HomeMy WebLinkAbout04/06/1999, 4 - HIGUERA STREET BRIDGE PROJECT WITH PEDESTRIAN ENHANCEMENT FEATURES council )rnl6, 1999
j acEnaa uEpont 4
CITY OF SAN LUIS 0 B I S P 0
FROM: Michael D.McCluskey,Director of Public WorksNbk
SUBJECT: HIGUERA STREET BRIDGE PROJECT WITH PEDESTRIAN
ENHANCEMENT FEATURES
CAO RECOIVEMNDATION
1. Approve the concept of widened sidewalks along Higuera Street in the vicinity of Osos Street
as a part of the Higuera Street Bridge Rehabilitation Project
2. Appropriate $ 43,000 from the unappropriated balance of the General Fund for Higuera Street
Bridge environmental and design services.
3. Authorize the CAO to execute the amendment to the agreement for environmental and design
services with Martin and Kane,Inc.
DISCUSSION
The City is in the midst of design for the rehabilitation of the Higuera Street Bridge in the
vicinity of Osos Street downtown. Design is expected to be completed in the fall with
construction to take place next summer. The Downtown Association (DA) parking committee
requested the City explore the possibility of installing "bulbouts" along Higuera in conjunction
with the bridge project However, the bulbouts proposed are much more than those found at
various intersections along Marsh Street What has been actually proposed is an area of widened
sidewalk which would allow the City the opportunity of providing various pedestrian activities.
The original request envisioned an area (most likely the old sidewalk area) that would be
available for outdoor dining from nearby/adjacent restaurants. While staff is open to this idea,
other ideas that have since been promulgated include: area for public art; drinking fountains;
sitting areas in general, planters and other amenities, etc. Assuming the Council supports the
concept of widened sidewalks, community development staff is currently working on preparing a
stakeholders meeting and from there bringing recommendations to the Council (in the future) on
how the extra space would be utilized and what, if any, income to the City might be achieved by
renting out such space to private entities, such as restaurants.
After first receiving the request from the DA Parking Committee, staff asked for the thoughts of
the DA Board of Director;, adjacent business owners, and the former design team for the
Conceptual Plan for the City Center (the "Downtown Plan".) The Board of Directors voted in
favor, as did the property owners (or their representatives) for three of the four affected
properties. The Board of Directors of First Bank did not favor the project because of the loss of
one of the three on-street parking spaces. Given the small loss, and because First Bank is the
only business in the area with their own on-site parking, staff recommends continuing to include
this component in the project
Four members of the Downtown design team met. They affirmed the conceptual plan does call
for eventual widening of the sidewalks. Those members expressed support for the project. The
4-1
- r
f
Council Agenda Report—Hignera Street Widened Sidewalks
Page 2
members reviewing the sidewalk proposal include, Pierre Rademaker, Chuck Crotser, Andrew
Merriam and Ken Schwartz.
This is a rare opportunity because of the bridge construction to complete work envisioned in the
conceptual plan for downtown. The project will also improve the pedestrian crossing by making
it shorter in all directions. The business community generally supports the project, including
those affected, as does the downtown parking association and the concept design committee.
Staff feels this project is a worthwhile one and should be pursued at this time. The sidewalk
work planned at the comer adjacent to First Bank is very minimal, only what is needed to allow
the sidewalks to line up with those on the other comers. The availability of off street parking for
their customers should minimize the effect of this project on them.
The project itself proposes to widen the sidewalks using standard Mission style sidewalk. North
of Osos Street, the widening will begin at the Higuera Street Bridge structure and continue
southerly to Osos Street (See Exhibit A). South of Osos Street the sidewalk would be widened
on the west side (over the bridge structure) the full distance from Osos to Court Street. The
parking configuration within the Court Street parking lot would be realigned to limit turning
movements to Court Street only. Minimal sidewalk widening on the east side would occur, in
fact so little that it could only be considered a true bulbout.
While the project will significantly increase the pedestrian environment, it will, by its very
nature, remove on-street parking spaces. A total of 16 parking spaces will be removed as
follows: a) seven spaces from the west side, north of Osos (Woodstocks) frontage; eight spaces
from the east side, north of Osos (Firestone); one space east side, south of Osos (First Bank).
The loading zone currently along Higuera Street adjacent to the Court Street parking lot will be
removed and additional length added to the loading zone around the comer on Osos Street.
The project also includes decorative crosswalks. Staff is going to specify a`paver"instead of the
stamped concrete used at other locations downtown due to issues raised by the disabled
community about the problems associated with the stamped concrete crosswalks found on Marsh
Street. Pavers give a flat surface while providing color contrast and textured appearance.
Finally,this project also includes a small amount of widening of Osos Street(west of Higuera)to
allow through traffic lanes to align correctly and installs a new signal pole that meets current
state standards.
The bridge construction project includes the replacement of the deck and for the length of the
project,the sidewalk. The existing sidewalk and street section above the deck will be removed in
order for the deck to be replaced Whether the City replaces the area above the deck with 8 feet
of sidewalk and 12 feet of paving or 15 feet of sidewalk.and 5 feet of paving is irrelevant to the
project But now is the time to make that decision. The Bridge project also includes a sewer
replacement project in the same area as well as complete new road resurfacing. Thus,on the east
side of the street the choice is repaving 25 feet of street or repaving 18 feet and constructing
seven feet of new sidewalk. Funds will be spent in the area anyway,the question is how does the
City want those fiords expended? Staff feels that the widened sidewalks will add value to the
downtown and thus recommends this project be approved.
4-2
Council Agenda Report—Hignera Street Widened Sidewalks
Page 3
CONCURRENCES
The Downtown Association Executive Board and Parking Committee, the adjacent property
owners with the exception of First Bank and the former design team for the conceptual plan have
all approved the concept.
FISCAL EVVIPACT
The bridge construction is fimded through the Federal Highway Administration Bridge
Rehabilitation program. The program reimburses the City for 80% of costs. The program will
not reimburse costs for improvements to the site. This includes items such as the extra costs
associated with Mission Style Sidewalk. There will be some cost benefit, as the City can be
reimbursed for a portion of the work, that portion of the cost which equates to the cost to install
standard gray sidewalks of the existing width as well as the asphalt cost saved. The costs of
additional design work for this work will be at the City's cost and is not covered by the FHWA
9=t-
Proposal Revised
City Funds Grant Funds City Funds CLty Funds Grant Funds
Desi Contract 124,600 498 414 43 000 167,600 498,414
Construction est 640,000 2,560.000- 134 000 774,000 2,560 000
ALTERNATIVES
If the Council chooses not to construct the sidewalk widening at this time, staff still recommends
Mission Style Sidewalk be installed in lieu of the standard gray.
ATTACMdENTS
Exhibit A-Location Map/Concept Design
Exhibit B -Example of pavers
Contract Amendment
"mss- WwW amnowmnu tea=
4-3
I
e I I I l i
II
II
II
I
�w1b
s 3
o I ! ♦"
I I I I I
II
I y
I: }}
I I
—!DODI N:4M.I�1 T ��i I�_T'_ �� -�_ i q:C•aD: .- ,.
I
I IT
I I
/� LR
s ,0, Acs I I�
E Vr 7
' _ • I I
• •r r l I I k
I1
• I� ,� ` l i I ' t c
•1 r: I I I �
y. I
II'' ..
6 i CR
Y r I I 1 V
C
II
N .
I
I I
_Lf I
�,•IY� i I I i -_
I I
4-4
(03
• I
x ,t
V", _
Nit
ss—
Is—
sif
-
�
,a
1 T
:Ft-� � -• c y d lz t-
�s � aai5 � .•
G`tea is 6° - �, ' zz t1 s ���r^c ,;A,� °' a� to•.
L r
-v, v s xt
Tey pa V r x S�ry orf
a--
_ �� ` ����s>cep 1 " °'•�- .. '�r
F T -�'7'n= Fcf Sao �
F <
C_�
AMENDMENT TWO TO AGREEMENT
THIS AMENDMENT TO AGREEMENT is made and entered in the City of San Luis
Obispo on this day of , 1999, by and between the CITY
OF SAN LUIS OBISPO, a municipal corporation, herein after referred to as City, and Martin &
Kane Inc., Consulting Engineers hereinafter referred to as Consultant.
WITNESSETH:
WHEREAS, on November 4, 1997 the City entered into an Agreement with Consultant
for design and environmental services for the Higuera Street Bridge;and
WHEREAS,the City desires to amend the scope of services to include additional design
services as outlined on the attached proposal;
NOW THEREFORE, in consideration of their mutual promises, obligations and
covenants hereinafter contained,the parties hereto agree as follows:
1. The scope of services and related compensation is hereby amended as set forth in the
revised work scope and Consultant proposal attached hereto.
2. All other terms and conditions of the Agreement remain in full force and effect
IN WITNESS WHEREOF,the parties hereto have caused this instrument to be executed
the day and year first written above.
ATTEST: CITY OF SAN LUIS OBISPO,
A Municipal Corporation
By:
City Clerk Mayor
APPROVED AS TO FORM: CONSULTANT
By:
ty MAY
Higuera-Bridge7- Amendme
REVISED WORK SCOPE-Amendment Two
The following lists the major elements needed to complete the revised work covered in this
amendment.
I. Design of new widened sidewalks and relocated sidewalks including:
A. Design of sidewalks
B. Accommodation in structure design for paver crosswalks and revised sidewalks
C. Survey
D. Utility Relocations
E. Drainage
F. Traffic Signal Modification
G. Environmental Clearance
H. Public Outreach
TOTAL not to exceed............................$41,400
Higuera Bridge- Amendm t
APR-07-99 07 :31 AM P. 02
MEET1 6 SEM #ENDA RECE .
DATE `�--1--
APR - 6 1999
To: Members of the City Council. SLO CITY G- .:
From: Concerned property and business owners.
Attached please find a sketch of our recommendation in regarc 5 to the proposed sidewalk widening being
considered as part of the Higuera Street Bridge project. As yo i can see our concept only removes six
spaces as opposed to 16 and is being recommended as a trial project only based on the following:
A parking in lieu fee be paid for all spaces removed.
All improvements to be paid for by the tenant or property I caner.
An allowable use be proposed and approved before any sp Ices are removed
These conditions are being recommended to ensure that all s cos removed will be beneficial to creating a
more friendly pedestrian environment while continuing to support the construction of future parking
structures.
RECEIVED
APR -.6 1999
SLO CITY CLE]
RK❑CDD DIR
O ❑FIN DIR
AO ❑FI CHIEF
ORNEY W DIR
LERKIORIO ❑POLICE CHF
GMT TEAM ❑REC DIR
❑UTIL DIR
❑PERS DIR
r1PR-07-99 07730 nM P. 01
facsimile tansmittal
To: Dave Romero Fox: 781-7109
FMM'. Mike SpW9lcr Date: 041061"
Re. lupero seed Bridge Pd9a1: 1
CC:
D urpett o Far Ard w 0 pkM Cemmad 13 Pam FOW D MOM P-Myck
Iloleploose review this with the drawing previot:sl faxed to you today. if t11is copy doesn't
came through please let me know.
. . . . . . . . . . .
. . . . . . . . . . . . .
,84/66/1999 16:05 7817196 PAM KING rapt 01/91
I
h�
�ti A I
I '
I
I
I
I tL
10,
I
I
� I �
1