,074,810
Amount of FFA grant funds requested $4,863,799
Applicant funded $1,211,011
Grant (excluding middle mile) per unserved
unit in the project area $5,035
Grant (excluding middle mile) per unit passing $300
Resolution T-17852
CD/CJ2
L-3
Map of San Luis Obispo Affordable Broadband Network
Resolution T-17852
CD/CJ2
M-1
APPENDIX M
Shandon Project
Key Information
Project Name Shandon
Applicant Name Surfnet Communications, Inc.
Community Names Shandon
County San Luis Obispo
County Allocation $22,346,936
Project Size (in square miles) 2
Maximum Download/Upload speed 1000 Mbps/ 1000 Mbps
Lowest cost plan (non-income qualified) $40 for 50/20 Mbps minimum
Low-income plan $15 for 200/200 Mbps
Low-cost plan $40 for 50/20 Mbps minimum
LifeLine Participation No
Percent Disadvantaged Communities 0 percent
Percent Low-Income Areas 4 percent
Median Household Income (weighted) $72,860
Area Households 422
Area Population 1318
Estimated locations within 1000 feet of the
project area (location passings) 432
Estimated units within 1000 feet of the project
area (unit passings) 455
Unserved locations proposed to be served by
the project 443
Unserved locations in the project area 403
Unserved units in the project area 424
Estimated unserved population in the project
area 1281
Resolution T-17852
CD/CJ2
M-2
Estimated unserved Multiple Dwelling Unit
(MDU) locations in the project area 21
Estimated unserved Multiple Dwelling Unit
(MDU) location units in the project area 42
Community Anchor Institutions benefitting
from the project 10
Public safety locations benefitting from the
project 3
Does the project connect to public open
access middle mile? Yes
Distance of middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project 6
Grant costs for middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project $0
Grant costs for last-mile delivery $722,821
Deployment Schedule 18 Months
Total Project Cost $722,821
Amount of FFA grant funds requested $722,821
Applicant funded $0
Grant (excluding middle mile) per unserved
unit in the project area $1,705
Grant (excluding middle mile) per unit passing $1,589
Resolution T-17852
CD/CJ2
M-3
Map of Shandon Project
Resolution T-17852
CD/CJ2
N-1
APPENDIX N
Whitley Gardens Project
Key Information
Project Name Whitley Gardens
Applicant Name Surfnet Communications, Inc.
Community Names Whitley Gardens
County San Luis Obispo
County Allocation $22,346,936
Project Size (in square miles) 2
Maximum Download/Upload speed 1000 Mbps/ 1000 Mbps
Lowest cost plan (non-income qualified) $40 for 50/20 Mbps minimum
Low-income plan $15 for 200/200 Mbps
Low-cost plan $40 for 50/20 Mbps minimum
LifeLine Participation No
Percent Disadvantaged Communities 0 percent
Percent Low-Income Areas 15 percent
Median Household Income (weighted) $86,087
Area Households 128
Area Population 332
Estimated locations within 1000 feet of the
project area (location passings) 160
Estimated units within 1000 feet of the project
area (unit passings) 171
Unserved locations proposed to be served by
the project 121
Unserved locations in the project area 123
Unserved units in the project area 131
Estimated unserved population in the project
area 330
Resolution T-17852
CD/CJ2
N-2
Estimated unserved Multiple Dwelling Unit
(MDU) locations in the project area 8
Estimated unserved Multiple Dwelling Unit
(MDU) location units in the project area 16
Community Anchor Institutions benefitting
from the project 0
Public safety locations benefitting from the
project 0
Does the project connect to public open
access middle mile? Yes
Distance of middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project 1.35
Grant costs for middle-mile, backhaul, and
connection to Middle Mile Broadband Initiative
in project $0
Grant costs for last-mile delivery $705,378
Deployment Schedule 18 Months
Total Project Cost $705,378
Amount of FFA grant funds requested $705,378
Applicant funded $0
Grant (excluding middle mile) per unserved
unit in the project area $5,385
Grant (excluding middle mile) per unit passing $4,125
Resolution T-17852
CD/CJ2
N-3
Map of Whitley Garden Project
Resolution T-17852
CD/CJ2
O-1
APPENDIX O
California Public Utilities Commission
Federal Funding Account, Last Mile Program
Guidance to Staff Regarding
CONSENT FORM
Acknowledgement and Acceptance of Terms
Awardee Name:
Key Project Contact:
Project Name:
The Awardee identified above acknowledges receipt of the California Public Utilities Commission
Resolution or Award Letter and agrees to comply with all grant terms, conditions, and requirements set
forth in the Resolution or Award Letter and those in the Federal Funding Account, Last Mile program
rules. Awards are contingent on available state budget appropriations funding.
Undersigned representative of __________________________________ [Name of Awardee] is duly
authorized to execute this Consent Form on behalf of the Awardee and to bind the Awardee to the
terms, conditions, and requirements set forth in California Public Utilities Commission Resolution or
Award Letter and those in the Federal Funding Account, Last Mile program rules.
Dated this _____ day of _____________, 20____.
Signature of Awardee Representative: _____________________________________________________
Title __________________________________________________________
Printed Name __________________________________________________
Name of Representative’s Organization:
______________________________________________________________
Business Address:
Street address, suite/apt. number
City, state, and ZIP Code
Telephone Number: ________________________________
Email Address: _____________________________________