Loading...
HomeMy WebLinkAbout05/20/2008, C6 - WATER RECLAMATION FACILITY: CLARIFIERS 4 AND 5 MAINTENANCE PAINTING PROJECT; SPECIFICATION NO. 9081 counat M °� May 20,2008 j acEnaa wpont 1�Nw CITY OF SAN LUIS OBISPO FROM: Jay Walter Public, Works DirecW10 Prepared By: Bridget Fraser, Engineer III SUBJECT: WATER RECLAMATION FACILITY: CLARIFIERS 4 AND 5 MAINTENANCE PAINTING PROJECT; SPECIFICATION NO. 90818 CAO RECOMMENDATION 1. Approve the plans and specifications for "Water Reclamation Facility: Clarifier 4 & 5 Maintenance Painting Project, Specification No. 90818" and authorize staff to advertise for bids. 2. Authorize the CAO to award the contract if the lowest responsible bid, plus the accepted alternate, is within Engineer's Estimate of$320,000. DISCUSSION Clarifiers 4 & 5 where originally constructed in 1994 as part of the last major upgrade to the Water Reclamation Facility (WRF). After fourteen years, the protective coatings on the equipment are starting to show signs of deterioration. The deteriorated coatings should be replaced to protect the clarifiers from further deterioration and costly repairs or replacement. As an added protection to the equipment, the coatings engineer recommends the addition of sacrificial anodes. Sacrificial anodes protect the structure from corrosion by being more corrodible than the steel structure. In other words, the anodes will corrode before the steel corrodes there by protecting the steel structure. Even though sacrificial anodes were not included in the budget, staff recommends including the sacrificial anodes as an additive bid alternate. Once bids are opened staff will evaluate the cost versus the benefit of this added protection. Staff will make a recommendation at time of award whether to include the anodes in the contract or to hold off and budget for them in a later budget cycle. CONCURRENCES The Utilities Department has reviewed and approved this project. FISCAL IMPACT This project is included in the Water Reclamation Facility Major Maintenance 2006-2007 project list identified in the 2005-07 Financial Plan on pages 110 to 112 of Appendix B. A budget of $295,000 is identified for the coating of these clarifiers. Funding for this project is available in the Water Reclamation Facility Major Equipment Replacement master account which has a current e � U Clarifiers 4 and 5 Maintenance Painting Project Page 2 balance of$1,547,230. At time of award funds will be transferred from the master account to the project account via a budget amendment request. The estimated project accounting is shown below: Estimated Project Costs: Design $ 7,500 Printing/Misc. 500 Construction Costs: Engineer's Estimate (Base Project) $300,000 Additive Bid Alt .— Sacrificial Anodes 20,000` Total Construction Estimate 320,000 Contingencies @ 10% 32,000 Construction Management/Inspection 30,000 Total Estimated Project Costs $390,000 The estimated project cost of$390,000 is over the budget of$295,000. For the most part this is due to costs for construction management, the addition of the sacrificial anodes and the general increase in material and labor costs since the budget was created 4 years ago. Although material and labor costs continue to rise, the recent bidding climate has been very competitive due to the declining construction markets. Given this bidding climate, it is possible that bids could come in lower than the estimate. ALTERNATIVES Defer the Project. If corrosion is allowed to continue, the clarifier equipment and components will continue to deteriorate to the point of requiring more costly replacement or repair. ATTACHMENT Vicinity Map COUNCIL READING FILE Specifications g:\staff-reports-agendas-minutes\_car\2008\cip\90818 clarifiers 45 painting\90818 car adv clarifiers 45 painting.doc Elm mimmi . sem.. ` �,� �.♦, ,, PROJECTLOCATION �i �� i �� • CITY MAP I � • CLARIFIER 4&5 RECOATING PROJECT SPECIFICATION N0.90818 •. SHEET V4 MMS