HomeMy WebLinkAbout11/16/2006, - ATTACHMENT 2 LONG TERM CAPITAL IMPROVEMENT PLAN ATTACHMENT
2
Attachment 2
LONG-TERM
CAPITAL IMPROVEMENT PLAN
Summary of Facility and Infrastructure
Improvements Through General Plan Build-Out
November 2006
SAN.LU1s0
city of
X1856. Rr Stt06
- CEI ����� SAn WIS OBI SPO
LONG-TERM CAPITAL IMPROVEMENT PLAN
November 2006
TABLE OF •
INTRODUCTION
Overview 1
Report Organization 2
Summary 3
CAPITAL IMPROVEMENT PLAN PROJECTS BY FUNCTION
Public Safety 4
Police and Fire& Environmental Safety
Public Utilities 5
Water and Wastewater
Transportation 6
Streets 6
Creek&Flood Protection 7
Pedestrian&Bicycle Paths 7
Parking 9
Transit 9
Leisure,Cultural and Social Services 10
Parks&Recreation,Adobe Restoration and Public Art
Community Development 11
Open Space Protection and Trails
General Government 12
Information Technology and Buildings
Cost Summary by Function 12
cityo San luis OBISPO
U� l
INTRODUCTION
OVERVIEW
The purpose of this report is to assist the Council in developing goals for 2007-09 by presenting
a comprehensive but concise summary of the City's long-term capital improvement plan (CIP)
for facility, infrastructure, equipment and land costs needed to serve the City at build-out under
the adopted General Plan.
Provides a `-`menu" of possible "goal entrees." On one hand, this report provides valuable
background information for Council goal-setting, as we have always defined the purpose of the
City's budget process as asking ourselves: of the many goals, objectives and work programs set
forth in our long-term planning and policy documents, which are we going to focus on in the next
two years?
With this approach, the City's two-year budget process becomes our key tool in programming
the implementation of these plans and policies by allocating the resources necessary to do so.
And our "very long-term CIP" is one of the key "menus" of candidate "goal entrees" for the
Council to consider in setting goals for 2007-09.
But it does not reflect agreed-upon priorities. that's the purpose of the budget process On the
other hand, as discussed in more detail below, this very long-term CII' is conceptual. And in
many cases, the projects have not undergone detailed analysis, nor undergone the rigor of the
public review process. As such, many of these projects may never emerge as high priorities —
regardless of our financial condition— and may undergo changes in scope or importance as new
challenges and issues emerge overtime.
Results Summary
Long-Term GIP By Function:$880.5 Million
As summarized in the IS Community O General
Development Govemment
"sidebar" chart; these 3% 3%
improvements total about 17 Public Safety
$880 million, with 6%
transportation improvements ❑ Leisure.
accounting for almost two- Cultural& 0 Transportation
Social Services 63%
thirds of these costs. 9%
Key Assumptions O Public Utilities
16%
The following are key
assumptions underlying. the
costs presented in this
report:
1. New Facilities Only. These costs only reflect new improvements needed to support General
Plan build-out, based on current policies, plans and goals in place today. Recurring,
maintenance oriented-improvements, such as pavement maintenance, are not reflected in
these costs. While they are significant (the "Maintenance-Only CIT" prepared as part of the
2005-10 General Fund fiscal forecast two years estimated that annual costs in the General
t �-3
INTRODUCTION
Fund alone to adequately maintain the facilities, infrastructure and equipment we already
have in place is about $7 million), these are incurred to adequately maintain what we already
have in place today. This report focuses on the new facilities and infrastructure needed to
support the City at build-out.
2. Not Just for "New Development" The improvements presented in this report are not needed
just to support new development: in many cases, they address current deficiencies as well.
For example, we estimate that it will cost $20 million to underground overhead utilities. This
is driven by the development in place today. .
3. Funding Sources. The costs presented in this report do not address funding sources. In
many cases, this will be the responsibility of new development. For example, under Parks
and Recreation, we estimate that the cost of meeting the need for parks for new development
(again, based on achieving the General Plan goal of 10 acres of park per 1,000 residents) is
about $50 million. However, it is the City's policy that new development is responsible for
this cost. Additionally, it is likely that grant sources will cover some of these costs,
especially in the transportation area. And many of these projects will be financed through
our enterprise funds, such as water; sewer and parking.
4. Priorities Yet to Be Set, and Needs Are Likely to Change Over Times ,As noted above, this
"very long-term CIP" is conceptual. Its purpose is to provide a starting point for the Council
in the goal-setting process; it is not intended to represent an agreed-upon list of high-priority,
"must do" projects. In fact, this is the purpose of the City's goal-setting and budget process;
and as such, this summary is a resource— not an outcome. It is the beginning of our priority
setting process, not the destination itself. For this reason, many of these projects may never
emerge as high priorities— regardless of our financial condition— and may undergo changes
in scope or importance as new challenges and issues emerge overtime.
In short, this report focuses on presenting the "inventory" of improvements that may be needed
at some time in the future, as a starting point in the goal-setting process. Crafting funding
solutions for implementation based on Council priorities is the next step in the process, and an
integral part of the Financial Plan process.
REPORT ORGANIZATION
Function Groupings. The report organizes CIP project into the six major functional areas used
in the City's Financial Plan:
Public Safety
Police Protection, Fire & Environmental Safety
Public Utilities
Water, Wastewater
Transportation
Streets, Pedestrian & Bicycle Paths, Creek & Flood Protection, Parking, Transit
-2- 0:2_y
1 ' 1
INTRODUCTION
Leisure, Cultural and Social Services
Parks &Recreation, Adobe Restoration, Public Art
Community Development
Open Space Protection, Trails
General Government
Information Technology, Buildings
As noted above, this report is not intended to reflect priorities: that's the purpose of the goal-
setting and budget process that we are just now initiating for 2007-09. Its organization simply
groups similar projects together, and as such, the order in which they are presented does not
reflect their relative importance.
Goal and Policy Links. For each project, the report shows the "goal or policy link" that is the
basis for the project. In most cases, these links come directly from the General Plan. In others,
the link may be to an adopted master plan. For virtually all projects, there is a link to a major
policy document approved by the Council.
Costs: High Level Estimates. In most cases, costs are "order of magnitude, reconnaissance
level" estimates. Only in very few cases have we formally studied the project; and we have gone
to the design phase in even fewer. As such, these represent the staffs best assessment of costs
based on what we know today.
SUMMARY
In placing these projects in the context of the 2007-09 goal-setting and Financial Plan process,
these costs — even at a "high level" — provide an important starting place in assessing which of
these projects should be a high priority over the next two years, given its likely cost and our
fiscal outlook.
-3 - ���
PROJECT SUMMARY
Pro ect Description Plan orPolic- Link Cost
PUBLIC SAFETY
Police Protection - _
Land Acquisition for New Police Headquarters
Police Facilities Master Plan 8,645,000
New Police Headquarters Facility Police Facilities Master Plan 33,044,000
Total Police-Protection 41,689,000_
Fire and Environmental Safety
Equipment
Tillered Quint Pending Fire Master Plan 950,000
Type III Fire Engine Wildland Fires Pending,Fire Master Plan 300,000
Fire En-ine fog Station 5 Pending Fire Master Plan 600,000
Squad/Ambulance Pending Fire Master Plan 165,000
MDC's:Truck-2, Squad-1, OES-271 Pending Fire Master Plan 30,000
EMS Interface& Maintenance Pending Fire Master Plan 35,000
Light and Air Trailer Unit I Pending Fire Master Plan 75,000
Technical/Heavy Rescue Response Vehicle I Pending Fire Master Plan 100,000
Facilities
Fire Station 2 Re lacement/Rehabiliation Pending Fire Master Plan 4,000,000
Fire Station 3 Re lacement Pendin Fire Master Plan 4,000,000
Warehouse Building Station No. 1 Pending Fire Master Plan 300,000
Expand Training Tower Pending Fire Master Plan 250,000
EOC/Instructional Facility Station No. 1 Pending Fire Master Plan 2,500,000
Storage/Garage Station No. 4 Pending Fire Master Plan 300,000
Fire Station Alertin System Pendin Fire Master-Plan - 250,000
Emergency Call-Back System Pending Fire MasterPlan 125000
Total Fire and Environmental Safety 13,980,000
TOTAL PUBLIC SAFETY $ 55,669,000
-4- —C.2
PROJECT
R•
Project Descri tion I Plan or Policy Link Cost
PUBLIC UTILITIES
Water Services
Water Supply
Nacimiento Pipeline Water Element, General Plan 75,023,000
Water Distribution
Telemetry System Improvements IT Strategic Plan, March 2001 845,600
Master Plan Implementation Water Master Plan, October 2000, 14,013,000
prepared by Boyle Engineering
Water Reuse Master Plan Implementation Water Reuse Master Plan, Sept. 2004 7,000,000
Prepared by Dudek and Assoc.
Total Water Service 96,881,600
Wastewater Services
Collection
Telemetry System Improvements IT Strategic Plan, March 2001 719,400
Calle Joaquin Lift Station Wastewater Master Plan, Oct 2000 2,000,000
prepared by Brown and Caldwell.
Silver City Lift Station Wastewater Master Plan, Oct 2000 180,000
prepared by Brown and Caldwell.
Treatment and Reclamation
Master Plan Implementation(plant Wastewater Master Pian, Oct 2000 19,000,000
improvements to meet General Plan po prepared by Brown and Caldwell.
Projected Treatment Requirements Im rovements Estimated by Brown and Caldwell 20,000,000
Total Wastewater Service 41,899,400
TOTAL PUBLIC UTILITIES $ 138,781,000
-5 - �2, 7
• C
SUMMARYPROJECT
Project Description Plan or Policy Link Cost
TRANSPORTATION
Streets
New Roads
Prado Road: Broad to Higuera Circulation Element A.1 20,000,000
Prado at Higuera Intersection Mar arita Area Specific Plan 286,000
Prado Road: Higuera to US 101 Circulation Element A.1, B.4 5,700,000
Buckley Road: Extend from Vachell to Higuera Circulation Element A.3 4,004,000
Bullock Lane Extension to Tank Farm Road Circulation Element A.4 3,000,000
Sacramento Drive Extension Orcutt Road Circulation Element A.5 1,500,000
Bishop Street Extension Across UPRR to Broad Circulation Element A.6 10,000,000
Santa Fe Rd: Realign s/o Tank Farm Road Circulation Element A.7, AASP 4,950,000
Santa Fe Rd: Connect with future Prado Rd Circulation Element A.7, Masp,AASP 1,404,000
Road Widenings
Higuera Street- High to Marsh Circulation Element B.1 3,500,000
Orcutt Road - Broad to Johnson Circulation Element B.2 1,500,000
Orcutt Road - UPRR Crossing Widening Circulation Element B.2 2,540,000
Tank Farm Road-S Higuera to Broad Circulation Element B.3, AASP 5,495,000
South Higuera-Madonna to Prado Road Circulation Element B.5 500,000
LOVR-Madonna to US 101 Circulation Element B.6 500,000
Santa Rosa Street-Olive to Foothill Road Circulation Element B.7 3,000,000
Santa Rosa Street at Foothill EB RT lane Circulation Element B.8(a) 1,000,000
Santa Rosa Street at Olive NB RT Lane Circulation Element B.8(b) 1,500,000
Santa Rosa Street at Walnut LT lanes Circulation Element B.8(c) 250,000
Santa Barbara Street: Upham to Broad Railroad District Plan 1,200,000
Santa Barbara Street: Leff to Upham I Railroad District Plan 250,000
Broad Street: South Street to Alphonso. I Four Creeks EIR 1,000,000
Freeway Interchanges
Prado Road Interchange Circulation Element C.1 40,000,000
LOVR Interchange Circulation Element C.2 27,010,000
Route 101/HWY 1 Santa Rosa Circulation Element C.3 40,000,000
Broad Street/US 101 Ramp Modifications Circulation Element CA 1,500,000
Other Street Projects
Monterey Street: Santa Rosa to Grand Circulation Element D.1 15,000,000
Orcutt Road Grade Separation at UPRR Circulation Element D.2 20,000,000
Prefumo Canyon Road-Landscaped median Circulation Element D.3 500,000
Broad Street Dogleg Circulation Element D.5 350,000
Guard Rail Upgrade and Replacement Safdty Element 1,000,000
Congestion Relief Projects Circulation Element 5,000,000
Neighborhood Traffic Management Circulation Element, LU 2.1.3. 800,000
Traffic Safety Mitigation Circulation Element 5,000,000
LOVR Landscaped Medians Circulation Element 2,000,000
Broad Street Landscaped Medians S of OrcuttAASP 2,500,000
Broad Street Corridor Enhancement Circulation Element 2,000,000
Santa Rosa Street Corridor Enhancement Circulation Element 1,500,000
Foothill Road Corridor Enhancement Circulation Element 1,500,000
Undergroundiri of Overhead Utility Lines Circulation Element 20,000,000
City Assistance: Neighborhood Improvements Housing Element 7.3.3 5,000,000
Parker Street Improvements Mid-Higuera Enhancement Plan 75,000
Brook Street Extension &Plaza Mid-Higuera Enhancement Plan 225,000
Walker/Pacific Closure&Plaza Mid-Higuera Enhancement Plan 225,000
-6-
z-F
\r
PROJECT
R.
Project Description Plan or Policy Link Cost
Traffic Si pals, Street Lights&Signals
New Traffic Si nals Circulation Element 2,500,000
Traffic Signal System Upgrade Circulation Element 750,000
Video Detect/Surveillance Circulation Element 1,000,000
Traffic Signal Communications Circulation Element 1,500,000
Downtown Pedestrian Level Street Lighting Circulation Element 2,300,000
New Street Lights $15,000 Per Year Circulation Element 30.0,000
Street Light Modifications/Upgrade Circulation Element 2,500,000
Downtown Pedestrian Signals Improvements Circulation Element 300,000
Billboard Removal Program Circulation Element 14.11 2,000,000
Acquire 975 Broad Street, Extend SLO Creek Circulation Element 2,000,000
Path West of Nipomo
Crosswalk Lighting S tems 1 Circulation Element 250,000
Street.Li hts at Crosswalks in Railroad District I Railroad District Plan 100,000
Bridge Replacements
Prado Road: SLO Creek Land Use Element 6.4.6E, OS 3.2.1 E 4,500,000
California Avenue: SLO Creek Land Use Element 6.4.6E, OS 3.2.1 E 6,100,000
Johnson Avenue: SLO Creek Land Use Element 6.4.6E, OS 3.2.1 E 2,900,000
Chorro Street: Stenner Creek _ Land Use Element 6.4.6E, OS 3.2.1 E 2,600,000
Madonna: Prefumo Creek Land Use Element 6.4.6E, OS 3.2.1 E 1,400,000
Bianchi Lane: SLO Creek Mid-Hi uera Enhancement Plan 500,000
Calle Joaquin: Prefumo Creek Land Use Element 6.4.6E, OS 3.2.1 E 1,700,000
MurrayStreet:Stenner Creek Land Use Element 6.4.6E, OS 3.2.1 E 2,000,000
Total Streets 301,464,000
Creek and Flood Protection __
Cuesta Park Detention Facility Waterway Management Plan 10,400,000
Mid-Higuera Bypass Channels Waterway Management Plan 5,070,000
Mid-Hi uera Enhancement Plan
Elks Lane B pass Channels Waterway Management Plan 12,350,000
Channel Modifications near LOVR Waterway Management Plan 6,500,000
Creek Bank Stabilization Waterway Management Plan 30,400,000
Creek Bed Stabilization I Waterway Management Plan 21,600,000
Total Creek and Flood Protection 86,320,000
Pedestrian and Bicycle Paths
Pedestrian
Complete Community Sidewalk System ($110,000
Per Year) Circulation Element, Cl 4.8 2,200,000
Continue Program of Replacing Existing Curbs with
Handicapped Ramps ($28,000 Per Year) Circulation Element, CI 4.9 560,000
Repave Pedestrian Crossings and Install
Pedestrian Bulb-Outs Circulation Element 500,000
Monterey Street Civic Center Plaza Installation Circulation Element 2,275,000
Garden Street Makeover Circulation Element D.4 330,000
Complete Downtown Mission-Style Sidewalks Downtown Plan; Resolution No. 9114 4,400,000
RR District Boardwalks Railroad District Plan 300,000
Leff and Osos Improvements Railroad District Plan 200,000
Walk of Histo West Side of Tracks Railroad District Plan 500,000
2- 9
PROJECT SUMMARY
Project Description I Plan or Policy Link cost
Bicycle Paths
Bob Jones Trail Prado to LOVR 2002 Bike Plan 2,200,000
Prado Road Bike Bridges 2002 Bike Plan 500,000
Bob Jones Trail Elks to Prado 2002 Bike Plan 1,500,000
Bob Jones Trail Madonna to Elks 2002 Bike Plan 1,200,000
Elks Lane Parallel Bike Bride 2002 Bike Plan 350,000
Bob Jones Trail (Marsh to Madonna) 2002 Bike Plan 1,400,000
Mid-Hi uera Enhancement Plan
Madonna Road Underpass 2002 Bike Plan 150,000
Bob Jones Trail LOVR to Barn2002 Bike Plan 500,000
Prefumo Arm Calle Joaquin to Madonna 2002 Bike Plan 930,000
Madonna Road Brid a to Laguna Park 2002 Bike Plan 1,600,000
Railroad Bike Path (Depot to Marsh 2002 Bike Plan 2,600,000
Railroad Bike Path Marsh to Hathwa 2002 Bike Plan 6,400,000
Railroad Bike Path (Hathway to Foothill 2002 Bike Plan 350,000
Railroad Bike Path Foothill to Campus) 2002 Bike Plan 155,000
Railroad Bike Path Foothill Bride 2002 Bike Plan 1,700,000
Path Along n/Orcutt to Laurel 2002 Bike Plan 130,000
Path NonCreek to Southwood 2002 Bike Plan 350,000
Railroad Bike Path Laurel to Tank Farm 2002 Bike Plan 1,100,000
Bride Over Tank Farm Road 2002 Bike Plan 1,500,000
Bridge Over RR @ Fairview/Penny Ln 2002 Bike Plan, Railroad District Plan 2,000,000
Underpass at Industrial Way 2002 Bike Plan 700,000
Bridge from Sinsheimer Park to Lawrence Drive 2002 Bike Plan 3,100,000
Railroad District Plan
Railroad Bike Path (High to Roundhouse 2002 Bike Plan 230,000
RR Bike Path Roundhouse to McMillian 2002 Bike Plan 720,000
Acacia Creek BP Rockview to Damon-Garcia 2002 Bike Plan 600,000
Acacia Creek BP Damon-Garcia to Tank Farm 2002 Bike Plan;AASP 250,000
Acacia Creek Underpass @ SR 227 2002 Bike Plan 350,000
Union Oil Prop BP(Tank Farm to Buckley) 2002Bike Plan; AASP 1,500,000
Buckley Road Path Broad to Vachell 2002 Bike Plan;AASP 3,300,000
Tank Farm Crk. BP Tank Farm to Vachell 2002 Bike Plan; AASP 1,400,000
Mon=o Street BB Santa Barbara to Pismo 2002 Bike Plan 50,000
South Street Widening for BP 2002 Bike Plan 50,000
Bikeslot at California-Foothill 2002 Bike Plan 155,000
Bikeslot at South-Broad 2002 Bike Plan 136,000
Bikeslot at S.Hi uera-LOVR 2002 Bike Plan 200,000
Bike Path Flora to Fixlini 2002 Bike Plan 300,000
Laguna Lake Park to Foothill 2002 Bike Plan 1,600,000
Marsh Street Interchange Mods 2002 Bike Plan 300,000
South Hills Path Mar arita Area to Exposition 2002 Bike Plan; MASP 1,500,000
Railroad Corridor Palm Tree Planting Railroad District Plan 100,000
Total Pedestrian and Bicycle Paths 54,421,000
-8-
o n • s
Project Descri-tion Plan oir Policy,Link Cost_
Parkin
NARF Parking Access and Parking Management Plan 30,000,000
New Parking Structure 1 every 5 ears Access and Parking Management Plan 60,000,000
New Parking Lot Ac uisition Access and Parking Management Plan 6,000,000
New Meter Installations- E/o Santa Rosa Access and Parkin--Mana ement Plan 50,000
Residential Parking District Implementation Access and Parking Management Plan 200,000
Develop Downtown Park and Ride Lots Circulation Element 12.6, Access and 2,000,000
Parking Management Plan
Additional Passenger Loading Area Near Depot I Railroad District Plan 100,000
Total Parking 98,350,000
Transit
Ca ital
Bus Stop Improvements Short Range Transit Plan 400,000
Bus Expansion 1 Every 3 Years Short Range Transit Plan 2,500,000
NARF:Transit Short Range Transit Plan 5,000,000
RTC Transfer Point Upgrade Short.Range Transit Plan 750,000
Transit Signal Priority System Short Range Transit Plan - 1,000,000
Freight Warehouse Transfer Center Re-ional Trans ortation Plan 1,300,000
Voice Enunciation System Short Range Transit Plan 250,000
Automatic Bus Washer Short Range Transit Plan 250,000
Bus Yard Expansion Regional Transportation Plan 3,000,000
Total Transit 14,450,000
TOTAL TRANSPORTATION $555,005,000
-9- //
•
PROJECT
Pro ect Descri tion Plan or Policy Link Cost
LEISURE, CULTURAL • SOCIAL
Parks and Recreation
Laguna Lake Park Master Plan Parks and Recreation Element 2.55.2 2,500,000
Laguna Lake Dredging Laguna Lake Management Program 7,000,000
Margarita Area Neighborhood Park MASP/Parks&Recreation Element 2.5 4,200,000
Orcutt Area Neighborhood Park OASP/Parks& Recreation Element 2f 3,000,000
Caltrans North Property Adquisition & Park Mid-Hi uera Enhancement Plan 450,000
Other Parks to Meet 10 acres/1,000 Goal I Parks and Recreation Element 2.1.1 43,350,000
Other Improvements
Mini Parks Parks and Recreation Element(2.401 1,000,000
Tennis Courts . Parks and Recreation Element 2.40 600,000
Sinsheimer'Park Master Plan Parks and Recreation Element 2.56.2 2,000,000
Community Center Parks and Recreation Element 2.54 8,000,000
Meadow Park Upgrades Parks and Recreation Element 2.54 250,000
Sand Volleyball Facility Emerson Park Parks and Recreation Element 2.57.5 100,000
Golf Course Parks & Recreation Element 1.33:2 200,000
Total Parks and Recreation 72,650,000
Cultural Services
Adobe Restoration Parks and Recreation Element 2.57.5 3,000,000
Railroad District Gateway Tree Plantin Railroad District Plan 25,000
Historic Railroad Car Display Railroad District Plan 25,000
Public Art @ 1% of CIP Costs Art in Public Places Policy 7,612,190
Total Cultural Services 10,662,190
TOTAL LEISURE, CULTURAL AND SOCIAL SERVICES 83,312,190
- 10- —��
PROJECT SUMMARY
Project Description Plan or Policy Link Cost
COMMUNITYDEVELOPMENT
Natural Resources
Open Space Acquisition, Trail Development Conservation &Open Space Element 25,000,000
Creek Pedestrian Trail and Open Space Mid-Hi uera Enhancement Plan 500,000
Total Natural-Resources 25,500,000
TOTAL COMMUNITY DEVELOPMENT 25,500,000
I - 02-13
PROJECT
R• SUMMARY
Pro ect Descri tion Plan or Poli!of Link Cost
GOVERNMENTGENERAL
Information Tec
hnolo
- - - -_
Document Management IT Strategic,Plan, March 2001 _ 650,000
E-Government IT Strategic Plan, March 2001 250,000
Technology Mgt Tools/Security Improvements IT Strate icPlan, Maroh2001 225,000
Technology Infrastructure Improvements IT Strategic Plan; March 2001 813,000
Total Information Technology 1,938,000
Buildinos
Conceptual Physical Plan for City Ctr;
City Hall Expansion Facilities Master Plan: 1988-2010 20,000,000
Corp Yard Admin Building Reconfiuration Facilities MasterPlan, 1998-2010 300,000
Total Buildings - 20,300,000
TOTAL GENERAL GOVERNMENT 22,238,000
FUNCTIONSUMMARY BY
Public Safety 55,09,000
Public Utilities 138,781,000
Transportation 555,005,000
Leisure, Cultural and Social Services 83,312,190
Community Development 25,500,000
General Government 22,238,000
Total $880,505,190
�7
- 12-