HomeMy WebLinkAboutConstruction Schedule Tracker - SLO January 2026Project Title:
Awardee
Work Package Boundary Name
Design in Progress - City received 95% plans. Review under way
Pole Access AT&T (Delayed due to AT&T requiring CPCN or CLEC. Consultant discussing with CPUC regarding potential excemptions or path moving forward)
Pole Access PG&E (Waiting to submit after verification of path forward on AT&T Pole Access)
Astound Partnership Agreement
ROW - Margarita Villa (Not required due to terminating fiber in public ROW. Astound to work with Margarita Villa to provide fiber within Margarita Villa)
Enviromental ((ISMND)
Cal Trans
Broadband Plan Implementation, Specification No. 20001063
City of San Luis Obispo
Addresses Served*
Nipomo/ Monterey
Grand / 101
First Permit Submitted**
Estimated Completion Date
4/1/2026
4/1/2026
6/1/2024
NA
10/1/2024
8/1/2025
Actual Completion Date
6/19/2024
NA
1/1/2025
Last Permit Submitted**
Estimated Completion Date
*Addresses Served should be a total unit count of all eligible served locations
**First & Last Permit Submitted/Received must exclude environmental permits; should be used for excavation, pole access, fiber lease, traffic control, or right-of-way access (e.g. CalTrans
permit)
Actual Completion Date
Last Permit Received**
Estimated Completion Date
Actual Completion Date
Construction Started
Estimated Completion Date
4/1/2026
4/1/2026
4/1/2026
Actual Completion Date
Construction Completed
Estimated Completion Date
Actual Completion Date