CITY OF SAN LUIS OBI SPO
FROM: Jay D. Walter, Director of Public Works
Prepared By: Barbara Lynch City Engineer$L-
SUBJECT: FOOTHILL BRIDGE REPLACEMENT PROJECT, SPECIFICATION
NO, 90197D CONSTRUCTION MANAGEMENT AMENDMENT
CAO RECOMMENDATION
Approve Amendment No. 9 to the Construction Management Services Agreement with MRO
Engineers and authorize the Mayor to execute the Amendment.
DISCUSSION
The replacement of the Foothill Bridge is largely complete after a year and a half of construction.
From the beginning, the project has required consultant services for construction. Inspection and
environmental monitoring were required on a full time basis and since the City does not have a
bridge inspector or a biologist to dedicate full-time to the project, this service has been provided
by the designers MRO Engineers. The project budget included funding for these needs at the
time of award.
As the project neared completion, it became clear that additional funds would be required to
provide the remaining inspection and monitoring services required. The key reason for this is
that the project construction timeline changed from that originally envisioned. This occurred
primarily for two reasons, each of which added over a month to the project. The first was the
conversion of the project to allow the bridge to be built over the existing culverts. This extended
the duration of the project but allowed the bridge to be completely open to traffic several months
sooner. The second was the discovery of contaminated water and extended unstable backfill in
the excavation. These conditions were unknown to the City at the time of award and also caused
delays to the construction timeline.
On December 6, 2005, the City Council authorized $50,000 for additional construction
management and monitoring services. Through an oversight Amendment No. 9 to the
Agreement with MRO Engineers was not included with the request for funding. Staff is now
requesting that Council authorize the amendment to allow Finance to process the final bills.
FISCAL IMPACT
Current Budget
Construction:.
Inspection & Monitoring $576,000 Original Agreement: $576,000
Contingencies $50,000 Amendment No. 9: $30,000
Total: $626,000 Total Revised.Agreement: $606,000
Cy--I
Foothill Bridge Construction Management Amendment Page 2
The bills associated with Amendment No. 9 represent approximately $30,000 of the total
$50,000 requested in December. At the time of the budget augmentation request, the extent of
the additional cost was not known. At this time, staff has all but a minor bill outstanding and is
able to provide a much better estimate as to the final additional cost needed to complete the
construction management and environmental monitoring. Of the $20,000 that appears will be
remaining in the account at completion, only $4,000 are actually City funds with the remainder
being grant funds.
ATTACHMENTS:
Attachment 1 - Amendment No. 9
f:L_=mporMk200ftpU0197 foothill DA4-4.06 cm am d.doc
Cy
Y
Attachment 1
AMENDMENT NINE TO AGREEMENT
THIS AMENDMENT NINE TO AGREEMENT is made and entered in.the City of San Luis
Obispo on this day of , 2006, by and between the CITY
OF SAN LUIS OBISPO, a municipal corporation, herein after referred to as City, and Martin, Rivett
& Olson Inc., Consulting Engineers hereinafter referred to as Consultant.
WITNESSETH:
WHEREAS, on September 26, 2001 the City entered into an Agreement with Consultant for
design and environmental services for the Foothill Street Bridge; and
WHEREAS, additional construction services are required beyond those anticipated in
Amendment 8 to inspect and provide material testing for the project;
NOW THEREFORE, in consideration of their mutual promises, obligations and covenants
hereinafter contained, the parties hereto agree as follows:
1. Authorization is given for additional work to provide construction related services in an
amount not to exceed $ 30,000 ;
2. All other terms and conditions of the Agreement remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed
the day and year first written above.
ATTEST: CITY OF SAN LUIS OBISPO, A Municipal Corporation
By:
City Clerk.Audrey Hooper Mayor David F. Romero
APPROVED AS TO FORM: CONSULTANT:
By:
mey Jonathan Lowell
g:l_darert pmpM'bndgeslg0197 fooftll_swnrier bridge\d=merdsl3premnsWCionlcansultent selecbon&corrtracWnm a9 cm.doc
Foothill Bridge at Stenner Creek Consultant Services Agreement—Amendment 9