HomeMy WebLinkAbout04/17/2007, BUS 3 - PUBLIC SAFETY COMMUNICATIONS AND EMERGENCY OPERATIONS CENTER IMPROVEMENTS • U
council M�D� 4-17-07
acEnaa acpopt '�-N 3
CITY O F SAN LUIS OBISPO
FROM: Bill Statler, Director of Finance & Information Technology
SUBJECT: PUBLIC SAFETY COMMUNICATIONS AND EMERGENCY OPERATIONS
CENTER IMPROVEMENTS
CAO RECOMMENDATION
Approve the site plan and design for the public safety communications and emergency operation
center improvements and the related implementing actions set forth in this report.
REPORT-IN-BRIEF
The Very Short Story. Reliable emergency communications for our first-responders in police,
fire, public works and utilities are essential in meeting our "mission-critical" public safety
obligations to the community. Due to inadequate facilities and obsolete equipment, our current
system simply isn't reliable. Because of new and increased service requirements combined with
obsolescence and related unavailability of replacement parts, this problem will get geometrically
worse as time goes by. And as discussed further in this report, even with the actions
recommended at this time, it will be almost two more years before this already bad situation will
be improved.
In addition to taking longer than we would like, providing adequate facilities for our emergency
communication operations that make sense now and in the future will also be more expensive
than we would like: $6.4 million versus a current project budget of $2.9 million. However, we
have extensively analyzed a wide range of options, taken a sharp pencil to project costs and
concluded that the proposed improvements are the wisest use of our limited resources in meeting
both our immediate and longer term needs for reliable emergency communications.
Storage Facility Alternative. From a programming perspective, the workscope for the public
safety emergency communications center has not changed since Council approval of this project
in March 2005. However, in preparing the site planning for this project, the opportunity surfaced
to address long-standing storage needs for the Fire Department. While not directly tied to work
on the emergency communications center, building these two projects at the same time will result
in significantly lower costs for the storage facility and less disruption to Fire Station No. 1
operations than if it was built at a later time as a separate project.
In short, this is our best opportunity to address Fire Department storage needs in the most
efficient and cost effective manner. As such, while it will add costs to an already expensive
project ($450,000), we believe that this is the best course of action in meeting Fire Department
needs on this site in both the short and Iona-term. We recommend including this storage facility
in the bid package as an "additive alternative," which will allow us flexibility in separately
evaluating the cost of this facility and awarding the construction contract.
C �
Public Safety Communications and Emergency Operations Center Improvements Page 2
Overall Improvements to Our Emergency Operations Center. While the focus in this report
is on improvements to our public safety emergency communications center (dispatch center), the
fact is that the proposed workscope will results in overall improvements to our emergency
operations center (EOC), which is located at Fire Station No. 1. These will not only improve our
emergency communications at the dispatch center, but they will improve security at the site,
make emergency supplies easier to organize and access, free-up bay space for emergency
vehicles and improve the site for staging emergency vehicles in the event of a major disaster.
DISCUSSION
Background
Along with planned improvements to our radio system, the dispatch center project is the highest-
priority technology project in the City,
and has been since March 2001 when the
Council adopted the 2001-05 Information
Technology Strategic Plan. Separate But Interrelated Projects
Concurrently with the dispatch center project, we
Both projects are essential in protecting will make significant improvements to our radio
our community by providing our first- system. While these two projects are separate
responders in Police, Fire, Public Works and distinct in their needs and solutions, there
and Utilities with the reliable emergency are significant technology interdependencies.
Stated simply, the dispatch center needs to be
communications that they require on a linked to our radio system; and the radio system
day-to-day basis. also needs significant improvements.
Additionally, the radio and dispatch We are further along in our plans for the radio
Y p system upgrade:the project is fully funded ($4.1
system also support users in Community million); and the Council approved the plans and
Development and Parks & Recreation in specifications for this project in March 2005.
their day-to-day operations; and in However, construction of the dispatch center is
disaster response situations, staff in these the "critical path" driver for radio system
two departments also become emergency improvements for three reasons.
responders. 1. It will be much more cost effective to install
the radio links in the new dispatch center,
On March 15, 2005, the Council took a rather than having to then relocate them
comprehensive look at both of the shortly thereafter.
dispatch center and radio system projects, 2. There is simply not adequate space for the
and approved plans and funding for both new radio equipment at the Police.Station
of them. As discussed in the sidebar (which is one of the reasons among many for
chart, planning for the radio system building a new center at Fire Station No. 1),
improvements is well underway: the especially since both the old and new system
project is fully funded; and the Council will need to be operational during the
conversion.
approved the plans and specifications for
these improvements at the March 2005 3. Placing the new radio equipment in the new
meeting. dispatch center will minimize operational
impacts during the conversion.
�-a
Public Safety Communications and Emergency Operations Center Improvements Page 3
Accordingly, while the radio system improvements are an integral part of overall plan in meeting
our emergency communication needs, the focus of this report is the on the construction of the
dispatch center.
Need for Dispatch Center Improvements
As noted above, replacing the public safety dispatch system is one of the highest priorities in the
2001-05 IT Strategic Plan. While there are many reasons for this, the key driver is that the
existing dispatch center console is over twenty years old and no longer reliable; and because it is
technologically obsolete, replacement parts are no longer made by its manufacturer(Motorola).
This is compounded by dispatch workloads that are much higher than they were when the current
system was installed over twenty years ago. In short, this "mission-critical" emergency dispatch
center urgently needs to be replaced and upgraded: an up-to-date, dependable dispatch center is
critical to the City's basic, public safety mission; and the existing dispatch center has outgrown
its current basement location within the Police Station.
A recent analysis of long-term police space needs recommends building a new station at another
site, rather than adding onto the current facility. However, given the land and construction costs
of a new headquarters police station facility, and the current economic situation, this is unlikely
to occur in the foreseeable future. For this reason, any "interim" space solution for public safety
dispatching needs to make sense for the next ten to twenty years (and perhaps longer).
Dispatch Center Site Options
At the March 2005 meeting, the Council comprehensively reviewed a number of options for
meeting the facility needs of our emergency communication operations, including:.
1. Police Station Remodel
2. 1016 Walnut (New Building Adjacent to the Police Station)
3. City Hall (Remodel of Downstairs Space)
4. Corporation Yard (New Building)
5. Fire Station No. 1 (Approved Project Location)
All of these options shared the following drawbacks in varying degrees: interim solution; limited
options for future growth; and no back-up center. However, after considering in detail all of the
pros and cons of each option, the Council selected Fire Station No. 1 as the best site option.
Unique advantages of this option include:
1. This is already a"24/7" public safety site.
2. There is a close, day-to-day working relationship between fire staff and the dispatchers.
2
•
Public Safety Communications and Emergency Operations Center Improvements Page 4
3. It was the most cost-effective option. The cost of building a new center would be the same at
all sites. And largely due to the costs of remodeling a 35-year building (and related problems
with electrical systems and meeting ADA requirements), this option was slightly less
expensive than remodeling the Police Station.
Given similar costs, other advantages included: adding building space with a new center,
rather than adding no additional space (other than an elevator shaft) at an already crowded
Police Station; better meeting our emergency response needs by designing a facility for this
purpose rather than rehabbing an existing one; and logistical issues in operating the existing
center while major construction work would be in progress.
The only downside of this option compared with continuing to locate dispatch at the Police
Station is the separation of the dispatch function from other Police operations. While this is a
significant concern, the Police Department believes that it is offset in light of the other
compelling advantages of this option and the design features of the proposed center:
This continues to be the right path. Even though the cost is higher than we estimated in March
2005, all of the reasons for building a new center at the Fire Station No. 1 site identified at that
time continue to support this option as the most cost-effective one in meeting our emergency
communication needs.
Dispatch Center Design
Space Needs
At the March 2005 meeting, the Council conceptually approved a3,044 square foot facility at the
Fire Station No.I site based on a detailed analysis by the architect (RRM Design Group) and staff
of space needs for the center that would support operational requirements for at least the next ten
years.
In anticipating future needs, we analyzed dispatch staffing levels for the past 15 years, and call
statistics for the past three years. Based on this information, we believe the proposed dispatch
center with six work stations will provide for our needs now and for the next ten years. Although
the current minimum dispatch staffing is two employees per shift, there are many times when at
least three are needed, and sometimes as many as five. Six work stations should adequately
support these needs and allow for appropriate short-term growth, with one caveat: the unknown
impact of transferring all "911-wireless" calls from the California Highway Patrol (CHP) to local
dispatch centers.
Unknown impact of 911-wireless calls. Currently, if someone calls 911 from a cellular phone,
the call goes to the closest CHP dispatch center. The CHP dispatchers screen the calls and
transfer those that are appropriate to the local police department.
Beginning in 2007, 911 calls made from cellular phones will go to the local law enforcement
agency where the caller is physically located. The CHP currently does a good job screening these
calls and only transferring those that should be handled by our City police or fire. However, once
�.
• 0
Public Safety Communications and Emergency Operations Center Improvements Page 5
these calls no longer route through the CHP, they will all come to us,including 911 hand ups and
multiple calls regarding the same incident. This will likely increase the workload of our
dispatchers.
Unfortunately, the CHP does not track how many cellular 911 calls they receive or transfer, so
we are not able to accurately assess the count of how many calls are being transferred to our
dispatch center. In short, we will not know the workload impact of this change until it happens.
However, we have considered this factor in our planning based on available information, and the
proposed center reflects our best judgment on our future dispatch needs.
Proposed center size. The current proposal makes no changes to the March 2005 "program"
with one exception: after we began detailed analyses of our radio, 9-1-1 system and computer
aided dispatch requirements (and related electrical and mechanical requirements), it became clear
that added space for these would be needed in supporting the operational requirements of the
center. Accordingly, the proposed center
includes added space of 578 square feet for Dispatch
these purposes, for a total facility size of March 2005
3,622 square feet. The internal lay-out of
the proposed facility is provided in Dispatch Floor 975
Attachment 1. Offices
Supervisor 132
Watch Commander/Communications Mgr 132
Dispatch Center Site Plan and Design Officer Report Writing 100
Support Areas
Provided in Attachment 2 is the Secured Entry 36
Ian and design Copy, Mail and Supplies 63
recommended site
P gn Radio and Computer Room 323
(elevations) for the dispatch center. These Mechanical& Electrical 236
have been reviewed and approved by the Break/Kitchenette 156
Architectural Review Commission and Dayroom 150
Restrooms and Locker Room 344
Cultural Heritage Committee. Circulation @ 15% 397
Total _ 3,044
These reflect the "program" approved by
the Council in March 2005, with the added
space (578 square feet) to meet radio, computer, mechanical and electrical needs. Along with
construction of the dispatch center, the site plan also reflects construction of an 80-foot radio
tower on the site in accordance with the approved radio system project; reconfiguration of public
and employee parking lots; and other site security improvements including gates, fencing and
video camera system.
Dispatch Center Project Costs
The current project budget approved by the Council for the dispatch center is $2,884;300. As
detailed below, the proposed project budget at $$6,484,000 is significantly greater than this. The
following chart compares the current and proposed budget by key cost components.
� -S
0 C
Public Safety Communications and Emergency Operations Center Improvements Page 6
Pro'ect Cost Summa : Current and Proposed Bud et
Description Current. Proposed
_Dis atch.Buildin __---- __ 1,240,000 2,890,000 _ 1,65.0;000
Conceptual building size(3,044 square feet) 1,240,000 2,429,000
Increased building size(578 square feet) 311,000
Floor coverings 40,000
Security systems and access control 110,000
Site Improvements 232,900 1,505,000_ _ 1,272,100
Improvements 152,900 1,088,000
Radio tower 80,000 108,000
Expanded parking lot infrastructure 280,000
Fiber infrastructure 29,000
Furnishings and Equipment 406,900 _ _... 469,000_ 62,100
Computer-aided dispatch servers 122,000
Network switches 100,000
Dispatch consoles 135,000
Monitors 15,000
Time synchronization equipment 29,000
Copiers,printers and scanners 13,000
Logging recorder 40,000
Other equipment costs 15,000
Design and Inspection - ____ 628,300 994;000 365,700
Design Fees 323,300 492,000 168,700
Architectural engineering fees 456,000
Technology consultant 25,000
Other consultant fees 11,000
Construction Management&Inspection 305,000 502,000 197,000
Construction management&inspection 400,000
Geotechnical reports 10,000
Special inspections and material testing 92,000
Other Costs __ _ _ _.____ 201,000 201,000
Bidding: plans&specifications,advertsing 32,000
Technology installation services 50,000
Job trailer and phone 10,000
Moving costs 10,000
Relocation of AT&T 911 service 15,000
Relocation of AT&T regular phone service 5,000
-Utility hook-up fees 79,000
Contingency: 10% of Construction-Costs _ _ _ -1 376,2601 425,000 1 48,800
TOTAL 1 2 884 00 1 6 484 000 1 3 599 700
Key Cost Drivers. The following provides detailed explanations for each key variance:
1. Dispatch Center Building. There are two key factors driving the higher construction costs
for the building:
a. Construction costs in general are much higher today than they were two years ago when
we prepared the current budget for this project. This reflects increased demand, both
locally and globally, for the key construction materials we will use in this project,
including petroleum-based products, steel, wood, copper and concrete. These
construction cost increases are not unique to this project: they have become the "new
3 _fn
0 0
Public Safety Communications and Emergency Operations Center Improvements Page 7
normal" for both the private and public sector. This accounts for most of the building
cost increase.
b. As noted above, the original cost estimate was based on a facility of 3,044 square feet.
However, in order to meet the center's operational support requirements for radios,
computers, mechanical and electrical
systems, we recommend adding 578
square feet for this purpose. This --Essential Services Buildings
adds $311,000 to the project cost. Under the "Essential Services Buildings
Seismic Safety Act of 1986," essential service
It should also be noted that we have to buildings, which include fire stations, police
build this facility in accordance with the stations, emergency operations centers or
requirements for "essential services emergency communication dispatch centers,
buildings" (see sidebar). This is not a must be capable of providing essential
new factor in our planning for this services to the public after a disaster.
project. However, it does mean that This means that both the structural systems
construction cost increases have an even and non-structural components (such as
greater impact on "essential services communications systems, main transformers,
buildings" like our dispatch center than switching equipment and emergency backup
other office or government buildings. systems) must be designed and constructed
to minimize fire hazards and to resist, insofar
2Improvements. There are four as practical, the forces generated by
. Site Im
P earthquakes, gravity, and winds.
factors driving higher costs for site
improvements: This means that essential services buildings
are typically designed to structural standards
a. As with the building construction, that are twice those for standard governmental
there have been significant cost or other office buildings. It also means that
the design and inspection of essential services
increases over the past two years in buildings are subject to added review
general. As described below, procedures that must performed by qualified
parking lot modifications are a large professionals to ensure that these standards
component of the overall site are met.
improvements.
In achieving the higher standards specified for
b. The initial cost estimate was this type of building, constructions costs are
typically 50%to 150% more expensive than
prepared before detailed soils that of a standard government office building,
analyses were conducted at this site, depending on use and circumstances.
and assumed "standard" soil
conditions. However, there is a very
high water table at this site; and in order to meet the structural requirements for essential
services buildings, we need to excavate five feet of soil for the building foundation and
refill and compact it. This added cost was not reflected in our initial cost estimates: it
was simply too soon in the design process.
c. The conceptual site plan in March 2005 included minor modifications to the parking
immediately adjacent to the dispatch center. However, in meeting the needs of this
facility both as our main fire station and emergency operations center (EOC), the project
� — l
• o
Public Safety Communications and Emergency Operations Center Improvements Page 8
scope redevelops much of the site to include redesigned gate access at Roundhouse and
Emily; additional parking spaces; an expansion of the back parking lot into the 30-foot
area added to the site from the recent South Street abandonment strip; and a redesigned
trash enclosure. The switchgear, transfer switch and generator were also upsized to
service the entire EOC site rather than just the dispatch center.
d. Increased construction costs have also increased the cost for the radio antenna tower,
largely due to increased concrete costs for the tower foundation.
3. Furnishings and Equipment. The increased cost for fixtures, furnishings and equipment is
due to the refinement of the technology systems during the design development phase. The
key additions include the need for time synchronization and call-logging equipment, totaling
$69,000. These are needed to ensure that the "time and date stamps" for all of the
documentation—call recordings, computer-aided dispatch records —are accurate and in synch
with each other.
4. Design and Inspection. We will see related increases in design costs from our architect
(RRM Design Group) and construction management/inspection services from our
construction manager(MarWal Construction) due to the changes in project scope.
5. Other Project Costs. These costs typically do not surface until the detailed design phase.
6. Construction Contingency. At 10% of construction costs, this represents a reasonable
contingency for change orders during construction.
Project Funding Sources
The following summarizes current and proposed project funding sources.
ProposedCurrent
Pay-As-You-Go 175,000 175,000 -
FEMA Grant 200,000 200,000 -
Bond Financing 2,509,300 6,109,000 3,599,700
Total 2,884,300 6,484,000 3,599 700
As reflected above, the proposed funding sources included the "pay-as-you-go" and FEMA grant
revenues that have already been appropriated for this project. Consistent with our current
funding strategy (and in accordance with the City's debt financing policies), we recommend
funding the remaining added balance ($3.6 million) with bond financing. There are two key
benefits of using bond financing at this time:
1. Interest rates are at historically low rates.
2. We can spread the cost of these improvements over the life of this, better matching the cost
of the project with its use.
3 ` U
• O
Public Safety Communications and Emergency Operations Center Improvements Page 9
Debt Service Costs. While public safety (police and fire) and other General Fund users account
for most of the dispatch center's operations, our analysis in March 2005 allocated about 16% of
the dispatch center benefit (and related costs) to employees in water, sewer and parking, who also
depend on the dispatch center for emergency communications. Accordingly, the following '
shows debt service costs for the General, Water, Sewer and Parking Funds, assuming a thirty
year term and annual interest at 5.5%:
Annual Debt Service
General Fund @ 84% 353,000
Water Fund @ 7% 29,000
Sewer Fund @ 8% 34,000
Parking Fund @ 1% 4,000
Total $420,000
The General Fund debt service costs shown above are consistent with the projections in the
2007-12 forecast presented to the Council in December 2006. Additionally, we will not incur
debt service costs for this project until the second year of the 2007-09 Financial Plan (2008-09).
Fire Storage Building Option
As noted above, our site planning for dispatch center surfaced the need to address long-standing
storage problems at Fire Station No. 1. The following outlines the existing storage situation at
this site, and the proposed solution.
Background. Fire Station No. 1 was designed in 1994, built in 1995 and occupied in 1996.
Original concerns for department storage were addressed in the original design phase; however,
due to funding constraints at the time, the needed storage space in the building was reduced.
Upon completion in 1996, several sea-land containers were placed on the property to meet
immediate storage needs. One file storage area on the original plans was converted into office
space that now is used by two fire inspectors.
Since 1996, the Fire Department has used one box trailer, two sea-land containers and three
temporary storage sheds to assist with meeting the storage needs of the department. These
storage options are full as are all the available storage closets and spaces inside the fire station.
In 2004, the training storage room was converted into an office and the training props and
training equipment were placed around the complex with no real home. More communications
and information technology has been introduced into the station since it was built, taking up
additional storage space.
Existing Situation. The Fire Department has no space left at this station for additional storage:
outside temporary storage solutions are full with no room for future additional storage. On the
other hand, the Fire Department needs to eliminate the unsightly storage sheds and sea-land
containers that hamper traffic circulation and have encroached into the training area of the station
property.
Public Safety Communications and Emergency Operations Center Improvements Page 10
Future Needs. With construction of the dispatch center, the Fire Department's useable space for
parking, circulation and department storage will be significantly impacted before and after
construction. Added Police staffing at the dispatch center will add more parking space
requirements, further impacting the rear yard of the station property. Relocating and protecting
the antique fire engines in the proposed storage building will free-up space in the existing engine
room to house reserve apparatus.
Proposed Solution. Site plans and schematic design for a 3,000 square foot storage facility at
Fire Station No. 1 are provided in Attachment 3. Uses at the proposed centralized storage
facility include:
1. Medical supplies and equipment.
2. Protective clothing for structural and wildland fires such as boots and helmets.
3. Public education supplies for both children and senior citizens including display boards,
handouts, smoke detectors, batteries, fire prevention files and miscellaneous documents such
as building plans.
4. Supplies and equipment for the "CERT" (Community Emergency Response Training)
program such as gloves, masks, plastic helmets, make-up kits, large training props and
student manuals.
5. Training props, supplies and educational displays including CPR mannequins and rescue
dummy.
6. Hazardous materials response supplies, including bagged absorbent material, absorbent pads,
and absorbent booms for creek spills.
7. Firefighting tools and equipment storage such as replacement tools, lights, fittings, out-of-
county bags and hoses.
8. Two valuable restored fire engines (1926 Seagrave and 1941 Mack) as well as related Fire
Department memorabilia.
9. Administrative financial and timecard files.
Future Fire Museum and Public Education Center. The Fire Department's vision is to create a
historical display for educating children and the public during tours. This center will consist of
the two antique fire engines, antique fire alarm boxes, ladders, helmets, historical pictures and
educational displays. These would be housed in the proposed storage facility.
Project Costs. Unlike the dispatch center, this storage facility does not have to comply with the
requirement for essential services buildings. As such, a more conventional pre-fabricated metal
building will meet our needs at this site. This is projected to cost $450,000, summarized as
follows:
C o
Public Safety Communications and Emergency Operations Center Improvements Page 11
Storage Building Cost-Estimate
Site and soil preparation 77,000
Building and foundation 225,000
Electrical and mechanical systems 88,000
Design and inspection 24,000
Contingency at 10% of construction cost 36,000
Total 1 $450,000
These costs assume construction concurrently with the dispatch center. Building these two
projects at the same time will result in significantly lower costs for the storage facility and less
disruption to Fire Station No. l operations than if it was built at a later time as a separate project.
Funding. If the Council approves going forward with this project, we recommend including it
with the bond financing for the dispatch center. This will increase annual debt service costs by a
modest $30,000.
Summary. As noted above, we believe that this is our best opportunity to address Fire
Department storage needs in the most efficient and cost effective manner. As such, while it will
add costs to an already expensive project, we believe that this is the best course of action in
meeting Fire Department needs on this site in both the short and long-term. Accordingly, we
recommend including this storage facility in the bid package as an "additive alternative," which
will allow us flexibility in separately evaluating the cost of this facility and awarding the
construction contract. In short, we believe the benefits of building the storage building now in
conjunction with the dispatch center outweigh the modest addition to debt service costs.
Masonry Block Walls on Emily and South Street Option
These improvements are a condition of development for the Maymont project, which is adjacent
to the Fire Station No. 1 site. We could wait until that project goes forward to make these
improvements. However, we do not control the timing of that project, and making these
improvements as part of the dispatch center project will cause the least disruption to Fire
Department and dispatch center operations, while providing needed site security.
Since this is a condition of the Maymont development, we expect to be fully reimbursed for these
costs if they are included in the scope of this project. Like the storage building, they will be
separately iternized in the bid submittal and provided as an additive alternate in the bid package,
which will allow us flexibility in separately evaluating the cost of these improvements and
awarding the construction contract.
In summary, there should be no net added costs if we include this with the workscope, but doing
so will mitigate disruption to our operations.
Project Schedule
The following summarizes the key remaining steps for this project:
3- H
C
Public Safety Communications and Emergency Operations Center Improvements Page 12
Tasks bays_ Date
1. Council approves implementation actions 4/17/07
2. CAO approves specs and invitation for bids 60 7/1/07
3. Bids close 60 9/1/07
4. Evaluate bids; CAO awards contract 60 11/1/07
5. Contractor executes contract, mobilizes and begins work 30 12/1/07
6. Contractor completes construction 300 10/1/08
7. Install furnishings and technology equipment 60 12/1/08
8. Training, cutover and occupancy 90 3/1/09
As reflected, the new dispatch center should be fully operational by March 2009, which is almost
two years from now.
CAO Recommendations Summary
Public Safety Emergency Communications Center
1. Approve site plan and design for the public safety emergency communications center located
at Fire Station No. 1.
2. Approve a revised budget of $6,484,000 for this project, including design, construction,
equipment and furnishings, and construction management.
3. Authorize the City Administrative Officer (CAO) to approve construction plans and
specifications, invite bids and award the construction contract for this project if it is within
the project construction cost estimate of$4,245,000.
Additive Alternate: Fire Storage Facility
4. Approve as an additive alternate to the bid package a storage facility at Fire Station No. 1 and
authorize the CAO to include this work in awarding the construction contract for public
safety emergency communications center if it is within the project cost estimate of$390,000.
5. Approve a budget for the storage facility of $450,000, including design, site preparation;
construction and construction management.
Additive Alternate: Masonry Block Wall on Roundhouse and Emily Streets
6. Approve as an additive alternate to the bid package for concrete block walls on Roundhouse
and Emily Streets and authorize the CAO to include this work in awarding the construction
contract for public safety emergency communications center if it is within the project cost
estimate of $275,000. This is a condition of development by the Maymont project, and if
included in the bid award, would be subject to reimbursement from them.
Design and Construction Management Services
7. Authorize the CAO to approve amended agreements with RRM Design Group and MarWal
Construction to reflect the changed scope of services.
Public Safety Communications and Emergency Operations Center Improvements Page 13
FISCAL IMPACT
As noted above, the projected debt service costs for this project are consistent with the
projections in the 2007-12 General Fund Fiscal Forecast
ALTERNATIVES
Dispatch Center
1. Do Nothing. Given the need to address to critical deficiencies in our emergency
communications system, we do not recommend this option.
2. Implement Other Options. As discussed above, the Council comprehensively considered a
full-range of options in March 2005. While this project is more expensive, none of the pros
and cons of other options analyzed then — including relative costs — have changed. In short,
we continue to believe that this is the right path to follow.
3. Defer the Project. Critical public safety communications will be at risk the longer we take to
complete this project. Even with the proposed project, it will be almost two more years
before the new dispatch center is operational. Additionally, deferring this project will only
result in higher costs.
Storage Facility
4. Do Not Include the Storage Facility as an Additive Alternate. We believe that for a modest
added cost, this is the best opportunity to address long-standing storage needs at this site.
Masonry Block Walls on Emily and South Streets
5. Do Not Include the Masonry Block Walls on Emily and South Streets as an Additive
Alternate. Again, we believe that this is the best opportunity to complete this work with no
net added costs to the City.
CONCURRENCES
Police and Fire Chiefs concur with the recommended actions.
ATTACHMENTS
1. Dispatch Center Floor Plan
2. Dispatch Center Site Plan and Building Design
3. Fire Station Storage Facility Site Plan and Building Design
G:Information Technology/IT Division/Dispatch Center Project/Council Agenda Reports/4-17-07
,3 , 13
Public Safety Communication and EOC Improvements ATTACHMENT 1
Proposed Dispatch Center Floor Plan
w..w,
M C )�
rC` 8 ..,0
O ti
v '
01
rM
UM E; i33\
Mm u, m
�O iii li ii
nm
i
City of
San Luis OBISpo 1
Public Safety CommunicatioCand EOC Improvements ATTACHMENT 2
Proposed Dispatch Center Site Plan
- _
alr o9aq iry,.. I _� � I
Perspective Rendering
i
n. I' ll
fl
city of
�� san US oBispo 1
Public Safety Communications and EOC Improvements 0 ATTACHMENT 2
Propose Dispatch Center Elevations
rMT
q qq o 0 0 0
I I n
i
- 0
MRM vc_
City of _
is san Luis osispo 2
Public Safety Communicatiotr., and EOC Improvements ATTACHMENT 3
Site Plan with Proposed Storage Building
I � it i II II ',�/ F. ♦ .irs tq
IT
KII mow'
T
G■� _
Y F
Proposed Storage Building Floor Plan
J WR P� SECT I r2
city of
`� san Us owspo
Public Safety Communicatior,� and EOC Improvements ATTACHMENT 3
Proposed Storage Building Exterior Elevations
i 1'-1.III I I III !ILII:LII I I I III I II I—,11.11ii u!III III III II M47
roxrMnn��laM MS At"
`� iy fjl
It
�l
'll I•t {li.11 II III II III III Ill-SII I; Ili I!I II .i��
63 I
wN.Rn.lgn uF�nEvm_+
city of - I�
`j san Luis oBispo 3 2
O Page 1 of 1
Council, SloCity
From: Terry Mohan [catsdad@sbcglobal.net] Sent: Sun 4/15/2007 4:35 PM
To: Council, SloCity
Cc:
Subject: Time for a New Police Headquarters
Attachments:
With the cost of the proposed city communications center more than doubling,to $6.6 million, it is time to seriously consider the construction of a
whole new police station.The current council agenda report states that one downside to the proposed communications facility's is it's location away
from police headquarters,also it may be ten,to twenty years(and perhaps longer) before we would be able to build a new station if we spend money
on this project.
Now is the optimum time to go ahead with the construction of a new police headquarters.We have an ideal,city owned, location in the parking lot at
the comer of Palm and Nipomo,and a new tax source to further supplement construction bond financing.A concerted effort by the council and city
administration to expedite development plans fora new headquarters at this location could see it's approval and construction in little more than the
time frame for the proposed communications center.
To spend$6.6 million,or more,on a communications center alone knowing that a new police headquarters is the ultimate,and now attainable,goal,
would be irresponsible. I would hope that with this new financial information the council will reconsider and opt to go ahead with a new police
headquarters instead.
Terry Mohan
2416 Santa Clara
San Luis Obispo,CA 93401 RECEIVED
(805) 547-9733
RED FILE - APR 16 2001
MEETING AGENDA SLO CITY CLERK
DA y/7 a7ITEM #A( . 3
7E!RECn)lll COUNCIL 15 CAO� ACAO ATTORNEYCLERK/ORIG❑ DEPT HEADS
UTIL DIR
P40 01P J
P QSuN u.0
https://mail.sloci ty.org/exchange/sl ocitycounci l/Inbox/Ti me%20for%20a%20New%2OPolice%2OHeadqu... 4/16/2007