HomeMy WebLinkAbout10/01/1975Pledge
Roll Call
City Staff
MINUTES
ADJOURNED..MEETING.OF:THE CITY COUNCIL
CITY OF SAN LUIS OBISPO
FRIDAY, OCTOBER 1, 1975 - 4:10 P.M.
COUNCIL CHAMBERS, CITY HALL
PRESENT: Councilmen Graham, Gurnee and Petterson
ABSENT: Councilman Norris and Mayor Schwartz
PRESENT: R.D. Miller, Administrative-Officer; J.H. Fitzpatrick,
City Clerk; A.J. Shaw, City Attorney; Bert B.'Townsend,
representing the County Health Department
Mayor"Schwartz-arrived at 4:30 p.m.
Vice- Mayor.Graham presiding.
1. The City Council considered.the.final passage of Ordinance No. 648,
an-ordinance of the City of San Luis Obispo authorizing an amendment.to the
contract between the.City of San Luis Obispo and the Board of Administration
of the California Public Employees Retirement System. _
Vice -Mayor Graham asked if there was any public input.
No one spoke for or against "the final passage of the ordinance.
On motion of Councilman Gurnee, seconded by Councilman Petterson, Ordinance
No. 648 was introduced for final passage.
Passed and adopted on the following roll call vote.
AYES: Councilmen Graham, Gurnee and Petterson
NOES: None
ABSENT: Councilman Norris and Mayor Schwartz
2.. R.D..Miller., Administrative Officer presented for the Council's
consideration a.memorandum from Wayne Peterson, City Engineer regarding.the
final pay estimate for work on the Edna Saddle Water Tank by Madonna Construction
Company. There were two potentially controversial items:
1. Deduction from Madonna's contract-for exceeding time for completion
2. Deduction from-Madonna's contract for payments to Pacific Erectors for
doing work shown on the plans to be Madonna's responsibility.
The contract for this work_was_clear:in this area and it stated a definite
time-to do the.work and a.penalty.for late completion as well as a bonus for
early..completion...The contract allowed 100 calendar days. The contractor
..took 193 days excluding.rainy days and .extra days for changes in the work.
These extra days had a direct cost to the City of about $7,300 for inspection
plus possible additional.amourits the engineer was requesting of $4,000 for super-
vision and contract administration.
The.second part of the project was work.not.required to be completed prior
to the beginning. -of tank construction—the time allowed was 80 calendar days.
The.contractor.had used 72; therefore, he would receive a bonus for early
completion of the work.
City Council Minutes
October 1, 1975
Page 2
The City Engineer recommended.that the-93 days over should be assessed
at $100 a.day, penalty ,or.$9,300:. ,Jnd.a.bonus.of $800 under on Phase II
a net.deduction.from the..Madonna.contract..of $8,500. On the deductions
..for.work done.by.Pacific.Erectors, the Engineer stated the contract
.....plans indicated ductile-iron pipe that.entered the bottom.of the tank
which.was to.be fitted with steel flange by the manufacturer. The
pipe brought to the site.did..not have such a flange. Madonna's plumbing
...subcontractor.was not.able.to do.the- field.weld; therefore, it was
agreed.to allow Pacific Erectors.to.do` the welding. This was-done via
.a change order.with Pacific Erectors and as a deduction from the final
payment to Madonna.
Wayne.Peterson stated in his.memorandum.he had received verbal objection
from .Madonna's.subcontractor.saying he.did.not feel the work was their
responsibility. There was.no.notice of.this objection in writing;.
therefore the Engineer had shown this item as a deduction on the pay
estimate to-Madonna.
It was the,consenus of the.Councilmen.present. that the City accept
the:recommendation.of the City Engineer -and show these deductions on
'the final payment -to "Madonna Construction Company.
Richard D: Miller, Administrative.-Officer submitted a communication
from Wayne Peterson-,- City.Engineer regarding a request.by`Penfield and .
Smith for.extra.payments.under their basic contract. Payment for extra
work authorized-but not built.
Wayne_ Peterson's memorandum.stated._that.he. had agreed. to pay :Penf,ield
and.Smith for extra.work_done.by.thein.to design an alternate grading" `
plan which. was' .not:built..This.authorizatiori was based on the fact that
wdrk.had been .clearly.authorized_.over.and above the contract and they
..submitted a bill.based.on..time and.mateiial to do the work: The Engineer
agreed -also to.consider time spent by them.to prepare contract documents
for the purchase of water -pipe materials as extra work because it normally
would not have been included in.the.contract for pipeline construction
and was clearly authorized by the.City. Since that authorization, the
City had received.an additional request by the Engineer to consider
.the design of slope protection fence work and pay them based.on_a percentage
of the bid 'or $3,045. ' The Engineer stated he had rejected this on the
basis that it was a contingent item that would only be required.if needed
and was included in the plans at their urging and was not used in the
final product. The contract with the Engineers clearly stated that the
City was obligated to.pay them based on the final construction cost.
It provided for extra payments.beyond the maximum if conditions beyond
the control of:the.engineer.required a change in scope of the project.
It .was the _City..Engineer'.s.opinion.that there had been no change in
the scope..of the project.in the.area. of the.slope protection fence and
he did_ not, intend to authorize payment.
The second.item.was a charge.for.payment for-work done during Madonna's
time over.. run; . -...As previously.reported. the site preparation contractor
.ran over his.time limits 93...days on Phase I and under 8 days on Phase
II fora net total of.85.days.over. The Engineer was.requesting extra
work for project-. management .during..this._over..run time. The amount requested
closely - matched the.entire.charges against the site preparation project
.management portion_of:the.contract. The detail in the billings indicated $
$1,378.75 for. project conferences.and.project management. This.was all
that -the City-. Engineer_. felt - was.justified - because the'remaining cfiarges
were not time related.but..rather work_for.change orders, reports and
design.work_that had been contemplated.from the - beginning of the project.
Whe maximum.amount.to.be _ paid.was automatically adjusted for change
orders. When.the contract was awarded, it was understood that - certain
designs would be done after the contractor had begun work and exposed
the areas for which there_was.no knowledge- before construction. Staff
recommended -the payment.of_$1,378.75 to the Engineer over and -above
.the contract.amount.for time incurred due_ to the contractor's project
extending beyond the time limits.
1
1
C
City Council Minutes
October 1, 1975
Page 3
It was the consensus of the City Council that the staff's recommendation
be accepted and that Item 1, payment for extra work authorized but not
billed, be denied and that the payment for work done during the Madonna's
time over run be approved.
4:30 P.M. Mayor Schwartz arrived at the meeting.
3. The City Council reviewed a report on the County -Wide Solid
Waste Management Plan being prepared by representatives of the various
City's sanitary districts and the County.
Mayor Schwartz, the City- County representative to the County -Wide Solid
Waste Management Plan reviewed for the City Council the work done to
date by this committee in preparing this plan.
Bert Townsend, Solid -Waste Management specialist for the County of San
Luis Obispo reviewed for the City Council,the plan for the San Luis
Obispo County Solid -Waste Management Plan developed to date and outlined
future hearings which would be held on the plan. Mr. Townsend presented
a summary of the inventory of existing solid waste and solid waste disposal
areas, the Resource Recovery activities, the handling facilities, storage,
collection and disposal systems within the County, forecasts and projections
of alternate future disposal methods, collection facilities, etc. and
a summary of preliminary litter management plans being adopted under
the provisions of the State Solid Waste Management and Recovery Act
of 1972.
The City Council discussed with Bert Townsend some of the benefits the
County would derive from a waste management program.
There being no further business to come before the City Council, Mayor
Schwartz adjourned the meeting at 5:45 p.m.
APPROVED:
. Fitzpatrick, City Clerk
L�l