HomeMy WebLinkAbout05-17-2016 Item 16 LOVR Interchange CM Services Contract Amendment
Meeting Date: 5/17/2016
FROM: Daryl R. Grigsby, Public Works Director
Prepared By: Kyle Rowland, Project Manager
SUBJECT: AMENDMENT TO CONSTRUCTION MANAGEMENT SERVICES
AGREEMENT WITH MNS ENGINEERS FOR LOS OSOS VALLEY ROAD
AT US 101 INTERCHANGE IMPROVEMENT PROJECT, SPECIFICATION
NO. 99821
RECOMMENDATION
Authorize the City Manager to execute Amendment No. 3 to the Construction Management
Services Agreement with MNS Engineers, dated July 1, 2014, increasing the contract by
$175,806, bringing the total contract allowable monthly cumulative payments from $2,650,224
to $2,826,030 for the remainder of the contract.
DISCUSSION
Background
On April 1, 2014, the City Council authorized inviting proposals for Construction Management
(CM) Services for the Los Osos Valley Road - Highway 101 Interchange Project, Specification
No. 99821, and authorizing the City Manager to award a contract up to $2,408,315. After
evaluation of all applicant proposals and interviews, MNS Engineers Inc. ranked the highest.
The anticipated total cost for the multi-year contract (pre-construction, construction, and post-
construction) was $2,352,870.
Since contract award, two previous amendments to the original agreement have been executed.
Amendment No. 1, on October 29, 2014, released the remainder of the contract value when the
Council approved bond financing became available to fund the consultant contracts for the
project. Amendment No. 2, on March 1, 2015, increased the total contract value by $297,354 due
to unforeseen circumstances resulting in an increased construction timeframe and required extra
services encountered during construction.
Amendment
The proposed Amendment No. 3 will cover all anticipated Construction Management tasks that
are remaining to close out the project. These tasks have increased due to the additional
construction oversight that is required as the contractor finalizes construction of the project.
Some of the additional and unexpected construction work that has recently come up is: (1)
additional paving to repair failing rubberized asphalt concrete on U.S. 101; (2) additional San
Luis Obispo Creek rock slope protection required by the Central Coast Regional Water Quality
Control Board; and (3) curb ramp reconfiguration and repair. All three of those items were
16
Packet Pg. 356
unexpected construction changes which require additional construction management expenses.
FISCAL IMPACT
The Interchange project is identified in the 2013-15 Financial Plan, Appendix B – Capital
Improvement Plan, page 3-252 through 3-255. Council approved the project financing at the
June 10, 2014 Council meeting. The project is partially grant funded, with 88.53% of eligible
expenses covered by a $16,000,000 STIP RIP Grant and bonds funding the remaining 11.47%.
The bond payments are secured by the General Fund but will ultimately be reimbursed by the
City’s Traffic Impact Fees and the LOVR Sub Area Impact Fee programs. The utilization of the
project grant will be maximized during the construction.
At this time, approximately $1,700,000 remains unallocated in the project budget, of which
$175,806 will fund the proposed Amendment No. 3. The remaining account balance will be
approximately $1,525,000.
Construction Management Services
Original Agreement $ 418,835
Amendment 1 $ 1,934,035
Amendment 2 $297,354
Amendment 3 (Proposed) $ 175,806
Total Construction Management Budget: $2,826,030
ALTERNATIVE
Do not approve Amendment 3. Council could choose not to approve Amendment 3. The
Interchange project is significant not only in the regional impact of its construction but in the
high cost and grant obligations associated with the funding. It is critical to keep the construction
team on the job to ensure complete and accurate records for the job, in its entirety. In that way,
clear and uniform information will be available for auditing. The contract services also
supplements City resources on labor intensive specialized set of duties. This allows City
resources to maintain the service levels for typical daily duties. For these reasons, this
alternative is not recommended.
Attachments:
a - 99821 CM Amendment 3
16
Packet Pg. 357
AMENDMENT NO. THREE
TO AGREEMENT
THIS AMENDMENT NO. 3 TO AGREEMENT is made and entered in the City of San Luis Obispo on
Tuesday, May 17, 2016, by and between the CITY OF SAN LUIS OBISPO, a municipal corporation,
herein after referred to as City, and MNS ENGINEERS INC., hereinafter referred to as Contractor.
WITNESSETH
WHEREAS, on Tuesday, July 1, 2014 the City entered into an Agreement with Contractor for
Construction Management Services for Los Osos Valley Road-Highway 101 Interchange Project per
Specification No. 99821; and
WHEREAS, on Wednesday, October 29, 2014 the City amended the monthly cumulative
payment amount limit from $418,835 prior to November 1, 2014 to $2,352,870 for the remainder of the
contract; and
WHEREAS, on Tuesday, March 1, 2016 the City amended the monthly cumulative payment
amount limit from $2,352,870 to $2,650,224 for the remainder of the contract; and
WHEREAS, the City desires to amend the monthly cumulative payment amount limit from
$2,650,224 to $2,826,030 for the remainder of the contract and Contractor has submitted a proposal for
this purpose that is acceptable to the City.
NOW THEREFORE, in consideration of their mutual promises, obligations and covenants
hereinafter contained, the parties hereto agree as follows:
1. The scope of services and related compensation is hereby amended as set forth below:
Monthly cumulative payment amount is limited to $2,826,030 for the remainder of the
contract unless adjusted by addendum.
2. All other terms and conditions of the Agreement remain in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed the day
and year first written above.
CITY OF SAN LUIS OBISPO
By: ____________________________
Katie Lichtig, City Manager
APPROVED AS TO FORM: CONTRACTOR
_____________________________ By: ____________________________
City Attorney MNS Engineers, Inc.
16.a
Packet Pg. 358
At
t
a
c
h
m
e
n
t
:
a
-
9
9
8
2
1
C
M
A
m
e
n
d
m
e
n
t
3
(
1
3
3
6
:
A
m
e
n
d
m
e
n
t
t
o
C
M
S
e
r
v
i
c
e
s
f
o
r
L
O
V
R
I
n
t
e
r
c
h
a
n
g
e
,
S
p
e
c
.
9
9
8
2
1
)
Page intentionally left
blank.