1. Approve Amendment No. 1 to the contract in the amount of $39,795 for design services
associated with 919 Palm Street Tenant Improvements from RRM Design Group.
2. Approve the transfer of $39,795 from the contingency account to the design account for
payment to RRM Design Group for these services.
DISCUSSION
On September 3; 2002 the City Council awarded an agreement in the amount of$89,290 to RRM
Design Group to furnish design services for tenant improvements at 919 Palm Street. Since then,
design revisions initiated by the City have resulted in five Additional Service Authorizations
totaling $60,898. Additional Services Authorization No. 5 was established as $24,973 plus
hourly tasks. These hourly tasks, along with other expenses from the original design contract,
totaled nearly $33,000, which has remained unpaid since September, 2004 due to questions
regarding some of the billing items.
In January, 2005, City Staff met with RRM Design Group and negotiated a credit for the City,
reducing the outstanding invoices to $22,256. Recently, a partial payment of $2,461 has been
made to RRM Design Group for the unpaid invoices, emptying the design account balance. Staff
recommends the transfer of$19,795 from the contingency account to the design account in order
to fully pay these outstanding invoices.
Also, in January, as a result of estimated increases in the cost of improvements, Staff initiated
value engineering, which entails investigating ways to lower the overall construction cost for the
tenant improvement project. Value engineering was recently concluded, finding a potential
$400,000 cost savings for construction by elimination and/or substitution of building materials
and redesign of certain components. These value engineering revisions must be incorporated
into the plans and specifications by RRM Design Group in order for the project to be bid at a
reduced cost. The proposed tenant improvement plans and specifications, and accompanying
construction budget estimates and adjustments, are currently scheduled for Council consideration
on May 17.
Staff recommends the transfer of an additional $20,000 to the design account to cover the costs
of the value engineering revisions (see Attachment). RRM Design Group and their consultants
have indicated they will not make design revisions to the plans and specifications until the
outstanding invoices have been paid. This will create a delay in the overall construction
schedule. p t
litX — l
Design for Tenant Improvements at 919 Palm Street Paget
FISCAL IMPACT
The following table summarizes existing and additional design contract costs:
Existing Design Contract Costs:
Construction Documents—Electrical/Lighting $1,353
Bidding Assistance 15,806
Construction Review 1;588
Statement of Probable Construction Cost 1,240
Meetings & Shell Coordination 11,205
Reimbursables 1,706
Credits (10,642)
Design Account Payment (2,461) $19,795
Additional Design Contract Costs:
Value Engineering Revisions by RRM&List Engineering $10;761
Value Engineering Revisions by Thoma Electric (estimated)* 7,500
Additional Meetings and/or Coordination 1,739 $20,000
Total Design Contract Costs:. $399795
* Note at this time no estimate has been provided for electricalflighting plan revisions. Staff is
estimating this to be $5,000 to $7;500., More specific information will be provided to the
City Council as it becomes available.
Currently; there is $171,000 budgeted for contingencies for the office component of this project.
This proposed funding transfer will leave a contingency balance of$131,200.
ALTERNATIVES
1. The City has a contractual obligation to pay for the fees incurred to date. Council could
direct Staff to attempt to further negotiate fee reductions. Staff believes that they have
negotiated as much of a reduction as possible..
2. A different architectural firm could be hired to complete the revisions. Staff does not believe
this is practical due to the costs involved and the time delays that would occur.
3. The current plans and specifications could be used for bidding purposes but the project would
be significantly more expensive to build.
ATTACHMENT Amendment No. 1 to Agreement To Furnish Design Services For Tenant
Improvements At 919 Palm Street with RRM Design Group..
I:\—Council Agenda Reports\W05 agenda reports\Engineering and Maintenance Services(Walter)\Capital Projects Design(Lynch)\Shortcut to
90323 CAR Value Engineering.doc
ATTACHMENT
AMENDMENT TO AGREEMENT
THIS AMENDMENT TO AGREEMENT is made and entered in the City of San Luis Obispo on this 19th
day of April, 2005,by and between the CITY OF SAN LUIS OBISPO,a municipal corporation,herein after referred
to as City,and RRM Design Group,hereinafter referred to as Consultant.
WITNESSETH:
WHEREAS, on September 3, 2002, the City entered into an Agreement with Consultant for design services
associated with the tenant improvements for 919 Palm Street Offices;and
WHEREAS, the City desires to amend the scope of services to include additional services and value
engineering revisions to the tenant improvement plans and specifications and Consultant has submitted a proposal
for this purpose that is acceptable to the City.
NOW THEREFORE, in consideration of their mutual promises, obligations and covenants hereinafter
contained,the parties hereto agree as follows:
1. The scope of services and related compensation is hereby amended as set forth in Exhibit A
attached hereto.
2. All other terms and conditions of the Agreement remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed the day and year
first written above.
ATTEST: CITY OF SAN LUIS OBISPO,
A Municipal Corporation
By:
City Clerk City Administrative Officer for Mayor]
APPROVED AS TO FORM: CONSULTANT
By:
ity A rney
r
Exhibit A
Existing Design Contract Costs:
Construction Documents—Electrical/Lighting $1,353
Bidding Assistance 15,806
Construction Review 1,588
Statement of Probable Construction Cost 1,240
Meetings & Shell Coordination 11,205
Reimbursables 1,706
Credits (10,642)
Design Account Payment .(2,461) $19,795
Additional Design Contract Costs:
Value Engineering Revisions by RRM &List Engineering $10,761
Value Engineering Revisions by Thoma Electric (estimated) 7,500
Additional Meetings and/or Coordination 1,739 . $20,000
Total Design Contract Costs: $39,795