HomeMy WebLinkAbout02/06/1996, 9 - PROJECT BUDGET FOR PARKS AND RECREATION OFFICE BUILDING SPECIFICATION NO. 94-13B �IIIN�I IWIIIIIQ�p �I�III r ME_ I t A :
c� o sap suis os�spo
COUNCIL AGENDA REPORT ITE NU ER: D
FROM: Michael D. McCluskey, Public Works Directovv/�
Paul LeSage, Parks and Recreation Director
Prepared by: David Elliott, Administrative Analyses 7
SUBJECT: Project Budget for Parks and Recreate Office Building
Specification No. 94-13B
CAO RECOMMENDATION:
Appropriate an additional $68,200 to the project budget ($36,400 from the capital outlay fund_
completed projects account and $31,800 from the general fund unappropriated balance)
DISCUSSION:
Construction on the Parks and Recreation Office Building is about 80 percent complete.
Construction remains on schedule and the project should be substantially completed in mid-April
1996. When the aggregate cost of construction contract change orders exceeds 75 percent of the
contingency allowed for that purpose, purchasing policies require staff to inform the awarding
authority, which is the Council on this project. Costs in six areas, including construction
contract change orders, will exceed the amounts budgeted and will require adjustments to the
project budget.
1. Miscellaneous Design Services. Money was not budgeted for several minor services
required to design the project and get it out to bid. Because existing surveys of the site were not
adequate, staff ordered a new survey at a cost of$1,150. Also, money was not budgeted for
blueprinting the plans ($1,506) and printing the specifications ($627).
Recommended increase to the design budget: $3,300
2. Construction Contract Change Orders The project budget allowed $22,300 (about four
percent of the construction contract cost) for change orders. Although this amount was lower
than the eight to ten percent normally allocated, staff thought it would probably be adequate
based on the relative simplicity of the project and the reputation of the construction contractor.
Contract Change Order No. 1 (copy attached) included eleven revisions for a total of $22,930.
$9,329 of this amount was required for changes made during planchecking to the complicated
roof structure, an important element in fitting the building into the surrounding neighborhood to
satisfy architectural review requirements. This change order has exhausted the contingency
allocation. It appears there may be up to $7,000 more in change orders, which would bring the
aggregate cost of change orders up to about six percent of the contract cost.
Recommended increase to the construction budget: $7,700
3. Special Testing and inspection Services Extraordinary soil conditions found on the site
required laboratory testing of prepared soil and foundation concrete. Staff did not expect the
9�
'��� »►►►I�IIIIIIIIIII► ►��III city of san i.,s OBIspo
Mii% COUNCIL AGENDA REPORT
need for this testing and inspection and did not budget for it. Also, some structural welding
required certified inspection. Some additional soils testing will also be required before the
project is completed.
Recommended increase to the construction management budget.- $4,000
4. Architectural Consultation Services. The project budget allowed $7,500 for architectural
consultation on a time and materials basis to clarify plans and to design required plan revisions
during construction. Because of extensive consultation required on the roof structure, the cost
for these architectural services will probably be $13,000.
Recommended increase to the construction management budget. $5,500
5. Systems Furniture Installation.
When a-preliminary space needs analysis was completed early in the project planning stage, staff
budgeted $71,000 for furnishings based on an preliminary quotation from the city's contract
dealer for systems furniture. Later staff reduced this budget to $60,000 assuming that a) two
workstations would be eliminated because of organization changes in the Parks and Recreation
Department and b) some existing furnishings (particularly file cabinets) would be used in the
new building. The final quotation for furnishings is $87,400. Three factors contributed to the
increase from $60,000 to $87,400:
O The original quotation was done without the final furnishings plan and assumed a high
level of panel sharing because workstations would be clustered. This assumption turned
out to be too optimistic, because the building floor plan did not allow the typical level of
clustering. An additional 130 lineal feet of panels are required at a cost of $9,400.
O The $60,000 budget included three supervisor workstations, eleven secretary/coordinator
workstations, and two temporary employee workstations (total: 16). The final quotation
includes three supervisor workstations, twelve secretary/coordinator workstations, and
seven temporary employee workstations (total: 22) required to accommodate the current
Parks and Recreation staff after some recent additions. Two of the additional
workstations are for reservations and clerical workers transferred to Parks and Recreation
from other departments. One additional workstation is for a ranger hired in November
1995 to patrol parks and open space areas. The other three additional workstations are
for volunteer interns recruited to start or expand new recreation programs. The cost of
the additional six workstations comes to $13,000.
O The original quotation and the existing budget were based on 1994 prices. Since then,
there has been a five percent price increase, which accounts for $4,200 of the final
quotation.
Significant reductions in the furnishings budget are not feasible because calculations of space
needs and building size are based on the use of systems furniture. Generally, systems furniture
9-
����H�ibi►►IVIIIIIIIIIPp1�u�q�plll city of San _ ,JS OBISpo
Aii% COUNCIL AGENDA REPORT
takes up about fifteen percent less floor space than conventional furniture, and electrical,
communication, and computer network circuits are built into the systems furniture panels. Both
of these features reduce construction costs significantly.
Recommended increase to the equipment budget: $27,400
6. Data/Communication Cabling Installation
This work includes extending fiberoptic cable from the Marsh Street Parking Garage, connecting
all workstations to the wide area network, and installing phone lines. Because staff thought most
of this installation might be covered by other capital projects, no money was allocated for this
purpose in the project budget. Staff has received a quotation of$20,300 from the company
which has performed previous cabling installations and upgrades for the City.
Recommended increase to the equipment budget: $20,300
FISCAL EWPACT:
The proposed adjustments to the project budget are summarized in the table below:
Current Proposed Recom-
Project Project mended
Design Budget Budge, t Increase
Appraisal Services (860 Pacific) $ 2,000 $ 2,000
Architectural Design Services 29,300 29,300
Geotechnical Services 1,700 1,700
Surveying Services 0 1X 200 $ 1 200
Printing Services 0 600 X600
Blueprinting Services 0 1,500 1 500
Construction '
Base Construction Contract 511,600 511,600
Construction Contract Change Orders 22,300 30,000 7,700
Utilities Installation 17400 19400
Construction Management
General Inspection Services 15,000 15,000
Architectural Consultation Services 7,500 13,000 59500
Special Inspection and Testing Services 0 4,000 4,000
Equipment
Systems Furniture Installation 60,000 871400 27,400
Data/Communications Cabling Installation 0 20.300 20,300
$650,800 $719,000 $68,200
There is $36,400 currently available in the capital outlay fund completed projects account to
1
����N�i�►►►�Illll�flli !IIUIII city of San L.,s OBrspo
C®`JIVCIIo �►C�ENDA REPORT
cover part of the recommended increase. The _remaining $31,800 must come from the
unappropriated balance of the general fund:
Based on current projections of.general fundrevenues, expenditures, and ending balance (which
will presented to the Council in greater detail at the midyear budget review), there are adequate
resources to make the recommended appropriation and maintain fund balance at adopted policy
levels.
AT TACBMEW:
Contract Change Order No. 1
6:Ufuilding\parkreclagn.
i f
��►����►�!►►i►� ►IIIIIIIIIIIIIIh1°"'��"���" III
IL ity of sAn tuis oaspo
955 Morro Street • San Luis Obispo, CA 93401
CHANGE ORDER
PROJECT: PARKS AND RECREATION OFFICE PROJECT CHANGE ORDER NO: ONE (1)
OWNER: City of San Luis Obispo DATE: December 18, 1995
955 Morro Street
San Luis Obispo, CA 93401 ARCHITECT: Bruce Douglas Fraser, AIA
971 Osos Street
San Luis Obispo, CA 93401
CONTRACTOR: Carroll Building Company PROJECT NO: 94-13B
P.O. Box 179
San Luis Obispo, CA 93406
CONFORMANCE WITH CONTRACT DOCUMENTS, DRAWINGS, AND SPECIFICATIONS
All Change Order work shall be in strict conformance with the Contract Documents, Drawings, and
Specifications as they pertain to work of a similar nature.
CRB NO. DESCRIPTION DEDUCT ADD
#01 Plan check corrections issued after the bid date. $2,283.00
#02 Credit for utility materials not provided for City $511 .00 ,
crew's use.
#04 Added traffic rated pull box in intersection for fiber $ 952.00
optic conduit. Plans indicated pull box was existing.
#05 Revised Prim Trim -width to 5 1/2", added 5/8" furring at $ 694.00
truss connections for shims, revised 2x4 furred wall to 2x6.
#06 Added shear panel to the vertical surfaces of the gables of $1,771.00
the box above the lobby.
#08 Furring down the ceiling in the Vestibule and select areas of $ 194.00
the Men's and Women's restroom to enclose a truss tie-rod and
provide clearance at the recessed light fixtures.
#09 Revised landscaping around D.I. to maintain slopes for drainage. $3,467.00
Revised walkway for future tie-in with park.
#10 Provide revised connector at (3) truss end connection points. $ 748.00
The City of San Luis Obispo is committed to include the disabled in all of its services, programs and activities. `
Telecommunications Device for the Deaf(805)781-7410. ® 9J
Change Order No. One (1), 12/18/95
Parks and Recreation Office Project
Project No. 94-13B
Page 2
#13 Added utility extensions above original scope in lieu of City crews $4,305.00
crews performing the work. Involves power, phone, cable TV and
fire line/PIV.
MISC1 Miscellaneous revisions due to responses to RFI's. Most are structural $5,922.00
in nature due to the complexity of the roof structure.
N/A Add back in monies incorrectly deleted when Alternate deducts $3,105.00
#1 and #2 were selected by the City vs the application of
Alternate deduct #03.
SUBTOTAL DEDUCTIONS $511 .00
SUBTOTAL ADDITIONS $23,441.00
NET CHANGE $22,930.00
ORIGINAL CONTRACT SUM $511,564.00
NET CHANGE - ALL PREVIOUS CHANGE ORDERS $ -0-
ADJUSTED CONTRACT SUM $511,564.00
NET CHANGE - CHANGE ORDER NO. ONE (1) $ 22,930.00
ADJUSTED CONTRACT SUM THROUGH CHANGE ORDER NO. ONE (1) $534,494.00
COMMENCEMENT DATE June 26, 1995
ORIGINAL COMPLETION DATE (300 CALENDAR DAYS) April 20, 1996
TIME EXTENSION - ALL PREVIOUS CHANGE ORDERS -*-0 Days
ADJUSTED COMPLETION DATE PRIOR TO THIS CHANGE ORDER . April 20, 1996
TIME EXTENSION - CHANGE ORDER NO. ONE (1) 0 Days
ADJUSTED COMPLETION DATE April 20, 1996
RECO MENDED FOR APPROVAL
DATE:
onstruction Manager
APPROVED(
I)' DATE: .Z
Contractor
APP OVED
( l Lg2:= DATE:
City of San Luis Obispo
9-6