HomeMy WebLinkAbout04/24(2)/2001, C5 - RAILROAD TRANSPORTATION CENTER: CONTAMINATED SOIL REMOVAL, SPECIFICATION NO. 99059. counat Ap 1 4, 290
j agenba REpoRt �H
CITY O F SAN LU IS O B I S P O
FROM: Michael D. McCluskey, Director of Public Wo sem'
Prepared By: Barbara Lynch Civil Engineer
SUBJECT: RAILROAD TRANSPORTATION CENTER: CONTAMINATED SOIL
REMOVAL, SPECIFICATION NO. 99059.
CAO RECOMMENDATION
1. Appropriate $151,000 from the unreserved General Fund balance to cover the costs
associated with the disposal of contaminated soil from the Railroad Transportation Center.
2. Authorize Public Works to proceed with stockpiling if a permit is issued and disposing of the
material at the end of the summer as clean fill or contaminated soil as determined by testing
under the supervision of the Fire Department.
DISCUSSION
On June 29, 2000 the CAO authorized contract award to R.Burke Corporation for the construction
of the Railroad Transportation Center. The site was known to have contaminated soil at the time of
bidding. The cost estimated for disposal of contaminated and hazardous soils at the time of bidding
was about$32,000. To date the City has spent over three times that amount.
The site grading has left two large stockpiles of contaminated soil with no place to go and no
funding to dispose of it. This material was believed to be free of contamination having been
separated during excavation, and was planned for use at another location. The City tested the
material to confirm it was clean. It turned up as marginal with some contamination present. It is
suitable for some conditions,such asunder parking lots,but not for others. The Contractor has been
unable to find a site that would be able to use it in its present condition. Of the two stockpiles, one
is at the City Corporation Yard temporarily. The other remains on site and is preventing the
completion of the work.
At the time of this report, Public Works is applying to Community Development for a temporary
stockpiling permit. A stockpiling permit will provide a way to remove the material from the site so
the project can be completed without further delay. The question of disposal remains.
Typically, this type of marginal material is sent to a "remediation" site. Remediation is
accomplished by adding certain fertilizers, mixing the material and giving it time. Public Works
staff is already adding these fertilizers to the material in the hopes of beginning the remediation
process. The City does not have an area where a significant remediation effort can take place;
however, there is a good chance this limited effort will result in remediation.
The material comes from property formerly owned by the railroad. The property was purchased"as
is." This makes it difficult to get the railroad to pay the costs associated with the contaminated soil.
It may cost more to pursue the railroad than to deal with the matter in house. As the material is
"contaminated"not"hazardous,"it will not be an ongoing expense. Had it been hazardous,the City
would retain ownership forever. When final costs are known,the information can be turned over to
the City Attorney to determine if there is any benefit to pursuing the matter with the railroad.
4-1
r
Council Agenda Report—Railroad Transportation Center
Page 2
CONCURRENCES
Public Works has been working with the Fire Department throughout the process to make sure
the material is handled appropriately to prevent contamination of other areas or stream water.
FISCAL IMPACT
Initially, about $2,000 of additional contaminated soil disposal was paid for through the project
contingency fund. Until the recent discovery of additional contaminated dirt, it appeared there was
enough money to cover the necessary construction changes and this small additional disposal cost.
Unfortunately, the volume of contaminated soil is now too great to fund through the existing
contingencies.
The project account now shows 95% of the contingency fund has been used. A third of that was
spent on contaminated soil disposal. Change orders not related to removal of contaminated soil
account for the remaining two-thirds.
Contingency Spending
Contingency Amount $193,300
Construction Change Order Costs to Date 111,000
Contaminated Soil Costs to Date * 73,000
Contingency remaining Now $99300
Additional Construction Change Orders Anticipated 48,000
Additional Soil Contamination Costs Anticipated 78,000
Recommended Additional Contingency for Unanticipated Items 25,000
Total Recommended Contingency After Council Action $160,300
Total Recommended Contingency Increase $151,000
'beyond the$32,500 provided for in the contract for hazardous or contaminated soil disposal
The project needs another $48,000 in contingencies to pay for changes known at this time to
complete the project. The project is currently 75% complete and contingency funding will be
necessary in completing the remaining 25%. It will, therefore, be necessary to repay the
contingency fund the $73,000 already spent on soil removal in addition to the $78,000 needed to
dispose of the remaining soil. If this is not done, the project will run out of money before it is
complete.
While $151,000 is the amount needed to dispose of all the contaminated soil not covered in the
original quantities, only $73,000 has already been spent. If remediation efforts are successful,
only a portion of the $78,000 in potential future costs will be spent. The rest can be returned to
support other projects.
This project previously consolidated several accounts to provide funding for construction and there
are no alternate sources available to us. As such, staff recommends appropriating $151,000 from
the unreserved General Fund balance. Based on the Mid-Year Budget Review for 2000-01 and
Council-approved changes since then, this will result in an ending fund balance that is 24% of
operating expenditures compared with our policy minimum of 20%. Additionally, after
adjusting for City's likely construction costs for our share of repairing the Santa Rosa-Sterner
4-2
� J
Council Agenda Report—Railroad Transportation Center
Page 3
Creek Culvert (about $200,000), this will reduce the estimated carryover balance available for
2001-03 to $810,000.
ALTERNATIVES
Staff has identified the following three alternatives and has summarized the estimated cost
differences in the ALTERNATIVE TABLE.
1. — STAFF RECOMMENDATION - Hold the material at a stockpile location, completing
what remediation effort the City is able to perform, until the fall. Retest the material. Give it
away if it is clean, or contract for disposal. NOTE: This alternative assumes a stockpile
permit can be obtained to hold the material through the summer
Pros — This has the potential to reduce the cost of disposal through remediation. If it
does not remediate over the summer it would cost about the same as Alt. 2. below.
Disposal at a remediation site is paid for by the ton. The summer drying will reduce the
tonnage and therefore the disposal cost.
Cons — The City will have to pay to haul the material to the stockpile location and there
will be staff time to arrange for the disposal.
2. Contract with a licensed trucking firm to haul the material to a disposal site.
Pros—This is the least cost option for disposing of the material soon.
Cons — Staff time will be required to arrange a separate contract with a trucking firm to
complete the hauling.
3. Have the Contractor's hazardous materials subcontractor haul the material and pay for the
disposal at a remediation site.
Pros — The material can be disposed of more quickly than with any of the other options.
This allows the project to proceed unrestrained and eliminates any future staff time to
deal with the dirt.
Cons—This is the most costly of all options.
ALTERNATIVE TABLE
Alternative Estimated Cost
1. Stockpile, remediate& give away or dispose of $6,500 to $78,000
2. Contract separately to haul & dispose of $78,000
3. Dispose of the material under the current contract $89,300
g1 wrrent projects\parking tots\99059 railroad transportation center\_staH reports\99059 contarnination.doc
4-3