HomeMy WebLinkAbout09-06-2016 Item 11 Review Luneta Street General Plan & Neighborhood Traffic Issues Meeting Date: 9/6/2016
FROM: Daryl Grigsby, Public Works Director
Prepared By: Jake Hudson, Transportation Manager
SUBJECT: REVIEW LUNETA STREET GENERAL PLAN AND NEIGHBORHOOD
TRAFFIC ISSUES
RECOMMENDATION
1. Authorize staff to evaluate an amendment to the General Plan eliminating the Luneta
Street connection and return to the Planning Commission and City Council with a
recommendation.
2. Authorize the use of $10,000 from 2015-16 General Fund carryover for the necessary
traffic study and environmental assessment for a potential General Plan and EIR
amendment.
3. Authorize the use of $25,000 from 2015-16 General Fund carryover for preliminary
design & right of way services to analyze fire turn-around options on Luneta.
DISCUSSION
Development is currently being proposed at 71 Palomar, and is proceeding through the review
and entitlement process. As part of that development, the Subdivision Regulations require
construction of the property’s frontage to complete the remaining section of Luneta and provide
enough width for the road connection to be opened to thru traffic. The connection is provided
for in the City’s Circulation Element Figure 1 and this is the same requirement that has been
conditioned upon and fulfilled by all other development on either side of Luneta. During the
project review and hearing process, neighborhood residents have raised concerns about potential
issues associated with the connection and have requested reconsideration. At its July 19th, 2016
meeting the City Council requested that staff return for discussion regarding a potential general
plan amendment eliminating the Luneta Street connection. Staff has been in communication with
neighborhood residents and attended a neighborhood meeting. In response to the neighborhood’s
concerns and Council’s request, staff is proposing to proceed with the traffic study to inform
future consideration of a General Plan amendment to eliminate the Luneta Street connection.
Background
The Luneta Street alignment and connection was first contemplated as part of the initial large lot
subdivisions which established the neighborhoods south of Foothill Blvd in the 1950’s. In the
1970’s the City Council approved the subdivision of lots on the north half of Luneta Dr. At this
11
Packet Pg. 175
time, all of the north half of Luneta was constructed with the exception of the frontage adjacent
to 71 Palomar. The developer was exempted from having to construct that piece because 71
Palomar was the remnant parcel of the subdivision and not proposed for development.
In the 1980s, the Council approved the subdivision of residential lots on the south half of Luneta
and that half of the planned street connection was constructed as those lots developed. Under the
subdivision regulations, the properties across from 71 Palomar were also required to construct
the last remaining piece on the north side. The developer unsuccessfully attempted to negotiate
the purchase of that frontage from the Delta Tau Fraternity. The Council considered obtaining
the necessary right of way through eminent domain or granting the developer an exception,
allowing them to proceed without constructing the final piece of Luneta. Ultimately, the Council
granted the exception and the developer constructed the south half of Luneta. When the south
half of the road was completed sometime around 1987, it was opened to thru traffic with parking
restricted.
In 1994, while Luneta was opened to thru traffic on the completed south half, the City updated
its General Plan. The Luneta connection was included in the Circulation Element at that time by
being shown on Figure 1 of the Streets map. In 1995, the bollards that exist today were installed
at the request of the fire department as part of a work order. In 2014 the City again updated its
General Plan. Since there were no changes proposed for the Luneta connection it was carried
forward from the 1994 General Plan into the current 2014 General Plan.
The combination of General Plan policy and subdivision regulations are now triggering the
frontage improvements and Luneta connection as part of the 71 Palomar development project.
Consistent with current City Municipal Code and General Plan requirements, staff has included
construction of the Luneta connection as a proposed condition of project approval. The proposed
condition mirrors the condition previously imposed on the other parcels along this section of
Luneta. However, the 71 Palomar project can still proceed through its review process separate
from the proposed Luneta connection assessment. In order to separate these two processes there
would be conditions on the 71 Palomar project to make an offer to dedicate right of way and
deposit the amount of funds necessary to construct the frontage improvements that would
otherwise be required under current policy as a through street. In the event the Council later
determines, after appropriate traffic and circulation impact analysis, that a General Plan
amendment to eliminate the connection is appropriate, the City could take action to ensure
improvements consistent with project impact nexus.
Policy Constraint: Circulation Element Volume Thresholds
The primary policy issue associated with a potential General Plan amendment that needs to be
addressed is the share of traffic volumes between Ramona and Luneta. Under the Circulation
Element, the maximum daily volume for Ramona is 3,000, and the current volume on Ramona
currently is approximately 4,000. The Maximum daily traffic volume for Luneta is 1,500, and the
current volume on Luneta is approximately 300. Based on the traffic model used in the general
plan update if the Luneta connection is completed as currently planned, it’s anticipated that
volumes within the neighborhood would rebalance to levels closer to General Plan policy
thresholds; 3,000 vehicles per day on Ramona and 1,300 vehicles per day on Luneta. If the
11
Packet Pg. 176
Luneta Connection is eliminated there may be policy conflicts and impacts to the neighborhood
traffic volumes and circulation conclusions that assume the Luneta connection, which would
need to be addressed in the course of review of a City initiated General Plan amendment process.
The proposed traffic study will be primarily focused on formally forecasting the change of future
traffic flows in the neighborhood and evaluating consistency with Circulation Element Policy
7.3, which establishes maximum traffic volume thresholds and speeds on the various
classification of streets. If a General Plan amendment is recommended it likely would consist of
modifications to Figure 1 of the Circulation Element and amendment of the proposed traffic
study into the General Plan EIR, with any necessary findings, modifications or mitigations
disclosed by the analysis.
Below is a conceptual project plan & schedule for this potential general plan amendment:
September Neighborhood Kick off Meeting
October – January Traffic Study, Environmental Review, & Fire Access Analysis
February-March Neighborhood Follow Up Meeting(s)
March Finalize Findings & Recommendation
April-May Planning Commission Review
May-June City Council Review & Action
Physical Constraint: Fire Department Turnaround
Accommodating fire access requirements would need to be addressed as part of permanently
eliminating the Luneta connection. Fire Department standards dictate that dead-end streets longer
than 150’ in length require an approved turn around as shown in Figure 1 below. Permanent
closure of Luneta would create a dead-end block length ranging from 500’ to 750’. The Fire
Department has allowed the current configuration of Luneta (closure with bollards & no turn
around) to exist to date because it has been considered a temporary condition until the remaining
frontage of 71 Palomar is constructed. Typically Fire Department access standards would have to
be satisfied when the street is put in its permanent configuration.
Luneta has been planned as a thru connection and, as a result, the additional right of way
necessary to construct a fire turn around was not acquired when properties in the area
subdivided. Potential options for achieving a Fire Department turnaround range from the Fire
Department granting an exception to the turnaround requirement or obtaining an access easement
on a private driveway, which could be relatively inexpensive, up to acquiring right of way and
constructing a turnaround as depicted in Figure 1 below, which would be very costly.
11
Packet Pg. 177
Figure 1: Types of Fire Turn Arounds
The 71 Palomar project would only be legally obligated to dedicate the right of way and
construct frontage improvements per the current plan and policy, which assumes the Luneta
connection. Any additional right of way or easement acquisition, and construction costs
associated with a fire turnaround, if the Luneta connection is eliminated, would be the City’s
responsibility. City Public Works and Fire Department staff will work in conjunction with
neighborhood residents to identify a preferred option for accommodating fire department access.
Staff is recommending that the Council authorize $25,000 for preliminary design and right of
way services to assist in evaluating fire turn around options.
CONCURRENCES
The Fire Department has reviewed the staff report and concurs with the staff recommendation.
The Community Development Department has reviewed and concurs with the staff
recommendations.
The City Attorney’s Office has reviewed and concurs with the staff recommendations.
FISCAL IMPACT
The total cost for the proposed studies to evaluate of potential general plan amendment is
estimated at $35,000, $10,000 for traffic studies and $25,000 to evaluate right of way and
estimate construction costs for the required fire turn around. Staff is proposing to fund this cost
from General Fund carryover. There is adequate funding for this allocation with savings that
occurred in the 2015- 16 Fiscal Year.
ALTERNATIVE
Direct staff not to proceed with an evaluation of a general plan amendment eliminating the
Luneta St. connection. The 71 Palomar project, if approved, would be required to fulfill its
requirements, completing the Luneta St. Connection.
11
Packet Pg. 178
Luneta Drive
1950 & 60’sFirst SubdivisionsAlignments- Ramona- Luneta-Verde- SerranoTract 134 –Luneta curvature established to facilitate future connection toPalomar.09-06-2016 Presentation, Item 11
1970’sLuneta North HalfSubdivisionsNorth half of LunetaConstructed as Required by Subdivision Regs71 Palomar Frontage not required to be constructed under regsbecause it was original lot. (Not a Part)Reduced Original 71 PalomarLot09-06-2016 Presentation, Item 11
1970 - 90’sLuneta South HalfSubdivisionsSouth half of LunetaConstructed as Required by Subdivision RegsCouncil granted exceptions deferring construction of the north half along 71 Palomar09-06-2016 Presentation, Item 11
Late 1980’sSouth Half LunetaConstructedOpened to Thru traffic.09-06-2016 Presentation, Item 11
1994Circulation Element1995 Bollards installed at request of Fire Department09-06-2016 Presentation, Item 11
2014Circulation Element09-06-2016 Presentation, Item 11
General Plan Amendment: Policy ConstraintCurrent Neighborhood Traffic FlowGeneral Plan Buildout Neighborhood Traffic Flow09-06-2016 Presentation, Item 11
Current Neighborhood Traffic FlowMax. Volume: 3,000 ADTCurrent Volume: 4,000 ADTMax. Volume: 1,500 ADTCurrent Volume: 300 ADT09-06-2016 Presentation, Item 11
General Plan Amendment: Physical Constraint150’ +REQUIREMENT150’350’400’600’09-06-2016 Presentation, Item 11
Recommendations1. Authorize staff to evaluate an amendment to the General Plan eliminating the Luneta Street connection and return to the Planning Commission and City Council with a recommendation.2. Authorize the use of $10,000 from 2015-16 General Fund carryover for the necessary traffic study and environmental assessment for a potential General Plan and EIR amendment.3. Authorize the use of $25,000 from 2015-16 General Fund carryover for preliminary design & right of way services to analyze fire turn-around options on Luneta.TENTATIVE PROJECT SCHEDULESeptember: Neighborhood Kick off MeetingOctober – January: Traffic Study, Environmental Review, Fire Access AnalysisFebruary – March: Followup Neighborhood Meeting(s)March: Finalize Findings & RecommendationsApril – May: Planning CommissionMay – June: City Council Review & Action09-06-2016 Presentation, Item 11
PROCESS FOR KEEPING LUNETACLOSED09-06-2016 Presentation, Item 11
09-06-2016 Presentation, Item 11
1980 & 90’sLuneta South HalfSubdivisionsSouth half of LunetaConstructed as Required by Subdivision RegsCouncil granted exceptions deferring construction of the north half along 71 PalomarLuneta opened to thru traffic on the south half in early to mid 1990’s. Then closed due limited street width.Reduced Original 71 PalomarLot09-06-2016 Presentation, Item 11
~1 min. 50 Sec~2 min. 30 Sec~2 min. 45 SecCut-thru Traffic09-06-2016 Presentation, Item 11
09-06-2016 Presentation, Item 11
09-06-2016 Presentation, Item 11
1970’sLuneta North HalfSubdivisionsNorth half of LunetaConstructed as Required by Subdivision Regs71 Palomar Frontage not required to be constructed under regsbecause it was original lot.Reduced Original 71 PalomarLot09-06-2016 Presentation, Item 11