HomeMy WebLinkAbout11/06/2007, C3 - HIGUERA STREET PAVING PROJECT FROM MORRO ST. TO NIPOMO ST. SPECIFICATION NO. 90684 WATER FUNDING IN council M 11/06,07
acEnaa REpoRt G 3
CITY OF SAN LUIS OBISPO
FROM: Jay D. Walter, Public Works Direc or�
Barbara Lynch, City Engineer
SUBJECT: HIGUERA STREET PAVING PROJECT FROM MORRO ST. TO
NIPOMO ST. SPECIFICATION NO. 90684 WATER FUNDING
INCREASE
CAO RECOMMENDATION
1. Approve a budget transfer of $81,000 from Water Fund Working Capital to fund additional
fire services and construction related costs.
2. Authorize staff to execute two contract change orders for additional fire service lateral
installations and sewer lateral repair work with an additional contract cost of $46,000 and
$35,000 respectively.
DISCUSSION
On July 17, 2007, the City Council awarded a construction contract to Granite Construction for the
Higuera Paving Project. On September 4, 2007 construction began. The project included the
repaving of Higuera Street from Morro to Nipomo. Prior to completing that paving,.the contractor
installed pedestrian lighting conduits and fire sprinkler laterals. Since the time that the City Council
awarded the project to Granite Construction two issues have developed which require additional
funds. Both of these construction issues are related to the installation of fire sprinkler laterals.
Added Fire Sprinkler Laterals
A fire sprinkler lateral is a large water service which runs from the water main in the street, into a
building to provide water to fire sprinklers in the building. Any major work to a building will
require installation of fire sprinklers. The laterals installed by the City terminate in the sidewalk,
awaiting final use by the building owner. Installation of the laterals in conjunction with this project
means the building owner does not have to open up the street to make the connection for service,
but rather can hook up in the sidewalk area. This significantly reduces disruption to the downtown
and damage to the street.
Originally the Hb era Paving Project included 13 fire service laterals to be installed. During
construction, four more buildings were identified that need a lateral. In order not to delay the
project or install the fire services after Higuera was paved, staff directed the contractor to proceed
with the installation of the additional services. At the time that direction was made, it appeared
from the plans that the lateral could be done for a lower cost than the original bid, due to the
proximity of the waterline designated for the hookup, and the contingencies would be adequate to
G3 - �
Higuera Street Paving Project Page 2
cover the additions. Unfortunately, the line that was originally designated for the connection was a
transmission main and so could not be used. The waterline to be used for the services is on the
other side of the street from the added laterals. Work continued in order to make construction
deadlines for the downtown without staff realizing the extent of the final costs to extend the lines.
The Contractor and the City negotiated a revised cost for the completed work, including some
revisions to the original services that could not tie onto the closer waterline and a credit for the
service laterals on the opposite side of the street that were shortened. The additional cost for the
needed fire service lateral work is$46,000.
Sewer Lateral Conflicts
Staff researched the location of existing underground utilities in the project area during design,
including the location of the sewer laterals. Most utilities were successfully identified as part of
that process; however,the contractor discovered that the sewer laterals in Higuera Street were not in
the locations shown on the plans. In several cases, the Fire Service lateral shown on the plans
corresponded with the location of the existing sewer lateral. The result was broken sewer laterals
and additional contract cost to relocate fire sprinkler services to a new location and repair the
damaged sewer laterals. The added contract cost for this work is estimated to be $35,000. The
actual cost is will be known once all the work has been completed.
CONCURRENCES
The Utilities Department concurs with the use of the Working Capital in the Water Fund for
purposes of completing needed Fire Sprinkler Service laterals.
FISCAL IMPACT
Standard change order procedures require the City Council to authorize additional expenditures
on construction projects exceeding $100,000 or where additional funds are required. On this
particular project, the extent of the financial commitment to the construction company was not
perceived by staff until too late. The contingency funds available for the service lateral portion
of this project is inadequate to cover the costs. Additional funds are needed to cover the added
service laterals, the extension and relocation of service laterals, and the repair of the sewer
laterals. The exact cost of this work is unknown at this time. The requested additional funding is
anticipated to be adequate for all this work leaving the original project's contingencies available
for future use.
Total increase in project cost for the Water Fund is $81,000. Requested funding is currently
available from Working Capital in the Water Fund. The Water Fund will still be above policy
minimum even after the supplemental appropriation.
C.� - 2
I/ it
Higuera Street Paving Project Page 3
Project Contract Amount (Water Fund Only): $179,700
Project Contingencies (Water Fund Only): $19,000
Total Construction Budget Available (Water Fund Only): $198,700
Estimated Additional Amount Needed: $81,000
Total Project Cost(Water Fund Only): $279,700
PchstoreZpublic rks\stO-reports-agendas rrinuteslcat\2007\cip\90684 higuera paving\90684 budget increase.dac
c3 -.�