Loading...
HomeMy WebLinkAboutConstruction Schedule Tracker - SLO June 2026Project Title: Awardee Work Package Boundary Name Design Complete - Project plans readvertised. Bid opening on July 2. Pole Access AT&T (Delayed due to AT&T requiring CPCN or CLEC. Finalizing path forward with Astound submtting pole access documents) Pole Access PG&E (Waiting to submit after verification of path forward on AT&T Pole Access.Finalizing path forward with Astound submtting pole access documents) Astound Partnership Agreement ROW - Margarita Villa (Not required due to terminating fiber in public ROW. Astound to work with Margarita Villa to provide fiber within Margarita Villa) Enviromental ((ISMND) Cal Trans - Permit resubmitted with environmental documents requested Broadband Plan Implementation, Specification No. 20001063 City of San Luis Obispo Addresses Served* Nipomo/ Monterey Grand / 101 First Permit Submitted** Estimated Completion Date 4/1/2026 4/1/2026 6/1/2024 NA 10/1/2024 8/1/2025 Actual Completion Date 3/26/2026 6/19/2024 NA 1/1/2025 Last Permit Submitted** Estimated Completion Date *Addresses Served should be a total unit count of all eligible served locations **First & Last Permit Submitted/Received must exclude environmental permits; should be used for excavation, pole access, fiber lease, traffic control, or right-of-way access (e.g. CalTrans permit) Actual Completion Date Last Permit Received** Estimated Completion Date Actual Completion Date Construction Started Estimated Completion Date 4/1/2026 4/1/2026 4/1/2026 Actual Completion Date Construction Completed Estimated Completion Date Actual Completion Date