HomeMy WebLinkAboutSpecNo2000403_Engineer Estimate_202504091 MOBILIZATION 1 LS $5,000.00 $5,000.00
2 WATER POLLUTION CONTROL PROGRAM 1 LS $3,000.00 $3,000.00
3 CLEARING AND GRUBBING 1 LS $3,000.00 $3,000.00
4 REMOVE CHAIN LINK FENCE 20 LF $50.00 $1,000.00
5 CLASS II AGGREGATE BASE 6 CY $250.00 $1,500.00
6 CHAIN LINK FENCE 53 LF $200.00 $10,600.00
7 POTHOLE EXISTING UTILITIES 5 EA $1,500.00 $7,500.00
8 POWER BLOCK CONCRETE PAD 1 LS $96,250.00 $96,250.00
9 POWER BLOCK MOUNTING PLATES 6 EA $100.00 $600.00
10 PULL BOXES 1 EA $3,000.00 $3,000.00
11 CONDUIT, BENDS, AND MATERIAL 1 LS $20,000.00 $20,000.00
12 CONDUCTORS 1 LS $86,000.00 $86,000.00
13 CIRCUIT BREAKERS 1 LS $1,700.00 $1,700.00
14 BOLLARDS 4 EA $3,000.00 $12,000.00
15 CONSTRUCTION SURVEY 1 LS $5,000.00 $5,000.00
BID SUBTOTAL = $256,150.00
Contingency (10% of Total) = $25,615.00
BID TOTAL = $281,765.00
EA = Each, LS = Lump Sum, LF = Lineal Feet, SF= Square Feet, SY = Square Yard, CY = Cubic Yard
ADMIN
In providing opinions of probable construction costs, the City must understand that AKA Engineering has no control over the costs or the price of labor, equipment or
materials, or over the Contractor's method of pricing, and that the opinions of probable costs provided herein are made on the basis of AKA Engineering's qualifications
and experience. AKA Engineering makes no warranty, expressed or implied, as to the accuracy of such opinions as compared to bid or actual costs.
TOTAL ITEM COST
BATTERY ELECTRIC BUS CHARGING INFRASTRUCTURE PROJECT
CITY PROJECT #2000403
ENGINEERS OPINION OF PROBABLE CONSTRUCTION COST
CITY OF SAN LUIS OBISPO, CA
April 9, 2025