Loading...
HomeMy WebLinkAbout06/05/2007, C5 - AMENDMENT NO.3 FOR TANK FARM GRAVITY SEWER, LIFT STATION AND FORCE MAIN DESIGN SERVICES council. M"°"`Dom June 5,2007 j apenaa Report I�Numbw CITY OF SAN LUIS O B I S P O FROM: John Moss, Utilities Director Prepared By: David C, Hix, Wastewater Division Mana SUBJECT: AMENDMENT No.3 FOR TANK FARM GRAVITY SEWER, LIFT STATION AND FORCE MAIN DESIGN SERVICES CAO RECOMMENDATION 1. Approve Amendment No. 3 of the agreement with Brown and Caldwell Engineers for additional design, additional cost estimation, and conversion to standard units for Tank Farm Gravity Sewer, Lift Station and Force Main project, specification No. 99703, in the amount of$142,000 and authorize the Mayor to execute the Amendment. 2. Appropriate $142,000 from Sewer Fund Working Capital to Tank Farm Gravity Sewer, Lift Station and Force Main Design Services DISCUSSION The Tank Farm Gravity Sewer, Lift Station and Force Main project will require additional funding for design, cost estimation and conversion from metric to standard units for completion of the final design of the project. Presently the plans and specifications are at 90% completion, but call for several critical components to address design, investigate alternative construction methods, incorporate environmental elements to the plans and specifications and conversion from metric to standard units. Design Changes and Cost Estimates Additional design services have been required to ensure the proper connection of a small private lift station at Hidden Hills Mobilelodge; address site and design changes for the Tank Farm Lift Station site and structures; modify the plans and specification because of the addition of new structures, such as the County's new bridge and intersection at Tank Farm and Sante Fe Roads; and add environmental information and assets to the specifications per the project's environmental document. Additional design work was also required to prepare cost estimates to determine if a trenchless construction method referred to as micro-tunneling would be a cost effective alternative. Micro-tunneling could be used to tunnel under sensitive environmental areas and through petroleum contamination instead of open trenching on the Chevron property. Analysis of the alternatives found that micro-tunneling costs far exceeded the costs of open trenching and the associated mitigations for open trench construction that were recommended in the project's mitigated negative declaration. As such, micro-tunneling is not being recommended in the final design. The Engineers were also asked to pren;::e,,n analysis of the added cost of dealing with the contaminated soil and water anticipated to be found on the Chevron property. Chevron has agreed to pay for any additional costs associated with petroleum contamination CS - � Contract Amendment No 3 for Tank Farm Lift Station Project Page 2 associated with past operations of the old Unocal petroleum tank farm. Staff will bring a separate agreement with Chevron to Council for approval this summer. Metric to Standard Initially proposed to be designed in metric in 2003, consultation with engineering design and field staff have concluded that converting the plans and specifications from metric to standard units will reduce costs for this project. The City and Cal Trans have recently dropped their metric requirements which would make this one of the few, if any, projects to be bid out in metric state-wide. Previous experience with bidding and construction of a project in metric has found that contractors add significant costs to their bids due to the difficulty and nuisance of metric plans, standards and specifications and large projects require significant additional contact and construction management. This request is critical to the completion of the plans and specifications and to clarify what has become an extremely complicated project. This project is essential to serving existing and new customers in the Airport and Orcutt areas by replacing aging overcapacity infrastructure. Staff anticipates bringing plans and specifications to Council for approval in late summer. CONCURRENCES City engineering staff has reviewed this report and concur with the recommendation. FISCAL IWACT Total cost of this project amendment is $142,000. Funding for this project is not available within existing budgeted resources. As such, we recommend appropriating $142,000 from available Sewer Fund working capital. Based on the Mid-Year Budget Review for 2006-07 and Council- approved changes since then, this will result in an ending fund balance that is 23% of operating expenditures compared with our policy minimum of 20%. Tank Farm Gravity Sewer and Lift Station Design/Engineering $704,916 $142,000 $846,916 520.50300.99703952.99703520.99703952 ATTACHMENT Amendment to Agreement G:\UTIL\CAR-CAOReports\2007 Council Agenda Reports\B&CTankFarmAmendNo3.CAR.doc Attachment AMENDMENT TO AGREEMENT NO. 3 THIS AMENDMENT TO AGREEMENT is made and entered in the City of San Luis Obispo on , by and between the CITY OF SAN LUIS OBISPO, a municipal corporation, herein after referred to as City,and Brown and Caldwell Engineers,Inc., hereinafter referred to as Contractor.. WITNESSETH: WHEREAS, on September 11, 2003 the City entered ,into an Agreement with Contractor for Design Services for Tank Farm Gravity Sewer;Lift Station and Force Main per Specification No.99703;and WHEREAS, the City desires to amend the scope of services to include additional design, costs estimation and conversion of plans from metric to standard and Contractor has submitted a proposal for this purpose that is acceptable to the City. NOW THEREFORE, in consideration of their mutual promises, obligations and covenants hereinafter contained, the parties hereto agree as follows: 1. The scope of services and related compensation is hereby amended as set forth in Exhibit A attached hereto. 2. All other terms and conditions of the Agreement remain in full force and effect. IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed the day and year first written above. ATTEST: CITY OF SAN LUIS OBISPO By: Audrey Hooper;City Clerk David F.Romero,Mayor APPROVED AS TO FORM: CONTRACTOR By: City Alforney _ C5 3 Exhibit Suite 10u,400 Exchange Irvine,California 92602 Tel:(714)730-7600 Fax:(714)734-0940 May 17, 2007 B R ; e Mr. David Hix City of San Luis Obispo 955 Morro Street San Luis Obispo,California 93401 1012/124881-130 Subject: Addendum No. 3 for Tank Farm Gravity Sewer, Force Main and Lift Station Project Spec. No. 99703.90052 Dear Mr. Hix: Brown and Caldwell has prepared this letter requesting additional funds to the project budget to compensate for services performed or to be performed that are not included in the original Scope of Services.These additional services have been executed at the request of the City staff to provide value to the project.The additional services are listed below with separated contract budget requests following its work task description. 1. Consultant was instructed by the City to include a small lift station adjacent to Tank Farm Road as tributary to the Tank Farm System. Consultant verified system hydraulics, and modified construction plans for reconfiguration of existing lift station discharge pipeline. (Additional Budget Request: $ 4,000) 2. Site layout has been modified during the 50 percent design to raise structures above the floodplain. Site layout was also modified to accommodate City's request for the following items: a. Move the sewer forcemain on the east side of the site. b. Delete the proposed flow meter. c. Locate the discharge manifold above grade and delete the proposed control valve vault. d. Modify the generator building layout to accommodate new generator set. e. Locate the proposed electrical panels in its own dedicated control room. The above listed items resulted in a reconfiguration of the parking area and the enlargement and layout of the site. (Additional Budget Request: $ 14,500) P:\ Proimm\724881...\WP\104134 Addendum No.3.doc Mr.David Hix May 17, 2007 Page 2 3. After the 50 percent review meeting,Consultant modified pipe material and relocated all manholes and associated pipeline (plan and profile) along Tank Farm Road to accommodate micro-tunneling construction. Consultant prepared cost estimates for the segment of the gravity sewer along Tank Farm Road with varying conditions; 1) micro-tunneling with non-contaminated material, 2) micro-tunneling with contaminated material, 3) open trench construction with non-contaminated material, and 4) open trench construction with contaminated material. After conversations with Chevron,who owns majority of the property along Tank Farm Road, the City decided to proceed with the 90 percent design, using open trench construction.The preparation of the cost estimates and coordination with Chevron has resulted in delay of work for approximately 2 - 3 months. Approximately 6 manholes and affected pipeline alignments were modified to accommodate the new construction method. Different pipeline materials were investigated to determine which was best suited to resist the influence of the contaminated soils. (Additional Budget Request: $20,000) 4. Several improvement projects have been constructed along the pipeline alignment after design had begun and the topographic survey and utility research were completed.These include the Tompkins Medical Center, the County's Santa Fe Road Project, the Maino project on Sueldo, etc. In most cases, these improvements did not affect the alignment of the pipeline and only required its addition to the background topography of the.construction plans. One exception is the County's Santa Fe Road Project that resulted in widening Tank Farm Road, addition of curb,gutters and sidewalks, addition of a CON/SPAN bridge with concrete headwalls,and relocation of the intersection of Santa Fe Road with Tank Farm Road.The Santa Fe Road Project prompted a re-evaluation of the pipeline alignment on Tank Farm Road and the plans will be modified as necessary. (Additional Budget Request: $ 10,000) 5. As requested by the City staff, Consultant has coordinated with the project environmental consultant,Morro Group, to prepare figures for inclusion in the EIS Report.Also requested by the City is the addition of the mitigation requirements as recommended by the EIS to the contract documents which included fencing locations,wetlands delineation, habitat delineation,and additional sections of the project specifications. (Additional Budget Request: $ 9,500) 6. As requested by the City staff, Consultant has participated in coordination meetings with Chevron for disposal of hazardous materials which may be encountered during construction. This effort resulted in a modification to the specification. (Additional Budget Request: $4,000) 7. As requested by the City staff,Consultant will include a groundwater dewatering disposal plan as required by the Water Quality Control Board. The disposal plan will address how the Contractor will handle the discharge of contaminated and P:_Proj«¢\124881...\WP\104134 Addendum No.3.dm , 1 Mr. David Hix May 17,2007 Page 3 non-contaminated groundwater. The plans will be modified to locate where groundwater can be discharged for land disposal (percolation in existing basins in Chevron's property).The specifications will be modified to account for two options for the Contractor; 1) discharge to existing lands, or 2) discharge to proposed Tank Farm pump station.The specification modification will include a work sequence to allow for the groundwater discharge to the proposed pump station. (Additional Budget Request: $ 5,000) 8. As requested by City staff, the construction plans and specifications will be modified to convert units from Metric (Sn to English (US).This is a fairly labor intensive task requiring that every aspect of the drawings, specs,and legal descriptions be redrawn or rewritten.The conversion will include the following items as a minimum: a. Rescaling survey collected information (property lines and boundaries); b. Adjusting of the orthophotos; c. Regenerating existing surfaces (DTM); d. Regenerating site contours; b. Rescaling the alignment and utilities; c. Rescaling existing grade profiles and utility crossings; d. Rescaling model files for use on mechanical,architectural,electrical, and structural sheets e. Rescaling the border f. Reconstructing the sheets g. Reestablishing the match lines between profile sheets h. Rescaling text heights and arrow sizes per English drawing standards Attached to this letter is a breakdown of man-hours required for this task. (Additional Budget Request: $ 75,000) P:\_Pmjecn\124881...\WP\I04134 Addendum No.3.doc I Mr. David Nix May 17,2007 Page 4 Brown and Caldwell is requesting a budget increase of$142,000 to complete the services listed above. If you have any questions or may have concerns regarding the items contained in this letter,please do not hesitate to call me. Very truly yours, BROWN AND CALDWELL o eph utirr ez,PE, PMP ACCEPTED FOR CITY OF SAN LUIS OBISPO Managing Engineer BY: JIG:ksy The undersigned agrees to the Terms and Conditions of this Contract Budget Addition. Enc. Signature: Printed Name: Tide: Date: P:LPmj=m\124881...\WP\104134 Addendum No.3.dm