HomeMy WebLinkAbout03-03-2015 C6 Monterey Street Water Main Replacement
March 3, 2015
C6
City of San Luis Obispo, Council Agenda Report, Meeting Date, Item Number
FROM
: Daryl R. Grigsby, Director of Public Works
Prepared By:
Manny Guzman, Engineer III
SUBJECT:
MONTEREY STREET WATER MAINREPLACEMENT, SPEC. NO. 91284
RECOMMENDATION
1.Award a contract to Whitaker Construction Group, Inc. in the amount of $388,334.00 for
the “Monterey StreetWater Main Replacement, Specification No. 91284”.
2.Approve the fund transfer amountof $77,570 fromthe water fund Completed Projects
account to the Monterey Street Water Main Replacement project’s construction phaseand
$60,000 from the Water Enterprise Fund’s General Carryoveraccountto the Monterey
StreetWater Main Replacementproject’s construction management phase.
DISCUSSION
On December 10, 2013, the City Council authorized the invitation of bids for the Monterey
Street Water MainReplacementproject, Specification No. 91284(Attachment 1).However,
because of design issues the project was not advertiseduntil January 17, 2015with the bid
opening occurring on February 4, 2015. A total of eight bids were received and opened, all of
which exceeded the Engineer’s estimate of $336,000 (Attachment 2).
High bids for the Monterey Street Water Main project could be attributed to the work items
added as the design progressed. Approval to advertise was requested a year before design was
completed. The initial cost estimate was generated before staff was aware the project could
encounter contaminated soil and cultural resources.
Staff Determination of Award Recommendation
After sealed bids werepublicly opened, all bidswereinitially reviewed for mathematical errors and
rankedfrom the lowest cost bid tothe highest cost bid. During this initial review two bidders,
Pacific Coast Excavation Inc. (PCE) and Crandall Construction (CC) were determined to have
committed arithmetic errors and their calculated bids are higher than their written bid total indicated,
taking them both out of the lowest bid position.
The issue with PCEand CC bidsubmittalswas that in both cases arithmetic discrepancies existed
between item prices and total prices. When this situation occurs, per the City’s specifications for
bidding, the bid totalis calculated by the Cityusing item prices.
PCEsubmitted a written protest, clarifying their bid intentions; however, this newly supplied
information cannot be used because of the unfair advantage that it would give PCE over other
contractors who followed the bidding instructions in their original sealed bid document
(Attachment 3).
C6-1
Monterey StreetWatermain Replacement, Spec. No. 91284Page 2
The third lowest bidder, Whitaker Construction Group, Inc.submitted a complete and responsive
bid package. Whitaker Construction possesses a valid contractor’s license and has completed like
projects in the past.
FISCAL IMPACT
There is currently $391,430 available in the Monterey Street Water MainReplacement
construction phase account. The additional funding of $60,000 needed for construction
management services will be transferred from general carryover which currently has a balance of
$228,400. The remaining $77,570 needed will be transferred from completed projects which has
an available balance of $90,033.
Monterey St. Watermain Replacement, Spec. No. 91284
Construction Cost:$388,334
Contingencies:$50,166
Construction Management Services:$60,000
Cultural Resources Monitoring:$25,000
Materials Testing:$5,000
Printing:$500
Total Project Cost$529,000
ALTERNATIVE
Reject all bids, and re-advertise the project.
The City Council could choose to reject all bids and
direct staff to re-advertise the project. Staff does not recommend this alternative because this will
delay the project without any guarantee of reduced bid amounts. Also the existing water main could
experience another failure which could cause traffic and water service disruptions to the
community. A delay in the start of construction could also cause traffic conflicts with another
City Project, the Johnson Waterline project that is scheduled to start construction in early June
and is adjacent to this project. Coordinating traffic control for adjacent projects is complicated
and it causes traffic delays, especially when dealing with arterial streets such as Monterey and
California.
ATTACHMENTS
1.Copy of original report authorizing advertising
2.Bid Summary
3.Pacific Coast Excavation Inc. protest letter
4.Contract with Whitaker Construction Group, Inc.
t:\council agenda reports\2015\2015-03-03\c6-award monterey st. watermain repl., spec. 91284 (grigsby-guzman)\91284 award - monterey watermain repl..docx
C6-2
ATTACHMENT1PG1
Dec. 10 2013
,
FROM
: Carrie Mattingly, Utilities Director
Prepared By:
Jennifer Lawrence, Project Manager
SUBJECT:
MONTEREY STREET WATERLINE REPLACEMENT,
SPECIFICATION NO. 91284
RECOMMENDATION
1.Authorize the City Manager to award a contract to Cannon in the amount of $59,840 for design
services for the “Monterey Street Waterline Replacement.”
2.Approve a Budget Amendment Request to transfer $59,840 from Water Completed Projects to
the design phase of the project.
3.Authorize staff to advertise for bids and authorize the City Manager to award the construction
contract if the lowest responsible bid is within the Engineer’s Estimate of $336,026.
DISCUSSION
In the past year the ten-inch waterline on Monterey Street between California and Pepper has
broken twice. Businesses in the area were without water and traffic was diverted around this section
of Monterey Street while crews spent several hours repairing the break.
An analysis of the risk and benefit of replacing the waterline was completed after the second break.
It is recommended, although the project is not currently on the list of scheduled waterline
replacements, that, due to age and condition of the existing pipeline, the entire section of pipe on
Monterey between California and Johnson be replaced as soon as possible.
There are two 16” water transmission line replacement projects (Phase I and Phase II) that will be
constructed in the area of this proposed project (see the 2013-15 Financial Plan, Capital
Improvement Plan, page 3-117). These projects are currently in the design stage with Phase I
scheduled for construction in April 2014. Phase II, which includes the intersection of California and
Monterey is scheduled for construction starting in July of 2014. Design and construction of this
proposed waterline replacement on Monterey would be scheduled concurrently with Phase II of the
16” water transmission line replacement to reduce costs and minimize traffic and service impacts.
CONCURRENCES
The Community Development Department has granted a Notice of Exemption for the proposed
project since minimal environmental impacts are anticipated.
FISCAL IMPACT
Staff has received a proposal for design from Cannon, one of the City’s on-call consultants
approved for engineering services (Attachment 1). Funding for the design and construction support
C6-3
ATTACHMENT1PG2
Monterey Street Waterline Replacement Page 2
portion of the project is available in the Water Completed Projects Account which has a current
available balance of $130,553. The construction services portion of the project will begin in fiscal
year 2014-15. Funding will be provided during the 2014-15 budget supplement process from the
Water Fund’s working capital.
The project costs are estimated as shown below. A Budget Amendment Request will be processed
to transfer funding from the Completed Projects account to the project’s design.
Monterey Street Waterline Replacement
Design Engineering and Construction Support
Design Services$34,540
Potholing$25,300
Total$59,840
Construction Services
Engineer's Estimate$336,026
Contingencies (15%)$50,404
Printing and Miscellaneous$5,000
Total$391,430
Total Project Cost$451,270
ALTERNATIVE
Council could choose to deny funding for this project and pursue construction and design services at
a later date. This option is not recommended due to the two recent breaks in this pipe segment.
Without replacement, this section of pipeline is expected to fail and again cause traffic and water
service disruptions to the community.
ATTACHMENT
1.Engineer’s Design and Construction Budget Estimates
2.Budget Amendment Request
..\Monterey Street Waterline Replacement
C6-4
THIS PAGE IS INTENTIONALLY LEFT BLANK
ATTACHMENT3
Pacific Coast Excavation, Inc.
316 N. Pine Street, Santa Maria, CA 93458
P.O. Box 452, Santa Maria, CA 93456
Tel. (805)925-6565 FAX (805)925-8565
www.PacificCoastExcavation.com
Manny Guzman, Project Manager
City of San Luis Obispo
Public Works Dept.
919 Palm Street
San Luis Obispo, CA 93401
Monterey St. Watermain Replacement Specification No.91284
Re: BID PROTEST for
Dear Mr. Guzman,
This letter is a Formal Bid Protest for the Monterey St. Watermain Replacement Specification
No.91284 Project that Bid on Wednesday, February 4, 2015. The reason for the protest is due
to a clerical error made on Bid Item No. 14 (Contaminated Soil Disposal). The intended
amount in the Total column reads $5,000 and is the correct amount for that bid item.
In the City Spec Book for the above mentioned project, Notice to Bidders, page iii reads as
follows:
AWARD
The lowest bidder will be determined using the BID TOTAL.
This supersedes the City’s Standards as per our telephone conversation earlier this morning.
The BID TOTAL for Pacific Coast Excavation, Inc. is $361,380 on page B of the submitted Bid
Forms.
Pacific Coast Excavation, Inc. is in fact the lowest bidder based on the above, and expects
the City of San Luis Obispo to remedy this protest by awarding this project to us as such.
Best regards,
Carie L. Slosson
President/Treasurer
Office (805)925-6565
Cell (805)709-3686
Enclosures
C6-9
THIS PAGE IS INTENTIONALLY LEFT BLANK
ATTACHMENT4PG1
AGREEMENT
THIS AGREEMENT
, made on this ______ day of ___________, 2015, by and between the City of San Luis
Obispo, a municipal corporation and charter city, San Luis Obispo County, California (hereinafter called the
WHITAKER CONSTRUCTION GROUP, INC.
Owner) and (hereinafter called the Contractor).
WITNESSETH:
That the Owner and the Contractor for the consideration stated herein agree as follows:
ARTICLE 1, SCOPE OF WORK:
The Contractor shall perform everything required to be performed, shall
provide and furnish all of the labor, materials, necessary tools, expendable equipment, and all utility and
transportation services required to complete all the work of construction of
MONTEREY ST. WATERMAIN REPLACEMENT, SPECIFICATION NO. 91284
in strict compliance with the plans and specifications therefor, including any and all Addenda, adopted by
the Owner, in strict compliance with the Contract Documents hereinafter enumerated.
It is agreed that said labor, materials, tools, equipment, and services shall be furnished and said work
performed and completed under the direction and supervision and subject to the approval of the Owner or its
authorized representatives.
ARTICLE II, CONTRACT PRICE:
The Owner shall pay the Contractor as full consideration for the faithful
performance of this Contract, subject to any additions or deductions as provided in the Contract Documents,
the contract prices as follows:
ItemItemUnit of Estimated Item Price Total
No. SSDescription Measure Quantity(in figures) (in figures)
1
()
$30,000.00$30,000.00
17Traffic Control LS1
$15,000.00$15,000.00
277PotholingLS1
$191.50$196,479.00
37710 Inch PVC Waterline LF1026
$4,500.00$4,500.00
477Abandon Waterline and Facilities LS1
Waterline Tie In and
Appurtenances at Johnson and
$9,900.00$9,900.00
577MontereyLS1
Waterline Tie In and
Appurtenances at California and
$14,500.00$14,500.00
677MontereyLS1
Fire Main Connection at Station
$3,000.00$3,000.00
7774+01.72LS1
Fire Main Connection at Station
$3,300.00$3,300.00
8774+65.70LS1
Fire Main Connection at Station
$3,300.00$3,300.00
9775+58.78LS1
Fire Main Connection at Station
$5,500.00$5,500.00
10776+55.35LS1
$1,300.00$19,500.00
1177Water Service Tie In EA15
$9,800.00$9,800.00
1277Fire Hydrant EA1
$8.00$4,400.00
1314Contaminated Soil Excavation CF550
$72.00$39,600.00
1414Contaminated Soil Disposal CF550
1 of 3
C6-6
ATTACHMENT4PG2
ItemItemUnit of Estimated Item Price Total
No. SSDescription Measure Quantity(in figures) (in figures)
1
()
$2,300.00$2,300.00
1515Reset Monument EA1
$25.00$25.00
1685Blue Hydrant Marker EA1
$12.50$150.00
178412 Inch White Stripe LF12
$6.00$270.00
1884Detail 38 Stripe LF45
$13.00$3,276.00
1984Detail 32 Stripe LF252
$6.00$900.00
2084Type IV Arrow SQFT150
$52.00$884.00
2159Bike Lane Coating SQFT17
$6,500.00$6,500.00
2214Comply with APCD Permit LS1
$1,000.00$1,000.00
2314Prepare Health and Safety Plan LS1
Comply with Health and Safety
$850.00$4,250.00
2414PlanDAY5
Comply with Mitigation
$1,500.00$1,500.00
2514MeasuresLS1
$8,500.00$8,500.00
267Comply with OSHA LS1
BID TOTAL: $388,334.00
Payments are to be made to the Contractor in compliance with and subject to the provisions embodied in
the documents made a part of this Contract.
Should any dispute arise respecting the true value of any work omitted, or of any extra work which the
Contractor may be required to do, or respecting the size of any payment to the Contractor, during the
performance of this Contract, said dispute shall be decided by the Owner and its decision shall be final, and
conclusive.
ARTICLE III, COMPONENT PARTS OF THIS CONTRACT:
The Contract consists of the following
documents, all of which are as fully a part thereof as if herein set out in full, and if not attached, as if hereto
attached:
1. Notice to Bidders and information for bidders.
2. Standard Specifications, Engineering Standards, Special Provisions, and any Addenda.
2. Accepted Bid.
4. Public Contract code Section 10285.1 Statement and 10162 Questionnaire.
5. Noncollusion Declaration.
6. Plans.
7. List of Subcontractors.
8. Agreement and Bonds.
9. Insurance Requirements and Forms.
ARTICLE IV.
It is further expressly agreed by and between the parties hereto that should there be any
conflict between the terms of this instrument and the bid of said Contractor, then this instrument shall control
and nothing herein shall be considered as an acceptance of the said terms of said bid conflicting herewith.
IN WITNESS WHEREOF,
the parties to these presents have hereunto set their hands this year and date
first above written.
2 of 3
C6-7
ATTACHMENT4PG3
ATTEST: CITY OF SAN LUIS OBISPO
A Municipal Corporation
______________________________ By:_____________________________
Anthony Mejia, City Clerk Jan Howell Marx, City Mayor
APPROVED AS TO FORM: CONTRACTOR:
Whitaker Construction Group, Inc.
_______________________________ By:______________________________
J. Christine Dietrick, City Attorney Matthew Bousman
Its: President
Rev. 12-28-09
3 of 3
C6-8
THIS PAGE IS INTENTIONALLY LEFT BLANK