From:Helene Finger <helenefinger@gmail.com>
Sent:Wednesday,
To:Advisory Bodies
Subject:ATC Nov 19, 2026 Meeting, Item 4b
Attachments:Pages from 02-16-2022 ATC Agenda Packet.pdf; Comments Madonna in Higuera ATP
app.pdf
Dear Active Transportation Committee Members,
Thank you to staff for preparing the report for Nov 19, 2026 ATC meeting Item 4b and providing context for the
ATC’s financial plan recommendations, including members’ funding priorities.
Having followed this process for more than a decade, I was encouraged to see the Madonna project rank near
the top in both Figures 3 and 4. Those rankings continue a longstanding commitment by the ATC and City
Council to create a safe connection along Madonna Road for people walking and bicycling.
I respectfully urge the ATC to move “Initiate feasibility study for Madonna Class I Overpass” to Priority
#1. Doing so would reflect members’ rankings and continue progress on a project that the ATC has supported
for years. The feasibility study is a practical first step that needs to happen now so the City can prepare the
project for future funding and construction.
For members who may be unfamiliar with the project’s history, the ATC selected the Higuera corridor as the
first Tier 1 Active Transportation Plan project to begin planning in 2021. At the same time, the committee asked
that Madonna Road from Higuera to the Madonna Inn be included because of the complexity of the
Madonna/Higuera intersection and the lack of a low-stress bikeway along that segment. The attached February
2022 staff report documents this decision.
The City later received an Active Transportation Program grant for the Higuera Complete Streets project, which
is now under construction. The grant application emphasized the need for a safe Madonna Road connection. It
described middle school students and staff bicycling over Highway 101 on their way to Laguna Middle School
and noted that they considered the route dangerous. It also reported that some parents would not allow their
children to bicycle through the area, even though they wanted to give them more freedom. Excerpts from the
application are attached.
The ATC and City Council have continued to support the Madonna project:
May 16, 2024:
The ATC unanimously approved a multiuse path on Madonna Road from the Madonna Inn to Higuera.
November 21, 2024:
After learning that the project had stalled, a majority of ATC members requested that staff seek grant
funding for it. This also led to a City Council study session.
1
February 4, 2025:
City Council unanimously directed staff to move the project forward. Council members emphasized its
importance for safe travel to work and school and for connecting the east and west sides of the
community.
October 15, 2026:
The ATC was informed that work in 2027–29 would be a feasibility study. The City has applied for a
SLOCOG grant that could fund 50% of this planning work.
The Madonna connection has been a priority for years, and members’ current rankings show that it remains
one today. With limited funding available, I urge the ATC to place the feasibility study in Priority #1 so this
essential connection can continue moving forward.
Kind regards,
Helene Finger,
2
CityofSanLuisObispo, Agenda, PlanningCommission
Active Transportation Committee
AGENDA REPORT ITEM 2
DATE: February 16, 2022
FROM: Adam Fukushima, Active Transportation Manager
SUBJECT: Higuera Corridor Complete Street Project - Preliminary Design
Recommendation:
1. Review and comment on the preliminary engineering concept plans to help guide further
development of the Higuera Corridor Tier 1 ATP project
Background
At the September 16, 2021 meeting the Active Transportation Committee (ATC) recommended a
prioritization list for the Tier 1 projects from the Active Transportation Plan. This list will help
staff get an early start in the planning and funding of these projects ahead of each budget cycle and
serve as a tool to inform the committee’s future budget requests. From that prioritized list, the ATC
selected the Higuera corridor from Marsh to Los Osos Valley Road as the first project to begin
planning and recommended use of $50,000 in the 2021-23 FY Budget toward preliminary
engineering. The Higuera corridor has a high ridership potential (40% of all trips as detailed in the
Active Transportation Plan) as well as the opportunity to take advantage of two already planned
improvement projects in the current budget cycle: repaving of Higuera (Marsh – Madonna) in 2023
and a safety widening project on Higuera (Bridge – Elks). Given the complexity of the intersection
at Madonna / Higuera and lack of low-stress bikeways on Madonna between Higuera and the
Madonna Inn entry, the committee also requested that the segment of Madonna Rd from Higuera
to the Madonna Inn also be included with this project.
Over the last few months City staff has been working with a consultant, Alta Planning + Design,
and have completed preliminary engineering plans (10% level completion) for committee input
and comment. It must be emphasized that these plans are preliminary and still require further
analysis. In particular, the design must also be guided with parallel analysis of any changes to
traffic operations associated with the proposed corridor improvements, which will help identify
any possible conflicts with the General Plan policies and help guide the final project
recommendations. While the intent of this project is to increase safety and priority for active
transportation users along the Higuera corridor, potential impacts to vehicular traffic operations
must at least be considered, evaluated and disclosed under the framework of the General Plan
circulation policies, particularly potential impacts to transit and emergency response.
The current design concepts have been guided by a high-level assessment of traffic capacity needs
based on existing and projected future auto traffic volumes, but staff did not want to progress with
Quotes from the City’s Higuera Complete Streets project ATP grant application:
● “The project includes improvements along Higuera St, Madonna Rd, South St. and
nearby neighborhood streets in South San Luis Obispo.”
● “This project will create an important North/South and East/West connection to
existing protected bike lanes in the city.”
● “Parents were able to provide input on their needs at Hawthorne Elementary
School’s Safe Routes to School Bike Safety Event (4/24/22) where parents
requested safer crossings at South & King St. and South Higuera & Madonna Road.
Parents also expressed the need for safer bike lanes for middle school aged
children biking to Laguna Middle School via Higuera Street & Madonna Road.”
● “There are over 20 middle school students and staff who currently bike to Laguna
Middle School from this side of the US-101, some riding as much as 5 miles to
school each day. These young active students love to start their day with a ride to
“wake up and get the energy out” before class. However, they all agree that the
route is dangerous from the Madonna & South Higuera intersection, over US-
101, to the Class 1 path on the other side. Many parents won’t let their children
bike through the area even though they’d like to give them more freedom.”
● “Currently, there are adults of all ages bike commuting along the route for work,
shopping, or recreation. Middle school students also travel through the South
Higuera & Madonna intersection and along Madonna Road over US-101 on their
way to school. The students and teachers that commute this way all express worry
about their safety when crossing through this zone. The bike lane is narrow, and
drivers are frequently distracted and drift into the bike lane. One teacher who bikes
remarked that his wife is afraid of him traveling this route since her own father was
killed in a cycling accident, but he needs to save money on gas. The couple has 4
children and many expenses. There have been twelve incidents (one a fatality) in
this zone of the project area in the last 10 years.”
● “Location: Intersection of South Higuera St. & Madonna Rd. This intersection is
difficult for cyclists to navigate, and students biking to Laguna Middle School pass
through here daily. There have been 4 bike collisions here and one pedestrian
collision.”