CITY OF SAN LUIS OBISPO
FROM: Jay Walter Public, Works Director JpW
Prepared By: Bridget Fraser, Engineer III
SUBJECT: WATER RECLAMATION FACILITY: CLARIFIER 2 AND FACILITY
MAINTENANCE PAINTING PROJECT; SPECIFICATION NO. 90907
RECOMMENDATION
1. Approve the plans and specifications for "Water Reclamation Facility: Clarifier 2 & Facility
Maintenance Painting Project, Specification No. 90907" and authorize staff to advertise for
bids.
2. Authorize the City Manager to award the contract if the lowest responsible bid is within
Engineer's Estimate of$220,000.
DISCUSSION
This project involves maintenance painting of four areas at the Wastewater Reclamation Facility
(WRF). More specifically work will involve cleaning, surface preparation, and recoating of
Clarifier No. 2, the adjacent pump island, the secondary recirculation pump island, and the below
grade pump pit that houses the five (5) million gallons per day (MGD) pumps at the head works
station. This project must occur during a time when flows at the facility are at their lowest.
During low flow periods, one of the two primary clarifiers can be taken out of service and still be
able to process incoming flows. Flows at the facility are lowest during the summer months when
Cal Poly is out of session and the City's population is reduced. Most WRF projects are scheduled
to occur during this time period.
Clarifier No. 2 Coating
Clarifier 2 was originally constructed in 1941 as part of the original treatment plant. The clarifier
equipment and internal mechanisms were replaced in 1982 as part of an enlargement project. No
major work or recoating has occurred on this clarifier since this time. After 27 years of service,
the protective coatings on the walls and equipment are showing signs of deterioration. The
deteriorated coatings need to be replaced to protect the underlying surfaces from deterioration
and structural damage that would require costly repairs or replacement. Sacrificial anodes will
be installed to provide added protection to the submerged mechanical equipment. This project
also includes sealing of cracks between the clarifier tank and the perimeter gutter and smoothing
of the clarifier walls to better prepare the surface for coatings.
Facility Maintenance Painting
As stated above, the original facility was constructed in 1941 with several major expansions
occurring over the years. The facilities that were constructed over ten years ago are showing
On — k
Clarifier 2 and Facility Maintenance Painting Project Page 2
signs of rust and corrosion. This is not surprising due to the generally corrosive environment of
the facility. Routine cleaning and recoating of the facilities is essential to slow the rate of
corrosion and substrate deterioration. Recognizing this, WRF staff implemented an annual
maintenance painting program to provide routine painting of these facilities. Areas in need of
painting were identified and prioritized by WRF staff. The most critical areas will be addressed
with this project.
Bid Alternates-Award of Contract
Timing of this project is critical. In order to complete the clarifier coating before students return
mid-September the work must begin in early summer. However, if bids come in higher than
expected requiring staff to return to Council for an award in July; work would not begin until the
end of July. In this case, the contractor will not have enough time to complete the work before
students return. To stay on track, it is essential that the City Manager award the contract as this
would cutoff nearly a month of processing time allowing the work to begin the end of June or
first of July. To accommodate this, two of the painting sites (the Secondary Island and the Pump
Pit) are being bid as additive alternates to allow flexibility in awarding a. project. Staff
recommends that the contract be awarded by the City Manager including or eliminating the bid
alternates, as needed, to keep the award within the Engineer's Estimate of$220,000.
CONCURRENCES
The Utilities Department has reviewed and approved this project.
FISCAL IMPACT
The Clarifier coating project is identified in the 2005-07 Financial Plan on pages 110 to 112 of
Appendix B where $120,000 is identified for coating of Clarifier 2 in the 2007-08 project list.
The maintenance painting portion of the project is identified in the 2007-09 Financial Plan on
pages 3-152 to 3-155 of Appendix B where $100,000 is identified for facility maintenance
painting in the 2008-09 project list for a total budget of$220,000. The estimated project costs are
shown below:
Estimated Project Costs:
Design $ 7,500
Printing/Misc. $ 1,000
Construction Costs:
Clarifier 2 Coating& Repairs $ 170,000
Primary Island Coating $ 20,000
Pump Pit Coating (Add Alt.) $ 20,000
Secondary Island Coating(Add Alt.) $ 10,000
Total Engineer's Estimate $ 220,000
Contingencies @ 20% $ 44,000
Construction Management/Inspection @ 15% $ 33,000
Total Estimated Project Costs $ 305,500
Clarifier 2 and Facility Maintenance Painting Project Page 3
The estimated total project cost of$305,500 exceeds the budget of$220,000. For the most part
this is due to costs for construction management, higher than normal contingencies (20% rather
than 10% due to the high potential for unknowns), and the fact that the clarifier coating budget of
$120,000 is low when compared with bids received a year ago for a similar coating project.
However, given the competitive bidding climate, it is possible that bids could come in lower than
the estimate.
Due to the special nature of industrial coatings work and the anticipated heavy summer workload
of City inspection staff, it is recommended that inspection and construction management be
handled by Advantage Technical Services, one of the City's on-call inspection firms specializing
in industrial coatings work. A work order for this work will be issued under their current
contract.
Funding for this project is available in the Water Reclamation Facility Major Equipment
Replacement master account which has a current balance of$1,444,623. At time of award, funds
will be transferred from the master account and two completed project accounts to this project's
account via a budget amendment request.
ALTERNATIVES
Defer the Project. If corrosion is allowed to continue, the facility equipment and components
will continue to deteriorate to the point of requiring more costly replacement or repair.
ATTACHMENT
Vicinity Map
COUNCIL READING FILE
Specifications
[•.\council agenda neports\public works car\cip\90907 car adv cLuifier 2-painting.doc
C � -3
jn •
m"J
j
I
�'� •� •
CITY MAP
I • `; t •
CLARIFIER ..
MAINTENANCE PAINTING PROJECT
NO.SPECIFICATION =
..