HomeMy WebLinkAboutConstruction Schedule Tracker - SLO February 2026Project Title:
Awardee
Work Package Boundary Name
Design in Progress - Comments for final plans sent back to Entrust. Expect Final Plans in March
Pole Access AT&T (Delayed due to AT&T requiring CPCN or CLEC. Consultant discussing with CPUC regarding potential excemptions or path moving forward)
Pole Access PG&E (Waiting to submit after verification of path forward on AT&T Pole Access)
Astound Partnership Agreement
ROW - Margarita Villa (Not required due to terminating fiber in public ROW. Astound to work with Margarita Villa to provide fiber within Margarita Villa)
Enviromental ((ISMND)
Cal Trans - Working on Revised plan and profile for Caltrans submittal
Broadband Plan Implementation, Specification No. 20001063
City of San Luis Obispo
Addresses Served*
Nipomo/ Monterey
Grand / 101
First Permit Submitted**
Estimated Completion Date
4/1/2026
4/1/2026
6/1/2024
NA
10/1/2024
8/1/2025
Actual Completion Date
6/19/2024
NA
1/1/2025
Last Permit Submitted**
Estimated Completion Date
*Addresses Served should be a total unit count of all eligible served locations
**First & Last Permit Submitted/Received must exclude environmental permits; should be used for excavation, pole access, fiber lease, traffic control, or right-of-way access (e.g. CalTrans
permit)
Actual Completion Date
Last Permit Received**
Estimated Completion Date
Actual Completion Date
Construction Started
Estimated Completion Date
4/1/2026
4/1/2026
4/1/2026
Actual Completion Date
Construction Completed
Estimated Completion Date
Actual Completion Date