HomeMy WebLinkAbout09-02-2014 B4 Financial Plan Schedule for 2015-17City of San Luis Obispo, Council Agenda Report, Meeting Date, Item Number
FROM: Katie Lichtig, City Manager,
Wayne Padilla, Director of Finance & Information Technology
Prepared By: Joe Lamers, Budget Manager
SUBJECT: FINANCIAL PLAN SCHEDULE FOR 2015-17
RECOMMENDATION
Approve the goal setting process and timetable for development of the 2015-17 Financial Plan.
REPORT-IN-BRIEF
This report sets forth the proposed Council goal setting process and schedule for the
development of the City’s 2015-17 Financial Plan. The key dates and steps in the goal-setting
process are summarized below and then discussed in greater detail. The Council meeting dates
shown in June 2015 cover the review and ultimate adoption of the budget generated by staff
following the Goal Setting and Strategic Budget Direction:
Proposed Key Council Meeting Dates: Goal-Setting Process for 2015-17
Thursday, November 13, 2014
Special Meeting
7:00 to 10:00 p.m.
1) Setting the Stage. Provide the background needed for goal-setting
by considering the current status of both long and short term goals
previously adopted by the City. This meeting will include an update of
the General Plan status, Capital Improvement Plan projects, and Major
City Goals.
Tuesday, December 16, 2014
Regular Meeting
2) Budget Foundation. Finalize plans for the goal-setting process
including deadline for submitting Council Member candidate goals;
review Financial Plan policies and organization of the Financial Plan;
review of results from 2013-14; hold initial discussion on options to be
considered for paying down the unfunded liabilities.
Tuesday, January 13, 2015
Special Workshop
6:30 to 9:30 p.m.
3) Community Forum. Consider comments and suggested goals from
residents, community groups, other interested individuals and Council
advisory bodies.
Saturday, January 24, 2015
Special Workshop
8:30 AM to 4:00 PM
4) Council Goal-Setting Workshop. Discuss candidate goals
presented at Community Forum; consider Council member goals;
prioritize and set Major City Goals.
Tuesday, April 14, 2015
Special Workshop
6:00 to 10:00 p.m.
5) Major City Goal Work Programs & Strategic Budget Direction.
Conceptually approve detailed work programs for Major City Goals
adopted by the Council; set strategic budget direction for preparation
of the 2015-17 Financial Plan.
9/2/14
B4
B4 - 1
Financial Plan Schedule 2015-2017 Page 2
Proposed Key Council Meeting Dates: Budget Adoption for 2015-17
June 8, 9, 10, 2015
(Mon, Tues, Wed)
Special Workshops
5:00 to 9:00 p.m.
Hold workshops to review and discuss Preliminary Budget
- June 8: General Fund operating programs
- June 9: General Fund CIP projects
- June 10: Enterprise Fund programs, CIP projects and rates
Tuesday, June 16, 2015
Regular Meeting
Continues Financial Plan review and adopts budget. Holds special
meeting on June 23 if needed to continue review and adopt budget.
DISCUSSION
Based on the City’s experience over the years, informed by Council and community feedback, staff
recommends beginning the two-year 2015-17 Financial Plan process with the Council setting goals
for the most important initiatives for the City to accomplish over the next two years. This has been
a successful approach in assuring the most optimal achievement of the fundamental purpose of the
City's budgetary process which is:
Linking what we want to accomplish for our community over the next two years with the
resources necessary to do so.
As mentioned above and as reflected in the schedule at Attachment 1, staff is recommending a five-
step process for identifying and reaching agreement on the Council’s Major City Goals. Each of the
five major goal setting steps is described in greater detail below:
1. “Setting the Stage” Workshop. A special
meeting on November 13th will be devoted to
a comprehensive review of the status of
current City plans, goals, policies and
programs. This is an especially appropriate
start as the Council goal-setting process
should take into consideration the City’s
adopted long-term plans, current two-year
goals, and updated fiscal outlook.
Accordingly, staff plans to present reports
on the following:
a. Status of General Plan Programs. Staff
plans to present an overview of the
status of each General Plan program in
all of the ten Elements (over 400
programs in total). Organized by
Element, staff will provide a short
New Council-Elect Members
In order to “set the table” in a timely
manner for the goal-setting and budget
process, this meeting must be scheduled
before any new Council members take
office in December. However, the
“Council-Elect Members” will be known by
then and will be encouraged to attend.
With its emphasis on revisiting existing
plans, policies and goals, this is an excellent
“primer” for any new Council members.
For this reason, staff will highlight the
importance of this workshop with Mayor
and Council candidates, and strongly
encourage them to put this on their
calendars to attend if they are elected.
B4 - 2
Financial Plan Schedule 2015-2017 Page 3
summary of each program, whether it has been completed, and if not, a high level
assessment of how difficult it will be to complete. As we did two years ago, we also plan
to present a similar summary of the status of the programs in the Conceptual Physical
Plan for the City’s Center. While this is not a General Plan Element, it is referenced in
the General Plan, and several of its programs are closely linked and provide a framework
for Downtown development.
b. Long Term Capital Improvement Plan. This will provide a “high level” summary of the
estimated costs of the new facilities and infrastructure that will be needed to implement
our General Plan at build-out based on plans and policies previously adopted by the
Council.
c. Status of Our Current Two-Year Major City Goals: Carryovers and Spin-Offs. Since
some of the Major City Goals may not be complete by June 2015 the unfinished work
needed to complete them may be candidate Major City Goals for 2015-17. For those
goals where the specific work programs for 2013-15 may be completed by June 2015,
there may be “spin-off” tasks as a result. This is especially true for work programs where
the objective was to complete plans or studies. A likely “spin-off” into 2015-17 may be
implementation of these studies.
d. Status of Current Capital Improvement Plan (CIP) Projects. This report will present an
overview of the status of all current CIP projects. It will also identify candidate projects
for deletion or deferral based on their status and priority relative to other needs that have
emerged since they were initially approved.
The volume of information to be conveyed at the “Setting the Stage Workshop” makes it most
effective to hold a dedicated budget workshop to ensure adequate time for the Council to ask
questions and fully discuss these issues.
2. “Budget Foundation” Workshop. This meeting on December 16th will be dedicated to
generating policy guidance from Council that will serve as the foundation for the City’s budget
and goal-setting process. Staff plans to cover the following topics at this workshop:
a. Finalize plans for the Community Forum and Council Goal-Setting Workshop. Staff will
present a proposed approach for the forum and goal-setting workshop at this meeting.
b. Review Financial Plan policies contained in Section H of the 2013-15 Financial Plan and
update or recommend changes as appropriate. This may include proposed changes to the
existing fund balance targets for enterprise funds and capital replacement funds.
c. Review the organization of the Financial Plan and obtain Council guidance regarding the
style of presentation expected or preferred by Council.
d. Present the Comprehensive Annual Financial Report and discuss financial results for 2013-
14 and their impact on the budget process.
B4 - 3
Financial Plan Schedule 2015-2017 Page 4
e. Hold initial discussion on the options to be considered for paying down the unfunded
liabilities. Based on Council feedback, staff would return in February with the plan
reflecting these options. Getting direction from the Council in February will be helpful in
crafting the recommendations contained when Strategic Budget Direction is sought in April
2015.
Staff recommends dedicating the second Council meeting in December to this workshop.
However, if other routine business is required, an earlier start time may be desired.
3. Community Forum. Held on the evening of Tuesday, January 13, 2015, the purpose of this
workshop is to solicit and discuss suggested goals and work programs from Council advisory
bodies, community groups and interested individuals. Advisory Body goals will be developed
during the fall of 2014 and submitted to staff in final form by the end of December 2014. As in
the past, staff plans to hold the community forum at the Ludwick Community Center.
Other Community Outreach Efforts. Following Council approval of the budget calendar, staff
will mail notices to community groups, governmental agencies, media organizations and
interested individuals inviting them to participate in this process. In addition to these notices,
staff plans to place display ads in The Tribune, SLO Journal, SLO City News, and New Times in
order to encourage the broadest possible participation in this process. Information about the
goal-setting and budget process will also be placed on the City’s web site. Staff will explore
other means such as social media outlets, that will help spread the word about this important
opportunity.
Staff also intends to again insert a Community Budget Bulletin in all utility bills inviting the
public to participate in the goal-setting and budget process, and soliciting comments on the
“three to five most important things for the City to do in the next two years.” In the past this
approach has generated hundreds of replies which were transcribed in their entirety and
distributed to the Council along with a summary of “top themes.”
4. Council Goal-Setting Workshop. Following the receipt of written and oral comments during
the Community Forum, the Council goal-setting workshop will be held on Saturday, January
24, 2015 in a suitable venue such as the City/County Library Community Room. This will be
an all day workshop to answer the question, “What are the most important, highest priority
things for the City to accomplish over the next two years.” Council will be asked to provide up
to five goals before the workshop which staff will organize and distribute prior to the workshop.
As in the past, staff recommends the use of a professional facilitator to assist in prioritizing input
into three categories, Major City Goals, Other Council Objectives, and Address as Resources
Permit. Using an independent facilitator allows all Council members to participate fully in the
process; and allows staff to devote our efforts to listening and learning. Moreover, the facilitator
can assist the Council ensuring that the number, size and scope of the goals established are
appropriate.
B4 - 4
Financial Plan Schedule 2015-2017 Page 5
5. Major City Goal Work Programs and Strategic Budget Direction. Following the Council
goal-setting workshop, a critical part of this process, referred to as Strategic Budget
Direction, affords the City Council an early opportunity to review the draft work programs
and associated financial resources proposed to accomplish Major City Goals established by
the City Council in January. At this stage of the process the City Council provides direction
on any changes needed to refine these work programs and resource allocations to better
achieve the desired outcomes. Additionally, the City Council is asked to provide the City
Manager with the key policy direction needed to allocate resources in line with Council’s
expectations or to further amend budget or fiscal policies that align with Council direction.
This process is extremely helpful so that the Preliminary Financial Plan that is presented to
the City Council and community in May mirrors the Council’s expectations as much as
possible.
At this meeting staff will prepare detailed work programs for the Major City Goals and present
them to Council in a special meeting and workshop scheduled for April 14, 2015 in order to:
a. Clearly define and scope the work program.
b. Ensure that there is a clear understanding of the means used in pursuing the goal.
c. Convert the general goal into specific action steps so we can measure progress in
achieving it.
Each work program will provide the following information:
Objective. What do we specifically want to accomplish? (This will be based on the
objective adopted by the Council at the January 24th goal-setting workshop.)
Discussion. What are the factors driving the need for this goal? What actions have we
already taken in trying to resolve this problem area? What are the key assumptions? What
key challenges, constraints or obstacles can we expect in achieving this goal? What concerns
or issues will remain unresolved even if the goal is achieved? Who are the key stakeholders?
Action Plan. What specific tasks will we need to accomplish in order to achieve the goal,
and when will we complete them? These “action steps” are the fundamental building blocks
in defining and scoping the work program, and in monitoring our progress in accomplishing
the goal over the next two years.
Responsible Department. Who is accountable for getting it done?
Financial and Staff Resources Required to Achieve the Goal. What will it take to achieve
the goal? Do we need to add resources (staffing, contract services, CIP project) to do this?
Outcome: Final Work Product. What will we get if we achieve the goal? What’s the
“deliverable?”
B4 - 5
Financial Plan Schedule 2015-2017 Page 6
6. Budget Hearings and Budget Adoption. Budget hearings (also known as “Fund Reviews” for
the enterprise funds) are currently scheduled for three consecutive meeting days in June. This
was done in the last budget cycle to address the council’s concerns that too much time came
between meetings when the hearings were spread out over a 2 to 3 week period. This is a perfect
opportunity for the Council to reflect on this schedule versus other options (3 meeting over a ten
day window as an example).
Council Advisory Body Participation
Consistent with past Council direction, the advisory bodies will again play an important role in
the goal-setting process by providing the Council with their recommended goals for 2015-17.
Staff will provide advisory body members with background materials outlining their important
role in this process and have scheduled an update on this process at the next quarterly meeting
with the Mayor and advisory body chairs on October 16, 2014. Lastly, support staff liaisons are
already beginning to work with Advisory Body Chairs in scheduling time for this purpose at
upcoming advisory body meetings.
SUMMARY
This report sets forth the proposed Council goal setting process and schedule for the
development and ultimate adoption of the City’s 2015-17 Financial Plan. Council will be asked
to consider whether the budget workshop dates are acceptable or need to be changed to suit their
needs for reviewing the preliminary financial plan.
FISCAL IMPACT
There is no direct fiscal impact from the adoption of the 2015-17 Financial Plan and Goal Setting
Schedule. The Goal Setting Process and the development of the Financial Plan inherently take
considerable amounts of staff time. Publicizing the process and notification of interested parties
will engender nominal advertising and mailing costs covered through current allocations in the
City Clerk and Finance and IT budgets.
ATTACHMENTS
1. Proposed 2015-17 Financial Plan Schedule
t:\council agenda reports\2014\2014-09-02\financial plan schedule for 2015-17 (padilla-lamers)\financial plan schedule for 2015-17.docx
B4 - 6
City of San Luis Obispo, Council Agenda Report, Meeting Date, Item Number
Attachment 1: 2015-17 Financial Plan Calendar: Proposed Key Dates for Council
When Who What
September 2, 2014 Council Approves 2015-17 Financial Plan Schedule
October 16, 2014 City Manager,
Finance
Updates advisory body chairs on the goal-setting process at the
Mayor's quarterly meeting
November 3, 2014 Finance Begin sending letters inviting participation in goal-setting process to
community groups and interested individuals. Begin inserting
Community Budget Bulletins in utility bills
November 13, 2014
Special Workshop
7:00 to 10:00 p.m.
Council Holds Setting the Stage workshop on status of General Plan
programs, long-term capital improvement plan (CIP), status of Major
City Goals and objectives, and CIP projects
November 15, 2014 Advisory
Bodies
Provide recommended goals to Finance
November 20, 2014 Finance Distributes consolidated listing of draft recommended goals to
advisory bodies for their review
December 16, 2014
Regular Meeting
May start early PM
Council Budget Foundation. Finalizes goal-setting process and plans for
Community Forum. Reviews and provides guidance regarding
Financial Plan policies. Reviews financial results for 2013-14 and
general fiscal outlook. Hold initial discussion on options to be
considered for paying down the unfunded liabilities.
January 5, 2015 Finance Receives written comments from community groups and interested
individuals, and any changes in goals from advisory bodies.
January 13, 2015
Special Workshop
6:30 to 9:30 p.m.
Council Holds Community Forum at the Ludwick Community Center to
receive and review goals presented by individuals, community
groups, and advisory bodies
January 24, 2015
Special Workshop
8:30 a.m. to 4:00 p.m.
Council Holds Saturday Goal-Setting Workshop to discuss candidate goals
presented at January 13 Community Forum; discusses Council
member goals distributed on January 22; prioritizes and sets Major
City Goals
February 17, 2015 Council Mid-Year Budget Review; Staff to return to Council with unfunded
liability repayment plan options.
April 14, 2015
Special Workshop
6:00 to 10:00 p.m.
Council Approves detailed work programs for Major City Goals. Sets
strategic budget direction in preparing Preliminary Financial Plan
May 13, 2015 Planning
Commission
Reviews CIP for consistency with General Plan
May 26, 2015 City Manager Finalizes budget recommendations and issues preliminary budget
9/2/14
B4
B4 - 7
Financial Plan Schedule 2015-2017 Page 2
June 8, 9, 10, 2015
Special Workshops
Preliminary Budget
5:00 to 9:00 p.m.
Council Holds evening workshops to review and discuss Preliminary Budget
- June 8: General Fund operating programs
- June 9: General Fund CIP projects
- June 10: Enterprise Fund programs, CIP projects and rates
June 16, 2015 Council Holds continued Financial Plan review and adopts budget
June 23, 2015 Council If required, holds special meeting to continue review and adopt
budget