HomeMy WebLinkAbout09-20-2016 Item 08 Laguna Lake Dredging and Sediment Management Project Meeting Date: 9/20/2016
FROM: Derek Johnson, Assistant City Manager
Prepared By: Robert A. Hill, Natural Resources Manager
SUBJECT: LAGUNA LAKE DREDGING AND SEDIMENT MANAGEMENT PROJECT -
PREFERRED PROJECT ALTERNATIVE SELECTION
RECOMMENDATION
Receive and file the Preliminary Dredging Report (the “PDR”) prepared by MNS Engineers, Inc.
and, as further described in the PDR, direct staff to proceed with further analysis and further
recommendations related to the following preferred project alternative:
1. Use of hydraulic or cyclonic dredging equipment as the dredging technology; and
2. Removal of 50,000 cubic yards of sediment from the Laguna Lake as the dredging
project option; and
3. Mechanical dewatering at Laguna Lake Park as the dewatering location and method; and
4. Off-site disposal at Cold Canyon Landfill as the sediment deposition location and facility;
and
5. Creek bank restoration and installation of a sediment basin at Laguna Lake Golf Course
along Prefumo Creek, as well as shoreline restoration at the lake itself, as short-term
sediment management strategies.
REPORT-IN-BRIEF
In January 2016, the City retained the firm MNS Engineers (“MNS”) to assist the City with the
work plan that was adopted by the City Council as part of the “Other Important Council
Objectives” associated with the 2015-17 Financial Plan. The first phase of the work prepared by
MNS, in consultation with staff, includes development of the Preliminary Dredging Report
(“PDR”). The PDR documents eleven significant key project elements.
The fiscal impacts associated with the Laguna Lake Dredging and Sediment Management
Project, as recommended, are substantial. Staff anticipates that the total project cost based on
staff’s recommended preferred alternative is estimated to be $10-12 million. Following the City
Council’s selection of the preferred project alternative, it is expected that staff and the City’s
consultant team will analyze the costs and the benefits that will accrue to the community, to
neighboring property owners and residents, and to the natural ecosystems found within Laguna
Lake and its surroundings, and complete the required California Environmental Quality Act
(CEQA) analysis. As overall project costs and project feasibility are further refined based on
subsequent engineering, environmental review, and evaluation of the potential for land-based
financing, staff will return to Council for additional actions necessary to move the project to
“shovel ready” status.
8
Packet Pg. 77
DISCUSSION
Background
The City of San Luis Obispo owns the 344 -acre Laguna Lake Natural Reserve (the “Reserve”)
that includes most of the lake itself, portions of Prefumo Creek and its outlet into the lake, and
adjacent upland areas. The City Council adopted the Laguna Lake Natural Reserve Conservation
Plan (“Conservation Plan”) on July 15, 2014 to guide future management of the Reserve by
offering a framework for conservation, restoration, recovery, and scenic recreational use.
Laguna Lake is primarily a naturally occurring lake, although the lake and its watersheds have
been altered and manipulated, to include the re-routing of Prefumo Creek into the lake in the
early 1960s to help facilitate the 1961 Master Plan for Laguna Lake and the construction of Tract
279 along Oceanaire. This has resulted in increased sediment deposition rates. Recent
bathymetric surveys indicate accelerated changes in lake depth and morphology resulting in
decreased water quality and aquatic habitat functions, as well as diminished aesthetic and
recreational values associated with the lake. As a result, dredging and sediment management
strategies are among the primary recommendations of the Conservation Plan.
The City’s Financial Plan for 2015-17 identifies implementation of the Conservation Plan as an
“Other Important Council Objective” and includes a work plan that contains all of the necessary
steps to make a dredging and sediment management project “shovel ready”. In January 2016,
the City retained the firm MNS Engineers (“MNS”) to assist the City with the work plan that was
adopted by the City Council. MNS is the prime contractor for a multi-disciplinary team to
complete the following main tasks: 1.) Prepare Design Plans and Engineering Specifications; 2.)
Environmental Studies and Project Permitting; and 3.) Public Outreach and Financing Options.
Preliminary Dredging Report
The first phase of the work prepared by MNS, in consultation with staff, includes development
of the Preliminary Dredging Report (“PDR”). The PDR documents 11 key project elements:
1. A review of the current status of the lake, previous studies, and management documents;
2. New geotechnical and water quality testing data;
3. New biological and cultural resource assessments;
4. A review of applicable dredging technologies and approaches;
5. Development of dredging alternatives;
6. Recommendations for deposition and disposal of sediments;
7. A preferred alternative recommendation;
8. Dredging operations recommendations;
9. Recommendations for future sediment management;
10. An overview of additional project amenities and project enhancement opportunities; and
11. An analysis of project funding options.
Of the project elements described in the PDR, those that are especially pertinent to the
recommendations set forth in this Council Agenda Report are further detailed below.
8
Packet Pg. 78
Geotechnical Investigation and Sediment Characterization
A geotechnical investigation and analysis was completed in the spring of 2016 by Leighton
Group, Inc., to characterize lake bed deposits, identify any contaminants present in lake
sediments, determine the slope stability of the existing lake shore banks, and provide dredging
recommendations based on the findings of their investigation. The complete geotechnical report
documenting the geotechnical investigation and analysis is provided in the PDR.
The subsurface investigation included five surface soil samples and eleven vibracore samples.
For each core, samples were taken at discrete intervals, three per core, in order to enable detailed
sediment chemistry testing. The results of the geotechnical investigation indicated that the
lakebed materials are largely silty to fat clays (CH) interlayered with lean clay (CL) and
inorganic silt (MH) throughout the lake and within the principal proposed dredging areas. There
is limited sand present in thin surface layers within the delta formed at the mouth of Prefumo
Creek. The clays generally transition from a soft oxidized clay to a stiff clay with little to no air
voids with increasing depth.
Sediment samples collected were analyzed for metal and nitrate and phosphate content. In
addition, modified elutriate tests were performed on sediment collected from Laguna Lake.
Sediment chemistry testing detected nickel, Chromium 3 (Cr+3) and Chromium 6 (Cr+6) in the
areas surrounding the lake as well as concentrations in the lake sediment. The detectable levels
of chromium and nickel in the soil samples are naturally-occurring and the result of outcrops of
serpentine rock located in the surrounding watersheds that drain to the lake. Detected levels of
nickel and Chromium (Cr+6) are below the EPA dictated National Action Levels (NALs).
However, at some locations, samples exceed the US EPA Region 9 Regional Screening Level
(RSL) for a residential setting. Soil chemistry is typical of the general region, with no
contamination noted from man-made sources such as Total Petroleum Hydrocarbons (TPH),
Volatile or Semi-Volatile Organic Compounds (VOC or SVOC), or Pesticides.
Dredging Technology
There are three main types of appropriate dredging techniques associated with small inland water
bodies: 1) mechanical, 2) hydraulic, and 3) cyclonic.
Mechanical dredging involves the physical excavation of sediment material using conventional
earth moving equipment, such as a backhoe, or specialized excavation equipment, such as a clam
shell excavator or draglines. The advantages of mechanical dredging are that water is not
required for dredging operations, little water is used in the dredging process and excavated soil
material maintains its in-situ density. Disadvantages associated with mechanical dredging are
that the excavation is not as precise as other methods and the reach distance of mechanical
equipment can limit excavation extents or require additional logistics; this is especially true
given the soil characteristics at Laguna Lake.
Hydraulic dredging is performed by using sucti on to pump sediments to the shore in a slurry
state. The advantages of hydraulic dredging are dredging precision, flexibility of reach, and
access to sediments. The chief disadvantages of hydraulic dredging are the required water use
associated with making the slurry, down times to repair and maintain piping, and the drying time
required for slurry dredged sediment. With cutting head attachments hydraulic dredging can also
8
Packet Pg. 79
increase the turbidity of the water body being dredged. Turbidity issues associated with hydraulic
dredging can be mitigated through the use of a turbidity curtain.
Cyclonic dredging is an emerging hydraulic dredging technology that generates a vortex to
transport sediments. The vortex reduces friction between transported sediments and the
transmission pipe resulting in higher excavation rates, increased percent age of solids in slurry
dredged sediment, less pipe break downs, and a longer pipe transport range. Dewatering
processes would limit typical excavation rates of both conventional and cyclonic dredging
operations. However, the increased percent solids of slurry material achieved by cyclonic
dredging would accelerate the dewatering process, which could translate to less onsite space used
for dewatering and an increased dredging rate. Even with cutting head attachments cyclonic
dredging reportedly does not increase the turbidity of the water body being dredged.
The following table provides a summary of different aspects of the three dredging techniques:
Color Key Poor Fair Fair Good
Dredging Technology Options Mechanical Hydraulic Cyclonic
Environmental Impact
Medium – Low
Turbidity
Medium
Turbidity, Some
Water Level
Impact
No Turbidity,
Slight Water
Level Impact
Works Offshore With barge or
constructed land
bridge
Yes Yes
Excavation Rate (CY/Hr)
NOte
70-100 200-400 900-1000
Percent Solids In Situ 10-20% Up to 80%
Daily Maintenance (Hrs/Day) 1 2 <1
Minimum Operational Depth None 3 feet < 3 feet
Accuracy Rough grading Precise Precise
Soil Transport via Pipeline No Yes Yes
Pipeline Transport Range N/A 3,000 feet >5,000 feet
The recommendation is to select hydraulic or cyclonic dredging as a combined option in the plan
specifications giving the City the opportunity to better understand the competitive bidding
environment for a project that utilizes either of these options. This is because cyclonic dredging
is relatively new technology and not all prospective contractors have access to it.
8
Packet Pg. 80
Dredging Priority Areas
Three Priority Areas were identified by staff and the engineering consultant as part of the PDR
and ranked in order of importance. These areas are outlined in the exhibit below, and are also
shown as Figure 8 of the PDR and in the Map Set that is Attachment A.
The area encompassing the northwest inlet, peninsula inlet, and transition into Center Lake was
not considered for the proposed dredging project. The northwest inlet and peninsula inlet areas
have high environmental and biological significance and should not be disturbed. The area
between the northwest and peninsula inlets and Center Lake experiences a low rate of
sedimentation because of the topography and characteristics of these drainages and the ability of
the marsh wetlands to capture the sediment.
Dredging Project Alternatives
Alternative 1 addresses Priority Area 1, the area identified as having the highest sedimentation
rate in Laguna Lake. Dredging in this area has the greatest impact on the lake’s ability to capture
sediment passing through Prefumo Creek and Prefumo Arm. This elevation was selected to
address the alluvial fan in Priority Area 1 but also to connect the northwest end of the lake to
Center Lake with a smooth transition. The total project hard costs would be roughly
$5.26 million with dewatering using onsite sedimentation ponds or $6.34 million with
mechanical dewatering. The physical characteristics of Alternative 1 are shown in the table,
below:
8
Packet Pg. 81
Characteristic Value
Target Priority Area(s) 1
Dredged Volume 36,500 CY
Dredged Area 15.95 acres
Max. Existing Elevation 119.2
Finished Elevation 114.0
Max. Dredging Depth 5.2 feet
Lake Capacity Increase 22.6 AF
A range is proposed for Alternative 2 in order to provide the opportunity to select a point within
the range that best satisfies the goals of this dredging project within potentially available
financing. The low end of the range is anticipated to cost approximately $6.95 million with
dewatering basins and $8.68 million using mechanical dewatering practices.
The high end of the range for Alternative 2 is anticipated to cost approximately $11.32 million
with the sedimentation pond method for dewatering and $14.55 million using mechanical
dewatering.
By addressing Priority Areas 1 and 2, Alternative 2 provides a greater ability to remove sediment
than Alternative 1. Alternative 2 also increases the lake depth over a larger area, which provides
both environmental and recreational benefits. Expanding the dredging area towards the boat
launch area provides access to deeper water for kayakers, canoers, and other recreational boaters.
A wider, deeper lake bed also provides aquatic wildlife with a larger habitat and overall healthier
ecosystem. The physical characteristics of Alternative 2 are shown in the table, below:
Characteristic Value
Alternative 2-Min Range Alternative 2-Max Range
Target Priority Area(s) 1 & 2 1 & 2
Dredged Volume 50,000 CY 85,000 CY
Dredged Area 21.40 acres 31.00 acres
Max. Existing Elevation 119.2 ft. asl 119.2 ft. asl
Finished Elevation 113.75 ft. asl 113.25 ft. asl
Max. Dredging Depth 5.4 feet 5.9 feet
Lake Capacity Increase 31.0 AF 52.7 AF
Alternative 3 represents the alternative in which all three priority areas are dredged. Alternative 3
would cost roughly $21.6 million with the sedimentation pond method for dewatering and $27.3
million using mechanical dewatering. The physical characteristics of Alternative 3 are shown in
the table, below:
8
Packet Pg. 82
Characteristic Value
Target Priority Area(s) 1, 2, &3
Dredged Volume 167,000 CY
Dredged Area 35.37 acres
Max. Existing Elevation 117.6
Finished Elevation 111.5
Max. Dredging Depth 6.1 feet
Lake Capacity Increase 103.5 AF
In sum, Alternative 1 represents the minimum economically feasible project in consideration of
mobilization costs and achieving the primary project goal of attending to the accumulated
sediment at the outlet of Prefumo Creek. Alternative 3 represents a project that would result in
lake depths of approximately 9 feet when full through the Center Lake and Southeast Arm,
which is consistent with prior Council direction in 2010; however, at an expected cost of over
$20 million, this alternative is likely to be financially infeasible.
Alternative 2 provides a project that achieves the primary project goal of attending to the
accumulated sediment at the outlet of Prefumo Creek, while also providing longer-lasting
benefits and additional aesthetic and recreational benefits. In consideration of these expected
benefits, on balance with anticipated financial feasibility, a project in the low range of
Alternative 2 that will remove 50,000 cubic yards of sediment from the lake is therefore
recommended as the preferred dredging option.
Dewatering
Dredged sediment can be mechanically dewatered, dewatered using dewatering basins, or
dewatered by a combination of the two methods.
Dewatering basins require adequate onsite space; in the case of the Laguna Lake project 6-8
acres would be necessary. A typical dewatering basin system has a sequence of at least three
basins. Dredge slurry is pumped into the dewatering basin at the top of the sequence until that
dewatering basin is full. The material is then allowed time to settle. Optionally, additives may be
used to decrease the settling time. Clarified water is then pumped or syphoned off the top of the
dewatering basin and sent to the second and third basins in the series for additional clarification.
The basin retention time required to meet turbidity requirements identified in the permitting
process is also another factor that will affect production schedule. Locating adequate space for
settlement basins will likely be challenging on City owned property on the north side of the Lake
within the park due to other ongoing uses.
Mechanical dewatering allows for faster return of water used in dredging operations but is
generally more expensive. However, mechanical dewatering can be accomplished with less
onsite space; in this case 3-4 acres. Mechanical dewatering methods can include belt presses,
centrifugal sludge handlers, screw presses, or heat, among others. Commercial sludge dryers of
various t ypes are commonly used due to their ability to incorporate return water treatment
processes.
8
Packet Pg. 83
Due to space considerations in the park and the goal of minimizing disruptions in the park,
timing dewatering with the pace of dredging production, as well as the opportunity to return
treated water back into the lake quickly, mechanical dewatering is recommended. The proposed
dewatering area is delineated in Figure 18 in the PDR and in the Map Set that is Attachment A.
This option was endorsed by the Parks and Recreation Commission at their meeting on August 3,
2016 (Attachment B).
A summary of dredging and dewatering project options is depicted in the table below:
Proposed
Alternative
Priority
Areas
Dredged Volume
(CY) Total Cost Cost Per CY
Alternative 1A 1 36,500 $5.3 million $144.1
Alternative 1B 1 36,500 $6.3 million $173.8
Mechanical
Alternative 1 1 36,500 $6.1 million $165.7
Alternative 2A-
Min Range 1 & 2 50,000 $7 million $138.9
Alternative 2B-
Min Range 1 & 2 50,000 $8.7 million $173.7
Mechanical
Alternative 2-
Min Range
1 & 2 50,000 $7.4 million $148.6
Alternative 2A-
Max Range 1 & 2 85,000 $11.3 million $133.2
Alternative 2B-
Max Range 1 & 2 85,000 $14.6 million $171.2
Mechanical
Alternative 2-
Max Ranage
1 & 2 85,000 $12.4 million $145.5
Alternative 3A 1, 2, &3 167,000 $21.6 million $129.1
Alternative 3B 1, 2, & 3 167,000 $27.3 million $163.5
Mechanical
Alternative 3 1, 2, & 3 167,000 $23.2 million $139.1
A – Hydraulic Dredging with Dewatering Basin
B – Hydraulic Dredging with Mechanical Dewatering
Sediment Deposition
Several sites were evaluated for the deposition of dredged material. To minimize hauling costs,
only sites within 10 linear miles of Laguna Lake were considered. Due to the silty, heavy clay
nature of the sediment, few beneficial uses exist for the dredged material. However, all potential
sites within the 10-mile radius were evaluated, including the Laguna Lake Natural Reserve and
Laguna Lake Park, privately-owned property adjacent to the Reserve, Cold Canyon Landfill, the
Chevron Tank Farm, and Price Canyon oil field.
8
Packet Pg. 84
The area directly to the east and northeast of Laguna Lake is part of the Laguna Lake Natural
Reserve and the Laguna Lake Park, both City-owned properties with open land available for
sediment deposition. Various areas within these properties were identified and evaluated for
potential sediment deposition. However, an on-site deposition strategy proved to be challenging
for three primary reasons: 1.) both prior and current botanical surveys (Keil, 1996; Terra Verde,
2014; Rincon 2016) documented the presence of numerous rare, special-status plant species
including the adobe sanicle (sanicula maritima) which would require an Incidental Take Permit
from California Department of Fish and Wildlife prior to any site disturbance under the
California Endangered Species Act; 2.) the geotechnical and chemical properties of the sediment
both in the lake and in the soil at the areas identified for potential deposition, as discussed above
under the Geotechnical Investigation sub-heading; and 3.) the total volumes of sediment under
consideration, if placed on-site, would result in substantial areas of the Reserve and Park being
disturbed during the course of dredging operations that would likely require most, if not all, of
the Reserve and Park to be closed during construction, while ongoing restoration and monitoring
efforts would continue for many years following the physical implementation of the dredging
project. For these reasons, on-site deposition should not be considered.
Various local ranch properties were also identified and evaluated as potential deposition sites for
the dredged sediment. Several of these properties are adjacent to Laguna Lake and these sites
could be accessed through public roads or roads created through private property. Several other
nearby and regional locations were also identified. However, large portions of these sites lie
within the 100-year flood plain, according to the Federal Emergency Management Agency
(FEMA) Flood Insurance Rate Map (FIRM), which limits the available area for deposition, while
the geotechnical and chemical properties of the dredged sediment would also be problematic for
potential deposition on private properties.
Currently, the only plausible and feasible deposition site of the dredged sediment is the Cold
Canyon Landfill (Cold Canyon), which is a Class III municipal solid waste disposal facility and
is already permitted by the appropriate regulatory agencies for accepting waste materials. It is
located seven miles to the southeast of the City along Highway 227. A meeting was conducted
on May 26, 2016, between MNS, the City, and Cold Canyon representatives to discuss several
criteria regarding the disposal of dredged sediment. Under its current permit, the dredged
sediment meets Cold Canyon acceptance criteria and the facility can receive up to 1,200 tons of
solid waste per day. Accounting for the Landfill’s average daily intake from municipal trash
collection, Cold Canyon can receive approximately 600 tons of sediment per day. At an
estimated unit weight of 125 pounds per cubic foot (lb/ft3), 600 tons equals roughly 350 CY of
sediment, which approaches the estimated daily dredging production rate. Cold Canyon plans to
open a new landfill cell on its property in the coming months, and under a new permit, it could
receive a total of 1,600 tons of solid waste per day. The increased capacity could allow for a
higher sediment disposal rate.
For planning and cost-estimating purposes, Cold Canyon suggests a tipping fee of $20 per ton
($33.75/CY). This rate is lower than the tipping fee for private entities, although further
negotiations would be made before a contract is finalized. When finalized, the contract would be
active for one year. Cold Canyon also imposes a moisture content limit of 50% for the sediment.
The quality of the sediment has been initially accepted; however, Cold Canyon requires a soil
8
Packet Pg. 85
sample report for every 1,000 CY of sediment disposed of at the Landfill, with soil samples valid
for up to one year before disposal.
Sediment Reduction
There are two areas within and tangent to Laguna Lake that are actively contributing sediment to
the lake environment due to eroded and unstable conditions.
Sections along Prefumo Creek within the upstream extent of the Laguna Lake Golf Course have
become over-steepened and present near vertical banks where this section of creek leaves the
original, historic alignment of Prefumo Creek and enters the re-aligned and straightened portion
of Prefumo Creek that was completed in the early 1960s. At this location, the creek appears to
be re-gaining sinuosity and a natural “angle of repose” but in doing so has caused significant
erosion. Stabilization measures should be evaluated on a case by case basis through this system
by the design engineer and biologist to insure desired outcomes due to the dynamic nature of
creek systems and the propensity of one action to cause another action further downstream.
Areas of erosion and shoreline sloughing exist along the northeast shore of the lake near the boat
launch/ramp area, access road and parking lot. In addition, the shoreline path has eroded and
parts of the path and road have failed due to wave action associated with the predominant
westerly winds frequently encountered at the lake. The design recommendations that govern
selection of shoreline erosion protection are further described in the PDR and include:
1. Indirect or vegetative methods preferred over structural methods such as is vegetated rock
slope protection ("VRSP"), as may be necessary;
2. Protect and conserve stream bank and shoreline features with the potential to attenuate
impaired runoff; and
3. Plan and manage activities within the water bodies adjacent to shorelines and along the
shoreline to limit erosion.
Over the longer-term, the Laguna Lake Natural Reserve Conservation Plan also recommended
seeking voluntary conservation easement agreements in the upper watersheds that drain to the
lake in order to maintain low-intensity land uses in these areas. Staff will continue to track such
opportunities through the City’s Greenbelt Protection Program, with recognition that protection
of the watersheds associated with Laguna Lake would represent an additional, substantive
benefit relative to the priority-setting of land conservation opportunities throughout the
Greenbelt.
Sediment Management
Prior studies indicate that the Prefumo Creek watershed deposits an average annual load of 8,000
CY of coarse sediment in the Prefumo Inlet and 3,900 CY of finer sediment in the Center Lake
portion of Laguna Lake. In total, an estimated 11,900 CY of sediment is carried from the
Prefumo Canyon watershed and deposited in the Prefumo Inlet and Center Lake per year. These
deposits are detrimental to the water quality, fish habitat, recreational use, and hydraulic capacity
of Laguna Lake.
It is recommended that sediment from the Prefumo Creek watershed be collected and removed to
8
Packet Pg. 86
the extent possible before they are deposited in the lake since the sediment deposits spread out
over a larger area. Soil deposits from the Prefumo Creek watershed also become more sorted
and have the potential to mix with contaminants, making the material excavated from the lake
less feasible for offsite placement.
In addition to collecting and removing sediment in the Prefumo Inlet downstream of Los Osos
Valley Road, it is recommended that a new sediment collection pond be created in the area
immediately upstream of Los Osos Valley Road. To capture the majority of the total average
annual sediment load of 11,900 CY, a four–feet-deep pond would require about a two-acre
footprint. The exact location of the placement of this pond would be identified through additional
analysis. The portion of the Prefumo Inlet located upstream of Los Osos Valley Road is part of
Laguna Lake golf course. The City could easily access the site to regularly remove sediment
deposits on a periodic basis and no land acquisition or easements would be required. This area is
also less environmentally sensitive than the portion of the Prefumo Inlet located downstream of
Los Osos Valley Road. The site that has been identified would be located in an area of regular
play within the golf course. The annual cost of regularly removing sediment from the basin
would be much less than the costs to remove the same sediment from Laguna Lake. Should the
Council support intercepting as much sediment as is reasonably possible, an estimate of the
annual operating costs to remove sediment and debris from the basin will be provided to the City
Council before making a final decision on this aspect of the project.
Additional Project Amenities and Enhancement Opportunities
One of the major findings and recommendations of the 2014 Laguna Lake Natural Reserve
Conservation Plan was to increase access and use of the lake as a valued passive recreational
amenity for boating, fishing, hiking, and bird watching1. Potential projects identified for further
detailed evaluation, design, and environmental review pursuant to the Conservation Plan include:
1. Improved signs and kiosks (currently underway pursuant to the Open Space Major City
Goal work plan);
2. An accessible walking path along the lake shoreline within the Reserve (also underway);
3. A raised boardwalk along the peninsula feature of the lake;
4. Improved boat launch and parking area;
5. Viewing platforms at two locations on the south side of the lake at Priolo-Martin Park
and adjacent to Laguna Middle School between the cul-de-sacs at the end of Vista Del
Lago and Vista Del Collados; and
6. Migratory fish passage improvements at the Prefumo Creek culverts below Madonna and
Los Osos Valley Roads, as well as potentially improved flood attenuation capacity and
surface elevation management through alterations of the Madonna Road culverts.
7. Future recycled water line extension to provide a base amount of water in the lake during
extreme drought events for dust control, weedy vegetation control, and to provide
watering opportunities for wildlife.
Option items 1-5, above, were endorsed by the Parks and Recreation Commission at their
1 “Throughout the planning process, community members were consistent in stating their preference that the lake
continue to be maintained to support recreational uses, and that the City should do more to increase access and use
of the Reserve as an attractive amenity” (p. 5).
8
Packet Pg. 87
meeting on August 3, 2016 (Attachment B).
Project Funding and Financing Recommendations
The recommended activities to be funded include the primary dredging and sediment
management components of the project, as well as ongoing operations and maintenance
associated with and the lake and sediment management aspects described above. These activities
have multiple benefits including drainage and flood control, recreation, water quality, habitat
restoration, and aesthetic benefits.
The expected project beneficiaries include residents and visitors of the City of San Luis Obispo,
as well as property owners that are proximate to Laguna Lake. The benefits accrued to these
parties must be allocated and the costs should be equitably assessed as a matter of sound public
policy. There are several mechanisms to levy the costs of allocated benefits. A preliminary
funding and financing plan was prepared and is included with the PDR.
Numerous grant opportunities were evaluated, as well as low-interest loans, City provided
funding sources, and land-based financing options. The recommended project, in its totality, is
comprised of a diverse combination of activities that would provide both community-wide, and
localized benefits. However, the initial and ongoing cost of accomplishing the project is
significant. Accordingly, a broad funding strategy is necessary for the project to be successful
given the range and scope of other pressing capital and maintenance projects needed throughout
the City. In order to provide the necessary funding to implement the various project elements, the
following recommendations are presented for consideration:
1. Monitor potential State and Federal grant programs on an ongoing basis. As each
potential project element is developed and approved, review the applicable programs for
the feasibility of a successful application, level of potential funding, and funding schedule
of the program. Because of the level of funding required and the broad range of benefits
provided, the highest priority should be given to grant programs that focus on water
quality, habitat restoration, non-point source management, and recreational development.
At this time, State of California grant funding has been identified for several of the
project’s sediment management and amenity enhancement features based on staff’s prior
experience. These are:
a) Peninsula Boardwalk - California Department of Parks and Recreation, Habitat
Conservation Fund Trails Program
b) Boat Launch and Parking Area – California Department of Boating and
Waterways
c) Creek and Shoreline Stabilization Projects, Fish Passage and Flood Control
Improvements – California Wildlife Conservation Board
8
Packet Pg. 88
2. Pursue land-based financing. Formation of a benefit-assessment district would provide a
vehicle for sediment removal and ongoing maintenance funding that would be allocated
based on the level of localized benefit that the project provides. Multiple districts or
zones may be necessary to separate the level of benefits anticipated in various areas,
although the allocation between these types of benefits cannot be determined until the
project benefits are quantified and addressed in the Engineer’s Report that would support
district formation. However, in the event that the Engineer’s Report cannot provide
quantifiable evidence of specific property benefit, a Community Facilities District (CFD)
is recommended to be pursued. A CFD has a higher threshold for successful formation,
but does not require an Engineer’s Report.
The potential for land-based financing was first included in Council direction set forth in
2010. Following the prospective selection of the preferred project as contemplated in this
Council Agenda Report, staff will work with the consultant team to determine the
feasibility of land-based financing options through public outreach with potentially
affected property owners and through public opinion research. As above, the use of a
benefit assessment district (if selected) requires the preparation of an Engineer’s Report
as a necessary condition precedent to district formation. This report would describe the
boundaries of the district and zones, the activities to be funded, the basis for allocating
costs, and the cost to each parcel. The formation of a benefit assessment district requires
voter approval.
3. Evaluate the level of financial contribution and commitment from the City’s General
Fund. The project is expected to accrue both community-wide benefits and specific
benefits to areas proximate to the lake. In support of the community-wide benefits, the
City should evaluate the level of financial contribution and commitment it is willing to
make with its General Fund through its normal, customary financial plan priority-setting
process.
4. Utilize an Infrastructure State Revolving Fund (ISRF) low-interest loan. The California
Infrastructure and Economic Development Bank (I-Bank) provides low interest loans for
eligible projects, such as:
a) Drainage, Water Supply, and Flood Control including ditches, levees, pumps,
pipes, as well as the acquisition, improvement, maintenance, and management of
flood plain areas and all equipment used in the associated maintenance and
operation;
b) Environmental Mitigation Measures including required construction or
modification of public infrastructure, and purchase and installation of pollution
control and noise abatement equipment; and
c) Parks and recreational facilities.
Financing amounts range from $50,000 to $25,000,000 per project with a maximum 30-
year term. The interest rate for each loan is set at the time the loan is approved and is
based on the Interest Rate Benchmark and Interest Rate Adjustments. For loans equal or
8
Packet Pg. 89
greater to $250,000, a one-time origination fee of $10,000 or 1% of the original loan
amount, whichever is greater is due at closing. The City would need to pledge a piece of
City-owned real property of equal or greater value as security for the loan.
A low-interest credit facility provided through ISRF would be a key element of the
overall funding and financing strategy as a means of providing the up-front capital
necessary to undertake the project, while revenues streams from potential land-based
financing and the City’s General Fund would be used for debt service. Staff met with
senior I-Bank representatives in Sacramento in July 2016 to ensure that the proposed
project meets with their eligibility and underwriting requirements, as well as to ensure
that the City would have adequate credit capacity for this project as well as other future
capital infrastructure projects. Based on this meeting and subsequent I-Bank review, the
City has been invited to apply.
CONCURRENCES
The Parks and Recreation and Public Works Departments have provided their concurrence for
the recommendations set forth in this Council Agenda Report.
ENVIRONMENTAL REVIEW
There is no environmental review required to provide direction on the recommended preferred
project options under the California Environmental Quality Act (CEQA). Once the preferred
alternative is selected, however, the City and its consultant team will be able to develop and
provide a detailed project description upon which the environmental review process will be
based. The City Council’s direction on the preferred project options is not intended to preclude
the formal alternatives analysis that would be required under CEQA if a full Environmental
Impact Report (EIR) is determined to be the appropriate environmental document.
In addition, the project will require review and regulatory permits from numerous other agencies
in order to be lawfully conducted, potentially including: California Department of Fish and
Wildlife; Regional Water Quality Control Board; Air Pollution Control District; U.S. Fish and
Wildlife Service; and, the National Oceanic and Atmospheric Administration (NOAA) Fisheries
Division.
FISCAL IMPACT
The fiscal impacts associated with the Laguna Lake Dredging and Sediment Management
Project, as recommended, are substantial. Staff anticipates that the total recommended project
cost is between $10-12 million. This estimate is based on known hard costs associated with
dredging production, dewatering, and sediment disposal as described above; however, exact
regulatory permit requirements and mitigation measures associated with the project are not yet
known (although mitigation costs as a percentage of total project costs are included for
estimating purposes, see Appendix F of the PDR), nor are exact costs and prospective grant
awards associated with project amenities and enhancements yet known.
8
Packet Pg. 90
Following the City Council’s feedback on the preferred project alternative, it is expected that
staff will return with more detailed costs and articulation of the benefits that will accrue to the
community, to neighboring property owners and residents, and to the natural ecosystems found
within Laguna Lake and its surroundings. As overall project costs and project feasibility are
further refined based on subsequent engineering, environmental review, and evaluation of the
potential for land-based financing, staff will return to Council for additional discussion and
subsequent action steps necessary to move the project to “shovel ready” status.
ALTERNATIVES
The City Council could:
1. Request additional information or analysis from staff.
2. Continue consideration of the recommendation with direction to staff on necessary
changes.
3. Select some of the recommended options, while selecting alternatives for other options.
Because there are five different preferred project elements set forth in the
recommendation, and there are various aspects to consider within each project element,
there are many possible permutations from which project choices could be selected.
AVAILABLE FOR REVIEW IN THE COUNCIL OFFICE
1. Master Plan Laguna Lake Park (1961)
2. Laguna Lake Management Program (1982)
3. Laguna Lake Technical Appendix (1982)
4. Laguna Lake Park Master Plan (1993)
5. Council Agenda Report (2009)
6. Council Agenda Report (2010)
7. Laguna Lake Natural Reserve Conservation Plan (2014)
8. Preliminary Dredging Report (2016)
These documents are also available for review on the City’s website using the following link:
http://www.slocity.org/government/department-directory/city-administration/natural-
resources/laguna-lake
Attachments:
a - Laguna Lake Dredging and Sediment Management - Map Set
b - Parks and Recreation Commission Draft Minutes of 8-3-16
c - Council Reading File
8
Packet Pg. 91
8.a
Packet Pg. 92 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 93 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 94 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 95 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 96 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 97 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 98 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 99 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
8.a
Packet Pg. 100 Attachment: a - Laguna Lake Dredging and Sediment Management - Map Set (1447 : Laguna Lake Dredging and Sediment Project - Preferred
Minutes - DRAFT
PARKS AND RECREATION COMMISSION
3 August, 2016
Regular Meeting of the Advisory Body Committee Commission
CALL TO ORDER
A Regular Meeting of the Parks and Recreation Commission was called to order on the 3rd day of August,
2016 at 5:32 p.m. in the City Council Chambers located at 990 Palm Street, San Luis Obispo, California,
by Chair Whitener.
ROLL CALL
Present: Committee Members Douglas Single, Greg Avakian and newly sworn-in Commissioner Rodney
Thurman, and Chair Jeff Whitener
Absent: Susan Olson, Keri Schwab, Susan Updegrove,
Staff: Parks and Recreation Director Shelly Stanwyck, Recreation Supervisor Devin Hyfield, Natural
Resources Manager Bob Hill
PRESENTATIONS, INTRODUCTIONS, APPOINTMENTS
1. Oath of Office
The City Clerk provided the Oath of Office for new Parks and Recreation Commissioner;
Rodney Thurman
PUBLIC COMMENT ON ITEMS NOT ON THE AGENDA
None.
CONSENT AGENDA AND CONSIDERATION OF MINUTES
ACTION: APPROVE THE MEETING MINUTES OF JULY 6, 2016 AS AMENDED BY
COMMITTEE MEMBER AVAKIAN, SECOND BY COMMITTEE MEMBER SINGLE.
2. Consideration of Minutes
CARRIED 4:0:0:3 to approve the minutes of the Parks and Recreation Advisory Body for the
meeting of 07/06/2016.
AYES: AVAKIAN, SINGLE, THURMAN, WHITENER
NOES:
ABSTAIN:
ABSENT: OLSON, SCHWAB, UPDEGROVE
8.b
Packet Pg. 101 Attachment: b - Parks and Recreation Commission Draft Minutes of 8-3-16 (1447 : Laguna Lake Dredging and Sediment Project - Preferred
DRAFT Minutes – Parks and Recreation Commission Meeting of August 3, 2016 Page 2
PUBLIC HEARINGS AND BUSINESS ITEMS
3. Presentation of Conceptual Designs and Proposed Park Site Plan for Froom/Il Villagio
Project
ACTION: RECEIVE INFORMATION AND PROVIDE FEEDBACK
Contract Planner, Shawna Scott, presented to the Commission the Conceptual Park Site
Plan component of the Froom / Il Villagio Specific Plan (Madonna on Los Osos Valley
Road Specific Plan). The proposed project would require several entitlements, which
would ultimately lead to the development of the project site. The applicant is proposing
a mix of land uses including a Continuing Care Retirement Community, housing,
commercial, open space, and park land. The applicant has identified an additional,
adjacent, 7.4-acre parcel located within the City limits as the potential site for a park.
Ms. Scott added that this is the first review of the project by the Parks and Recreation
Commission. She noted that the applicant is seeking early feedback from the
Commission on the proposed, conceptual, park facilities identified for the Specific
Plan, and for the Commission to provide preliminary input with respect to their
potential consistency with policies and programs contained in the Parks and Recreation
Element before preparing the Draft Specific Plan for the project.
Ms. Scott noted that the applicant team met with Parks and Recreation while
developing conceptual plans to determine the character and range of improvements
desired in a park for this project. The applicant has made an effort to make the character
of the proposed park more “naturalistic”, celebrating the “uniqueness of the site”. In
addition, parking and access to the open space have been identified as priorities at this
location. Ms. Scott said that the applicant is proposing a 4.7-acre park with the
following amenities:
Parking lot area to provide approximately 26 spaces
Historic plaza including relocated historic residence and bunkhouse (to be used as a
ranger’s office and storage building) and a public restroom
Playground area with naturalistic equipment
Dog park area
Wetland overlook
Trail rest area
Drought-tolerant landscaping
Developer Representative, Pam Ricci, RRM spoke about the park design
Commission Comments followed.
Commissioner Single asked for clarification on screening between current development (Home
Depot) and Primary Park in reference to area in between park and home depot. Director
Stanwyck responded that loading area could not be adjusted but that fencing could be required
to alleviate safety concerns behind the trees. Commissioner Single expressed concern about
8.b
Packet Pg. 102 Attachment: b - Parks and Recreation Commission Draft Minutes of 8-3-16 (1447 : Laguna Lake Dredging and Sediment Project - Preferred
DRAFT Minutes – Parks and Recreation Commission Meeting of August 3, 2016 Page 3
safety and suggested small fencing. Ms. Ricci responded that the plans at this time are
conceptual.
Commissioner Thurman asked about workout equipment and the continued usage of the
equipment.
Commissioner Avakian asked about access to the park with the adjacent Home Depot and
Costco traffic. Ms. Ricci commented added that there has been discussion with current stores
for alternate routes.
Commissioner Avakian commented on senior living and access to the trail through the new
proposed neighborhood. Ms. Ricci added that there would be additional pedestrian access
between residential trails with a five-minute walk. Commissioner Thurman commented about
trailhead plaza being private. Commissioner Avakian asked about lighting and ADA access.
Chair Whitener asked about connectivity of the park to City. Ms. Scott responded that the park
would connect to Irish hills and current development with potential additional connection.
Commissioner Single said he viewed the conceptual park design more as a pocket park and
noted the need for a dog park in this area.
Chair Whitener added he was not in support of the location as there was not enough usable park
space.
Public Comments:
Michael Parolini, San Luis resident, commented that the conceptual design does not feel like a
typical park given its isolation and potential maintenance issues and suggested this located be
considered as open space.
Neil Havlik, San Luis resident, agreed that this is not an ideal location for a park.
John Madonna, San Luis resident, spoke about the ease of access to the trailhead as opposed to
the access from Madonna Road.
4. Update for Laguna Lake Dredging Project Relative to Laguna Lake Park
ACTION: RECEIVE INFORMATION AND PROVIDE FEEDBACK
Natural Resources Manager, Bob Hill, presented the Commission an update on the Laguna
Lake Dredging and Sediment Management Project relative to the Laguna Lake Park Area. He
added that he is seeking the Commission’s input and consensus relative to the aspects of the
project that are pertinent to the recreational uses at Laguna Lake Park and Natural Reserve.
Commission Comments followed.
Commissioner Thurman commented about capturing sediment attachment into the lake. Hill
explained the procedure in excavation of sediment and dewatering plans for removal.
8.b
Packet Pg. 103 Attachment: b - Parks and Recreation Commission Draft Minutes of 8-3-16 (1447 : Laguna Lake Dredging and Sediment Project - Preferred
DRAFT Minutes – Parks and Recreation Commission Meeting of August 3, 2016 Page 4
Commissioner Single asked about the dry lake conditions and cost associated with dredging.
Staff Hill explained difference between hydraulic (wet) and mechanical (dry) dredging and
condition of lake during dry conditions.
Commissioner Avakian asked about the project duration and impact on other park usage. Staff
Hill responded that dredging would potential occur over several seasons to minimize
construction impacts and employ a sediment management strategy would limit amount of
sediment flowing into lake, thereby minimizing future impacts to the lake. Staff Hill added that
there would be minimal impacts to the public and estimated approximately 400 cubic yards per
day could be removed (approximately 10 truckloads).
Public Comments:
Mike Parolini asked about the cost of the project and the tax incurred by the residences of
Laguna Lake.
John Smeglski, San Luis resident, asked if the improvements to Vista Lago Park would be
associated with the project. Staff Hill responded to provide feedback about how the
improvements could be incorporated.
5. Selection of Wes Conner Awardee for 2016
Director Stanwyck recommended the Commission postpone this agenda item to the September
meeting to allow the full Commission the opportunity to consider and select the Wes Conner
awardee.
ACTION: MOTION BY COMMITTEE MEMBER AVAKIAN, SECOND BY COMMITTEE
MEMBER SINGLE, to recommend postponing the selection of the 2016 Wes Conner Awardee
to the September 7, 2016 meeting. Motion passed 4:0:3:0 on the following roll call vote:
AYES: AVAKIAN, SINGLE, THURMAN, WHITENER
NOES:
ABSTAIN:
ABSENT: OLSON, SCHWAB, UPDEGROVE
6. Discussion of Annual Park Tour Dates and Topics
Director Stanwyck explained the itinerary of annual park tour and potential locations to visit.
The Commission agreed to finalize this at its September meeting.
COMMITTEE COMMUNICATIONS
Director’s Report
Director Stanwyck provided a brief overview of current Parks and Recreation programming.
Hydro Flask Rewards for staff
Box Art Policy – Vote for next locations to be painted by August 28th
SLO Triathlon - a Success!
Movies in the Mission, 8/6, 8/13, 8/20
8.b
Packet Pg. 104 Attachment: b - Parks and Recreation Commission Draft Minutes of 8-3-16 (1447 : Laguna Lake Dredging and Sediment Project - Preferred
DRAFT Minutes – Parks and Recreation Commission Meeting of August 3, 2016 Page 5
Family Overnight Camp Out in Laguna Lake Park will be held on August 13-14
Skate Park Ramp n’ Roll 8/20 (Fun & Educational Event)
Volunteer Appreciation Dinner 9/22 (at Jack House)
Commission Communications
LIAISON REPORTS
Adult and Senior Programming: Commissioner Single said adult softball ended last week
and it was a great season. Fall softball sign-ups are starting. French Park pickleball is
being played twice weekly after restriping of the basketball courts. The Ludwick
Community Center hosts volleyball and table tennis – and attendance is in good numbers.
Adult soccer is starting at Damon Garcia Sports Fields. Seniors are staying active with
fun, well-attended, activities at senior center including bunko and bridge. Commissioner
Single requested a list of Senior Center Board Meeting dates.
Bicycle Advisory: No report. Commissioner Olson absent.
City Facilities (Damon Garcia, Golf, Pool & Joint Use Facilities): Commissioner
Avakian said that summer is busy. Damon-Garcia is open as of August 1 but still closed
on Mondays for field recovery. Jack House weddings are booked through October. New
tables were ordered for the Ludwick Center. The City/County Library conference room
will for library use from October 2016 through January 2017. The Swim Center saw rise
in attendance and will be closed for two weeks in August for maintenance. Golf Course
had good summer with rounds up 100 from previous month and 550 rounds in one
weekend. Increased youth participation at the Golf Course and increase in merchandise
sale. Tournaments were held over summer months. Middle school classes held at Golf
Course during school year.
Jack House Committee: No Report. Vice Chair Updegrove absent.
Tree Committee: No Report. New subcommittee assignment for Commissioner
Thurman.
Youth Sports: Chair Whitener said YSA had some issues with field use due to
construction at SLO High School. YSA is planning a meeting with the School District to
discuss topics related to youth sports.
ADJOURNMENT
The meeting was adjourned at 7:55 p.m. The next Regular meeting of the Parks and Recreation
Commission is scheduled for 07, September, 2016 at 5:30 p.m., in the City Council Chambers, 990 Palm
Street, San Luis Obispo, California.
APPROVED BY THE PARKS AND RECREATION COMMISSION: 09/07/2016
8.b
Packet Pg. 105 Attachment: b - Parks and Recreation Commission Draft Minutes of 8-3-16 (1447 : Laguna Lake Dredging and Sediment Project - Preferred
Page intentionally left
blank.
Laguna Lake Dredging & Sediment Management
Presentation to City Council, September 20, 2016
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
1
Laguna Lake Dredging & Sediment Management
Presentation to City Council, September 20, 2016
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
2
Receive and file the Preliminary Dredging Report (the “PDR”) prepared by MNS
Engineers, Inc. and, as further described in the PDR, direct staff to proceed with
further analysis and further recommendations related to the following preferred
project alternative:
1.Use of hydraulic or cyclonic dredging equipment as the dredging technology;
2.Removal of 50,000 cubic yards of sediment from the Laguna Lake as the
dredging project option;
3.Mechanical dewatering at Laguna Lake Park as the dewatering location and
method;
4.Off-site disposal at Cold Canyon Landfill as the sediment deposition location
and facility;
5.Creek bank restoration and installation of a sediment basin at Laguna Lake
Golf Course along Prefumo Creek, as well as shoreline restoration at the
lake itself, as short-term sediment management strategies.
Staff Recommendation:
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
3
Laguna Lake Natural Reserve is 344 acres
Presentation to City Council, September 20, 2016
Ca. 1900s –Laguna Lake is a naturally occurring freshwater lake
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
4
Presentation to City Council, September 20, 2016
USGS, 1895 –Prefumo Creek did not drain into the lake until ~1960
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
5
Presentation to City Council, September 20, 2016
1965 1977
Laguna Lake Dredging & Sediment Management
6
Presentation to City Council, September 20, 2016
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
7
The center of the lake is filling in at a rate of 1”-3” per year on average
Presentation to City Council, September 20, 2016
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
8
Prior Planning & Studies
1.Laguna Lake Master Plan, 1961
2.Laguna Lake Management Plan, 1982
3.Laguna Lake Park Master Plan, 1991 (amended 1998 and 2005)
4.Council Agenda Report, 2009
5.Laguna Lake Natural Reserve Conservation Plan, 2014
Current Work Completed
1.A review the current status of the lake, previous studies, and
management documents
2.New geotechnical and water quality testing data
3.New biological and cultural resource assessments
4.A review of applicable dredging technologies and approaches
5.Development of dredging alternatives
6.Recommendations for deposition and disposal of sediments
7.Dredging operations recommendations
8.Recommendations for future sediment management
9.An analysis of project funding options
Presentation to City Council, September 20, 2016
Primary Areas of Interest for Dredging Project
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
9
Presentation to City Council, September 20, 2016
Alternative 1 –Small Project –36,500 cubic yards
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
10
Presentation to City Council, September 20, 2016
Alternative 2A –Medium Project –50,000 cubic yards
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
11
Presentation to City Council, September 20, 2016
Alternative 2B –Medium Project –85,000 cubic yards
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
12
Presentation to City Council, September 20, 2016
Alternative 3 –Large Project –167,000 cubic yards
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
13
Presentation to City Council, September 20, 2016
Example Project –City of Westlake Village, CA
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
14
Presentation to City Council, September 20, 2016
Example Project –City of Westlake Village, CA
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
15
Presentation to City Council, September 20, 2016
Example Project –City of Westlake Village, CA
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
16
Presentation to City Council, September 20, 2016
Example Project –City of Westlake Village, CA
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
17
Presentation to City Council, September 20, 2016
Example Project –City of Westlake Village, CA
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
18
Presentation to City Council, September 20, 2016
Potential dewatering and hauling plan
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
19
Presentation to City Council, September 20, 2016
Dredging Project Cost Matrix
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
20
For planning, tipping fee assumed @ $33.75 per CY.
Cost estimates include 20% markup for Contractor OH&P and 20% Estimate Contingency.
Costs for Mechanical Dredging alternatives may change due to mobilization estimates.
Alternative Volume Dredging Method Dewatering Method Total Cost (Million)Cost Per CY
1A 36,500 Hydraulic Dewatering Pond $5.26 $144.11
1B 36,500 Hydraulic Mechanical Dewatering $6.34 $173.77
MECH1 36,500 Mechanical N/A $6.44 $176.31
2A-Low 50,000 Hydraulic Dewatering Pond $6.95 $138.92
2B-Low 50,000 Hydraulic Mechanical Dewatering $8.68 $173.68
MECH2-Low 50,000 Mechanical N/A $7.82 $156.32
2A-High 85,000 Hydraulic Dewatering Pond $11.32 $133.17
2B-High 85,000 Hydraulic Mechanical Dewatering $14.55 $171.22
MECH2-High 85,000 Mechanical N/A $12.75 $150.05
3A 167,000 Hydraulic Dewatering Pond $21.56 $129.12
3B 167,000 Hydraulic Mechanical Dewatering $27.31 $163.50
MECH3 167,000 Mechanical N/A $23.62 $141.45
Presentation to City Council, September 20, 2016
SMALLMEDIUMLOWMEDIUMHIGHLARGE
Dredging Project Cost Matrix
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
21
For planning, tipping fee assumed @ $33.75 per CY.
Cost estimates include 20% markup for Contractor OH&P and 20% Estimate Contingency.
Costs for Mechanical Dredging alternatives may change due to mobilization estimates.
Alternative Volume Dredging Method Dewatering Method Total Cost (Million)Cost Per CY
1A 36,500 Hydraulic Dewatering Pond $5.26 $144.11
1B 36,500 Hydraulic Mechanical Dewatering $6.34 $173.77
MECH1 36,500 Mechanical N/A $6.44 $176.31
2A-Low 50,000 Hydraulic Dewatering Pond $6.95 $138.92
2B-Low 50,000 Hydraulic Mechanical Dewatering $8.68 $173.68
MECH2-Low 50,000 Mechanical N/A $7.82 $156.32
2A-High 85,000 Hydraulic Dewatering Pond $11.32 $133.17
2B-High 85,000 Hydraulic Mechanical Dewatering $14.55 $171.22
MECH2-High 85,000 Mechanical N/A $12.75 $150.05
3A 167,000 Hydraulic Dewatering Pond $21.56 $129.12
3B 167,000 Hydraulic Mechanical Dewatering $27.31 $163.50
MECH3 167,000 Mechanical N/A $23.62 $141.45
Presentation to City Council, September 20, 2016
SMALLMEDIUMLOWMEDIUMHIGHLARGE
Examples of erosion sources in the watershed above the lake
Photo credit: Aleksandra Wydzga
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
22
Presentation to City Council, September 20, 2016
Areas to address erosion sources above the lake
Photo credit: Aleksandra Wydzga
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
23
Presentation to City Council, September 20, 2016
Examples of erosion sources within the Laguna Lake Natural Reserve
Photo credit: Aleksandra Wydzga
Photo credit: Aleksandra Wydzga
Laguna Lake Dredging & Sediment Management
24
Presentation to City Council, September 20, 2016
Laguna Lake Watershed Map
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
25
Presentation to City Council, September 20, 2016
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
26
Accessible Path, Signs & Kiosks, Peninsula Boardwalk, Viewing Platforms, and Boat Launch Area
Presentation to City Council, September 20, 2016
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
27
Potential Funding Options and Strategy
1.State of California Grant Funding:
a)Peninsula Boardwalk -CA Department of Parks and
Recreation, Habitat Conservation Fund Trails Program
b)Boat Launch and Parking Area –CA Department of
Boating and Waterways
c)Creek and Shoreline Stabilization Projects, Fish
Passage Improvements –CA Wildlife Conservation
Board
2. Land-Based Financing:
a)Benefit Assessment District, or
b)Community Facilities District
3.City of San Luis Obispo General Fund
4.Infrastructure State Revolving Fund (ISRF) Loan, California
Infrastructure and Economic Development Bank
Presentation to City Council, September 20, 2016
Laguna Lake Dredging & Sediment Management
Brief Project History
Dredging Options
Sediment
Management Options
Project Amenities
Financing Options
Next Steps
28
Next Steps
1.MNS prepares 95% Plans, Specifications & Engineering for
preferred project alternative
2.Staff and consultant team continues to evaluate and refine
financing options through public opinion research and
outreach, as well as legal and technical review
3.Staff and consultant team pursues regulatory permits and
prepares CEQA documents for preferred project alternative
4.Staff and consultant team return to City Council with next
steps related to financing options.
Presentation to City Council, September 20, 2016
Robert A. Hill
Natural Resources
Manager
(805) 781-7211 or
rhill@slocity.org
Derek Johnson
Assistant City Manager
(805) 781-7112 or
djohnson@slocity.org
Doug Pike
Principal Engineer
MNS Engineers
(805) 688-5200 or
dpike@mnsengineers.com
Photo credit: Halden Petersen
Staff Recommendation:
Laguna Lake Dredging & Sediment Management
29
Presentation to City Council, September 20, 2016
Receive and file the Preliminary Dredging Report (the “PDR”) prepared by MNS
Engineers, Inc. and, as further described in the PDR, direct staff to proceed with
further analysis and further recommendations related to the following preferred
project alternative:
1.Use of hydraulic or cyclonic dredging equipment as the dredging technology;
2.Removal of 50,000 cubic yards of sediment from the Laguna Lake as the
dredging project option;
3.Mechanical dewatering at Laguna Lake Park as the dewatering location and
method;
4.Off-site disposal at Cold Canyon Landfill as the sediment deposition location
and facility;
5.Creek bank restoration and installation of a sediment basin at Laguna Lake
Golf Course along Prefumo Creek, as well as shoreline restoration at the
lake itself, as short-term sediment management strategies.