CITY OF SAN LUIS OBISPO
FROM: Jay D. Walter, Director of Public Works
Prepared By: Barbara Lynch, City Engineer
SUBJECT: LAGUNA LAKE DREDGING ENVIRONMENTAL DOCUMENT
RECOMMENDATIONS
1. Adopt a resolution approving a Mitigated Negative Declaration (ER 31-06) for the Laguna
Lake Dredging project, Specification No. 99110.
2. Provide direction to staff on next steps.
REPORT-IN-BRIEF
Over several years, staff has provided a discussion of dredging and related issues for several
Council study sessions, Parks and Recreation Commission meetings, as well as collected input
from the community, generated technical reports through consultants, and developed alternatives
to complete the dredging of Laguna Lake. (Attachment 1) Staff has provided a summary of many
of the items discussed over this period (Attachments 2, 3, 4, and 5), including general
information about dredging and dredging alternatives, other related issues, and public input.
At the September 6, 2005 study session, the Council authorized staff to proceed with
development of the environmental study for the project. The Council endorsed a general project
description presented by staff for purposes of completing the study shown in Attachment 6. Staff
was clear at the time that the project may change in the future, and the.environmental study
might need to be updated;however, the project description would include the most likely project
elements to maximize the benefit of completing the document. Most recently the document was
updated to meet the requirements of the California Global Warming Solution Act, targeting
green house gas emissions.
Project Description Summary
As outlined in greater detail in Attachment 6, the proposed project is to continuously dredge the
lake for twenty-two weeks annually for the next ten years. This should result in the removal of
150,400 cubic yards of silt and other material at the end of this ten-year period, which will lower
the average depth of the central lake by about 1.5 feet, for a resulting average depth of about 9
feet. Dredged materials would be disposed of via a combination of the construction of berms in
the active park, wetland creation (filling in low areas of the lake near the peninsula,) and offsite
disposal. At the end of the ten-year cycle, it is likely that the City would need to begin
maintenance dredging to keep the lake at the new depth. In summary, with this approach,
maintaining the lake is likely to be an ongoing operation indefinitely.
130-1
l
Laguna Lake Dredging Environmental Document Page 2
Based on this ten-year approach, the "mid-range" average annual cost estimate is $460,000,
summarized as follows in 2009 dollars:
Mid-Range Annual Cost
Annual lease-purchase payment for equipment * 40,000
Staffing 135,000
Silt disposal 240,000
Other costs 45,000
Total $460,000
*Based on purchase cost of$300,000, 5%interest rate and ten-year term
As discussed in Attachment 5, the cost could be different, depending on how much of the lake is
dredged, how quickly, and how the material is disposed of.
Feasibility Assessment
The Initial Study provides the information that the project, as described, is feasible as long as
reasonable care is taken to protect the environment. It does not address the feasibility from a
funding perspective. The Initial Study resulted in a Mitigated Negative Declaration of
environmental impact. Mitigation measures are incorporated in the Resolution to approve the
environmental document incorporated in this report as Attachment 7. This report, the
attachments, and the Initial Study provide historical context and technical information. It must
be noted that the project is subject to regulation and approval by the Army Corps of Engineers
and the Department of Fish and Game. It is anticipated that further detailing of the manner of
dredging, configuration of the temporary basins, and ultimate disposal of dredge spoils will be
done to provide further reduction of environmental impacts of the project as part of the
permitting process.
The heart-of-the-matter is really about our vision for this body of water as a park amenity over
the long term, and whether or not the vision is achievable and sustainable. It is not just the initial
dredging that is required, but ongoing dredging to maintain the lake depth. In order to answer
this core question it may be necessary to engage a broad cross-section of the public (and not only
lake area residents) to study the issue, the options and the level of community support for the
various options. An alternative is provided in the staff report that would make a citizen
engagement process the next step.
Prior to considering the options, it is important to outline the early history of the park, including
how the lake came about. Staff has also included information to refresh Council members on
dredging methods and related issues, including dredging alternatives and rough estimated costs,
in the attachments. The Initial Study and companion documents also provide significant
amounts of technical information. This report is organized to provide this information as
follows:
Staff Report: Historical context, status and"next step" alternatives
13.2
Laguna Lake Dredging Environmental Document Page 3
Attachments: Project description and negative declaration resolution, summaries regarding
dredging and related issues; 2004 Parks and Recreation Commission and public input; dredging
and disposal alternatives detailed.
Council Reading File: Historical park plans and environmental technical studies
DISCUSSION
Background and Historical Context
History bears out that this has been one of the City's more challenging projects to bring to
completion, and so staff has been looking deeper into the history of the park and lake to better
understand its beginnings, the original intent, and the City's obligations. The history of the lake
not only gives the Council a frame of reference for how the City got into this position, but helps
understand the community interests and how they have changed over time.
1.The first Laguna Lake Committee and Laguna Lake Master Plan - 1955-1964
Council records indicate that in 1956 the Laguna Lake Committee reported to the-Council its
recommendation to proceed with lake development and property acquisition. At that time, the
City owned a portion of the property, but not all. Adjacent property owners were not interested in
developing a lake for a recreational area then. The Council supported the Committee's
recommendation for the park, including pursuing condemnation of properties if necessary.
The original vision of the lake appears to have come about through the Laguna Lake Committee
and the development of the first Master Plan for the park. More commonly known as the Hector
Plan, named after its author, the Master.Plan outlined a very developed park estimated to have
10,000 visitors a day, 500 of.which were sightseers only. The park was envisioned to include
conversion of the marsh to a lake and included the following vision:
A lake "...filled frequently to capacity with ... boats," with sheltered coves, fishing,
boat launching and docking, a 1000 foot long swimming beach sheltered by
vegetation and fencing and accommodating 1000 people at a time, a golf course, a
peninsula for fisherman, picnickers, and "strolling visitors," a club house with a
social room, restaurant, snack bar and park office, a tot lot, a dancing and skating
facility, ping pong tables, junior museum, senior citizens building and facilities,
playfields for football, softball, volley ball, and lawn bowling, along with horseshoe
pits, handball and shuffleboard areas, a nine hole golf course and driving range, a fire
circle, outdoor amphitheater, camp-out areas, archery range, hiking, and picnic
facilities for 300 families and a group picnic area for 600.
In 1964, the Council adopted the Hector Plan for a balanced recreational use of the property.
When looking out across the park today, it is possible to see how that vision started to take
shape:
1. The lake was partially dredged out to assist adjacent property development
2. Additional properties were acquired
3. Roads and restrooms were installed
$c2 - 3
I\
Laguna Lake Dredging Environmental Document Page 4
4. A play ground and some picnic tables were installed
5. A boat launching area was built
6. Trees were planted to begin the landscaping that would provide shelter from the wind
7. The outflow from the lake was controlled to store more water
2.The Laguna Lake Management Plan—1979-1982
In 1982, a separate Laguna Lake Management Plan was completed for the lake only, separate
from the prior park master plans which address the park as a whole. In that plan, community
desires for the lake were condensed into four essential goals, wildlife preservation, recreation
enhancement, shoreline home protection and agricultural preservation. The plan identified a
variety of potential uses of the lake including:
1. Shore Fishing
2. Boating
3. Swimming
4. Open-Water Wildlife Habitat
5. Bird Watching
6. Riparian Wildlife Habitat
7. Sediment Retention
The management program adopted by the City Council at that time included only two measures
to be undertaken by the City, maintenance of the Prefumo Creek sediment basin and control of
aquatic weeds by mechanical harvester. Some of the programs for lake management discussed in
the study included dredging; however, the Council did not adopt any of those programs at the
time. The management plan identified the following objectives, which dredging could assist in
achieving:
1. Increase the depth so that in dry weather water would remain in the lake
2. Reduce aquatic weeds
3. Prevent sediment from reaching the lake
4. Preserve the characteristics of the lake that are important to wildlife, flood protection and
recreational opportunities
The City has pursued the adopted management program. For many years after Prefumo Creek
was diverted to flow through the lake, silt transported down from the Irish Hills accumulated in
the Prefumo Arm, gradually filling that area and effectively reducing the surface area of the
original lake. Regular projects to remove silt from the area near Los Osos Valley Road have
prevented more sediment from reaching the lake. While the delta that has formed at the mouth of
the creek, where it reaches the lake, is not popular with some local residents, it probably serves
to slow water in the Prefumo Arm and allow it additional time to release sediment. Fine silts,
suspended in the water, still reach the lake, which is the source of much of the turbidity
(cloudiness) when the prevailing winds blow. Aquatic weeds were harvested for several years.
They are now not the problem they were at the time the management plan was developed. Actual
harvesting of weeds has not been done in many years. Reeds along the lake edge continue to
grow and will until such time as the City invests in a removal operation. The reeds grow in
Laguna Lake Dredging Environmental Document Page 5
shallow water close to the shore, an area not suitable for dredging because of potential for shore
destabilization and erosion.
Dredging, although not identified in the originally adopted program, will certainly deepen the
lake and reduce the likelihood of it going dry. This original plan envisioned a long-term project
whereby material would be dredged from the lake each year, dried and disposed of on site. That
plan acknowledged that: "Due to cost, it is not considered feasible to transport the material away
from the disposal site." Discussions continue today on how to accomplish this.
The proximity of the lake to the surrounding open space in and near Cerro San Luis contributes
to the ongoing presence of wildlife at the lake. Whether we have a lake or a marsh, wildlife will
continue to be a part of the park(and lake)environment.
3. The Laguna Lake Master Plan
In 1993, when the next Laguna Lake Park Master Plan was completed, an on-site and telephone
survey ranked expanded use for natural wildlife as the number one priority. Clearly the vision
had changed from a very developed and heavily used active park represented in the original
Hector Plan, to one that was passive in nature. Even the name of the park was recommended to
be changed to Laguna Lake.Nature Park. That plan also established the Nature Preserve area of
the park.
The lake itself has remained at the heart of discussion over the years most likely because whether
the park is a highly developed park with thousands of people, or a park supporting wildlife, the
lake is a part of the vision. At least for some members of the public, there is a fear that the lake
will gradually fill in because of sediment deposited by Prefumo Creek, and there is still a desire
that the lake be available for recreation. The drying-out of the lake during droughts also draws
concerns from those advocates of the lake as a recreational resource. For those whose vision is
solely for a nature preserve/passive setting, the loss of the lake seems to matter less.
4.Previous Council Direction
After the completion of the Laguna Lake Management Plan and at the urging of members of the
community, the Council authorized an environmental study with the assistance of outside
expertise. Cutbacks in funding resulted in that effort going uncompleted for several years.
Council action in 1999 confirmed their intent to maintain the lake as a recreational facility and
resurrected the effort to explore the possibility of a dredging project. The Council allocated
approximately $200,000 in funding over a two year period and staff obtained the services of a
firm to complete various technical studies and produce the environmental document.
During the preparation of the most recent technical studies, Council direction was to look at a
short term dredging project to see how that might be accomplished. After reviewing technical
studies and costs, the Council directed staff to return to the slower, long term dredging concept
for purposes of the environmental document. This concept is described in more detail in the
project description, but in summary it details a seasonal removal of material with an electric
dredge, stretching over 10 years, costing approximately $2 million over that period to operate the
dredging and drying program, with additional costs for disposal. The dredging would have to
�v2�S
Laguna Lake Dredging Environmental Document Page 6
eventually become a maintenance dredging-program if the money invested was to be meaningful.
Just like streets, the condition will deteriorate if maintenance is not ongoing and the money spent
initially to complete the dredging would have been wasted.
The other major, and very significant change in terms of cost since dredging was originally
proposed in the Laguna Lake Management Plan, was the designation of the nature preserve area
in the Laguna Lake Park Master Plan, which severely limited the area (25 acres) originally
identified in the for large scale disposal of dredged material. The Council did ultimately
authorize the use of 5 acres for drying operations, but this would be suitable only for the longer
term/low volume dredging operation, with the area used for drying beds.
Environmental Document
The environmental document is a Mitigated Negative Declaration of an Initial Study. It was
made available for public comment as required and is now ready for Council approval. Staff
recommends approval of the document, even though there is no dedicated funding for any
project because the document is the culmination of several years of work on technical
documents, Council Study Sessions, and revisions. Although the City did not have funding
allocated for dredging at the time the direction to move forward with the document was made,
staff recommended the development-of a project description and completion of the document for
two reasons:
1. The completed environmental document would provide information on whether it was
possible to reasonably mitigate the work.
2. Possession of a completed document could assist the City in obtaining grant funding if a
suitable grant source was located.
Several mitigation measures have been identified, which are specified in the Council Resolution
for approval, Attachment 7. In general, the mitigation measures cover a series of requirements to
be used in guiding the work to ensure the impact of the project is minimized to the largest degree
possible:
1. The measures are standard practices seen in grading projects and projects near water bodies.
2. The project will include monitoring for biological and archeological resources and for noise
levels.
3. In addition to the monitoring for biological resources, pre-construction surveys will be
carried out, as well as training and work area delineation.
4. Dust control will include normal measures for wetting and reseeding along with a mandatory
slow speed limit for hauling vehicles.
5. Other air quality measures include using modern, lower emission equipment and an electric
dredge. The document specifies carbon neutrality through offsets.
Laguna Lake Dredging Environmental Document Page 7
6. Dredging will not encroach too close to the shore line to prevent destabilization. (This means
that reeds will remain along the shore unless a separate reed removal operation is
undertaken.)
Next Steps
With the completion of the environmental document, staff would normally be ready to proceed
with preparation of construction documents for public bidding. Given the lack of budget for the
construction and an alternative to complete the work as a staff maintenance operation, direction
is needed from the Council as to how they wish to proceed. Staff has outlined some options for
the Council's consideration below.
1. Pursue Citizen Outreach and Engagement
The completion of the environmental document has shown that there are no fatal technical flaws
for the project, as described. However, while feasible, it is anticipated to be about $5,000,000 to
complete the dredging as described and dispose of the material. Funding, therefore, is the major
stumbling block for moving forward. One option to address this is to have staff create a citizen
engagement program to help determine if there is enough community support for dredging and
how much time and money the community is willing to spend on dredging versus other
important priorities. Grants are available for citizen engagement, a process intended to address
problems faced by agencies for which there are no preconceived outcomes, where an agency
truly does not have firm direction on what to do. The remaining project funding of might also be
used to achieve this. The information from such an effort would give the Council a better
understanding of how high a priority this is for the community at large (not just for the
neighborhood), and whether the City should move forward or not.
Over the years, the City has involved the community to varying degrees:There was a committee
in 1955 that discussed what should be done with the lake and it supported dredging. The Laguna
Lake Study Committee was set up in 1979 to assist the consultants with the development of the
Laguna Lake Management Program. The outcome of that was the Lake Management Plan
which, with Council approval, recommended a program of sediment removal in Prefumo Arm
and weed harvesting. Dredging was identified as the last option due to the cost. In 2004 the Parks
and Recreation Commission discussed the dredging on three occasions and received public
comment. That input is summarized in Attachment 4.
At the Council's request, the survey in the spring of 2005 to gage support for a revenue measure
included a question that dealt with Laguna Lake Dredging. The survey indicated about 44% of
the citizens may be supportive of spending some new revenue on a dredging project. However,
in comparison to all the possible service issues presented to survey respondents, such as public
safety, senior services, traffic congestion, street paving and flood protection, Laguna Lake
dredging rated at or near the bottom of interest.
The downside of proceeding with an engagement program is that it may appear the City is going
to study dredging again and that the City has been doing that for 50 years.
3a - �
Laguna Lake Dredging Environmental Document Page 8
2. Discontinue or postpone project work
The City's current financial situation may speak to simply postponing consideration of a
dredging project at this time, or the Council may decide the City will never be able to afford
(without significant grant assistance) a large-scale dredging project. The consultant's reports
have been accepted and the environmental document can be approved. Specifications for the
dredging project could be put off until such time as a funding mechanism for dredging is
developed. The other downside to continued pursuit of the dredging is that it takes staff time
away from priority infrastructure maintenance projects that are funded, on top of staff reductions.
If the lake is allowed to gradually fill in, a channel of some type would remain, conveying
Prefumo Creek through the area to the outlet. The lake would increasingly take on marsh
qualities and remain a wildlife refuge. While this would be a difficult decision, it has the
advantage of discontinuing the frustration for dredging proponents of City studies and
discussions about dredging with no actual dredging completed. Instead, it would let the
community know that other services have been determined to be more important.
3. Investigate an Assessment District
A survey of the neighborhood regarding assessment district support has not been undertaken to
staff's knowledge and may be worthy of further consideration. The City, as a lake front property
owner, should consider its own response to such a question. The City would conceivably be
responsible for half the cost as a lake front property owner.
4. Complete Financial Plan Submittals
If the Council would like to continue to work on this project, staff can be directed to prepare
Financial Plan submittals for continued work. Those submittals could take a variety of forms
including, a request for funding to pursue disposal easements on adjacent property, staff and
equip an in-house dredging program, contract with grant acquisition firms to research and apply
for grants to dredge the lake or allocate a portion of the general fund for a.contract dredging
operation.
Summary—The Heart of the Matter
Although a great deal of technical, environmental and financial information is outlined in this
report, the attached materials, and within the environmental document, the "elephant-at-the-
table" is that we do not have funding to move this project forward in a timely and sustained way,
unless the Council is willing to reallocate funding from other priorities. In the meantime, the
lake continues to silt up. Therefore, we need to eventually get to the heart of the matter, which
is:
How much are we willing to invest as a community to drastically alter the present
"evolution" of the lake in order to assure its long term future as a man-made lake
suitable for boating and other activities? Or, do we allow it to evolve into something
different?
Laguna Lake Dredging Environmental Document Page 9
As the elected representatives of the community, the Council may choose to directly answer this
question. Or, the Council may wish to initiate a more extensive citizen engagement process
before making a final decision. If the "citizen engagement" option is chosen, staff will need to
develop an engagement concept and submit a grant application for support funds. An entity
exists within California (Common Sense California) to promote such engagements through small
grant awards (for example, Morro Bay received a grant to engage a discussion about a future fire
station). Staff would pursue this grant source first. A requirement of this program is that the
grantee does not have a preconceived outcome in mind when initiating the engagement. If we
truly are not sure what to do and how much to invest in restoring Laguna Lake, then this issue
may be a good candidate for such a grant.
While the cost will depend on the engagement concept, it is estimated to cost $15,000. If the
grant application is not successful, and the remaining project balance is not adequate, the staff
could return to the Council for consideration of other funding options.
CONCURRENCES
The Community Development Department has reviewed the Initial Study and concurs with the
outlined findings and mitigation measures. Planning Commission review is not required for this
environmental Study. Earlier Parks and Recreation Commission reviewed the project alternatives
during a series of meetings and their input has been provided as Attachment 4. They will also be
part of the final project plan design at such time as the project moves forward. Natural Resources
staff has been involved during the development of the technical reports and environmental study,
and will continue to be involved as the project is developed. Regulatory permits will need to be
acquired if the City moves forward with implementation, and additional requirements -and
mitigation are anticipated from those agencies.
FISCAL IMPACT
The approval of the environmental document has no fiscal impact. Additional action on the
project may have significant costs, depending upon what Council directs. The project has a
current unencumbered balance of just under$14,000.
The alternatives for the initial dredging range in cost from about $4 to $9 million dollars
depending upon how much of the lake is dredged, if some disposal is included at the park, and
where the remaining material is disposed of. These costs would need to be periodically paid out
to sustain the lake depth. Most likely, only during the initial dredging operation would the
material be able to be placed at the park, after the available area had been used, future material
from maintenance dredging would have to be disposed of off site. More detail of the alternatives
can be found in Attachment 5, or in the Tables section of the Engineering Analysis of Dredging
and Disposal Alternatives.
ALTERNATIVE
Stop work altogether on the dredging project with no further staff resources spent. This
alternative, while definitively conveying the message to staff that there would not be continuing
work on the project, would not answer the question about the community's desires for the lake
8a- 9
Laguna Lake Dredging Environmental Document Page 10
and park. It would also fall short knowing whether dredging work is a priority worth spending
limited City resources on, if there was community support for any dredging option.
ATTACHMENTS
1. Site Map
2. About Dredging
3. Related Issues
4. 2004 Parks and Recreation Commission Input
5. Dredging and Disposal Alternatives
6. Project Description
7. Resolution for approval of the Environmental Document
AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE
Laguna Lake Master Plan (1961 —The Hector Plan)
Laguna Lake Master Plan (1993)
Laguna Lake Management Plan (1982)
Environmental Document
Technical Reports prepared by LFR Levine-Fricke:
1. Ecological Resources and Potential Impacts of Dredging Operations at Laguna Lake
2. Characterization of Sediment and Water at Laguna Lake
3. Engineering Analysis of Dredging and Disposal Alternatives at Laguna Lake
tAmuncil agenda reports\pubfic corks tar12�\99110 II dredging\11-17-09 laguna lake dredging car.doc
ATTACHMENT 1
S
ra
C
s
c s
a
PROJECT
LOCATION
O� 1
e �
O
®� q
9
/ a
s
� o
r
�a
P
r
9
a
a
LAGUNA LAKE DREDGING
LOCATION MAP
i
ABOUT DREDGING ATTACHMENT 2
What are the goals for the lake?
In the Laguna Lake Park Management Plan the goals are listed as Wildlife Preservation,
Recreation Enhancement, Shoreline Home Protection and Agricultural Preservation.
Comments from the public vary and include concerns about mosquitoes, smell, flooding,
recreation uses and, particularly when the lake dries out during droughts, the subject of dredging
the lake comes up.
What dredging will do?
The dredging will maintain the lake as a recreational facility for the community. Parks and
Recreation is even considering the possibility of stocking the lake for fishing. The lake will also
be more conducive to wind surfing and boating. The completion of the dredging will result in
deeper open water habitat, less subject to roiling by the wind, which should reduce the turbidity
that currently exists at the lake. The deeper, cooler water may also discourage the growth of
certain weeds, which need sunlight to grow, and possibly the algae.
Finally, increasing the depth of the lake by dredging will increase the likelihood that there will
be water in the lake during drought years.
What dredging will not do?
Dredging Laguna Lake is not a storm water management activity. Water remains in the lake
during the summer months. This is because the lake bottom is lower than the outlets. Because
that water level is relatively constant, the lake can not take in significant amounts of storm water
in the winter from the adjacent residential area. Once the lake is full, water begins to back up in
the system and flooding occurs. The lake would have to be emptied prior to winter rains .to
provide any significant flood protection.
Dredging the lake will not take care of the reeds and associated mosquito problem along the
shore line. Recommendations for dredging are clear that dredging should not start closer than 50
feet from the shore line. The reason for this is to prevent destabilizing the shore. Dredging too
close to the shore could result in excessive shore line erosion or collapse.
The seven basic components to the dredging project:
1. How much of the lake is dredged (quantity)
2. Material removal technique
3. Material drying technique
4. Material disposal/placement
5. Environmental Impacts
6. Cost
7. Duration
1. Quantity
How much of the lake we dredge will clearly have an impact on cost. The project description
used for the Initial Study is for a reduced dredging area. In general, this approach looks at
ed—/J—
ABOUT DREDGING _, ATTACHMENT 2
dredging the lake, from above the inlet at Prefumo Creek, to Madonna Road. The alternative is
to dredge to the northern end of the lake.
The delta which has formed at the mouth of the Prefumo Arm has grown to such a size that it
now serves as a wildlife habitat and one consulting biologist recommended that it be left in
place. There has been interest expressed in removing it to allow deeper dredging in the Prefumo
Arm and reestablishing open water in that area. Based on biological studies, it may be difficult
to get approval to do so from regulatory agencies. The City should continue its practice of
routine dredging in the arm to remove the collection of material. This helps to control what
reaches the lake.
2. Material Removal Technique
The material will either be scooped or pumped out. Once the material is manageable, it can be
placed at the park or hauled away. The scooping methods reduce the amount of water that is
taken with the material. This shortens the drying time. Pumping is accomplished by mixing
water with the material at the lake bottom and pumping it to shore. The water content can be as
high as 90 percent.
3. Material Drying Technique
There are two basic drying techniques. The first method is to use nature to do the work. The
material is set out and allowed to drain and dry. The second is a mechanical means. Specialized
equipment processes the material through something equating to the spin cycle on a washing
machine. The effectiveness can be heightened with additives to absorb water. This equipment is
proprietary and can add cost, but the trade off is avoiding the need to find areas large enough to
construct drying beds without impacting sensitive species.
4. Material Disposal/Placement
Disposal of dredge materials is a significant portion of the cost to complete the dredging. If a
location can be found for disposal on the lake property, it would reduce the cost. The Nature
Preserve portion of the park is home to various protected plants and wildlife. Portions of the
front of the park are dedicated to the memorial grove, with the rest of the park considered the
"active" park. There are areas within the active park were spoils could be placed, changing the
contours of the park. This will not be enough to handle all of the spoils but would still reduce
the cost of the project.
Off-site disposal is an unknown cost. It could be very costly or relatively inexpensive. It relies
on available uses at the time the material is removed. In the past, on small dredging projects, the
City has left disposal to the contractor. If the City completes the dredging in a short period of
time, finding a single location in need of that much material could be difficult. If a site adjacent
to the lake could be found and the material used to re-contour the ground, it would be relatively
inexpensive. Sometimes use can be made of this type of material at landfills for cover. Probably
the worst situation is that the City will have to pay to place it at the landfill as waste.
While it seems extremely odd to put the material back in the lake, that is an option. The project
description used for the Initial Study proposes that the material would be used to fill in an area of
the lake to create a different type of habitat from that of open water, and to enlarge the peninsula.
ABOUT DREDGING - ATTACHMENT 2
Additional islands could be created by berming the soil with rock structures below the water to
prevent the material from drifting.
Metals in the sediment are not found in extreme amounts and are most likely of natural origins.
This finding is based on a review of surrounding rock formations and their makeup. However, if
for any reason, the sediment was determined to be "regulated," and require special handling and
disposal, the project costs would increase dramatically. Based on the information collected to
date, this problem is not anticipated.
5. Environmental Impacts
In the short term, the project has the potential for noise, both from the dredging equipment and
the hauling of material. This noise could be constant at times. There is the potential for odors
and unsightliness if the material is dried at the site. Disruption to plants and wildlife is to be
expected primarily as a result of a decreased water surface elevation as water gets removed with
sediment. Also placement of the spoils at the park and / or hauling activities can disrupt plant
and wildlife as well as park activities.
6. Cost
Costs to complete the project have been estimated in the $4,000,000 to $9,000,000 range.
7. Duration
The alternatives described in the technical report vary from 1 to 3 summers, working with
aggressive schedules. Less aggressive approaches could easily extend the duration for many
years.
tAcoundl agenda reportslpublic works raA2009rcip19911011 dredgingW-about dredging.doc
ad -�
RELATED ISSUES �' - ATTACHMENT 3
Below are summaries of other items the Council has requested for discussion at various
points during the project,related to the dredging:
Related Issues
1. Aeration
2. Lake Depth versus Turbidity
3. Lake infill rate review and historical depth
4. North Oceanaire Area Drainage Improvements
5. Upstream Sediment Control
6. Water Pollution
1. Aeration
Aeration is a process by which air is introduced to the lake to increase the level of dissolved
oxygen in the water. A secondary result can be mixing of the water which reduces temperature
differences in the water, ie warm at the top, cool at the bottom.
The value in introducing oxygen is to assist with the breakdown of organic material. If the
volume of organic material is great enough, it will tend to use up the available oxygen and then
the process slows or stops. The result is turbidity and.lack of oxygen for fish. Oxygen in the
bottom water of the lake also reduces the release of elements such as iron and manganese from
the sediments.
The City does not have data on the volume of organic sediments in the lake. However, studies
were completed in previous years to determine the levels of dissolved oxygen. Due to the wind
that whips the lake, typically most afternoons, the lake generally has oxygen throughout its
depth. There.may be a few of the deepest areas that do not. The.wind also blends the lake
temperature and so there is little differential in lake temperatures. There can be low levels of
oxygen in the morning, both because plants do not generate oxygen at�night:.and because the
water.is calm. This is relieved by both the wind and rainy weather which'increase the oxygen in
the lake. Aquatic weeds, noted as a problem in the 1980's studies have not been a problem in
recent years and the City has taken no action in that area since halting the weed harvesting
program and does not receive complaints regarding weeds.
The primary issue at the lake, besides mosquitoes, for which the City staff takes complaints, is
the algae bloom which occurs in mid to late summer during some years. Algae are a part of a
normal lake environment and provide food and energy for other animals. When algae grow
rapidly it is referred to as an algae "bloom." Blooms are typically a result of high levels of
nutrients, particularly nitrogen and phosphorus. These nutrients can come from a variety of
sources. The most likely sources for this lake are the birds and storm water runoff carrying
detergents, fertilizers and organic debris. An active public information program as part of the
City's efforts to reduce pollutants in the storm water is probably one of the best actions to take
against this particular problem. The City should also discourage feeding of birds by the public.
Other options include chemical treatment which causes the precipitation of the phosphorus in the
water.
8a_i5
RELATED ISSUES ATTACHMENT 3
The estimated cost for solar aeration units is $150,000. The current condition of the lake does
not appear to warrant the expense of aeration, primarily because of the wind action which
provides this activity free of charge most afternoons. If the lake is dredged, it is possible
aeration may be need if the wind action does not allow the lower depths to be stirred up.
2. Lake Depth versus Turbidity
To date, none of the studies have covered the relationship between the lake depth and the
turbidity. The amount of material removed from the Prefumo Arm indicates this area serves to
remove the larger material, such as sands and gravels. The fine clay remains suspended in the
water and moves out into the lake. Some of it remains suspended as long as the lake is turbulent.
There has been testimony from the public indicating that in the early days of the lake (1960's,)
the water was clearer. Using the historical information on the lake, and the above testimony, a
bottom depth of about 9 feet should reduce the muddy appearance. The area of the lake nearest
Madonna Road is the closest to that, ranging from 8 to 9 feet depth when the lake is full, with the
central portion of the lake ranging from 6 to 8 feet deep. It should be noted that the lake near
Madonna Road is currently at about 5 feet deep.
3. Lake infill rate review and historical depth
Using 1957, 1977, 1992 and 2001 lake bottom surveys, staff reviewed historical data to take
another look at the rate of sedimentation accumulation in the lake. The rates are higher near the
delta at Prefumo Creek and lower in the northern reaches. Using average rates of fill since
1957, and assuming no filling occurred until 1964 when Prefumo Creek was rerouted into the
lake, it would take between 40 and 180 years to fill the lake depending upon the location in the
lake. Taking the highest rate of sedimentation between the various surveys, again depending,
upon the location in the lake, it would take between 20 and 100 years to fill.
4. ..North Oceanaire.Area Drainage Improvements
The north.Oceanaire area is subject to flooding due to its low elevation in relation to the lake:
The storm drain system for this area is very simple. It accepts street water and pipes it directly to
the lake. Once the lake is full, that system backs up and no longer drains the streets. The
subdivision was designed with the street system as the backup to the pipe system, allowing the
water to inundate the streets but not the homes. Staff was asked to look at the possibility of
collecting the water from the north Oceanaire neighborhood and carrying it, via pipe, to below
the outlet of the lake on the southerly side of Madonna Road.
Assuming a design for a 10-year storm capacity, a 42" pipeline would have to be installed the
length of Oceanaire Drive. Due to the distance to reach the outlet of the lake culverts on the
southerly side of Oceanaire,Drive, the resulting depth is such that a lift station would be required
to bring it above the creek waters. After including needed manholes in the system and upgrading
the inlets for increased capture ability, this project is estimated to cost $2.2 million. The area
would still flood in heavier storms.
5. Upstream Sediment Control
The watershed for Prefumo Creek includes the Irish Hills area in addition to some residential
tracts. This area is steep and sparsely vegetated. Water can be observed running down cuts in
i
RELATED ISSUES - ATTACHMENT 3
the slopes along Prefurno Canyon Road. In a nutshell; the potential for sediment is very high.
There is not one particular spot that is responsible for the debris found in the Prefumo Arm of the
lake. This makes control in the watershed difficult.
One option for sediment control was discussed in the 1982 Laguna Lake Management Plan and
that is to dredge the arm much deeper., The creek would then encounter an area of open water in
the Arm prior to entering the lake. The slower open water area would be more likely to cause the
creek to give up its fine sediments at this point in addition to the heavy material it now yields.
Dredging the arm deeply is no small task. It is a restricted area with considerable vegetation and
residences nearby. To date, the regulatory agencies have been anxious that we keep the upper
vegetation. At least some of this would have to go.in order to establish stable banks as we went
deeper. We could no longer dredge with earth moving equipment as we do now because we
would be working in a wet environment. Sediment removal would have to be done regularly
with a dredge or we would return to the situation we have now. This returns us to the issue of
the need for dredging equipment and dealing with dewatering dredging slurry.
Another option is establishing sedimentation basins upstream. The only property controlled by
the City upstream is the Laguna Lake Golf Course. Such basins would impact the course and are
probably not desirable.
The Master Plan for flood control and drainage in the watershed that was completed in the late
1970's discussed the use of a debris dam on Prefumo Creek. The dam was proposed to be 20
feet high and sized to hold 100,000 cubic yards of material. The estimated cost of construction
at that time was about $0.5 million. This study was completed for the purpose of proposing
flood protection improvements. The dam was not recommended for flood protection because of
the low cost-benefit ratio. Building the dam at this time would be very difficult due:°to . .
development that has occurred near the recommended area for the dam, environmental issues'
associated with dams and a high cost.
6. Water Pollution
The lake is home to a number of birds that feed along the shore and likely is contaminate with
waste from them. The lake also does not have fresh water flowing through it in the summer
months providing water exchange. There are naturally occurring metals in the surrounding hills
which may be present in the water. The water appears turbid due to the suspended silts in the
water. The City does not do routine testing of the water and is not aware of testing by any other
agency. The lake was posted for no swimming some years ago. Shoreline banks are eroded and
so not suitable for swimming entry.
ftoundl agenda reportslpublic corks mr1200g1r: 9911011 dredging\O related issumdoc
43 OL �/,'1
I j i
PUBLIC INPUT ATTACHMENT 4
Parks and Recreation Commission Review
Staff presented the project to the Parks and Recreation Commission on June 2"d, October 6`h and
November 3`d of 2004. The Commission took testimony during the first meeting, but did not
discuss it.
For the second and third meetings, staff presented the following six questions to help focus the
discussion of this complex issue and gage the Commissions feelings about the project. The
Commission created a seventh question themselves. The results of the straw polls at these two
meetings are shown after each question.
1. Does the Commission agree dredging of Laguna Lake is an important Parks and Recreation
goal?
October-4 Yes,3 No/November-3 Yes,4 No
2. Does the Commission agree dredging of the lake is more important than other improvements
in City parks such as upgrades and expansions if limited funds are available?
October- 0 Yes, 7 No/November -0 Yes,7 No
3. Does the Commission support dredging a portion of the lake, in lieu of the entire lake, as a
reasonable alternative to reduce project costs?
October- 4 Yes,3 No/ November-0 Yes, 7 No
4. Does the Commission support use of portions of the park for deposition of dredged material,
and if so, where?
October- 6 Yes, 1 No/November-4 Yes, 3 No
(The Commission was clear that disposal was in the Active Park area not the Nature
Preserve. It would be reasonable to assume before the park was used to accommodate
dredging spoils, they would want to see a specific plan of the disposal proposal.)
5. Does the Commission support creation of islands or wetlands in the lake using the dredged
material?
October- 1 Yes,5 No, 1 Undecided/November - 0 Yes, 7 No
6. Does the Commission support a long term (over 10 years) project if necessary as a
reasonable alternative to reduce project costs?
October-2 Yes,4 No, 1 Undecided/ November - 0 Yes,7 No
7. Does the Commission support buying adjacent land for deposition of dredged material
disposal?
October- 6 Yes, 1 No/November -3 Yes,4 No
The change in the results of the two polls could be attributed to additional time for the
commissioners to consider the questions or it could have resulted from the testimony of the
public at the second meeting.
The Commission expressed mixed feelings about dredging. They are concerned about the cost
and understand that the cost will just continue to rise if the project gets put off. However, they
are also very concerned about the impact of dredging on the surrounding community and
activities at the lake.
PUBLIC INPUT - ATTACHMENT 4
One clear message from the Commissioners was the unanimous agreement that dredging should
not come before other Parks and Recreation needs when funding is limited.
Citizen Input
At the goal setting sessions a few citizens have attended meetings to date and the majority speak
in favor of dredging. There appears to still be some misconceptions that dredging will take care
of mosquito problems or flooding, which it will not.
The preference of citizens speaking out appears to be to dredge the entire lake in a relatively
short period of time, removing the spoils from the park. The creation of islands or wetlands has
not been well received because it reduces the amount of open water, and raises concerns that it
would increase the breeding grounds for mosquitoes.
At the two Council Study Sessions 16 different citizens spoke in favor of dredging, three lived
outside the Oceanaire neighborhood, two spoke regarding concerns about mosquitoes, and three
about flooding.
I:rmurfdl agenda reWnstpub is works car120091opM110 H dredging1a4-public inpucdx
't31.2 -I!
DREDGING AND DISPOSAL ALTERNATIVES - ATTACHMENT 5
Dredging Alternatives
The alternatives presented by the consultant in the Engineering Analysis are a mix of quantity,
technique, drying and disposal, giving resulting impacts, cost and duration. The alternatives are
presented in the Engineering Analysis as a way of looking at the project, but are by no means the
only permutations available. Below is a summary of the information provided in detail in the
Engineering Analysis
Alternative 1 - Full scale dredging with near shore placement and habitat restoration
This alternative uses a closed clamshell to scoop the material from the bottom. The closed
clamshell minimizes fall back of material into the lake in comparison to an open loader such as
those we might use in the street. The material is placed on barges and taken to shore.
At the shore, the material is dried and left in place on a large area of the park. The area
proposed is a 25 acre site in the Nature Preserve which, while dominated by non-native grasses,
is also home to several sensitive botanical species. Significant impact can be expected. The
alternative would then include the importation of topsoil for plant reestablishment.
Estimated duration - 12 months. Restoration would take several years.
Estimated cost- $6.9 Million
Altemative.2—Dredging with off-site commercial or agricultural beneficial reuse
A special hydraulic dredging and dewatering device is used for this alternative. The electric
remote ability of the unit allows 24 hour dredging. The material processed by this method is dry
enough to be trucked from the site without,separate drying beds. The number of trucks to
remove the material is estimated at 30 trucks a day. There is a high probability for concerns
resulting from the noise and disruption of the trucking activities. The City will need to locate a
receiving site where the material could be used.
If the City were able to acquire rights to dispose of the material on one of the agricultural sites
that already abuts the lake, the material could be removed directly to the agricultural area and
trucking from the park would not be required.
Estimated duration - 4 months to perform the dredging with continued hauling for 8 months to
dispose of the material.
Estimated cost - $6.2 Million plus any costs for reuse site
Alternative 3—Dredging with off-site landfill disposal
The material would be removed as in Alternative 2. The difference is in how the material is
disposed of. In this alternative, the material is taken to the land fill to be used as cover or paid
for as waste.
y
DREDGING AND DISPOSAL ALTERNATIVES ATTACHMENT 5
Estimated duration - 4 months to perform the dredging with continued hauling for 8.months to
dispose of the material.
Estimated cost- $7.5 Million
Alternative 4—Dredging with combined on-site island and wetland creation
The material is removed as in Alternative 1 with the closed clam shell. The material is dried on a
4 to 10 acre area of the park. Special berms -are constructed in the lake and the material
reintroduced to the lake to form an island. A portion of the material can be directly deposited
back in the lake without drying to create wetlands. Some existing wetlands will be lost if
expansion of the existing peninsula is done, but new wetlands would be created in the upper area
of the lake..
Estimated duration - 12 months
Estimated cost $8.6 Million plus any costs to acquire rights to deposit material in privately
owned portions of the lake
Alternative 5 —Limited dredging with near-shore placement.and habitat restoration
This alternative is a reduced version of alternative 1 or 2. It requires an on shore area of 10 to 15
acres combined drying and fill area.
Estimated duration—8 months
Estimated cost - $3.9 Million plus land cost if placement occurs off park property
._ Alternative 6—Limited dredging with expanded wetland.creation -
Altemative 6 is a reduced Alternative 4 with wetland creation, but no island creation. This
eliminates the need to dry the material if it is to be used for wetlands.
Estimated duration—6 months
Estimated cost - $6.3 Million
Incremental Dredging—Not covered in Consultant's Engineering Analysis Report
The City would purchase a small electric suction dredge and operate it remotely using a cable
system. The slurry would be pumped to the shore where a system of drying ponds would be set
up. The slung would be retained long enough in the pond system to allow the solids to drop out
and the water to flow off. The water would have to be sampled and tested prior to returning it to
the lake. With a City staffed operation, activity would occur every year until the work was
completed. Based on use of 5 acres of the Nature Preserve for drying beds, drying time and
seasonal constraints, it would take approximately 10 years to remove the sediment that has
accumulated in the lake to date. Given the duration of the initial dredging, the lake would
accumulate additional sediment during that time and the dredging operation would have to be
undertaken regularly to maintain the lake depth.
DREDGING AND DISPOSAL ALTERNATIVES _ ATTACHMENT 5
Staffing for this operation would require at least a two people, with significant oversight, given
the complexity and regulatory issues involved. One person would take on the entire
responsibility for the dredging equipment and operation, including construction and maintenance
of the drying beds, purchase of equipment, locating and arranging for disposal of the solids and
the hiring of temporary help as needed to assist them with the operation of the dredge and drying
facility.
Costs - The initial cost to construct the drying beds, drains and purchase equipment is estimated
at $550,000. An additional $150,000 would be needed on an annual basis to fund the new
dredging staff position, provide temporary help, fund operation costs and fund equipment
maintenance and replacement costs. A dredge that would be able to work independently (off a
cable) would cost an additional $150,000 to $300,000*. It would also be a larger and more
powerful dredge to accelerate the operation and could do reed removal. The public has
expressed a strong desire to have the reeds removed because of the potential for mosquito
breeding. *(These cost estimates do not include disposal costs which are covered in more detail
below.)
Incremental Dredging - "Spin Dry" method using a Contractor
The material is dredged with an electric dredge. The slurry is pumped back to a mechanical
device on shore which removes the water and leaves the sediment. The "Spin Dry" equipment is
proprietary in nature, thus not available for purchase and use by the City. No drying beds are
needed, however some area is needed for stockpiling. Contracted dredging would occur on a
periodic rather than annual basis, as funds were available and to reduce mobilization costs.
_. Incremental Dredging Alternatives - 10 Year cost summary-for ftill lake dredging:
Method Frequency Annual Cost Total Cost
City Staffed Annual project Dredge, w/Piping & Cabling: $200,000 $ 550,000
for 10 years Loader & Pickup: $ 100,000 "'
Pond Construction Costs: $ 250,000 (1)
Annual Staffing & Operation: $ 150,000 $ 1;500,000
$ 2,050,0001'1
Contract 2 projects - Annual set aside amount: $620,000 $ 6,2009000(2)
1 every 5 years
First year only costs
(2) Does not include disposal costs—see below
In summary, on an annual basis, assuming a worst case for disposal costs as outlined in the next
section, dredging the lake could cost up to an estimated $705,000 to $1,120,000 per year over a
ten year period. (Total Cost above plus $5,000,000 disposal discussed below, divided by 10
years.)
Fa ��
DREDGING AND DISPOSAL ALTERNATIVES ATTACHMENT 5
Initial Study Project Description
Incremental Dredging—Partial Lake Dredging
Worked would be accomplished as described above for the City operated electric dredge: Only
the central portion of the lake and some areas of the southern part of the lake, would be dredged.
Assuming material would fust be disposed of in the active park, then through wetland creation,
and lastly by off site landfill disposal, the costs over the 10 year operation would be as follows:
Year 1 Costs: Dredge, cabling & Piping $200,000
Pickup & Loader $100,000
Pond Construction $250,000
Staff $135,000
Disposal at on active park $42,000
Operations & hydroseeding $20,000
Total: $747,000
Year 2 Costs: Staff $135,000
Disposal at on active park $42,000
Operations & hydroseeding $20,000
Total: $197,000
Year 3 Costs: Staff $135,000
Wetland Preparation Construction $1,200,000
Wetland Disposal $170,000
Operations & planting $20,000
Totals $1,525,000
Year 4- 7 Annual Costs: Staff $135;000
Wetland Disposal $170,000
Operations & planting $20,000
Annual Total: $325,000
Year 8-10 Annual Costs:
Staff $135,000
Landfill Disposal $81,000
Operations $15,000
Annual Total: $231,000
10 Year Total: $4,462,000
Disposal Alternatives
The consultant discussed several options in their report for the disposal of the material. To
recap, these are; 1) send the material to the landfill 2) barge the material out into the ocean
z3a -a3
DREDGING AND DISPOaAL ALTERNATIVES ATTACHMENT 5
dispose of it there, 3) deposit it on land, either a parcel leased or owned by the City, including
the park property or 4) deposit it back into the lake to create wetlands and islands.
Disposal costs are a significant part of the overall costs and it could be cost effective to purchase
property for the disposal and sell it after the work is complete. This would not address future
dredge disposal needs. The other option relating to land disposal is to have a dredging contractor
be responsible to locate a disposal site and haul it.. The availability of property for the
contractor's disposal would make the cost of dredging difficult to predict. Costs would range up
to $5,000,000 for disposal of the current accumulation in the lake in addition to the other costs
outlined to complete dredging. This cost assumes disposal at the landfill.
The active park can accept approximately 10-20% of the total amount estimated to be dredged.
These would appear as two mounds of approximately 12 feet in height relative to the
surrounding area and would be located adjacent to the memorial grove and to the playground.
Drainage facilities may have to be included in at least one of these areas as there are numerous
drainage ways in the park. The mounds would need to be amended to some degree and planted
to prevent erosion and blend them better into the park.
Ocouncil agenda repodstpublic works cark200916#19911011 dredgingla5-dredging alts.doc
8a -OUT
ATTACHMENT 6
Excerpt from Laguna Lake Dredging Initial Study (ER 31-06)
Description of the Project:
Laguna Lake is a shallow urban lake located in the City of San Luis Obispo, California. It is currently
surrounded by residential development to the southwest,ranch land to the northwest,the municipal
Laguna Lake Park to the northeast,and Madonna Road to the southeast(Figure 1 and Figure 2).
The major open-water portions of the lake,known as the Central Lake and the Southeast Arm, cover a
total area of approximately 23 hectares(57 acres.) In addition, there are approximately 10 hectares (25
acres)of open water and 27 hectares(67 acres)of wetland habitat in adjoining areas, including the
Prefumo Inlet,the Northwest Inlets,and the Peninsula Inlet(Figure 2).The main body of Laguna Lake
has not previously been dredged, although the Prefnmo Creek inlet has been periodically dredged in the
past by the City, County and local contractors to remove deposited gravel material coming in from
Prefumo Creek.
The area now occupied by Laguna Lake was historically a low-lying area that collected storm water
drainage from the surrounding fields and hillsides. In 1963,nearby Prefumo Creek was rerouted to
drain into the lake area. Continued siltation from the creek began to gradually fill the lake, and so a
small dam was subsequently built at the southeastern end of the lake, near Madonna Road, to raise the
lake's water level. In spite of these measures, the lake has gone nearly dry twice during the last 20
years. In order to maintain the lake's suitability for recreational purposes and wildlife habitat, the City
is proposing dredging as described herein as part of the broader management plan for the park.
Dredging of the lake has been studied extensively over the last 25-30 years. The following documents
have been prepared and the findings are incorporated into the proposed project description and
associated studies.
• Archeological Subsurface Testing at the Laguna Lake Project(Heritage Discoveries (2007)
• Archeological Surface Survey for the Laguna Lake Project; (Heritage Discoveries (2006)
• Ecological Resources and Potential Impacts of Dredging Operations at Laguna Lake;LFR Inc.
(2003)
• Engineering Analysis of Dredging and Disposal Alternatives at Laguna Lake; LFR Inc. (2001)
• Characterization of Sediment and Water at Laguna Lake; LFR Inc. (2001)
• Rare Plants, Vegetation, and Flora of Laguna Lake Park; Keil(1996)
• Laguna Lake Park Master Plan; City of San Luis Obispo(1993)
• Geotechnical Report Laguna Lake Dredging Project; Earth Systems Consultants (1992)
• Wildlife of Laguna Lake Park Relationship to Proposed Dredging;Michael T. Hanson(1992)
• Laguna Lake Management Program; City of San Luis Obispo(198 1)
• Final EIR—Laguna Lake Management Program;City of San Luis Obispo(198 1)
Through the most recent studies,conducted between 2000 and 2007,the City has evaluated a number
of dredging alternatives including the use of different types of dredging equipment, different methods
to dry the dredged material, and different end uses for the dredged materials.The proposed project is a
hybrid of previously studied approaches to meet the project objective of maintaining suitable lake depth
while limiting costs.The proposed approach utilizes techniques to avoid and minimize potential
impacts through all phases of the dredging operations. As part of the impact avoidance and
minimization approach, the total volume of dredging has been reduced from approximately 230,000
cubic meters(300,800 cubic yards)to approximately 115,000 cubic meters(150,400 cubic yards.)
Lia as'
ATTACHMENT 6
The proposed project would entail the use of an electric suction(hydraulic)dredge to remove sediment
from the bottom of the lake. Most areas of the lake would be dredged including the main body and
Prefiuno arm, though setbacks have been established that prohibit dredging activities near the lake
banks to prevent potential bank destabilization. The dredge would operate during approximately 22
weeks per year as necessary during the dry season from June through October. As much as 15,300
cubic meters(20,000 cubic yards)would be dredged from the lake each year over a period of ten years
to achieve a total removal of approximately 115,000 cubic meters of material.The overall rate of
dredging is restricted primarily by the drying time of the fine grained dredged material.The dredged
material would be pumped via temporary piping from the dredge to an approximately two hectare(5
acre)upland drying facility to be constructed in the undeveloped portion of the park(Figure 2). The
drying facility would be comprised of bermed areas created with earthen berms up to two meters(6
feet) in height.Dredged material would be pumped into the drying areas in approximately 60
centimeter(2 foot) lifts with approximately six weeks of drying time estimated to meet sufficient
dryness for hauling or rehandling for subsequent use. The final configuration and lift size within the
anticipated drying area is subject to input from the dredge contractor though it would not affect the
analysis of impacts. The percent water,particle size,and weather conditions (particularly wind and
temperature)will affect the drying time significantly. It is anticipated that the particle size of most of
the dredged material will be primarily clay and silt size(requiring a long settlement period)but that the
area is subject to a high percentage of days through the summer with strong winds and warm
temperatures. As the material dries, a crust is anticipated to form due to the clay nature of the
sediments from the main body of the lake(the Prefurno inlet area has historically been the only area
with larger sediment size). To maximize drying efficiency, it is anticipated that heavy equipment(e.g.,
bull-dozer or equivalent)will be used to turn over and wind-row the dredged material as it dries.
Decanted water from the drying facility would pass through a filter at the outlet of the drying facility
prior to re-entering the lake.The City has also considered the use of a mechanical dewatering system
that would eliminate the need for the large upland drying area and the associated impacts from its
construction and that would substantially reduce the drying time. However the system is more
expensive than the traditional approach proposed. Mechanical dewatering uses a self contained
centrifuge system that rapidly dries dredged material and immediately returns the water fraction back
to the lake. While the mechanical dewatering is feasible and will likely be evaluated from a cost
perspective by the City for implementation,this Initial Study addressed the upland drying facility to be
certain that all potential impacts of the project were evaluated from the most conservative("worst
case")perspective.
When dry, a portion of the dredged material would be placed within the parkin several locations as
described below and in the supporting documents for the project(referenced in Section 19 below),
however this analysis assumes that approximately 30,000 cubic meters of the material would be
trucked off-site for beneficial re-use(when suitable locations are available)or to a landfill where it
would be used for clean cover.
In developing this project description, the City has studied alternatives and options for each of the
principal components of the project (dredging methods,drying and rehandling options, disposal/reuse
options).The studied alternatives included the following:
Dredaine Methods
• Hydraulic dredging(hopper dredge, cutterhead dredge)
8a�6
ATTACHMENT
• Mechanical dredging(dipper dredge,bucket dredge)
• Specialty options(digger dredge for dry lakebeds)
Drying/Rehandling Options
• Dewatering basins and mechanical handling (using heavy equipment)
• Centrifuge decanting(specialty equipment)
Disposal Options
• On-site beneficial reuse(park amendments, wetland creation, island creation, habitat
restoration)
• Off-site beneficial reuse(agricultural fill,commercial fill)
• Off-site commercial disposal(class III landfill, ocean disposal)
After assessment of the potential options, five dredging alternatives were studied in greater detail:
• Full-scale dredging with near shore placement and habitat restoration
• Dredging with off-site commercial or agricultural beneficial reuse
• Dredging with off-site landfill disposal
• Dredging with combined on-site island and marshland creation
• Limited dredging with near shore placement
Based on input from the City Council, City Staff,and the consultants preparing the engineering studies,
soil and water studies,and the ecological assessment, this project description was prepared combining
aspects of several of the studied alternatives to result in a limited dredging project with combined on-
site and off-site use of dredged material. On-site re-use of materials would include creation of wetland
habitat(by filling an area of shallow open water) and through the creation of hills and berms within the
developed portion of the park that would be subsequently planted with lawn or landscaped for
recreational use. It is anticipated that the wetland creation component would utilize approximately
60,000 cubic meters (78,500 cubic yards)of dredged material.The material would be placed in the
peninsula inlet area and potentially in one of the small inlets of the Northwest Inlet area(Figure 2).
Technical details for this and all of the studied approaches are provided in the Engineering Analysis of
Dredging and Disposal Alternatives at Laguna Lake(LFR Inc., 2001). This document is on file at the
Public Works Department.
The final volume of material to be placed within the developed portion of the park and planted with
lawn would be determined in cooperation with the City's Parks and Recreation Department but it is
feasible that at least 25,000 cubic meters(32,700 cubic yards)of the fill could be utilized in this
manner. For example a round hill with a maximum height of six meters (20 feet) and a diameter of 125
meters (4 10 feet, resulting in a 10:1 slope)would utilize approximately 25,000 cubic meters of soil
without compaction. However,because the proposed annual dredging is limited to 15,000 cubic meters
(20,000 cubic yards)per year this approach would require that the first year of material for this purpose
be stockpiled until the second year of material is available, or that the material is placed and
temporarily stabilized(for erosion control)until the second year's material is dry and ready for .
placement on top. As such, several smaller features, each using less than 15,000 cubic meters may
simplify implementation and eliminate the delay in completion for the construction for landscaping. The
impact analysis herein assumes that 25,000 cubic meters of material will be placed within the already
developed portion of the park.
The remaining dredged material would be taken off-site for beneficial re-use if suitable sites are
available such as agricultural fill or commercial fill. If no such beneficial reuse sites are available,the
Sa -a-4,
ATTACHMENT 6
material would be taken to a commercial landfill. Material taken off-site would be hauled from the
dewatering/rehandling facility through the park to Los Osos Valley Road and east to highway 101
(Figure 2). Off-site hauling of 30,000 cubic meters(40,000 cubic yards)of material would require
approximately 750 truck loads. It is anticipated that the hauling could be completed in one month with
approximately ten truck trips per day. The number of trucks employed and the total round trip haul
time will affect the potential number of trucks per day and it is expected that the number of days of
hauling could be reduced significantly if desired by increasing the trucks per day, though that would
not affect the total number of trips. The impact analysis herein assumed up to 30 truck trips per day.
Through the inclusion of the proposed minimisation and mitigation measures,the project will be
"carbon neutral"with no net increase in greenhouse gas emissions.
Project Description
1. An archeologist will review the final plans for the dredging project to confirm that the final plans
do not conflict with the findings of this Initial Study and that there are no project activities in the
vicinity of site CA-SLO-605
2. An electric suction dredge would be used to remove sediment from the lake bottom. The
discharge would include a significant percentage of water(80%to 90%)that would flow
passively back to the lake from drying areas.Use of an electric system would minimize noise and
air emissions.
3. The dredge would operate on cables and may or may not have an operator on the dredge itself.
4. Most of lake would be dredged(including the Prefumo Arm and removal of the delta at the mouth
of the Prefumo Arm)
5. The project would'be conducted seasonally over approximately ten years. Periodic or low volume
dredging would occur as follow up to maintain the lake depth.
6. Approximately 15,000 cubic meters of material would be removed per year.
7. The operation would occur for approximately 22 weeks per year through the summer season with
most of the time required for drying. The actual dredging component would likely be completed
within four weeks per year.
8. State and federal regulatory agency permits would be obtained as required.
9. Approximately two hectares (5 acres) of the upland area adjacent.to the lake would be used for
settling, drying, and rehandling operations.
10. Once dried for rehandling, a portion of the sediment would be kept in the developed park area to
form berms or hills which would be vegetated to blend into the park landscaping.
11. A portion of the dredged material would be placed on the peninsula area to raise its level and/or in
the adjacent open water area to decrease the depth and create vegetated wetlands.
12. The dredged material that is not re-used on-site,would be trucked off-site following drying to an
alternative disposal area(either a landfill for clean cover or potentially a construction site or other
beneficial reuse site as available and appropriate).
13. Haul routes will be marked with signs notifying park visitors of truck hauling activities and park
speed limits enforced.
14. Berms for drying beds would be created in the upland area using primarily onsite materials
potentially with some import. The berms would be approximately two meters high.
15. Noise level monitoring of equipment will occur to ensure it is below required levels.
16. Construction and handling activities will only occur during normal working hours on weekdays.
8C ag
ATTACHMENT
17. Filters would be installed at the water outlets of the drying beds to ensure that water returning to
lake does not contain excessive suspended sediment.
18. Water samples will be collected and tested to ensure compliance with local, state and federal
standards pertaining to Total Dissolved Solids limits. Adjustments will be made to the dewatering
operation if needed to maintain standards.
i
ATTACHMENT 7
RESOLUTION NO. (2009 Series)
A RESOLUTION OF THE COUNCIL OF THE CITY OF SAN LUIS OBISPO
APPROVING THE MITIGATED NEGATIVE DECLARATION
FOR THE LAGUNA LAKE DREDGING PROJECT
WHEREAS,the City is pursuing the dredging of Laguna Lake; and
WHEREAS, an environmental review was prepared and made available for public
comment at the time and in the manner required by law; and
WHEREAS, the Council has reviewed and considered the Negative Declaration of
environmental impact for the project;
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of San Luis
Obispo as follows:
SECTION 1. Environmental Determination. The City Council finds and
determines that the project's Mitigated Negative Declaration adequately addresses the potential
significant environmental impacts of the proposed project entitlements in accordance with the
California Environmental Quality Act and the City's Environmental Guidelines, and reflects the
independent judgment of the Council. The Council hereby adopts the Mitigated Negative
Declaration incorporating all of the mitigation measures listed below into the project:
Mitigation Measures:
1. Air Ouality Mitigation
a. AIR-01 Restrict Footprint: Reduce the amount of the disturbed area where possible.
b. AIR-02-Prevent Airborne Dust: A dust control plan shall be submitted to Air Pollution
Control District at least 30-days prior to construction and should consider employ
measures such as water trucks or sprinkler systems in sufficient quantities to prevent
airborne dust from leaving the site. Increased watering frequency would be required
whenever wind speeds exceed 15 mph. Reclaimed (non-potable) water should be used
whenever possible. All PM10 mitigation measures required in the plan should be shown
on any construction plans and monitored in the field to prevent transport of dust offsite.
c. AIR-03-Stockpile Management: If stockpiled soil remains on-site beyond the appropriate
drying period for reuse or disposal, spraying to prevent dust shall be required or the
material shall be adequately covered and secured.
d. AIR-04-Dust Control Implementation: Permanent dust control should be implemented as
soon as possible following completion of any soil disturbing activities.
R
Oce - 3o
1 i
Resolution No. (2009 Series) ATTACHMENT 7
Page 2
e. AIR-05-Extended Soil Stabilization: Exposed ground areas that are planned to be
reworked at dates greater than one month after initial grading should be sown with a fast
germinating native grass seed and watered until vegetation is established.
f. AIR-06-Vehicle Speed: Vehicle speed for all construction vehicles shall not exceed 15
miles per hour on any unpaved surface at the construction site.
g. AIR-07-Haul Truck Dust Control: All trucks hauling dirt, sand, soil, or other loose
materials are to be covered or should maintain at least two feet of freeboard (minimum
vertical distance between top of load and top of trailer) in accordance with California
Vehicle Code Section 23114.
h. AIR-08 -Roadway Dust Control: If visible soil material is carried onto adjacent paved
roads, install wheel_washers where vehicles enter and exit unpaved roads onto streets, or
wash off trucks and equipment leaving the site, and sweep streets at the end of each day.
Water sweepers with reclaimed water should be used where feasible.
Standard NOx Control Measures for Construction Equipment:
L AIR-09-Equipment Maintenance: Maintain all construction equipment in proper tune
according to manufacturer's specifications.
j. AIR-10-Fuel: Fuel all off-road and portable diesel powered equipment with Air
Resources Board certified motor vehicle diesel fuel (non-taxed version suitable for use
off-road.)
k. AIR-11-Diesel Equipment: Maximize, ,to the extent practical and feasible, the use of
diesel construction equipment meeting Air Resources Board's Tier III equipment.
1. AIR-12-Equipment Certification: Maximize to the extent practical and feasible, the use of
on-road heavy-duty equipment and trucks that meet the Air Resources Board's Tier III
certification standard for on-road heavy-duty diesel engines.
in. AIR-13-Idling of Diesel Equipment: All on and off-road diesel equipment shall not be
allowed to idle for more than 3 minutes. Signs shall be posted in the designated queuing
areas and or job sites to remind drivers and operators of the 3 minute idling limit.
n. AIR-14 Queuing of Haul Trucks: Queuing of haul trucks should be in location to
minimize impact to park visitors or neighboring residents.
o. AIR-15 Dredge: Electrification of dredging and pumping equipment is recommended as
feasible.
Greenhouse Gas Emissions:
8a -3 A
Resolution No. (2009 Series) ATTACHMENT 7
Page 3
p. AIR-16- Carbon Neutrality: Greenhouse gas emissions will be minimized through the use
of an electric dredge rather than a diesel dredge. The off-site greenhouse gas emissions
associated with the power production by the energy company (PG&E) will be offset
through participation in PG&E's Climate Smart Green House Gas offset program.
2. Biological Resources Mitigation
a. BIO-01 Project scheduling: Dredging activity in or within 23 meters of nesting areas will
be scheduled to avoid the bird breeding season (March 1 —August 31.) The initial upland
disturbance (creation of the drying facility) will be scheduled outside the bird breeding
season unless a nesting survey of the disturbance area is completed immediately prior to
disturbance and finds no nesting activity. Dredging is proposed to occur during the
summer to avoid the winter/spring breeding season of amphibians and to minimize the
likelihood of turtles in the bottom material within the dredging areas.
b. BIO-02 Field Design Placement: The City Biologist and the Biological Monitor
(discussed below) will walk the construction areas as drawn in the final design
specifications for the drying/rehandling facility to confirm that the location is the most
appropriate and maximizes resource avoidance. Minor adjustments to the disturbance
area may be made at that time to further reduce impacts. The City Biologist and the
Biological Monitor will work with the dredge contractor to determine the onshore landing
of the temporary pipeline to connect the dredge to the drying facility. The portion that
extends through the wetlands should be flagged in advance and should ideally remain in
place throughout the entire project to avoid temporary impacts associated with installation
and removal.
c. BIO-03 Biological awareness training: All contractors will participate in meetings be
designed to inform construction personnel of issues related to sensitive biological
resources potentially encountered during the project. These meetings will cover the basic
biology and identification of sensitive species occurring at the project site and cover on-
site protection measures of these species. State and federal laws protecting sensitive
species and penalties for non-compliance will also be discussed. Other topics such as spill
prevention and cleanup procedures and the location of areas off limits to construction
personnel will be addressed.
d. BIO-04 Work area delineation: All work areas will be delineated using silt fence, caution
tape, cones or other appropriate material to indicate where work is permitted to occur and
what areas are to be avoided. All work areas and avoidance areas will be discussed with
construction personnel during daily"tailgate" meetings.
e. BIO-05 Pre-construction wildlife surveys: These surveys are designed to detect sensitive
species occurring in the work area just prior to the start of dredging. Pre-construction
surveys allow for sensitive species occurring in the work area to be re-located as
appropriate, avoided, or protected by other means so that no take occurs as a result of
project activities. Pre-construction wildlife surveys will occur no sooner than two weeks
ria -3a
I
Resolution No. (2009 Series) ATTACHMENT 7
Page 4
prior to the start of the project. If a federally or state listed threatened or endangered
species is observed in the work area, the proposed activities in the area will be re-
evaluated by the contractor, the City and the Biological Monitor to ensure that no take
will occur. No disturbance activities are allowable in an area supporting a state or
federally listed species if the activity could result in take of the listed species.
f. BIO-06 Biological monitoring: The purpose of an on-site Biological Monitor is to ensure
that all sensitive species avoidance and protection measures agreed upon for the project
are properly implemented and maintained and to ensure that all work procedures are
conducted-in a manner that maximizes resource avoidance and impact minimization. The
Biological Monitor will also help to make on-site decisions regarding any sensitive
species identified during dredging operations. Monitoring is not required daily, but will
be required during all initial clearing and then periodically (at least weekly) through the
dredging or at the discretion of the Biological Monitor in coordination with the City. If at
any time a state or federally listed threatened or endangered species is observed in the
work are, all work activities will stop in the area. The Biological Monitor will be
responsible for a determination of what activities may proceed that do not pose the risk of
take of the listed species.
g. BIO-07 Exclusion fencing: Exclusion fencing (silt fence) will be installed to reduce the
likelihood of species such as southwestern pond turtles from entering the work areas
(particularly the settling ponds or along hauling roads). It is very important that silt fence
be installed properly and checked regularly by the Biological Monitor for issues requiring
repair or re-installation due to wind or mechanical impacts.
h. BIO-08 Avoidance areas: Areas of important biological significance to potentially
occurring sensitive species will be flagged or marked in some way to signify that no
project related activities are to occur within these areas. Avoidance areas will be
displayed in a figure and shown to the construction personnel during the tailgate
meetings.
i. BIO-09 Habitat replacement: Any impacts to sensitive native habitats will be mitigated.
On-site restoration of impacted plant communities will occur within the areas disturbed
by the project and/or within the park. Restoration activities including weed abatement of
otherwise high quality habitat and installation of propagules in areas where native
emergence is needed are appropriate and will be implemented under a habitat restoration
plan that identifies specific areas of impact and restoration. The restoration plan will be
reviewed and approved by the City Biologist. Temporary impacts of native habitat will be
mitigated on a minimum 1:1 basis. Permanent impacts to native habitat will be mitigated
on a 3:1 basis. Because the dredge will remain outside marsh habitat (minimum 23-
meters from the bank) and because the drying and rehandling facility will be constructed
in an area of non-native annual grassland, impacts to sensitive native plant communities
are expected to be minimal and temporary.
i
Resolution No. (2009 Series) ATTACHMENT 7
Page 5
j. BIO-10 Biological monitoring: An on-site Biological Monitor will review the final design
plans and will survey the disturbance area for the drying and rehandling facility with the
City Biologist when it is flagged in the field. The Biological Monitor will be on-site
during project activities to ensure that all sensitive species avoidance and protection
measures agreed upon for the project are properly implemented and maintained and to
ensure that all work procedures are conducted in a manner that maximizes resource
avoidance and impact rfminimization. The Biological Monitor will also help to make
implementation decisions throughout the project regarding any potential ecological issues
or to address sensitive species identified during the project operations. Monitoring isnot
required daily, but will be required during all initial clearing and then periodically (at
least weekly) through the dredging or at the discretion of the Biological Monitor in
coordination with the City. The Biological Monitor will have stop-work authority and
will do so should a listed species be identified in the work area. Work will not
recommence in the area until the Biological Monitor determines what activities may
proceed that do not pose the risk of take of the listed species. The Biological Monitor will
prepare regular monitoring reports during all phases of the work for review by the City
Biologist. Monitoring reports will briefly describe the work activities conducted during
the monitoring period, the status and/or condition of resource protection measures, and
any occurrences of sensitive species or events requiring the involvement of the Biological
Monitor.
3. Cultural Resources Mitigation
The project does not require mitigation for cultural resources impacts; however, the following
monitoring is required as a measure of caution.
a. CULT-01 Cultural resource monitoring: Prior to project implementation, an archaeologist
will review the final project plans for the Laguna Lake dredging project to confirm that
the final plans to not conflict with the findings or recommendations from the current
studies.
4. Geology &Soils Mitigation
a. GEO-1 Use appropriate shoreline setbacks and dredging deaths: ESC (1992)
recommended that no dredging be conducted within 15 meters (50 feet) of the shoreline
as mapped at maximum lake elevation. ESC (1992) further concluded that dredging shall
be conducted to depths of 0.76 meters (2.5 feet) at distances of 15 to 23 meters (50 to 75
feet) from the shoreline, and to depths of 1.5 meters (5 feet) at distances of more than 23
in (75 ft) ft from the shoreline. The current proposal incorporates a complete setback of
23 meters to avoid potential impacts.
b. GEO-2 Conduct pre-dredging reconnaissance of shoreline structures: ESC (1992)
indicated that it would be prudent to document the existing structures, fences, retaining
walls, and other improvements along the shoreline just prior to initiation of dredging.
Ba-3.
Resolution No. (2009 Series) ATTACHMENT 7
Page 6
This could facilitate recognition of any adverse effects related to dredging, and would
document pre-existing conditions.
c. GEO-03.Monitoring Program: An appropriately licensed engineer or geologist will certify
the final dredging design specifications and confirm that the proposed 23-meter setbacks
from the banks of the lake avoids the potential for significant impacts.
5. Hydrology and Water Ouality Mitigation
The project does not require mitigation for water quality impacts; however, the following
monitoring is required as a measure of caution.
a. HYDRO-01 - Monitoring Program: Testing return water for Total Dissolved Solids
content: Samples of return water from the dredge operation shall be collected and tested
regularly or as needed to insure compliance with local, state, or federal standards
pertaining to allowable Total Dissolved Solids limits. If test results show unacceptable
amounts of Total Dissolved Solids in the return water; then the release of return water
will be stopped to allow for changes to the system that will result in returning the Total
Dissolved Solids to acceptable levels upon start-up of operations.
6. Noise Mitigation
The project does not require mitigation for noise issues; however, the following monitoring is
required.
a. NOISE-01 Monitoring Program: Periodic noise level monitoring: The noise levels
produced by equipment working on the project shall be monitored routinely throughout
the project. Equipment or activities found to be exceeding noise standards established in
the noise ordinance are to be prevented from conducting further work on the project site
until such time as it can be demonstrated that they can operate below such standards.
7. Recreation Mitigation
The project does not require mitigation for recreation impacts; however, the following
monitoring is required as a measure of caution.
a. REC-01 Monitoring Program The allowable work periods (regular business hours on
weekdays with no weekend or holiday work) shall be a part of the contract for the project
and compliance shall be monitored by City Staff as part of standard monitoring for
construction projects.
8. Transportation Mitigation
The project does not require mitigation for transportation issues; however, the following
monitoring is required as a measure of caution.
Ba:35
i
Resolution No. (2009 Series) ATTACHMENT 7
Page 7
a. TRANS-01 Monitoring Program: Installation of appropriate signage identifying haul
routes and notifying park visitors of truck hauling activity, and the required speed limit
shall be a part of the project contract and shall be monitored by City Staff as part of
standard monitoring of construction projects.
Upon motion of seconded by
and on the following vote:
AYES:
NOES:
ABSENT:
The foregoing resolution was adopted this day of 2009.
Mayor David F. Romero
ATTEST:
Elaina Cano
City Clerk
APPROVED AS TO FORM:
onathan P well
City orney
From: Dick Bray [mailto:lsloguy@charter.net]
Sent: Tuesday, November 17, 2009 9:00 AM
To: Walter, Jay
Cc: Romero, Dave
Subject: Laguna Lake Dredging
Barbara Lynch was kind enough to send concerned property owners a notice of the City Council
meeting regarding the dredging of Laguna Lake.
My wife and I have lived on property bordering Laguna Lake for the past twenty-one years.
During this time we have seen the lake slowly deteriorate.What was once a lovely body of water
frequented by many small boaters, fisherman (yes there once was fish)canoes, wind surfers, and
many other activities, as well as an abundance of wild life, is now shallow, muddy, and on the
verge of being lost all together.
As the lake has slowly filled with dirt washed down from the surrounding hills most of the
recreational activity is disappearing, and the wild life is being reduced as well.
We view Laguna Lake as a'city treasure".A beautiful resource the likes of which very few cities
could claim within their city limits.
We would fully support a dredging project and any other efforts to maintain and improve the lake
and surrounding park area. Please, before it becomes too late.
We thank you for your attention and efforts.
Mr. and Mrs. Richard Bray
958 Vista Collados
San Luis Obispo
HAnD CDp �rr1�4lL
RED FILE ; C�COUNCIL Q'CDD DIR
a � Q- 0-FIN DIR
MEETING AGENDA �' RNA D-FIRE CHIEF
DATE /-D ITEM # aa. O-CLERK CRIG ErPW DIR
" 0 DEPT HEADS POLICE CHF
ry ply C�REC DIR
� a_TJTIL DIR
? HR DIR s
tiLWrtM� C-OU UL
Cert INsk,
C LC-k.*-
RECEI ED
NOV 17 2009
SLO CITY CLERIC