HomeMy WebLinkAbout06-12-2012 PH3 B1 MattinglyGoodwin, Heather
RECEIVED
JUN 1 1 2012
IN
Subject: FW: June 12, 2012 Meeting Addition to Items PH3 and 131.
From: Lichtig, Katie
Sent: Friday, June 08, 2012 5:46 PM
To: Mattingly, Carrie
Cc: Codron, Michael; Schroeder, Sheryll; Head, Greg; Horton, Wade; Hix, Dave; Blair, Cheryl
Subject: RE: June 12, 2012 Meeting Addition to Items PH3 and B1.
Sheryll - AGENDA
CORRESPONDENCE
Please distribute as Agenda Correspondence on Monday. Thanks. Dated of 1I2- Item# 04,5 +B
Katie E. Lichtig
City Manager
City of San Luis Obispo, CA
990 Palm Street
San Luis Obispo, CA 93401 -3249
805- 781 -7114
www.slocity.org
From: Mattingly, Carrie
Sent: Friday, June 08, 2012 5:18 PM
To: Lichtig, Katie
Cc: Codron, Michael; Schroeder, Sheryll; Head, Greg; Horton, Wade; Hix, Dave; Blair, Cheryl
Subject: June 12, 2012 Meeting Addition to Items PH3 and B1.
Importance: High
Dear Mayor and Council,
Attached are the Significant Operating Program Change (SOPC) write -ups for the water and sewer enterprise
funds. They should have been included as attachments to these items and were not. Please accept my apology for this
oversight.
What funds are these related to?
Water Quality Studies = sewer enterprise fund
Naci Budget Reduction = water enterprise fund
Business Manager, Impact Fee, and Org. Consultant = shared between both enterprise funds
If you have any questions, please give me a call.
Sincerely,
Carrie Mattingly
Utilities Director
781 -7215
bcc: CC
1
Ilarn co
exuafil•
o COUNCIL
u CDD DIR
a CITY MGR
o FIT DIR
• ASST CM
a FIRE CHIEF
• ATTORNEY
o PW DIR
o CLERKIORIG
a POLICE CHIEF
o PIB
C PARKS k REC DIR
o TRIBUNE
o UTILDIR
• NEW TIMES
n HR DIR
• SLO CITY NEWS
o COUNCIL
o CITY MOR
o CLERK
MEETINv DATE: June 12, 2012
ITEM: BI
WATER QUALITY STUDIES FOR SAN LUIS OBISPO CREEK
Request Summary
Performing enhanced studies and continuing stakeholder facilitation to better quantify water quality and the
related beneficial uses of San Luis Obispo Creek will cost $275,000 in 2012 -13
Key Objectives
1. Providing comprehensive information of water quality in San Luis Obispo Creek.
2. Determining the impacts and effects on the aquatic habitat.
3. Providing an effective and reasonable process to determine appropriate water quality objectives.
4. Eliciting community and stakeholder input.
5. Working collaboratively with regulators and stakeholders.
6. Identifying options and alternatives to meet regulatory and stakeholder conditions.
7. Providing reasonable and protective discharge limits for the Water Reclamation Facility (WRF).
Existing Situation: Factors Driving the Need for Change
The City's Water Reclamation Facility (WRF) discharges to San Luis Obispo Creek and operates under a
National Pollutant Discharge Elimination System ( NPDES) permit issued by the Central Coast Water Board
(CCWB). The State has listed San Luis Obispo Creek as a Municipal and Domestic water supply (MUN) which
may require nutrient and Trihalomethane (THM) removal in the WRF's next NPDES permit resulting in a costly
upgrade to the WRF.
Nutrients are found in wastewater and THMs are a by- product of wastewater disinfection. The WRF is in
compliance with its current discharge limits, but if a new permit, with more stringent discharge limitations, is
adopted the City will have 5 years to construct new facilities.
The City has completed a study that shows the creek is not being used as a drinking water source and proposes to
remove the MUN beneficial use. The CCWB disagrees with these findings. The City, in collaboration with the
CCWB, has begun a stakeholder process to involve the community for input into protecting the beneficial uses of
the creek including habitat and recreation and to move the process for resolution of this issue forward.
The WRF has a compliance order to achieve the proposed THM limits which will expire in a little less than three
years. Staff is proposing the CCWB extend this order to coordinate with the resolution of the MUN beneficial use
issue and allow the development of a reasonable THM limit.
More stringent nutrient requirements referred to as "biostimulatory" to protect habitat are being proposed
throughout the State. The CCWB has proposed postponing the issuance of the WRF's NPDES permit until the
new biostimulatory methodology has been adopted. It has proposed the City study biostimulatory effects to
provide additional biostimulatory data and information for San Luis Obispo Creek. It has been determined
developing a biostimulatory nutrient limit will postpone the issuance of a revised WRF NPDES permit for 2 -3
years.
The proposed biostimulatory methodology for determining nutrient limits may have one or more major problems.
San Luis Obispo Creek is a thriving aquatic habitat and the City has data that indicates the proposed methodology
will not adequately take into account the creek's specific conditions. If this is the case the result may be the
development of very stringent and expensive discharge limits. To provide more additional analytical data and run
the biostimulatory methodology to ensure reasonable and scientifically defensible discharge limits will cost
$250,000 in 2012 -13. To provide effective facilitation with stakeholders and regulators and move the process
forward will cost $25,000 in 2012.
B1 -1
MEETING DATE: June 12, 2012
ITEM: BI
WATER QUALITY STUDIES FOR SAN LUIS OBISPO CREEK
Implementation
1. Meet and confer with the CCWB May 2012
2. Stakeholders meeting July 2012
3. Enhanced sampling of San Luis Obispo Creek July —Oct 2012
4. Comprehensive constituent sampling of San Luis Obispo Creek April — Oct 2013
5. Biostimulatory study of San Luis Obispo Creek December 2013
Key Program Assumptions
This request will provide a short term comprehensive look at water quality in San Luis Obispo Creek and
facilitation to determine if additional studies or work will be required prior to the adoption of the biostimulatory
nutrient limit in the WRF's revised NPDES permit. Cost estimates and implementation have been developed
utilizing past City studies and ongoing regulatory work within the State in conjunction with the on -going
collaboration with the CCWB and stakeholders.
Program Manager and Team Support
Program Manager. Deputy Director of Utilities
Project Team. Utilities Director, Water Quality Lab Manager, Environmental Services Manager, the City's
water quality consultant, and contract facilitator.
Alternatives
1. Continue the Status Quo. This is not a recommended. The City has an opportunity to continue to work
collaboratively with regulators and stakeholders while collecting valuable data that may result in more
reasonable discharge requirements. EPA and CCWB staff believe that the biostimulatory issue must be
answered before a new permit can be issued to the WRF. The collection of additional data and analysis will
provide information that will support the City's position when negotiating and discussing revised discharge
requirements and upgrades at the WRF.
2. Defer or Re -Phase the Request. Deferring this request will result in the loss to collect crucial data and
analysis along with the loss of stakeholder engagement and buy -in. Similar to continuing the status quo, the
loss of a "sampling season" and the momentum of working with the stakeholders and CCWB, may be
detrimental to the City's goals of reasonable discharge limits for the WRF.
3. Change the Scope of Request. This request has been scoped to provide the most responsible and cost
effective study to furnish valuable information and determine the next steps in this process. A complete, in-
depth study would cost $1 million and would likely not provide significantly more valuable data than the
scope of this request. If required or needed, staff will return with additional information and a request to
expand the scope of the study.
Operating Program
Utilities Administration / Engineering (55300)
B1 -3
MEETr..,; DATE: June 12, 2012
ITEM: PH3 & BI
UTILITIES BUSINESS MANAGER
Request Summary
Meeting the complex analytic and fiscal needs of the Utilities Department enterprise funds requires the addition of
a Utilities Business Manager to the department's workforce. Adding one FTE will not result in the need to
allocate additional funding as costs are currently budgeted in the 2011 -13 Financial Plan for 2012 -13 and split
between water and sewer enterprise funds.
Key Objectives
Providing comprehensive Water and Sewer enterprise fund analyses will ensure improved responsiveness to a
changing environment.
Developing grant and low interest loan opportunities will assist to maximize capital infrastructure
improvements and minimize expenses to the ratepayer.
Adding a Utilities Business Manager will most appropriately structure the department's administrative
functions to meet the complex and diverse requirements of the department's budget development, financial
administration and reporting, revenue oversight and forecasting, purchasing, contract administration, metrics,
and systems evaluation.
Existing Situation: Factors Driving the Need for Change
Since the Utilities Department was formed in 1988, over 20 years ago, the current administrative staffing structure
has remained essentially unchanged. In the past two decades many changes have taken place, not just in the fiscal
and regulatory environment in which the Utilities Department operates, but within other City departments as well.
Staffing reductions in the Finance Department, especially the elimination of the Revenue Manager position,
which provided significant assistance to the enterprise funds, has impacted the Utilities Department. Significant
work previously performed for the department by the Revenue Manager was transferred to the Utilities
Department administrative staff. As complex changes have occurred in the environment impacting the enterprise
funds, its administrative structure has not kept up with the changes.
+v V
1988
2011
Proposed 2013
Utilities Director I
Utilities Director 1
Utilities Director 1
Utilities Engineer I
Utilities Project Manager 1
Utilities Project Manager 1
Administrative Analyst I
Senior Admin Analyst 1
Administrative Analyst 1
Secretary I
Supervising Admin Assistant 1
Supervising Admin Assistant 1
Administrative Assistant .75
Administrative Assistant .75
Utilities Business Manager 1
Total Full Time Equivalent 4
Total Full Time Equivalent 4.75
Total Full Time Equivalent 5.75
Based on the City's 1988 Comprehensive Annual Financial Report (CAFR), the water fund had total operating
revenues of $3,319,675 and operating expenses of $2,721,226. Today the 2011 CAFR reports total operating
revenues are $14,256,100 and total operating expenses are $12,389,200. While a significant portion of the
increase in operating expenses are directly attributable to debt service related to bringing on a new water supply,
increased complexities related to managing the fund have occurred.
In 1988, sewer fund total operating revenues were $1,512,711 with total operating expenses of $1,256,648. In
2011, the CAFR reports sewer fund total operating revenues at $13,318,600 with total operating expenses of
$7,119,500.
PH3 & B1 -1
MEETL.., DATE: June 12, 2012
ITEM: PH3 & BI
UTILITIES BUSINESS MANAGER
The department must think differently about how it is structured and the long -term effectiveness of its business
model. It must provide adequate resources to be good stewards of its growing and changing fiscal and analytic
needs in order to effectively and efficiently function.
Emerging regulatory requirements in water and wastewater treatment will require future infrastructure investment.
Pursuit of grant funding opportunities to offset these costs is not currently pursued due to lack of resources.
Research and applying for grant opportunities would be assigned to the Utilities Business Manager.
The proposed organizational structure related to the department's fiscal and analytic needs, which includes the
addition of a Utilities Business Manager, has been pilot tested since November 2011. The department is seeing the
benefits of increased in -depth analysis related to the department's revenues, operational changes are being
enacted, and processes are being streamlined to improve effectiveness. The structure is more collaborative with a
broader range of staff involved with the review and accomplishment of fiscal and analytic activities. It supports a
more appropriate division of duties, which is good business practice. Field supervisors will begin to reap the
benefits of the new structure as it solidifies and stabilizes.
The addition of a Business Manager in advance of the completion of the broader organizational structure analysis
(scheduled for completion in 2012 -13) is necessary and critical to meet the immediate and long -range needs of the
department. The broader analysis has been underway for almost a year; the Business Manager position is aligned
with findings to -date from that analysis.
Goal and Policy Links
1. Major City Goal — Preservation of Essential Services and Fiscal Health
2. Other Important Council Objectives — Infrastructure Maintenance
3. General Plan Water and Wastewater Management Element
4. City of San Luis Obispo Organizational Values
5. Utilities Department Strategic Plan
Program Work Completed
The comprehensive analytic and fiscal needs of the Utilities Department have been undergoing assessment since
July 2010. This work complements the broader organizational structure analysis that commenced in July 2011.
The administrative assessment included an extensive analysis of the fiscal and analytic needs of each of the nine
major work groups (or sections) in the Utilities Department and the appropriate division of work/skill level
required to meet those needs. A minimum of one FTE is needed to meet the position requirements with
intermittent, reasonable overtime requirements related to the financial planning process. The day -to -day staff
engagement and supervisory requirements, as well as the diversity and complexity of position job duties, does not
effectively lend itself to contracting out.
Information regarding the administrative /fiscal structure in similar enterprise fund -based organizations was
gathered and analyzed. The organizations are the cities of Davis, Napa, Monterey, Palo Alto, Palm Springs, Santa
Barbara, Santa Cruz, Santa Maria, and Ventura.
Due to a staff resignation in Utilities Administration, the department was allowed the opportunity to pilot test the
proposed structure since November 2011. Staffing associated with this pilot test has provided critical resources to
manage the complex analytic demands of the department and maintain proper stewardship of resources. While
staffing has been temporary, and portions of it on a part time basis despite full -time workload requirements, the
proposed structure is working and essential to meet the department's overall fiscal and analytic needs.
PH3 & B1 -3
MEET,,., .3 DATE: June 12, 2012
ITEM: PH3 & BI
UTILITIES BUSINESS MANAGER
Alternatives
Continue the Status Quo. While the status quo is no longer a sustainable business model, if Council should
choose not to authorize the Utilities Business Manager position, the community would continue to receive clean
water and the collection and treatment of wastewater. The Senior Administrative Analyst position currently
authorized would be filled. There is not capacity in one FTE, even with so many tasks delegated throughout the
department, to accomplish all the work required to adequately meet the department's complex fiscal and analytic
needs, even utilizing consultant services. A reduction in responsiveness and customer service would result with
serious workload impacts on existing staff. There would be no capacity for new initiatives. The magnitude of
overtime currently required by exempt staff to accomplish the work would remain unsustainable and could result
in significant position turnover.
Operating Program
Water and Wastewater Administration and Engineering.
Cost Summary
Funding for the anticipated addition of a Utilities Engineer (or similar position) was included in the 2011 -13
Financial Plan as part of the fund analysis for 2012 -13 and incorporated into future year projections. Additionally,
as part of the proposed changes, the department's existing Senior Administrative Analyst position (currently
vacant) will be reclassified to an analyst position resulting in lower staffing costs for the reclassified position.
Line Item Description I Account No.1 2012 -13'
Staffing 125,400
Water Administration
500 -55100 -7010
38,900
500 -55510 -7040
9,000
500 -55510 -7042
6,700
500 -55510 -7044
600
500 -55510 -7046
200
500 -55510 -7048
300
Sewer Administration
520 -55300 -7110
48,600
520 -55300 -7040
11,300
520 -55300 -7042
8,400
520 -55300 -7044
700
520 -55300 -7046
200
520 -55300 -7048
1 500
Total Operating Costs
1 125,400
PH3 & B1 -5
MEETING _.ATE: June 12, 2012
ITEM: PH3 & BI
UPDATE WATER AND WASTEWATER DEVELOPMENT IMPACT FEE STUDY
Request Summary
Using consultant services to complete an update of the Water and Wastewater Development Impact Fee Study
will cost $15,000 in 2012 -13.
Key Objectives
Ensure future development pays its proportionate share of water and wastewater facilities.
Existing Situation: Factors Driving the Need for Change
In 1991 the City implemented water and wastewater impact fees for the first time. In 2002, the fees were updated
based on a study performed by David Taussig and Associates (DTA). The fees were updated in 2004 by City staff
based on costs associated with the Nacimiento, Water Reuse, and Tank Farm projects.
In November 2006 the City Manager approved a contract in the amount of $19,500 to DTA for consultant
services to update the water and wastewater AB 1600 (development impact fee) study. Over time, there were
several rounds of review and revision associated with finalizing the development impact fee update, some of
which resulted in changes of scope and additional work for the consultant. The time frame to complete the fee
update extended beyond that originally anticipated which resulted in the need to update portions of the data
originally provided to the consultant. In January 2009, the City Manager approved Amendment No. l in the
amount of $14,510 and in March 2010, the City Council approved Amendment No. 2 in the amount of $10,000.
The primary factors driving the remaining work to be funded by this request include: 1) updating facility costs
based on actual and/or revised estimates especially related to the water reclamation facility; 2) updating
demographic data and growth assumptions; 3) updating the water supply component of the fee study; and 4)
consideration of secondary dwelling units /guest houses.
Goal and Policy Links
1. Major City Goal — Preservation of Essential Services and Fiscal Health
2. City of San Luis Obispo, General Plan, Water and Wastewater Management Element, policy A5.2.5 (water)
and B2.2.3 (wastewater).
Program Work Completed
The identification and creation of wastewater catchment area maps, impact methodology, update of water maps
with specific plan areas, draft development impacts in specific plan areas (Margarita, Airport, Orcutt),
comprehensive narrative updates, draft calculation of add -on fees, draft calculation of citywide fees,
demographics and population estimates, and a draft report have all been completed.
Environmental Review
No environmental review required.
Program Constraints and Limitations
Bringing this project to completion has been challenging due to a myriad factors. It is imperative to focus on
bringing closure to this specific scope of work and ensure development impact fees that reflect past and proposed
facility expenditures are in place for incorporation into the FY 2013 -15 Financial Plan fund analyses. There may
PH3 & B1 -1
MEETING AT F: June 12, 2012
ITEM: PH3 & BI
UPDATE WATER AND WASTEWATER DEVELOPMENT IMPACT FEE STUDY
Cost Summary
The cost of these services will not exceed $15,000.
line Item Ilescri lion Account No. 2012 -13
Contract Services $15,000
Water Administration
Wastewater Administration
500 -55100 -7227
1520-55300-7227
$7,500
$7,500
Total Operating Costs
$15,000
PH3 & B1 -3
MEETI, , -j DATE: June 12, 2012
ITEM: PH3 & BI
ORGANIZATIONAL STRUCTURE REVIEW - CONSULTANT SERVICES
Request Summary
Continuing improvement in organizational efficiency and effectiveness by ensuring the Utilities Department is
appropriately structured will cost $25,000 in 2012 -13.
Key Objectives
1. Completing this review, with consultant expertise, will assist in determining the best organizational structure
for the Utilities Department. While the current structure may turn out to be the best structure; it is good
business practice to conduct such an assessment on a periodic basis. The last organizational structure
assessment was done approximately 20 years ago.
2. Involving all staff in a collaborative process related to this review is key to understanding the influences upon,
and changes taking place in, the workplace and the reasons driving organizational structure change, if change
is required.
3. Ensuring continued responsiveness and provision of outstanding service to the community in an effective and
efficient manner is of high priority and an expected outcome of the organization structure assessment.
Existing Situation: Factors Driving the Need for Change
In an effort to ensure and validate the effectiveness and efficiency of the organizational structure of the Utilities
Department, Utilities staff at all levels have been engaged in discussions to determine current and future
organizational demands and alternative organizational structures that might better serve its stakeholders and the
community.
The current regulatory and economic environment requires an assessment of the department's organizational
structure to ensure continued responsiveness and provision of outstanding service to the community in an
effective and efficient manner.
Hiring a consultant to assess staff work done to -date in this area and related findings from the recent Public
Works organizational assessment, providing expertise to augment staff's work related to the department's internal
organizational structure assessment findings and any proposed organizational structure changes will assist the
department in remaining responsive to the ever - changing regulatory and economic environment.
A focus on continuous improvement to better meet the department's strategic plan goals drives the need to utilize
consultant services to provide further guidance and expertise in the area of organizational structures.
Fundamental shifts in the economic and regulatory environment in recent years have impacted the department;
ensuring the department is appropriately structured to continue to respond effectively to a changing environment
is critical to its long -term success.
Goal and Policy Links
1. Major City Goal —Preservation of Essential Services and Fiscal Health
2. Utilities Department Strategic Plan
Program Work Completed
The proposed use of consultant services is the second phase of a two - phase, two year work effort. The first phase,
on track for June 2012 completion, consists of an internal assessment of the organizational structure of all Utilities
Department sections. These sections are: Water Supply, Water Conservation, Water Distribution/Customer
PH3 & B1 -1
MEET �.. J DATE: June 12, 2012
ITEM: PH3 & BI
ORGANIZATIONAL STRUCTURE REVIEW - CONSULTANT SERVICES
Alternatives
Change the Scope of Request. This work effort could be completed without utilizing the expertise of a
consultant. A significant amount of work has been accomplished by staff and, although staff is not an
organizational structure expert, completing the study in -house is a viable alternative. There is value -added to
having a consultant review staff's work, bringing a broad perspective to the process, identifying any gaps in
staff's analysis, and assisting staff in grappling with complex organizational structure questions and the roll -out of
any proposed changes.
Operating Program
Utilities Administration/Engineering; Water and Sewer
Cost Summary
The funding source is working capital.
Line Item Description
Account No.1 2012 -13
Contract Services
25,000
Water
Sewer
500 -55100 -7227
1520-55300-7227
12,500
12.500
TotalOperating Costs
25,000
PH3 & B1 -3
MEETI , j DATE: June 12, 2012
ITEM: PH3
WATER SOURCE OF SUPPLY: Nacimiento Water Project
Request Summary
Aligning the 2012 -13 Source of Supply operating program budget with the 2012 -13 Nacimiento Water
Operating Fund budget recently adopted by the Nacimiento Project Commission will reduce costs by
$276,438.
Key Objective
Ensuring budget projections appropriately reflect water supply costs.
Existing Situation: Factors Driving the Need for Change
1. The Nacimiento Project Commission adopted the 2012 -13 Nacimiento Water Operating Fund budget on April
19, 2012. Changes to the budget reflect increased experience with project implementation. This is the second
year of operation for the project.
2. Nacimiento Water Project routine operation and maintenance expenditures (excluding energy costs) decreased
$197,219 due to the following:
a) Transition of contract project management to County Utility Operations staff
b) Environmental Mitigation Efforts. Expenses will be paid out of construction fund savings rather than
operations budget until such time construction funding is exhausted.
c) Operator and Office Engineering Efforts. Budget reduced as District continues to refine line item with
operating history data.
3. Master Water Plan decreased $10,321
4. Variable Energy Costs projection decreased $36,117
5. Non - Routine Operations and Maintenance decreased $12,720
6. Capital Projects decreased $20,000
7. Capital Reserves / Equipment Replacement decreased $61
NWP Budget Line Item
Projected
Adopted
Variance
Routine O &M
$1,003,700
$806,481
(_$197,219
Master Water Plan
$82,000
$71,679
($10,321
Variable Energy___
$453,800
$417,683
($36,117)
Non - routine O &M
$15,000
$2,280
$12,720
Capital Projects
$20,000
$0
$20,000
Capital Reserves /
Equipment Re lacement
$171,600
$171,539
($61)
TOTAL
$1,746,100
$1,469,662
($276,438)
Goal and Policy Links
1. Major City Goal — Preservation of Essential Services and Fiscal Health
2. General Plan Water and Wastewater Management Element
Program Work Completed
Nacimiento Project Commission adopted its 2012 -13 budget on April 19, 2012.
Environmental Review
No environmental review required.
PH3 -1