Loading...
HomeMy WebLinkAboutConstruction Schedule Tracker - SLO December 2025Project Title: Awardee Work Package Boundary Name Design in Progress - Consultant working on 95% PSE to be submitted in January Pole Access AT&T (Delayed due to AT&T requiring CPCN or CLEC. Consultant discussing with CPUC regarding potential excemptions or path moving forward) Pole Access PG&E (Waiting to submit after verification of path forward on AT&T Pole Access) Astound Partnership Agreement ROW - Margarita Villa (Not required due to terminating fiber in public ROW. Astound to work with Margarita Villa to provide fiber within Margarita Villa) Enviromental ((ISMND) Cal Trans Broadband Plan Implementation, Specification No. 20001063 City of San Luis Obispo Addresses Served* Nipomo/ Monterey Grand / 101 First Permit Submitted** Estimated Completion Date 4/1/2026 4/1/2026 6/1/2024 NA 10/1/2024 8/1/2025 Actual Completion Date 6/19/2024 NA 1/1/2025 Last Permit Submitted** Estimated Completion Date *Addresses Served should be a total unit count of all eligible served locations **First & Last Permit Submitted/Received must exclude environmental permits; should be used for excavation, pole access, fiber lease, traffic control, or right-of-way access (e.g. CalTrans permit) Actual Completion Date Last Permit Received** Estimated Completion Date Actual Completion Date Construction Started Estimated Completion Date 4/1/2026 4/1/2026 4/1/2026 Actual Completion Date Construction Completed Estimated Completion Date Actual Completion Date