HomeMy WebLinkAbout11/18/2003, BUS 3 - PRELIMINARY DESIGN REPORT FOR WATER TREATMENT PLANT MASTER PLAN IMPROVEMENTS council Nov. 18, 2003 j acEnaa REpoRt H pc)S 3 C I TY O F SAN L U I S OBISPO FROM: John Moss, Utilities Director,, Prepared By: Gary Hender , Water Division Manager -:*--J4 SUBJECT: PREL 41NARY DESIGN REPORT FOR WATER TREATMENT PLANT MASTER PLAN IMPROVEMENTS CAO RECOMMENDATION 1. Approve the project components recommended for inclusion in the final design of improvements for the Water Treatment Plant Improvement Project. 2. Approve the amendment to the contract with Black and Veatch for Phase II services for the design of the recommended improvements at the Water Treatment Plant for an additional amount not to exceed$519,680. 3. Authorized the Utilities Director to approve additional compensation for an amount not to exceed $53,029. 4. Authorize the transfer of$375,109 from Water Fund Working Capital to the project account. REPORT-IN-BRIEF In October 2000, Boyle Engineering Corporation completed the City's Water System Master Plan (Master Plan). The Master Plan included the following recommended improvements at the WaterTreatment Plant: A. Seismic evaluation of the existing water storage tanks B. Addition of a second treated water storage tank(clearwell) C. Upgrades to the transfer pump station D. A new pipeline to serve the Water Treatment Plant from Reservoir#2 E. An additional sedimentation basin The consulting firm of Black and Veatch was selected by the City to prepare the preliminary design report (PDR) for the recommended improvements. The purpose of the PDR is to evaluate the recommendations identified in the Master Plan and develop the preliminary design and cost estimates for recommended improvements at the site. The improvements are intended to enhance the plant's ability to meet future water supply demands, improve operational capabilities, and ensure that the facilities perform adequately following a seismic event. 3-/ Council Agenda Report—Water Treatment Plant Preliminary Design Report Page 2 The major improvements recommended in the PDR are shown below: A. Demolish existing 4.0 million gallon (mg) treated water storage tank and construct new 3.0 mg replacement tank. B. Construct second 2.0 mg water storage tank C. Replace existing Transfer Pump Station with new pump station located at the Water Treatment Plant site. D. Seismic upgrades for the washwater storage tank. E. Provide plant water supply from Reservoir#2 The total construction cost for all of the recommended improvements is estimated to be $4,476,748. This includes additional items which were identified during the development of the preliminary design report. The total construction cost also includes a 30% contingency. To proceed with the recommended improvements, staff recommends approval of the amendment to the contract with Black and Veatch for preparation of the final plans and specifications and completion of the environmental documentation. In addition, additional analysis associated with the potential for reactivation of the Stenner Canyon Hydroelectric Plant (covered under separate Council agenda report) is included in the recommended scope of work and the associated compensation. The implementation of the recommended improvements identified in this report will ensure that the City's Water Treatment Plant will continue to provide safe and reliable water supplies to meet the City's demands well into the future. DISCUSSION Background Several years ago, in conjunction with the development of the Airport Area Specific Plan, the City of San Luis Obispo initiated the development of a Water System Master Plan. The Master Plan was prepared by Boyle Engineering Corporation through subcontract with Wallace,Roberts, and Todd (the lead consultant for the Airport Area Specific Plan). The overall purpose of the Master Plan was to evaluate the existing raw water delivery facilities, the water treatment plant, and the water distribution system to identify existing deficiencies and necessary improvements needed to meet both existing water service demands as well as those at full build-out as identified in the City's General Plan. The Master Plan identified the following improvements and studies to ensure reliable operation of the Water Treatment Plant to meet current and future city water demands. A. Seismic evaluation of the existing water storage tanks B. Addition of a second treated water storage tank (clearwell) C. Upgrades to the transfer pump station D. A new pipeline to serve the Water Treatment Plant from Reservoir#2 3-Z Council Agenda Report—Water Treatment Plant Preliminary Design Report Page 3 E. The need for an additional sedimentation basin On January 30, 2003, the City Council approved the scope of work and contract with Black and Veatch for preparation of the preliminary design report for recommended improvements to the Water Treatment Plant. This report will present the findings of the consultant's evaluation of the improvements recommended in the earlier Boyle study as well as additional items that have surfaced during project stakeholder meetings which included the consultants and operations, maintenance and management staff of the Utilities Department. The scope of work also included an evaluation of the potential to reactivate the existing Stenner Canyon Hydroelectric Facility. The hydroplant evaluation is presented as a separate agenda item. Purpose The purpose of the Preliminary Design Report (PDR) for the Water Treatment Plant (WTP) Improvement Project is to evaluate the recommendations identified in the Master Plan and develop the preliminary design and cost estimates for recommended improvements. The improvements are intended to enhance the plant's ability to meet future water supply demands, improve operational capabilities, and ensure that the facilities perform adequately following a seismic event. Treated Water Storage The largest capital cost item identified in the Master Plan is the need for an additional treated water storage tank (clearwell) at the WTP. The WTP currently has one 4.0 million gallon (mg) clearwell which was installed in 1964 when the WTP was originally constructed. The clearwell does not meet current seismic design criteria and is in a deteriorated condition. Most water treatment plants have two tanks onsite for treated water storage to allow one tank to be taken out of service for maintenance or repairs, while the other tank provides minimum operating storage for the facility. The Master Plan recommended construction of a second 4.0 mg storage facility. An evaluation of the total onsite storage required was undertaken to determine whether 8.0 mg was ncessary for plant operations at future City build out water demands. The evaluation determined that 4.0 mg was the minimum required onsite storage for long-term operation of the facility. Additional analysis was performed to determine what the minimum short term storage needs would be to allow maintenance or repair of either tank. It was determined that 2 mg of storage would be sufficient to allow maintenance to be undertaken. Five alternatives were evaluated relative to providing the necessary onsite storage. These alternatives are discussed in detail in the PDR on page 19. The alternatives ranged from constructing a temporary tank and replacing the existing 4.0 mg tank (with a new tank with two separate cells) to demolition of the existing tank and construction of a 3.0 mg replacement tank and a new 2.0 mg tank. The costs of the various alternatives ranged from $1.6 million to $2.1 million (Table 2-5 of the PDR). While the minimum storage for the plant operations was identified as 4.0 mg, the alternative which would provide 5.0 mg of onsite storage (one 3.0 mg 3-3 Council Agenda Report—Water Treatment Plant Preliminary Design Report Page 4 replacement tank and one new 2.0 mg tank) is recommended because it will provide additional capacity and redundancy while not significantly increasing construction costs. Transfer Pump Station The existing transfer pump station is located approximately '/z mile from the WTP on Stenner Canyon Road. The pump station provides water to Reservoir#2 and the high pressure portion of the City's water distribution system. The high pressure zone currently provides water to approximately one third of the City water customers. The pump station is located on a small parcel of land which is owned by the City and is surrounded by property owned by the State of California (Cal Poly). The Master Plan recommended replacement of the three existing pumps and motors, as well as replacement of other equipment and piping within the exiting building. The pump station was originally constructed in 1964 when the WTP was constructed. The existing pumps and motors are very inefficient and have inadequate capacity to serve future water demands. During project stakeholder meetings, it was determined that essentially all of the equipment within the existing pump station would need to be upgraded as part of the project. In addition, it is recommended that the new facility include 4 pumps to meet projected water demands and provide operational flexibility in the future. The pump station's maximum capacity is designed for three pumps operating and one as a backup. This is industry standard to insure system reliability and allow for maintenance and repair of one pump while the others are in service. Following the determination of the upgrades necessary for the pump station, an evaluation of site alternatives was undertaken. Since the existing pump station needs to remain in service until the new pump station is constructed, the consultants considered construction of a new pump station adjacent to the existing site as well as relocating the pump station to the WTP. It was determined that with the construction of the new storage tank at the WTP there will be available space to locate a new pump station adjacent the tank. The new site is preferable because of the availability of land currently owned by the City, increased security and proximity to the WTP operations and maintenance staff. Washwater Storage Tank There are two washwater tanks at the WTP that are used to backwash the filters. The newer tank was constructed as part of the WTP Upgrade Project that was completed in 1994. The other tank was constructed in 1964 and was evaluated to identify upgrades necessary to meet current seismic design standards. In addition to the recommended seismic upgrades, it is recommended that the interior coating of the tank be removed and recoated and that a new cathodic protection system be installed to extend the life of the tank. The exterior of the tank was recoated 10 years ago and appears to be in good condition. The condition of the tank exterior will be further evaluated during the final design phase to determine if any additional action is warranted at this time. 3-� Council Agenda Report—Water Treatment Plant Preliminary Design Report Page 5 Washwater Reclamation Junction Box The existing facility that allows diversion of washwater from the filters to the two reclamation basins has operational deficiencies which cause overflows of the junction box. To correct these deficiencies, the Master Plan recommended extending the walls 6 to 8 feet above grade. Upon more detailed evaluation, it was determined that a more cost effective approach would involve demolition of the open junction box structure and construction of a closed pipe diversion system. This solution will cost significantly less than raising the walls of the existing junction structure and will considerably simplify operations. Plant Water Supply The current water plant onsite pump station includes two plant service water pumps, two washwater pumps, one fire pump, and two washwater treatment supply pumps. The pumps that provide treated water for plant water service, ozone cooling system and washwater require a substantial amount of maintenance, have improper motor design and are difficult to obtain parts for repair due to the age of the pumps. A study was conducted to evaluate the feasibility of serving the plant water supply from Reservoir #2 and the High Pressure Zone to allow the aging equipment to be decommissioned. In addition, service from Reservoir#2 (7.5 mg) will provide a reliable, gravity-fed supply to meet onsite plant water needs. The analysis also revealed that there is not adequate pressure available from Reservoir #2 to meet the requirements for the ozone building fire sprinkler system, so the fire pump will be retained. Since the fire pump was installed in 1994 as part of the last upgrade project, the pump meets current design criteria and does not require significant maintenance. The recommendation is to abandon the service water pumps onsite and provide water for plant operations from Reservoir#2. Treatment Process Improvements The City Water Treatment Plant has a design capacity of 16 million gallons per day (mgd). To achieve this capacity, the plant needs to be operated in a split flow manner with water from Whale Rock bypassing the sedimentation process. The existing sedimentation basin has a design capacity of 8 mgd and the Master Plan recommended that an additional sedimentation basin be considered. The Master Plan estimated the cost for a new sedimentation basin to be $1.3 million in 2000. Due to limited site locations and adverse geological conditions, the actual costs may be significantly higher than this estimate. As part of the PDR, a plant performance test was initiated to evaluate the performance of the plant at full 16 mgd capacity with split flow operation. The test was conducted on a Sunday and confirmed that the plant can hydraulically handle the 16 mgd flow rate even with one filter out of service for backwashing (cleaning). The test was scheduled to last a minimum of 4 hours but due to a power outage in Cayucos, the test was discontinued after three hours. The test did reveal some potential questions relative to the ability of the plant to effectively and reliably operate at these high flow rates for extended periods of time. Bypassing the sedimentation basin with the 3-5" Council Agenda Report—Water Treatment Plant Preliminary Design Report Page 6 water from Whale Rock will "load up" the filters in a shorter period of time which will require more backwashes. Long-term operation of the treatment plant with direct filtration of Whale Rock may not remain a viable option. To increase the sedimentation capacity, a new sedimentation process was recommended by Black and Veatch for the City's consideration. The process is called "Actiflo" and is manufactured by U.S. Filter. This process utilizes sand as a "ballast" to rapidly settle out material from the raw water. The Actiflo pretreatment system would be capable of providing a reliable treatment process for the full 16 mgd plant capacity, with limited space requirements and simplified plant operation. It may also be able to reduce the amount of ozone used for primary disinfectant which could result in long term savings in operation costs. The process is being used at a number of existing treatment plants and is being planned for many treatment plant upgrades around the United States. Staff would recommend further evaluation of the potential benefits of utilizing this enhanced pretreatment process during the next phase of this project. In addition, a small scale pilot test of the equipment with our raw water may be warranted following the cost/benefit evaluation.. U.S. Filter has a portable small scale facility that can be brought onsite to test the effectiveness on our raw water sources. The cost for the rental of the portable facility from U.S. Filter is $58,000 for a five-week test. Black and Veatch support services and analysis brings the total cost to $76,185 for the pilot plant study. These costs are not included in the contract amendment with Black and Veatch. Staff will return to Council following.the cost/benefit evaluation for recommendations relative to the Actiflo process and authorization for the additional compensation of$76,185. Additional Items During meetings relative to the development of the Table 1: Additional Items Construction Costs PDR for Master Plan Description Total improvements, a number _-_p— A. Ozone building HVAC system $12,500 of additional items and B. Upgrade fluoride feed system $12,000 improvements were C.New Cal Poly vault, valve&meter $55,156 identified by staff for D. New HVAC system for filter building $12,320 potential consideration. Appendix F of the PDR E. Replace Washwater drain line $9,250 lists 17 different potential F. Repair drain line across entry road $6,250 projects that were deemed G. Construct"erosion control"retaining wall $8,809 appropriate for H. Repair slope erosion below basins $3,500 consideration and Black I. Install ventilation system in chemical $14,000 and Veatch developed Building preliminary cost estimates J. Automate washwater pump operation $10,500 for each. Based on an TOTAL $144,285 evaluation by staff of the -- - cost/benefit of each item, staff would recommend that the items shown in Table 1 be included in 3-� Council Agenda Report—Water Treatment Plant Preliminary Design Report Page 7 the project design. Table 1 also includes the estimated construction costs without the 30% contingency factor. Environmental Documentation An initial study was prepared as part of the work scope for development of the PDR. There were some mitigation measures proposed to reduce potential impacts to a level of insignificance. The initial study only involved those improvements originally identified in the Water Master Plan. The additional items that have surfaced during preliminary project design discussions may require some addition evaluation. Following Council's direction on the scope of the project, a complete project description will be developed and additional environmental evaluation will be undertaken. Phase 77 Contract for Final Design Attachment 1 is the amendment to the contract with Black and Veatch for Phase II. The scope of work for Phase II is shown in Exhibit A of the contract and is summarized below: 1. Geotechnical investigation and evaluation 2. Environmental documentation 3. Preparation of plans and specifications for recommended improvements 4. Additional work associated with the Stenner Canyon Hydroelectric facility project (discussed under separate agenda report). Summary The implementation of the recommended improvements identified in this report will ensure that the City's Water Treatment Plant will continue to provide safe and reliable water supplies to meet the City's demands well into the future. FISCAL IMPACT The Water Treatment Plant Master Plan Implementation Project was identified in the 2003-05 Financial Plan, Appendix B, Pages 61-63. The financial plan request estimated $197,600 for final design and environmental documentation. The cost associated with the amendment to the contract with Black and Veatch for Phase II of the project is $519,680. In addition, a design contingency amount of $53,029 is recommended, to be authorized for use by the Utilities Director, for improvements that require additional evaluation and scoping prior to final design. An additional $375,109 will need to be appropriated from Water Fund Working Capital to support the Phase II contract. There is sufficient available working capital in the Water Fund to fund the contract and still meet minimum reserve policy levels. 3 -7 Council Agenda Report—Water Treatment Plant Preliminary Design Report Page 8 Table 2 below identifies the current estimated construction costs for each of the major components of the project. Table 2: Construction Cost Estimates Description Total General Conditions $313,060 Clearwell No. 1 $1,091,335 Clearwell No. 2 $899,018 Transfer Pump Station $635,352 Washwater Tank $118,202 Plant Water Supply $21,300 Backwash Wastewater Junction Box $62,350 Pipeline $158,750 Additional Items $144,285 Subtotal $394439652 Risk Contingency (30%) $19033,096 TOTAL $4,476,748 ALTERNATIVES 1. Modify Work Scope of the Project: Staff believes that the proposed project scope will provide the proper facilities to ensure that the City can meet water quality standards into the future and provide reliable water service to the community. Staff recommends the project work scope is appropriate and necessary, however staff is prepared to discuss any scoping changes Council may desire and incorporate those changes into the contract agreement. ATTACHMENT: 1. Amendment to Agreement for Consultant Services with Black and Veatch * Full copy of the Water Treatment Plant Preliminary Design Report is in the Council reading file. 3-� J ATTACHMENT 1 AMENDMENT 1 TO AGREEMENT THIS AMENDMENT TO AGREEMENT is made and entered in the City of San Luis Obispo on this day of by and between the CITY OF SAN LUIS OBISPO,a municipal corporation,herein after referred to as City,and BLACK AND VEATCH,hereinafter referred tows Consultant. WITNESSETH: WHEREAS,on February 26, 2003 the City entered into an Agreement with Consultant for preparation of the preliminary design report for the Water Treatment Improvement Project;and WHEREAS, the City desires to amend the scope of services to include additional analysis and preparation of final plans and specifications for the Water Treatment Plant Improvements and Consultant has submitted a proposal for this purpose that is acceptable to the City. NOW THEREFORE, in consideration of their mutual promises, obligations and covenants hereinafter contained,the parties hereto agree as follows: 1. The scope of services is hereby amended asset forth in Exhibit A attached hereto. 2. For providing the services as specified in Exhibit, City will pay and Consultant shall receive additional compensation of$519,680 for a total sum not to exceed$750,615. 3. For providing additional design services associated with Subtask 810,additional compensation not to exceed$53,029 may be authorized in writing by the City's Utilities Director. 4. All other terms and conditions of the Agreement remain in full force and effect. IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed the day and year first written above. ATTEST: CITY OF SAN LUIS OBISPO By: Lee Price,City Clerk David F.Romero,Mayor APPROVED AS TO FORM: CONSULTANT a, . Iona ' well,City Attorney 3-t 1 EXHIBIT A SAN LUIS OBISPO WTP IMPROVEMENT PROJECT AMENDMENT 1 OWNER: City of San Luis Obispo CONSULTANT: Black & Veatch Corporation PROJECT: Water Treatment Plant Improvements Project, Specification No. 90225 PURPOSE The following is an amendment the contract signed on February 26, 2003, between the City of San Luis Obispo and Black & Veatch Corporation. The Consultant's obligations are amended according to the following "Scope of Work" section.The City's obligations are amended according to the"Compensation" section at the end of this amendment. All other terms and conditions of the original contract apply. SCOPE OF WORK This amendment replaces the scope of work for Exhibit A, Task 500, WTP Detailed Design, of the original contract and provides for additional tasks to be completed under Task 730, Stenner Canyon Hydroelectric Feasibility Study - Additional Evaluations, and Task 800, Additional Project Components. Task 500-WTP Detailed Design-Phase II The tasks and deliverables described below apply to each project element for which bid documents are anticipated to be prepared. The project includes the components described in the Preliminary Design Report (PDR), dated October 17, 2003, and several additional components described below. The project components outlined in the PDR include: • New 2 million gallon (mg) clearwell on hillside of sludge ponds, including piping and appurtenances, relocated septic system and leach fields, and retaining wall. • New 3 mg clearwell on site of existing clearwell (to be demolished), including demolition plans,piping, and appurtenances. • New Transfer Pump Station, to be located on the WTP site, including piping and appurtenances, and site landscaping. • Components required to serve onsite plant water demand from Reservoir No. 2, including piping,valving, and demolition plans. • Seismic upgrade and relining of 180,000-gallon wash water tank. • Piping and valving modifications to existing wash water control structure. • Demolition of existing Transfer Pump Station. SLD-Phase 11 FINAL 10. EXHIBIT A i l City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 The additional project components (not covered in the PDR) undergoing detailed design are as follows: • Cal Poly Raw Water Line Improvements • Washwater Basin Drain Line • Sludge Pond Underdrain Improvements • Slope Repairs • Washwater Treatment System Evaluation • Paving Improvements These project components will undergo the same detailed design process as the components included in the PDR, as outlined in Tasks 505 through 535. Refer to Tasks 550 through 580 for scope and budget assumptions for these additional project components. Subtask 505. Monthly Status Report and Project Invoices During Phase H,project invoices will be submitted monthly accompanied by a project status report documenting key activities of the previous and upcoming months, project action items,project expenditures, and project schedule updates. Deliverables: 1 copy of Status Report and Project Invoice each month for the duration of the phase (4 months). Subtask 510. Progress Meetings/Coordination During Phase H, continual communication and coordination of activities will be maintained with the City. Regular meetings will be conducted with the City to review progress and exchange ideas and information. Assumptions: 3 Progress Meetings are assumed for this phase. Deliverables: Draft Meeting Agenda(3 days before meeting). Meeting Agenda-copies as required. Meeting Minutes (within 1 week following meeting) — copies as required. Subtask 515. 30%Design Submittal Develop drawings and specifications to approximately 30% completion. Specifications will include a Table of Contents, all standard specification sections, and draft sections for major engineered equipment systems. Under this subtask, survey work will be conducted, through a subcontract, to supplement available topographical survey data and to identify locations (horizontal and vertical) of key connection points. SLA-Phase II FINAL 2 EXHMIT A City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 Submit 5 copies for review. Deliverables: 30% Half-Size Drawing Set (5 copies). Technical Specifications (5 copies). Subtask 520. 50%Design Submittal Develop drawings and specifications to approximately 50% completion. All major drawings and specifications will be represented and will reflect in-house quality control comments. A progress cost estimate will be provided with this submittal. Submit 5 copies for review. Deliverables: 50% Half-Size Drawing Set (5 copies). Technical Specifications (5 copies). Subtask 525. 90%Design Submittal Develop drawings and specifications to approximately 90% completion. All drawings and specifications will be "engineering complete" and will reflect in-house quality control comments. An updated cost estimate will be provided with this submittal. Deliverables: 90% Half-Size Drawing Set (5 copies). Technical Specifications(5 copies). Subtask 530. 100%Design Submittal Incorporate City comments into the drawings and specifications, and provide a final submittal. Deliverables: Final Construction Drawings (Vellum Full-Size Drawings, 1 copy). Technical Specifications. Subtask 535. City Council/Architectural Review Commission Presentation Project status and design recommendations will be presented to: • City Council and Architectural Review Commission during the Final Design Phase Assumptions: Up to 20 Microsoft PowerPoint slides will be prepared for each presentation. Deliverables: Presentation Materials for Presentation. Subtask 540. Credit for Preliminary Design of Transfer Pump Station The budget for this task provides for credit to Consultant for preliminary design work sw-Phase a Fant. 3 0. 3-/z EXHIBIT A i City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 related to the new transfer pump station, which was not included in original Task 200 scope of work. Subtask 545. Credit for Deletion of Transfer Pump Station Pump/Motor Replacement and Clearwell No .] Seismic Upgrade The budget for this task provides for credit to City for detailed design work related to the replacement of pumps and motors at the existing transfer pump station and the seismic rehabilitation of the existing clearwell. This detailed design work is not longer required because these facilities will be demolished. Task 550—WTP Detailed Design—Plant-Wide Improvements—Phase II Subtask 555. Cal Poly Raw Water Line Improvements New flow meter and motorized valve installed in a new buried vault on the Cal Poly raw water pipeline. Subtask 560. Washwater Basin Drain Line Repairs and/or replacement of the drain line from the Washwater Basins to the drainage swale near the existing clearwell. Subtask 565. Sludge Pond Underdrain Improvements: Repairs and/or replacement of the Sludge Pond underdrain pipeline that crosses the WTP access road. Subtask 570. Slope Repairs. Slope repairs and/or modular retaining wall installation in steep slope areas above and below the Washwater Basins. Subtask 575. Washwater Treatment System Evaluation. Evaluate treated washwater return system hydraulics to address limitations and recommend improvements to increase flow capacity. Develop Detailed Design of modifications to washwater treatment pump controls and telemetry to allow pumps to start and stop based on levels in washwater basins. Assumptions: Budget does not assume redesign of the washwater return system. Subtask 580. Paving Improvements. Design of paving improvements throughout the plant, including paving replacement and slurry seal application. SIA-Phase 11 FINAL 4 EXHIBIT A i l City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 Task 730- Stenner Canyon Hydroelectric Conceptual Design Evaluations- Phase II The following tasks are added for refining and further developing the conceptual design associated with the preferred alternative selected from the feasibility study for the Stenner Canyon Hydroelectric Project: Subtask 731. Assistance with PG&E Coordination/Negotiation This task includes scheduling and attending project coordination meetings to be conducted between the City and PG&E for the purpose of clarifying project alternatives and operation; amending the City's power sales agreement; and confirming conceptual design requirements associated with PG&E interconnection requirements and special facilities. Assumptions: Three (3)meetings are assumed. Deliverables: Draft Meeting Agenda(3 days before meeting). Meeting Agenda-copies as required. Meeting Minutes (within 1 week following meeting) — copies as required. Subtask 732. Additional Evaluations This task includes updating and refining the Feasibility Study Technical Memorandum estimates of hydroelectric facility flowrate, power generation estimates, energy revenue estimates, power costs, and financial analyses based on any project concept changes resulting from discussions between the City and PG&E under Subtask 731. This task also includes additional research and computations to determine the structural and hydraulic capacities of existing pipelines in the Salinas raw water system. Assumptions: Prepare the additional evaluations for one (1)preferred alternative. Deliverables: See Subtask 734. Subtask 733. Develop Operational Strategy This task is for developing a step-by-step procedure that defines integrated operation of the Salinas raw water system, Stenner Canyon hydroelectric facility, and water treatment plant. Operational protocols will be developed for the daily startup and shutdown routines, as well as for planned and unplanned shutdowns of the hydroelectric facility. The objective is to achieve seamless operation of all facilities and minimize the extent of PG&E power purchases needed to operate the major WTP process equipment. Assumptions: Prepare the operational strategy for one (1)preferred alternative. Deliverables: See Subtask 734. SIA-Phase U FINAL 5 EXHIBIT A L City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 Subtask 734. Technical Memorandum This task will document the work activities included under Task 730. Deliverables: Draft TM submitted for City review (5 Copies). Final TM with City comments incorporated(5 Copies). Subtask 735. Meetings and Consultation This task is allocated for miscellaneous meetings and technical consultation, including design reviews with City staff. Sixteen (16) manhours are budgeted. Task 800—Additional Project Components —Phase II The following additional project components have been added to the scope of work: Subtask 805. Plant-Wide Control System Evaluation This task includes an evaluation of existing control systems, including software and hardware, and meetings with plant staff to determine preferred control system capabilities, operator interfaces, and system reporting capabilities. This task includes the preparation of a letter report presenting findings and recommended improvements to the plant-wide control system. It is envisioned will be followed with an additional task involving the detailed design and actual implementation of the recommended improvements by Consultant's instrumentation and control technicians. Deliverables: Draft Letter Report submitted for City review(5 Copies). Final Letter Report with City comments incorporated (5 Copies). Subtask 806. Plant-Wide Control System Design Based on the approved recommendations in the Plant-Wide Control System Evaluation letter report, construction documents will be prepared under the same detailed design process as is outlined for Task 500. Input will be gathered from WTP operations staff to establish design criteria and to assure staff needs and preferences are being incorporated into project documents. The key tasks involved in the Control System Replacement detailed design involve clear specifications of technology the suits the City's needs and minimizes disruptions to the plant operation. The detailed design documents will include specification of the following: • The existing Plant Control System utilizes Bristol Babcock 3330 RTUs that last had a firmware upgrade 10 years ago. These RTUs are operating on computer processors that are 10 years old. A specification will be written to SLO-Phase 11 RNAL 6 0. EXHIBIT A i City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 have the RTU's firmware upgraded so they are capable of communicating with a new Human-Machine-Interface system. • The existing Human-Machine-Interface Software is a DOS based program and will be upgraded to an HMI program that runs in a Windows based operating system, utilizes OPC data transfer, and has SQL reporting capability. It is important to keep the existing Genesis Dos Based HMI software operational during the replacement of the System. • New Computers will be specified for the New HMI system. • A new RTU will be designed into the existing plant control system such that is allows monitoring and control of the transfer pumping station. • A Control System Programming Description specification will be written. This speciation will identify the graphic screens that must be recreated for the new HMI system and identify the control interfaces to the existing RTU program. For example, the specification will include-a picture of the existing Filter Backwash Setpoint Control screen and identify the RTU signals that must be programmed into the new HMI system. The existing system contains 81 graphic screens and approximately 1500 HMI data points. • A specification will be created to delineate the start-up and testing procedures required at each stage to insure minimal disruption to plant operations while providing a tested system. These detailed design documents will provide direction for the replacement of the HMI program by the Consultant's instrumentation and control technicians during the construction phase. These documents will also integrate the control system upgrade project with work to be conducted by the contractor hired for the WTP Improvements. Subtask 810. Other Plant Improvements This task includes evaluation and design work related to several plant improvement projects that are not fully defined. It is envisioned that Consultant will conduct evaluation work for each project. Following development of detailed design scope, Consultant will meet with City staff to confirm availability of adequate funding for detailed design under this task budget. As currently defined, these projects include: HVAC Improvements: Includes an evaluation and detailed design for addition of air conditioning on the Ozone Building operating floor and heating and air conditioning in the laboratory and office areas in the Filter Building. Budget excludes evaluation of Title 24 compliance requirements. Ventilation Improvements: Includes an evaluation and detailed design for ventilation improvements in the Chemical Building. Plant-Wide Sampling System Improvements: Plant staff has indicated that specific portions of the plant's sampling system do not function effectively, such as the clearwell effluent sampling system. This task includes an evaluation of improvements to these areas SLO-Phase 11 FINAL 7 Q EXHIBIT A "Will City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 of the plant sampling system. This task includes meeting with plant staff to determine system deficiencies and development of recommended improvements. Emergency Power System Modification: Includes an evaluation of modifications to the emergency power system to allow additional plant loads to be fed from the emergency generator in the event of a power failure. Additional capacity is expected to be available following the feeding of plant water service from the Transfer Pump Station and Reservoir No. 2. Fluoride Feed System Improvements: Includes an evaluation and detailed design for improvements to the fluoride feed system such as replacement of specific system components. Budget.does not include a complete system redesign, such as would be required with a change to hydrofluosilicic acid. Subtask 815. Ballasted Flocculation Evaluation This task includes additional evaluation of the potential addition of Ballasted Flocculation (Actiflo) to the WTP. This evaluation will build upon the information presented in the PDR and will include an analysis of potential reductions in ozone demand and other water quality implications. The evaluation findings will be presented in a letter report including a life cycle cost evaluation of capital costs, energy costs, chemical costs, and other operations and maintenance expenses. Deliverables: Draft Letter Report submitted for City review (5 Copies). Final Letter Report with City comments incorporated(5 Copies). Subtask 820. Ballasted Flocculation Pilot Study(Optional Task) This task includes the implementation of a 5-week Actiflo pilot test and a 5-week test of pilot filters. Budgeted costs include the following: • equipment rental • equipment transportation • equipment start-up • periodic observation of operation (3 one-day site visits assumed) • coordination of equipment procurement, setup, operation, and breakdown • preparation of a technical memorandum at the conclusion of the testing to summarize findings and recommendations Assumptions Budget assumes the City will be responsible for providing day-to- day operations and maintenance of the pilot facilities and will be responsible for installing and removing piping and power interconnections required to operate the pilot facilities. SIA-Phase 11 FINAL 8 Q f I r EXHIBIT A l City of San Luis Obispo B&V Project 132365 WTP Improvement Project November 2003 COMPENSATION Payment terms shall be as called for in the original contract. In addition to the compensation stipulated in the original contract, the City will pay and the Consultant shall receive compensation in a total sum not to exceed$519,686 for the services outlined in this Amendment. Additional compensation not to exceed $53,029 may be authorized by the City Utilities Director for work associated with Subtask 810. If the City elects, at a later date, to proceed with Subtask 820, Ballasted Flocculation Pilot Study (Optional Task), the Consultant shall receive additional compensation in a total sum not to exceed $76,185. SLO-Phase 11 FINAL 9