HomeMy WebLinkAbout08/04/2009, C 3 - WATERLINE IMPROVEMENTS - VARIOUS LOCATIONS, SPECIFICATION NO. 90788 council. �0m4 8/4/2009 j acEnaa nEpont �N CITY OF SAN LUIS O B I S P O FROM: Jay D. Walter, Director of Public Works -70W Prepared By: Christine Comejo, Engineering Technician III SUBJECT: WATERLINE IMPROVEMENTS- VARIOUS LOCATIONS, SPECIFICATION NO. 90788 RECOMMENDATIONS 1. Approve the plans and specifications for the "Waterline Improvements, Various Locations" Project, Specification No. 90788. 2. Authorize staff to advertise for bids and authorize the City Manager to award the contract if the lowest responsible bid is within the Engineer's Estimate of$377,644. DISCUSSION Replacement of water distribution pipes and related facilities is an ongoing program to replace aging, substandard and deteriorating infrastructure. This program has three objectives: 1) Ensure reliable water services 2) Reduce the need for emergency repairs 3) Enhance available fire flows Based on priorities set by the Utilities Department, certain waterlines have been selected for replacement as shown on Attachment 1. These water lines have seen an increase in required maintenance and emergency repairs in recent years, as a result of their age. The assumed useful life expectancy of water lines is fifty years. The waterlines proposed for replacement with this project were originally installed in 1942 or earlier. Replacing these waterlines will result in lower costs and reduced customer impacts that would otherwise be associated with emergency repairs. CONCURRENCE The Community Development Department has granted a Notice of Exemption because of the potential for minimal environmental impacts. FISCAL IMPACT Waterline improvements have been identified in the Preliminary 2009-11 Financial Plan Appendix B, page 3-71 and 3-77, for Water Distribution System Improvements. Funding for this project is available in the Water Distribution System Improvements Main Account, which has a �-3 Waterline Improvements Various Locations, Spec. No.90788 Page 2 current balance of$1,878,720. The estimated project costs are displayed below.. Currently, there is sufficient funding to support this project request. -project Costs BMidget Project Pending Construction Budget: Engineer's Estimate: $377,644 Ella - Ruth to Osos $ 30,000 Contingencies: $56,647 Rachel Ct-Renew 2" $ 30,000 Total for Construction: $434,291 Toro - Phillips to Huguera $ 530,000 Approved Budget: $ 590,000 Testing: $8,000 Miscellaneous (incl printing): $250 Funding Available: 81,878,720 Total Project Cost: $4429541 ATTACHMENT Location Map AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE Plans and Special Provisions G:\Staff-Reports-Agendas-Minutes\-CAR\2009\CIP\90788 Waterline Improvements Various Locations.doc �3-a ATTACHMENT 1510 NABS MO ;ENTER Um PHIWPS � o AA O F/r0 � ON , ON �O O m� � O QO ® G\E\G OO P .01 y O O °O4AND �t�EL qo Gy G O OO EN 2�0 O 2 3 O q� O a KRI Z Q �y O NIFER qG CHEXI.Ll 0 0 11 EQ z REN BRAN CH L� o OUNDHO SOUTH C] G. F] PROJECT SCOPE LOCATION MAP Toro Street: Phillips - Higuera Ella Street: Osos - Ruth N Rachel Court: Rachel - End C,Q' �,7 city O� WATERLINE IMPROVEMENTS � VARIOUS LOCATIONS 2008 San tui S OBI SPO SPECIFICATION NO.90788 Gt 3 ,3