HomeMy WebLinkAbout10/04/2011, C5 - DOWNTOWN PARKING SIGN REPLACEMENTS Council tl` tober
j acEnda izepoit °��rc�s
C I T Y OF SAN LUIS OBISPO
FROM: Jay D. Walter, Director of Public Work
Prepared By: Robert Horch, Parking Services Manager�/
Jake Hudson,Traffic Operations Manager
SUBJECT: DOWNTOWN PARKING SIGN REPLACEMENTS
RECOMMENDATION
1. Approve a new Capital Improvement Project(CIP) for replacement of downtown parking
enforcement signs.
2. Approve the transfer of$102,500 from the Parking Fund completed projects account to the
new parking enforcement signs replacement project.
3. Approve the plans and specifications for the Downtown Parking Sign Replacement Project,
Specification No. 91139.
4. Authorize staff to advertise for bids and authorize the City Manager to award the contract if
the lowest responsible bid for the Downtown Parking Sign Replacement Project is within
the Engineer's Estimate of$82,000.
SUMMARY
The original cost estimate for sign replacement to implement the Sunday parking change was
$11,000. The revised cost to replace these signs has increased to $102,500. The primary reasons
for the increase in costs are: 1). the need for federal standard, higher reflectivity signs, which are
more expensive, 2). An increase in the number of signs needed, 3). The need for larger signs which
require sign post replacement, and 4). The overall increase to the work scope requiring contracting
the work out, instead of using in-house staff. With this change included, implementing Sunday
parking operations is anticipated to bring an annual increase of$167,135 in net revenues.
DISCUSSION
Background
In response to recent changes in both Federal and State sign reflectivity requirements and expansion
of City parking services to Sundays, all regulatory parking signs in the downtown must be replaced.
The cost of replacement was originally anticipated to be $11,000. This estimate was based on an
estimate of the total number of signs, the assumption that the work could be completed internally by
City crews (with no labor costs), and no new sign posts would be needed. However, since that time
these assumptions have changed.
First, additional parking signs have been identified for replacement increasing the total number of
signs needing to be replaced. Second, having different or variable hours for Sunday parking
enforcement require larger signs to conform to State sign legibility standards. Larger signs require
C5-1
Downtown Parking Sign Replacements Page 2
replacement of the older poles and existing "P" posts for the installation of the new signs to fit.
Other non-parking related traffic control signs will be upgraded at the same time (paid by another
contract) so that downtown blocks will have a fresh appearance with new sign faces. Although it
was originally believed that the City streets crew could complete this work, their current prioritized
workload does not allow the crew to perform the sign removal and replacements within the required
timeframe. As a direct result, the only way to complete the project is to be contracted out with a
higher labor cost.
All together, these combined changes result in the proposed project cost increasing to an estimated
$102,500. The revised budget includes contractor removal of existing parking signs and posts on
downtown streets, contractor replacement of those signs and posts, and construction management
services.
Although the cost for replacing these signs has increased substantially, staff still recommends
proceeding with the project because new Federal Retroreflectivity requirements mandate that signs
be replaced by January of 2015, regardless of the changes in Sunday enforcement. Also the
expected net revenue from Sunday parking enforcement is approximately$167,000 annually which
will provide a return on the new estimated cost in little more than seven months.
Time Line for Sunday Parking
Based on the time lines outlined in the Request for Proposals (RFP) for sign replacement, staff
estimates that Sunday parking services will not begin until after the first of the year when the annual
downtown holiday shopping season construction ban is lifted. Staff plans to work with the
Downtown Association on a public outreach campaign in addition to providing notice to all of the
downtown churches, posting information on the City's website and Channel 20, and developing
press releases for the local news media.
FISCAL IMPACT
The Parking Fund's completed projects account has a current balance of $206,900. Staff
recommends a transfer of$102,500 from the Parking Completed Project account to the Downtown
Parking Sign Replacement Project. Following this transfer, $104,400 will remain in completed
projects for contingencies and to support other Parking Fund capital projects.
C5-2
Downtown Parking Sign Replacements Page 3
Estimated Project Cost by Funding Source
• Parking Completed
Projects(5 10 10 100- Total
99899999)
Construction Estimate: $821.000 $82,000
Contingencies: $8,200 $8,200
Construction Management: $12,300 $12,300
Total for Construction: $102,500 $102,500
Current Funds A vailable: $206,900
Funds Avail after Transfer. 5104,400
Sunday parking will net approximately $167,100 annually. The capital cost of $102,500 for the
project will mean the return on investment would be approximately seven and a half months from
date of implementation.
The table below provides information on the annual on-going costs and revenues estimates for
Sunday parking.
Table 1 —Sunday Parking
l pm - 6pm
5 hrs
Revenues
Structures 37,600
Streets 106,750
Lots 36,000
Fines 32,000
Revenue Subtotal 212,350
Expenses
Structures (15,800)
Lots (9,854)
Streets (19,561)
Expense Subtotal (45,215)
Total 167,135
ALTERNATIVES
1. Defer the sign replacement and subsequent implementation of the Sunday parking services.
The Council may decide to defer the sign replacement project and in doing so postpone
implementation of Sunday parking enforcement. Staff does not recommend this because
Federal requirements mandate replacement of these signs by January 2015, regardless of
changes in Sunday enforcement. Deferring implementation would result in an overall loss
of approximately $400,000 between now and January 2015 considering the expected
revenues and the cost of the signs.
C5-3
Downtown Parking Sign Replacements Page 4
2. Direct staff to alter the existing signs in place. The Council may direct staff to alter the
existing signs with the use of stickers or other similar methods. Staff has evaluated these
possibilities in great detail and does not recommend any variation of this approach. The new
information for Sunday enforcement requires additional information which will not fit on
the current sign panels and reducing the font will make the new parking requirements
unenforceable. In addition, altering the existing signs will not address the requirement for
the signs to be replaced by January 2015 as part of the Federal Sign Retroreflectivity .
requirements.
AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE
Request for Proposal/Special Provisions, Specification No. 91139
\\chstorc4\Team\Counci1 Agenda ReportsTublic Works CAR\201 ITarking\Sunday parking Signs v3.doc
C5-4
^ � U
council MCMORAnoum
RED FILE had oo • eniap:
a COUNCIL a CDD DIR
October 3, 2011 MEETING AGENDA a CITY MGR o FrrDIR
Cc� / _" ITEM # o AssrCM aPWDUt F
a ATiGRNEY oPWDIR
TO: City Council o C BMMRIG a POUCECHU
a PDI a PAW&RECDIR
o TRIBUNE a UTILDIR
FROM: Jay D. Walter, Director of Public Arks o NEW TIMES a HR DM
a SLocrrvNM a rouxcn.
VIA: Katie Lichtig, City Manager o CITY MGR
a CLERK
SUBJECT: RED FILE ITEM—SundayJParkinSign Replacements
There have been several questions raised for the Sunday Parking Sign Replacement project, primarily
regarding cost and federal retroreflectivity requirements. The purpose of this memo is to provide more
detailed information on these concerns.
Why is the cost so much higher than originally estimated?
The new estimate is significantly higher primarily for three reasons:
1. Contractor labor was not included in the original estimate because it was assumed at the time that these
sign replacements could be absorbed into the City Street Crew's regular workload. However, since the
scope of the project has increased,the Street Crew no longer has the capacity to complete this work in the
timeframe needed. As a result,the project must now be contracted out.
2. The original Sunday parking times proposed coincided with current weekday times, and the text
required for this fit on a sign size that could be accommodated on current sign posts. However, when the
time for Sunday parking was changed to be different from weekday times the sign size to accommodate
this text needed to be significantly larger and requires replacement of older posts in order to accommodate
the larger signs. This cost is substantially higher because it requires some concrete demolition and
sidewalk repair for the sign foundations.
3. The original number of signs was estimated using an incorrect downtown boundary. During preparation
of construction documents this error was identified, corrected, and the new estimate has been updated to
reflect an accurate accounting of parking signs.
The table below shows the approximate cost increase associated with each change in the project
assumptions since it was first estimated, and contract inspection and contingencies are included in these
costs.
Original Estimate1$ 1.000
City Maintenance Crew at Capacity Requires Contractor Labor +S44,000
Change in Sign Size Requires Post Replacements +$32,000
Increase in Total Signs +$15,000
Federal Mandate on Sign Sheeting Material: Retroreflectivity +$500
New Estimate $102,500
How does the price of contract work compare to the cost of City crew work for this project?
In order to try to create an "apples to apples" comparison, staff considered the new project scope, and
estimated the cost difference between City Crews and contractor at approximately $34,000 or 33%. The
significant difference between City and Contract work is due to Contractor's higher wages, overhead, &
material markups. Also for Contract work it is customary to include contingency and inspection funding
which would not otherwise be necessary for City Crews. It was preferential at the time to utilize City
crews due to the lower cost and because the cost is already incorporated into the City's operating budget.
However, because of the change in scope,the City crew is no longer the appropriate choice for that big of
a project.
City Staff i Contractor j
i
Staff Labor $28,000 Contract Labor $35,200
Materials $40,500 Materials+Markup $46,800
Contingencies $0 Contingencies $8,200
Inspection $0 Inspection $12,300
Total: $68,500 Total: $102,500
How do the Federal retroreflectivity requirements affect the project?
The US Department of Transportation has established minimum visibility levels(Retroreflectivity) for all
roadway signing. From a budgetary standpoint the project cost associated with these requirements are
negligible, rather deadlines established as part of this requirement affect when these signs need to be
replaced regardless of the project. Currently the City is required and in the process of replacing all non-
compliant signs Citywide by January 2015. Replacing them now means that the City would be in
compliance when the signs are replaced and would not have to do this work later. There is proposed
legislation to eliminate this deadline, however until this legislation is adopted the City must proceed
under the current regulations.
It is important to understand that regardless of federal deadlines or new Sunday parking hours
replacement of non-compliant signs will be required because these signs are in most cases faded to the
point where they are no longer legible and cannot be enforced. The images below are examples of non-
compliant signs in the downtown.
......vim
6
METERED
PARKING
QA.M. to 6P.M.
EXCEPT Osu" 5
Return on Investment
The City's Parking Enterprise Fund will see its return on the sign and post investment after 7.5 months
once Sunday parking is established. The net Parking Fund revenue forecast for Sunday parking is shown
in the table below:
Revenues $212,350!
Expenses -$45,215
Net Revenue $167,135.
The $167,135 annual net revenues break down to a monthly amount of $13,927. In a little under 7.5
months the City will recoup the $102,500 investment in the sign and post replacement. ($13,927 x 7.5 =
$104,453). It is also important to remember that the net revenue is intended to be accumulated in order to
afford the Palm Nipomo Parking Garage as the next major investment in downtown parking assets.
zT� GS
f�s,S�L'�Tri X62 ffpKCH �cJGL.
�D2N�y l�-ciaSorJ �!'LL,
From: Betty Sloan
Sent:Wednesday, October 05, 201111:13:56 AM (UTC-08:00) Pacific Time (US&Canada)
To:Council,SloCity
Subject: sign increase
I want to say thank you to the two members that seem to like to obey regulations and put their garbage
cans as required. They seem to be the same two that know that when they OK a charge of a certain
amount and then are told that it will be 10 times that amount, it is not proper. Thank you Kathy and
Dan. If you other three were going to remodel your kitchen and were given a price of$10,000,
agreed to that amount,and then told it was going to be$100,000, would you say, "Oh,well,go ahead,
That is what we planned". What a disgrace. You better not even think about trying to put another
vote for more taxes on any ballot. What do you not understand about people not having any money.
Betty Buchanan
5449630
From: womouthag120 <
To:j.marx <j.marxCcDslocitv.con
Sent: Sun, Oct 2, 2011 2:59 am
Subject: parking meters
To the Mayor and all Members - having just read the article regarding the
error made by the city estimators regarding the parking meter replacements, it
reminds me of the error made in the estimate for the parking lot some 10
years ago, when they used metric system for calculations. These are the
same government employees who retire at 45 and live off pensions. It's a
perfect example of how the pension system helps to maintain mediocrity in the
workplace. As for the actual issue of the meter replacements, it doesnt seem
fiscally appropriate to spend the money presently. Parking is so horrendous
downtown anyway, this might be an excellent rationale for delaying this
decision downsizing the city departments that maintain this high level of
expertise. As far as I have seen in the past 18 years here, the city planners
and all of the extended departments have priorities that are self serving and
would have been unemployed if they had worked in the private sector. Just
one voters thoughts. Thank you for your time and consideration.
anne keller
From: Kevin P. Rice
Sent: Thursday, September 29, 2011 10:33:54 AM (UTC-08:00) Pacific Time (US &Canada)
To: Council, SloCity
Subject: Sunday parking: Surprise cost of$102,500 for new signs
Regarding agenda item C-5 (10-04-2011): RED FILE
http://www.slocity.orgLityclerk/agendas/2011/100411/c5.pdf MING AGENDA
i
PATIE4Q ITEM #,e_
I support the option to DEFER sign replacement at this time.
A monumental staff blunder: "The original cost estimate for sign replacement to implement
the Sunday parking change was $11,000. The revised cost to replace these signs is
$102,500."
If that's not bad enough...
"Other non-parking related traffic control signs will be upgraded at the same time aid b
another contract) so that downtown blocks will have a fresh appearance with new sign faces."
STOP THE TRAIN, HONORABLE COUNCIL!
Prior to spending this amount of money, can we please ENSURE that Sunday hours are
agreeable and steadfast? You recall there was some bickering and 'splitting the baby' when hours
were decided, right? Let's make sure we're not going to change the signs for a number of years if
we must spend this money.
However, I suggest deferring this project until city staff can perform the work for a lower cost.
There is plenty of time before the federally mandated 2015 replacement.
Kevin P. Rice
(805) 602-2616
hard co cm9di.
c COUNCIL o CDD DIR
o CITY MGR a PITDTR
D ASST CM o FIRE CHIEF
o ATTORNEY o PW Dut CHIEF
CLEASfORIG
a PIRo PARKS&RECDIR
0 TRIBUNE o UTILDIR
o NEW TNES a AR DIR
o sLocrryNEWs oCOUNCIL
o CITY MOR
o CLERK
From: James Smith
Sent: Sunday, October 09, 2011 1:04:04 PM (UTC-08:00) Pacific Time (US & Canada)
To: Council, SloCity
Subject: Parking Meters
Hello City Council,
I have an issue on how your spending my and other residents of SLO money.
It doesn't take much intellect to figure that the $102000 spent for the sign replacement is way too
much to make the investment worth it.
To make it worth it all 130 meters would have to be used all 5 hours every Sunday for the next 3
years just to pay the investment back.
Please have more common sense and watch how your spening my money.
Jim Smith
26 year resident at 639 Leff Street
From: Devina Douglas
Sent: Monday, October 10, 2011 8:17:17 AM (UTC-08:00) Pacific Time (US & Canada)
To: Council, SloCity
Subject: Parking Sign Fiasco
Dear City Council,
I urge you to reconsider this fiasco you've create with the parking signs. You've got a
great staff working within the city, why not reward them in these hard economic times
by paying them the overtime to reduce these labor costs?
It is ridiculous that we would pay an outside contractor to do such simple work. Please
spare the city, and the taxpayers you are supposed to be serving, the expense and
humiliation of proceeding with the plan you approved at this last meting.
Thank you,
Devina Douglas