HomeMy WebLinkAbout04/07/2009, C4 - CHORRO-HATHWAY WATER AND SEWER IMPROVEMENTS, SPECIFICATION NO. 90640 council Mfi�D� 4/7/2009 acEn6A REpoRt C I TY O F SAN LU I S O B I S P O FROM: Jay Walter, Public Works Direct Carrie Mattingly, Utilities Director Prepared By: Jennifer Lawrence, Engineering Technician SUBJECT: Chorro-Hathway Water and Sewer Improvements, Specification No. 90640 RECOMMENDATION 1. Approve a Contract Change Order for additional work on the Chorro-Hathway Water and Sewer Improvements Project, Spec No. 90640. 2. Approve a transfer of funds in the amount of $43,500 from Water Distribution System Improvements Main Account and $132,600 from the Sewer Collection System Improvement Main Account to this project's account. DISCUSSION Background On June 17, 2008, the City Council authorized inviting bids for the Chorro-Hathway Water and Sewer Improvement Project, Specification Number 90640 and on July 10, 2008 bids were opened. R. Baker, Inc. was the lowest bidder and on July 29, 2008 the,City Manager awarded a contract to R. Baker, Inc. in the amount of$770,570. See Attachment 1. A pre-construction meeting was held on August 21, 2008 and construction work began on September 2, 2008. The project included water and sewer improvements on Hathway Avenue between Montalban and Murray. It also included installing a new waterline on Chorro Street between Mission and Lincoln and on Chorro Street between Palm and Mill. The work on Hathway and the section on Chorro between Palm and Mill have been completed. During excavation for construction of the line on Chorro between Mission and Lincoln, it was discovered that the existing utility lines deviated significantly from where archived records showed them to be. Because of this, and the fact there are three existing sewer mains in this stretch of Chorro, as well as a number of private underground utilities, there is not enough room to place the new waterline and maintain required separation standards between water and sewer lines as originally designed. Construction Change Order Per the City's purchasing policy, a change order of this size must be approved by the City Council except under special emergency circumstances. As outlined in the change order itself, the problem requiring resolution is the result of utility overcrowding in this section of street (see Attachment 2). Chorro Street has so many utility lines in it, that there is no room for the new main to be placed and 1 q,l Chorro-Hathway Water and Sewer Improvements, Specification No. 90640 Page 2 still meet separation criteria. In order to accommodate the new main, some sewerline work has to occur to create space in the street. That work involves tying over existing sewer laterals to a deeper main line, removing one main and modifying and removing several manholes. The final project goal is still the same; complete the replacement of a transmission main in the City's water system. Because this line serves as a transmission line, different from a distribution line, staff has heightened concerns regarding the quality and timeliness of the replacement work. This particular transmission line carries water from the Water Treatment Plant to the Downtown area. The proposed sewer main work covered in the change order was anticipated to occur as a future project. The larger two of the three sewer mains serve different areas of the City, and take different routes to the Water Reclamation Facility. Because of this, the two larger sewer mains must remain. The third sewer main in Chorro is substandard in size, has significant structural and root intrusion issues, requires an inordinate amount of regular maintenance by staff, and is essentially redundant. The removal of this line will benefit wastewater collection maintenance activities. Why now? If the work is completed under change order, there will be no further delay to the construction. Staff in the construction management area of Public Works has been reviewing project schedules in recent months to determine how best to handle anticipated workloads and minimize contract inspection to lower costs. With anticipated resource reductions in this area, project construction schedules are being more rigorously managed. If the City Council determines that it is preferable to create a new project and bid it, in lieu of authorizing a change order, it would take approximately 3 months before we would be ready to break ground again, putting the construction in the peak construction season. There will not be sufficient staff to inspect the work. The project would have to be shifted to the end of the year, where it would compete for priority with projects already scheduled for that time. Delivering a new project will require approximately 110 hours of staff time to prepare, bid and award a new contract. The reallocation of staff resources and the impact on delivery of other projects creates problems for overall project delivery when looking at the Capital Improvement Program as a whole, rather than on a project by project basis. As noted above, this project is a transmission, not a distribution line. Transmission lines carry water long distances from storage facilities and distribution lines are local service lines that provide water to properties. This particular line has experienced periodic breaks. Given that it is a 14" main, it releases significant water and produces considerable roadway damage when it breaks. Recent waterline breaks resulted in considerable overtime and nearly $30,000 in roadway repair costs. Delaying the construction for eight months, increases the Likelihood of an additional break occurring. Waterline breaks result in disruption to customers as crews shut off water service to isolate the break and reroute delivery around the failed area. The existing contractor has already procured the waterline pipe, under the original contract, and has performed pothole investigation work for the change. While in all likelihood the pipe will be fine, the material warranty will not carry to a different contractor should the City choose to bid the new work. If the pipe fails, the City will have to pay the costs associated with repairs during the warranty period, rather than requiring the contractor to make repairs at no cost to the City. The other option is to have the current contractor pay to ship and restock the pipe at the suppliers. This is more expensive than taking the pipe, but would eliminate the warranty issue with a new contractor. C q—,�- Chorro-Hathway Water and Sewer Improvements,Specification No. 90640 Page 3 The current contractor. R. Baker Construction, is an experienced pipeline contractor. Staff has been pleased with the level of cooperation they have received and the quality of the work completed. In addition to the other information conveyed above, this has been a consideration in staff's recommendation to proceed with the work as a change order. CONCURRENCES The Utilities Department has reviewed the cost proposals and discussed the various implications of each approach and concurs with proceeding under contract change order. The Wastewater Collections Division had previously identified these sewer improvements as a future project and they concur with this request to perform the work sooner rather than later. FISCAL IMTACT R. Baker Inc. submitted a proposal for the change order work of$210,275. This is in addition to the contract work that is yet to be completed. This compares well with the estimate of$200,000 prepared by staff independently. Cost increases for the water construction reflect additional pipe needed and the lengthening of a number of water services. The necessary sewer main construction as well as striping and additional potholing account for the remaining costs. Because of the high cost associated with the work, in addition to completing their own estimate, staff engaged an independent contractor to prepare a cost proposal to be used as a comparison with R. Baker Inc.'s proposal. This estimate was less than R. Baker's to complete the project under contract change order. Actual bids that might be received if the City put the remaining work out to bid are unknown and could vary one way or the other from the estimate provided. However, the City would be obligated to buy the pipe and fittings already purchased for the project and handling and delivery of pipe to City property under the current contract, or pay to have it shipped and restocked. There are also other minor investigation costs and storage costs that have been incurred during the time staff has been preparing the change order for approval, with the total costs summarized below. The table assumes the amount spent to purchase the pipe, in the event Council does not approve the change order, will be recouped through reduced bid costs. cq-3 Chorro-Hathway Water and Sewer Improvements, Specification No. 90640 Page 4 Water Fund Sewer Fund Total Cost to Complete Project and Change Order: $355,520 $147,194 $502,714 -includes the $210,275 change order plus original project work not yet completed Cost to Closeout Existing Contract: $30,000 $0 $30,000 Estimated Cost to Complete New Project: $329,259 $126,345 $455,604 Estimate-End Contract& Bid Work: $359,259 $126,345 $485,604 Cost Difference (Change Order vs Bid) -$3,739 $20,849 $17,110 Original Construction Contract: $561,489 $209,081 $770,570 Existing Contingencies: $84,223 $31,362 $115,585 Costs to Date: -$298,102 -$211,133 -$509,235 Remaining Funding Available: $347,610 $29,310 $376,920 Additional Funding Required-Change Order*: $43,462 $132,603 $176,065 Additional Funding Required-Bid*: $47,575 $109,670 $157,244 *Includes 10%contingencies for remaining work The "Additional Funding Required" items detail the additional funding staff anticipates will be needed to complete the new work, either as part of a change order on the existing contract, or by bidding a new contract. The Water Distribution System Improvement account has a balance of$774,665 to support the water portion of the project. The Wastewater Collection System Improvement account has a balance of$1,169,580 to support the sewer portion of the project. ALTERNATIVES Reject the Contract Change Order and rebid the remaining portion of construction as a new project. As discussed in the report, staff does not recommend bidding the new work due to the impact on design and construction schedules, the risk of pipe breakage and resulting emergency repair costs, and the unknowns associated with obtaining a new, low bid contractor. Staff felt the resulting price difference, accounting for all costs associated with closing the contract with R. Baker and the risks associated with a new contractor,was not significant enough to warrant finalizing the existing project and re-bidding the remaining portion as a new project. Based on several considerations, staff recommends retaining the services of R. Baker, Inc. to complete the project, including the additional work specified in the Contract Change Order. cq-q Chorro-Hathway Water and Sewer Improvements,Specification No. 90640 Page 5 If the Council prefers staff to bid the remaining work as a new project, staff recommends the Council authorize staff to advertise the bids and allow the City Manager to award the contract if the low bid is below$460,000(Estimated Cost to Complete Project.) ATTACHMENTS 1. City Manager Report Authorizing Award 2. Contract Change Order 3. Additional Work Proposal AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE Change Order Plans g:Wnff-mpon agendas.minu=\-cwVDD9kip\0640 chor hathway wamr and scwcr improvcmcrosl90W car ccoldoc Attachment 1 CAO REPORT Final CAO Approval Approver Name Date Approved City Administration Shelly Stanw cl: July 30, 2008 Reviewer Routing List Reviewer Name Date Reviewed City Attorney Jonathan Lowell July 29,2008 City Engineer Barbara Lynch July 29,2008 Finance& Information Technology Bill Statler 7-29-08 Utilities Gary W. I lenderson July 29, 2008 July 29, 2008 FROM: Jay Walter, Public Works Director JVW PREPARED BY: Jennifer Lawrence,Engineering Technician SUBJECT: Chorro-Hathway Water & Sewer Improvements Project, Specification No. 90640 RECOMMENDATIONS 1. Award a contract to R. Baker, Inc. in the amount of$770,570 for the Chorro-Hathway Water and Sewer Improvements Project, Specification 90640. 2. Approve a transfer of$660,362 from the Water Distribution System Improvements Main Account and $240,593 from the Sewer Collection System Improvement Main Account to this project's account. DISCUSSION On June 17, 2008, the City Council authorized inviting bids for the Chorro-Hathway Water & Sewer Improvements Project, Specification Number 90640 and authorized the CAO to award the project if the lowest responsible bid was within the Engineer's estimate of$933,725. Ten bids were received and opened on July 10, 2008, six of which were under the Engineer's estimate. R. Baker, Inc. of Oceano, California submitted the low bid of$770,570. See attached bid summary(Attachment 1). FISCAL IMPACT The water line replacement project was originally identified in the 2005-07 Financial Plan Appendix B, pages 77 through 81. The water lines designated for repairs are identified in the project list located on page 80. Funding for this project will come from the Water Distribution System main account. The sewer line replacement portion of this project is identified in the 2007-09 Financial Plan Appendix B, pages 3-132 through 3-135. Funding for this project will come from the Wastewater Collection System Improvements main account. C`"f -(O, I' CAO REPORT—continued page 2 of 2 Estimated Project Cost by Funding Sources Water Fund(500) Sewer Fund(520) 90227 90239 Total Budget Construction Costs: $561,489 $209,081 $770,570 Contingencies: 84,223 31,362 115,586 Archeological Monitoring(Water) 7,000 0 79000 Material Testing: 7,500 0 7,500 Printing: 150 150 300 Total for Construction: $660,362 $240,593 $900,956 Funds Available: $1,479,420 $1,618,816 ATTACHMENTS 1. Bid Summary 2. Council Agenda Report from June 17, 2008 3. Budget Amendment Request 4. Contract TACAO RcportsTublic Works\2008\CIP\90640 Chorro-Hathway Water and Sewer Imps\90640 eCAO Award.doc Attachment 2 CITY OF SAN LUIS OBISPO, CALIFORNIA CONTRACT CHANGE ORDER Change Order No.: 7 Sheets: 1 of 12 Date: 2-26-09 Project: Chorro—Hathway Water and Sewer To: R. Baker,lnc. Specification No.: 90640 As requested by: City of San Luis Obispo DRAFT ONLY You are hereby authorized and directed to make the herein described changes from the plans and specifications, and/or to increase or decrease contract quantities,as follows: While potholing for new 14"water main alignment,field inspection discovered the existing 14"water main was not located as expected.Project plans show a 5'separation between new water main alignment and the existing water main.The actual separation verified in the field is 1'. R. Baker completed remaining portions of contract work excluding 14"ductile water main installation on Chorro between Lincoln and Mission.The deferred portion of work has been redesigned by City staff and submitted to R. Baker,Inc for price adjustments.The City has agreed to the following price adjustments and additional cost associated with new design. (Please see attached spread sheet identifying additional cost.) AN labor,material and equipment associated with additional work on Chorro between Lincoln and Mission Shall be paid at lump sum. Total cost of additional work=$248,220.00 By reason of this proposed change?day(s)extension of time will be allowed. Total cost of change shall not exceed: $248,220.00 We,the undersigned contractor, have given careful consideration to the changes proposed and hereby agree, if this proposal is approved,that we will provide all equipment,furnish all materials, except as may be noted above and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above. Accepted by:Contractot's Authorized Agent Date accepted cl�ma4'�l2 27-0!Z Sub 'tted by—Residerif Engineer Date submitted Submitted by: Project Manager Date submitted 10 Approved by:City Engineer Date approved Change Order over$25,000 or funding required Change Order over$100,000 or funding required Date Approved: Date approved by City Council: By:City Administrative Officer G.\Reference-Lbtary\Fomrs-Templates\Construction\City_CCO.doc I Attachment 3 000000000000000000 0 M � O O O O O O O O O O O O O O O O O O O 00000 6100000000000 Lo In 0CO O O Lo M M CO M O O D Lo M Lo O O LO Il- rl T LO CT N V M CO CO I-- CO N M N O M O ^ T N E Lo M V CO M P. M Cj T M 0 Q rl -li Lo r cM N O .0 IZT N r T N T T r U O N C6 (•- Q O O O O O O O O O O O O O O O O O O 0 0 N O O O O 6 6 O O 0 0 0 0 0 0 0 0 LC) � r 0 0 U7 M M CO M O O co Lo M LO O O LO I7 LO N CC) C O CO CO I*- a0 , O N O 0) M h r �+ M r r cli fl cli O r ci' V Lo N r r N M D IA_ U) m m -j -j -j -j U) -j -j -j -j � LLD -j J W W —j —j —j J J W J —j -j —j -j W W .I 0 m T N N T T T T T C) T T T T N LO LO 0 + 0 3 C) a) v j m Ln co a3i o 0 0 a) c O J 00 7 C r C CO a C y O O 3 G a) U) . r 3 O C) r2 C - W y c c o c v a3 o m c m 0 m > U Z o = o o n a) N Uj o)s U t t > C X m w NY .YYiYY i oU mUU N = O W T `. ` 0 >0 >0 >0 >0 Q v N N fa C O E LL Q > m a) a) � » » OdmN cvv E c -O U 0 m m a) a) m a) a) a) U Q C C C C 7 0 C Ln E 3 torn 3 3 3 3 3 = c L a) m 0a) _ _ a) () ma) a) � � a) a) a) m0oic o � cnvvcncnv� cncnMrP: P: P: i= 2aW E d �+ 'C T N coV Lo CO 1- c0 O O r N M R Lo CO I� 0) ,a Z T r r r r r r r r M