HomeMy WebLinkAbout07/02/1996, 8 - CHANGE ORDER FOR ASBESTOS REMOVAL CITY HALL SEISMIC SAFETY AND HVAC IMPROVEMENTS PROJECT SPECIFICATION NO. 9101-540-553 ,
council " - ° )
j acenba RepoiA
C I T Y OF SAN LU IS O B I S P O
FROM: Michael D. McCluskey, Public Works Director
Prepared By: David Elliott, Administrative Analystl�
SUBJECT: Change Order for Asbestos Removal
City Hall Seismic Safety and HVAC Improvements Project
Specification No. 9101-540-553
CAO RECOMMENDATIONS
1) Appropriate an additional $550,000 to the project construction account
2) If change order details have been successfully negotiated and a change order document
has been prepared, approve Change Order No. 2 for removal of roof panels containing
asbestos
3) If change order details have not been successfully negotiated and a change order
document has not been prepared, authorize the city administrative officer to approve
Change Order No. 2 for removal of roof panels containing asbestos
DISCUSSION
Background
One primary objective of this project was to remove and dispose of existing cementious roof
panels which contain high concentrations of asbestos.
In 1990 H.G. Degenkolb Associates, a structural engineering firm, surveyed all city buildings
to evaluate their ability to survive seismic forces. This firm found that certain structural
elements of the City Hall building might not withstand a major earthquake because of various
deficiencies, including the unanchored cementious roof panels. The entire sloped area of the
roof is formed by these panels (each measuring 30 inches by 18 inches by three inches thick
and weighing about 40 pounds) lying in L-shaped steel channels. A major earthquake could
dislodge or break these panels, which could in turn cause the roof system to collapse, release
harmful asbestos fibers, and expose employees on the upper floor to the danger of falling roof
material.
In 1992 Howard F. Stup & Associates, another structural engineering firm, analyzed the
structural deficiencies and recommended the current project. During schematic design, the
structural engineer from Stup & Associates observed that a panel near the rooftop access
hatch could be pushed up away from the steel framework with very little effort. From this
observation, the engineer apparently concluded that the panels could be removed without
breaking them and without creating a hazardous condition.
Council Agenda Report - Change Order for Asbestos Removal
Page 2
Construction started on May 28, 1996, with R.P. Richards, Inc. as the prime contractor. On
June 18, 1996 Lee Construction, the state-certified asbestos abatement subcontractor, tried to
remove a roof panel and found that the panel could not be dislodged as easily as the
construction documents implied without creating an asbestos hazard. Evidently, when the
panels were originally installed in the early 1950s, the contractor filled the gaps between them
with a mortar that produced a strong bond between the panels and the steel channels. After
alternative removal techniques were tested unsuccessfully, Ecosystems Technologies, the
City's state-certified asbestos consultant, determined that the panels would have to be removed
and disposed of as a hazardous material using full asbestos containment safeguards, including:
0 full tenting of the roof and attic
0 separate electrical service for the containment area
0 negative air pressure for the containment area
0 fully enclosed suits for abatement workers
0 elaborate decontamination areas
0 24-hour air quality monitoring throughout the building
0 extensive documentation of all work and conditions
At that point the City notified the County Air Pollution Control District and the State
Department of Occupational Safety and Health about the situation. Those two agencies will
be monitoring the project until completion of the asbestos abatement.
Change Order Negotiation
To estimate the time needed for panel removal, Lee Construction built a small containment
area and had asbestos abatement workers take out 15 panels under the identical circumstances
they would face in removing all of panels under the change order. Based on this information
and the mandatory containment procedures dictated by state regulations, the contractor
submitted a preliminary change order cost proposal in the amount of $530,000.
Richard Fisher and David Elliott from Public Works and Marcia Walther, the City's
contracted resident inspector, formed a team to review this cost proposal. The team first
consulted with Remtech, the certified asbestos abatement contractor which performed much of
the previous abatement work at City Hall (including encapsulation of the roof panels). From
a contractor's perspective, Remtech reviewed the proposal and found it reasonable, without
any apparent padding. The team then brought in American Environmental Specialists, a
second, independent, state-certified asbestos consultant, to examine in detail the supporting
documentation for the change order. From a certified inspector's perspective, American
Environmental determined the proposed scope of work and cost to be fair and typical.
Although the team and the consulted firms concluded that the proposal accounted for a high
level of financial risk, they could find no unwarranted cost items. What contributed most to
the high cost was the unconventional use of asbestos in the cementious roof panels. No one
from the consulted firms had ever seen or heard of a similar installation. Consequently, it is
O '�
Council Agenda Report - Change Order for Asbestos Removal
Page 3
not surprising that the cost estimates included contingencies for unanticipated problems.
When this agenda report was completed, Public Works was still negotiating details of the
final change order document with a goal of having a completed document available for
distribution and discussion at the Council meeting. If that document is completed, Public
Works recommends Council approval of the change order. If the document is not completed,
Public Works recommends Council authorization for approval by the city administrative
officer to avoid construction delays.
Building Safety During Construction
Lee Construction is a state-certified asbestos abatement contractor. Overseeing Lee
Construction is Ecosystems Technologies, a state-certified asbestos consultant. And
overseeing the entire operation are the County Air Pollution Control District and the State
Department of Occupational Safety and Health. With all the containment and monitoring
procedures required by law, the safety risk entailed with removing the roof panels is virtually
nil, and certainly far less than the potential risk during and after an earthquake.
FISCAL IMPACT
The estimated cost of Change Order No. 2 is $530,000, and there will be other associated
costs for independent consultation and monitoring. Public Works recommends appropriating
an additional $550,000 to the project account from the unappropriated balance of the general
fund.
The balance of the general fund is currently projected to be $4,261,800 at the end of 1996-97.
(See page G-6 of the Approved 1996-97 Budget.) This amount is sufficient to maintain a
reserve equal to 20 percent of operating expenditures as required by the City's general budget
policies. (See page B-10 of the 1995-97 Financial Plan.)
Appropriating $550,000 from this projected balance would reduce the reserve to 17 percent of
operating expenditures. But this temporary reduction would be justified by one of the stated
purposes for the reserve, which is to cover unforeseen operating or capital needs. A
reasonable goal would be restoration to the 20 percent level by the end of 1998-99.
ALTERNATIVES
The only alternative to removing the roof panels would be closing the roof back up and
terminating all work on the roof and in the attic. Although this alternative might be feasible,
it would create three major problems:
1) None of the heating, ventilating, and cooling (HVAC) equipment for the upstairs areas
could be installed, because state law would prohibit continuing this work with the roof
O ��
Council Agenda Report- Change Order for Asbestos Removal
Page 4
panels in place. There is currently no HVAC equipment serving the upstairs areas.
2) State law would prohibit any future construction or repair work on the roof or in the
attic with the roof panels in place.
3) The potential seismic hazard would go uncorrected, and City Hall would remain
vulnerable to a major earthquake. This situation would not:only jeopardize
continuation of essential services, but could also hamper future enforcement of seismic
safety correction ordinances in cases where property owners might encounter
unexpected and costly complications.
hAbuilding\chhvac\asbestos.agp