HomeMy WebLinkAbout10/17/2006, C3 - EMERGENCY STORM DRAIN PROJECT: RAMONA AT PALOMAR C; o council Mtig D� 10-17-06 j ac En oa Repont c 3 CITY OF SAN LU I S O B I S P O FROM: Jay Walter, Public Works Director Prepared By: Christine Comejo, Engineering Technician SUBJECT: EMERGENCY STORM DRAIN PROJECT: RAMONA AT PALOMAR CAO RECOMMENDATION 1. Authorize the CAO to approve plans and specifications to advertise for emergency repair work on the storm drain located near the intersection of Ramona and Palomar. 2. Authorize the CAO to award the contract if it is within the engineer's estimate of$130,000. 3. Appropriate$145,000 from the unreserved General Fund balance for this emergency work for construction($130,000),contingencies($13,000) and materials testing($2,000). DISCUSSION Streets maintenance staff recently discovered a depression .in the asphalt and gutter on Ramona Street near the intersection of Ramona and Palomar. The depression is located at the bottom of the curb, extending through the gutter and into the roadway adjacent to a bus shelter(See Attachments 1, 2 and 3). The depression is approximately three feet wide and five feet long. The original storm drain was installed in 1966 in conjunction with the shopping center at Foothill and Broad. In 1972 Ramona was widened adding curb, gutter and sidewalk to accommodate Tropicana Village. The existing drop inlets were installed and an additional 22 inch X 36 inch arch Corrugated Metal Pipe (CMP) was connected to the end of the existing pipe to accommodate the additional width of the street. A video pipeline inspection revealed the existing CMP pipe to be in poor condition with a portion of the pipeline beginning to collapse just below the depression. Further investigation of the complete length of pipe showed the remaining pipe to be in a poor condition as well. The existing pipe's ability to support surrounding soil pressure, handle sidewalk loads, bus traffic and cant' storm water has been substantially reduced. This project will remove the existing CMP in this area. A new and slightly larger storm drain pipe will be installed in the existing location to replace it. Two existing drain inlets and one manhole will be replaced, and one new manhole will be added. Because of the urgency of this necessary repair, Staff is requesting that Council authorize the CAO to approve plans and specifications in order to expedite construction. O O Emergency Storm Drain Project: Ramona at Palomar Page 2 Project Design and Management City engineering staff will design and inspect this project. While this will adversely impact our resources in meeting the current CIP work program, it is important that this emergency work go forward in a timely manner. NEXT STEPS The following outlines the next steps in completing this emergency work: Task 1 Complete plans & specifications and invite bids 11/18/06 Open bids 12/07/06 Award and execute the contract 12/28/06 Begin construction 01/22/07 Complete construction 03/23/07 FISCAL IMPACT This is an emergency project and as such is not currently funded in the 2005=07 Financial Plan. The following summarizes project costs: Project Costs Construction 130,000 Contingencies @ 10% 13;000 Materials Testing/Soils Reports 2,000 Total $1459000 We recommend funding this from the unreserved General Fund balance: given its one-time, emergency nature, this is an appropriate use of General reserves and the remaining balance will still meet our policy minimum. ALTERNATIVES The City Council could decide to replace only the damaged portion of the existing Storm drain and install one new manhole at a cost of$34,500. This would leave the remaining sections of poor condition pipe in place. Those sections will eventually cause problems, require replacement, and will be even more costly to do at a later date. As such, we do not recommend this option.. ATTACHMENTS 1. Vicinity Map 2. Photos 3. Photos G:\Staff-Reports-Agendas-Minutes\_CAR\2006\ClMamona SD Replacement\CAR Ramona Storm Drain Replacement.DOC c3 -2 ATTACHMENT 1 FOOTHILL RAMONA r - ----------- SD - - _ _ _SD TO BE CD j REPLACED Q i LUN ETA 8 Ramona Emergency SM US OBIO Storm Drain Replacement Project City or ATTACHMENT 1 c3 - -3 ti ATTACHMENT 2 SHADOW FROM BUS SHELTER Outline shows area of failure. Buses stop and travel directly over SD failure. �y Curb and gutter separating leaving crack for water to travel through and further undermine and erode the already failing structure. Ramona Emergency j crtyaF Storm Drain Replacement Project SM LLUS OBISPO ATTACHMENT 2 6 %3 -el ATTACHMENT 3 \ ` tl SD pipe is collapsing & turning in on itself at outlet to creek. Y �44 J t Section where SD pipe was added. Pipe is collapsing, becoming oblong and water is pooling behind the connection. Ramona Emergency Sm LU1S OBISPO Storm Drain Replacement Project ATTACHMENT 3 13 -3