HomeMy WebLinkAbout04/04/1990, C-4 - PAYMENT ADJUSTMENT FOR LIQUIDATED DAMAGES IN WATER MAIN RECONSTRUCTION PROJECT - JOHN MADONNA CONST "�'I�IIIIIII�IIII yJ 1 � MING DATE: C� Q SlU�s �BISpO April 4, 1990 wa COUNCIL AGENDA REPORT ITEM NUMBBi: � FROM: David Romero, Public Works Director SUBJECT: Payment Adjustment for Liquidated Damages in Water Main Reconstruction Project - John Madonna Construction Company, Contractor CAO RECOMMENDATION: By motion, approve payment adjustment on liquidated damages item BACKGROUND: This water main reconstruction project involved construction in four different areas: Hathway/Montalban, Grand/Wilson, Warren/Patricia, and Flora/Alrita. Total cost of the project was $92, 302.91. It was very complicated and required careful planning and substantial organization in order to be completed within the specified time frame. The contractor completed the work long after the specified completion date. Therefore following provisions of the specifications, the City assessed liquidated damages in the amount of $9, 000 which were deducted from the final payment. John Madonna was slow in presenting information regarding this liquidated damages assessment, and did not meet with City staff to discuss the matter until after the final payment for the. contract had been approved. After a lengthy discussion, staff and John Madonna compromised on an amount of $2,500 for liquidated damages. Since final payment has been made on the contract, the $6,500 ($9, 000 - $2, 500) of the adjustment must be made outside of the contract. DISCUSSION: Calculations of construction days on a contract is subject to many variables and much judgement. The City often requests contractors to delay the start of a job due to conflicts with other work in an area, holiday traffic, or might delay work on a job during its progress for these same purposes. Sometimes the contractor is delayed because the City is unable to provide a water main turn off, thus delaying the contractor through no fault of his own. There is also judgement involved at the end of a job when major items of the work are functioning, but minor pickup items have not been completed. The City and the contractor each keep detailed lists of these items during the progress of the work, and these are usually resolved between the contractor and the inspector before final payment. In this particular case this was not done, thus creating the necessity for separate action. _ `r ga ;; 4 kir 3 13;0 oAh LUIS OMPO,CA III�11 i�IIIIIIIppo �i��III MY Of San LUIS OBISPO =MoGs COUNCIL AGENDA REPORT Liquidated Damages Page Two STAFF RECOMMENDATION: Staff feels that the best way to determine liquidated damages is at a negotiating session between the contractor and the staff, and that the figure finally arrived at is probably the fairest means of adjusting this difficult item. Unfortunately on this particular job, this did not take place in a timely fashion. However, staff feels it is proper to reimburse Mr. Madonna $6,500 of the $9, 000 imposed for liquidated damages. APPROVED: City Adpinistrative Officer At n Finance Director_ Public Works Director i Attachment: Inspector memo johnm/dfr#20 I I 1 City Of SAn luis OBISPO 955 Morro Street • San Luis Obispo, CA 93401 March 14, 1990 MEMORANDUM TO: Dave Romero, Public Works Director VIA: Tom Gingg, Engineering Field Supervisor FROM: Bill Coates, Public Works Inspector SUBJECT: Liquidated Damages - Water Main Reconstruction Project: Hathway/Montalban; Grand/Wilson; Warren/Patricia; Flora/Alrita - City Plan Nos. N-30P, N-23P, N-24P, N-26P. John Madonna Construction Co. - Contractor Subsequent to final acceptance of the project, further negotiations of liquidated damages have resulted in a reduction from $9,000.00 to $2,500.00, which means that an additional sum of $6,500.00 is due to the Contractor. Please authorize the payment of a purchase order in this amount. bcl/damages by