j acEnaa Repout N, r1
CITY OF SAN LUIS 'OBISPO
FROM: Mike McCluskey, Director of Public Works Yo -
Prepared By Keith Opalewski, Parking Manager
SUBJECT: FINAL CONSTRUCTION MANAGEMENT CONTRACT
AMENDMENT FOR MARSH STREET PARKING GARAGE
EXPANSION PROJECT
CAO RECOMMENDATION
Approve contract amendment No. 2 for additional construction management services to Hams &
Associates in the amount of$200,794 and authorize the Mayor to sign the contract amendment.
DISCUSSION
The construction contract for the Marsh Street Garage expansion officially started on August 6,
2001. The original contract was for a 12-month construction period, which by industry standards
was a very aggressive schedule that assumed minimal problems during the course of the
construction.
However, due to a number of issues (archeological discoveries and monitoring, site constraints,
design changes, change orders, Post Office operations, and maintaining garage operations) the
construction continued beyond the 12-month period. Moreover, although the garage expansion
was formally dedicated on October 22, 2002, additional construction refinements continued on
until early 2003. These final construction issues, more commonly known as "punch list" items,
are typical for most construction projects, especially one the size and complexity of the garage
expansion project.
As a result of the delays and difficulties encountered to complete the project, the current contract
for construction management services is substantially under funded by $200,794 and will need to
be amended in order to finalize the project and the consultant budget.
FISCAL IMPACT
The additional funding for the construction management consultant can be met through use of the
construction contingency fund, which was approved as part of the original construction budget.
The original proposals submitted by Harris & Associates (construction management consultant)
were for a 12-month construction period. However, since the construction contract for ARB, Inc
has gone for 16 months, the contract needs to be amended to match costs incurred for the 16-
month period for the actual construction of the garage, along with close out issues for the project
that still need to be finalized. The following summarizes the contract amendment and
contingency fund balance.
� n� _ 1
i 1
Council Agenda Report=Construction Management Contract Amendment-Marsh Street
Garage
Page 2
Construction Management Contract
Harris & Associates Original Contract $304,600
Amendment 1 $72,480
Amendment 2 (Proposed) $200,794
$577,874
Contingency Fund
Contingency Fund $654,800
Expended Contingency Funds ($86,489)
Pending Change Orders ($246,678)
Subtotal $321,633 ($321,633)
Harris Contract Amendment ($200,794)
Contingency Fund Balance $120,839
Remaining costs that may be incurred include the possibility of increased architect's fees for
construction services and items related to construction or design quality issues. Neither set of
expenses is expected to approach the amount of the remaining contingency amount.
ALTERNATIVES
Contract obligations must be fulfilled for the completed garage expansion project and as such
there is no other viable alternative.
ATTACHMENT—Attachment 1—Contract Amendment
hCouncil Agenda Reports\2003 agenda reports\CM contract amendments mss.doc
ATTACHMENT I
AMENDMENT NO. 2
AGREEMENT WITH HARRIS AND ASSOCIATES
The AGREEMENT dated March 10, 2000 between the CITY OF SAN LUIS OBISPO, a
municipal corporation, hereinafter referred to as "City" and "Harris and Associates", hereinafter
referred to as "Contractor", is hereby amended to as follows:
A. DESCRIPTION OF WORK
2. Workscope
Provide additional services for construction management, inspection, and close-out
services pursuant to the extended project construction phase for an adjusted contract
amount of$200,794 as outlined in Exhibit "A".
All other terms and conditions of the AGREEMENT remain the same.
Both CITY and CONTRACTOR do covenant that each individual executing this
addendum on behalf of each party is a person duly authorized and empowered to execute
Agreements for such part.
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed on this
day of , 2003.
CITY OF SAN LUIS OBISPO
A Municipal Corporation
David F. Romero, Mayor
APPROVED AS TO FORM: CONTRACTOR
r.
City Attorney Print Name:
G:/Contracts&RIWAmendtnmt 2—Hams&Assoc.
C ,7 - 3
Exhibit A
January 20, 2003
Mr. Keith Opalewski
Parking Services Manager
City of San Luis Obispo
1260 Chorro Street
San Luis Obispo, CA 93401
Re: City of San Luis Obispo
Marsh Street Garage Expansion Project
Additional Services Proposal for Extended Project Construction Phase
Dear Keith,
This letter is to request that the City consider Harris' proposal to provide additional services
pursuant to the subject project The additional services are required to provide construction
management, inspection, and close-out services pursuant to the extended project construction
phase.
The project extended duration is approximately 3 to 4 months beyond the original anticipated
construction duration. The project delays appear to have been caused by a combination of
Contractor caused delays, unforeseen conditions, and design changes required during
construction.
Harris &Associates' estimated cost for the required additional services is $200,794.
A breakdown of this estimated cost is attached.
As we have discussed, Harris & Associates will continue to provide the necessary project
services while the City reviews and processes our request.
Thank you for your consideration and please do not hesitate to contact me at 805.890.0128 if
you have any questions, comments, or wish to discuss this matter.
Sincerely,
HARRIS & ASSOCIATES
Steve Mimiaga, P.E.
Project Manager
0, 7' 4
Exhibit A
1/21/2003
Harris&Associates
CASH FLOW REPORT I STAFFING PLAN/ESTIMATE OF ADDITIONAL COSTS
DATA DATE:31 DEC 02
MARSH STREET GARAGE EXPANSION PROJECT
City of San Luis Obispo
Estimate of Additional Construction Management and Inspection Costs
Projected Project Schedule 2002/2003
Au a I Sea Oct Nov Dec Jan Feb Mar Aor
Project Construction Period
Project Closeout
Stffing Plan
Months I Billingeo*I Oct' I Nov'I Dec'I Jan Feb I Mar I Total Project
I Rate P22� " Hours Totals
Jim Guerrero(PD) 220.001 1 1 9 1,980
Steve Mimiaga(PM) 140.001 1 1 11 171 121 21 20 201 201 20 141 19,740
Mary Jo Bachini(CM) 100.001 1 1 137 1081 1 1 1— 2451 24,500
[Ea!Skrabanek(Closing CM) 90.001 1 1 `1031 1701 120 1 1 3931 35,370
2
3 4
9
I
12 3
20
1201 10�800
in Kimbedin(Back up Inspector) 90.001 1 1 1201 1 — I
liceasar Moran(Office En r. 40.001 1 1 121 351 251 92 20 201 20 20 353 14,113.
puly Structures Inspector(req) 65.001 1 2001 r5-9 1841 1441 102 80 20 1 20 20 929 60,385
V
puty Structures IME 97.50 1 651 73 991 141 1 251 24,473
or g�5 time 0
30.W -T— 7
at
dy Structures im. 231 2o 4 9,620
total estimated cost P2 —0,9811
WORK ALREADY COMPLETED,COSTS ARE ACTUAL
20
Harris Total Amount Needed to Finish Project 200,981
Harris Total Amount Remainina In Current Bud et 187
HARRIS TOTAL AMOUNT OF PROPOSED INCREASE 200,794
BUDGET SUMMARY
Ori incl Harris Fee 1 $304,6001
[Contract Amendment No. 1 172 480
1WAmendment No; (Dendinq) 1 $200,794
(I Total Contract Amount 1 $577,8741