HomeMy WebLinkAbout06-20-2017 Item 11 Monterey/Osos Traffic Signal Installation Spec No. 91377 Meeting Date: 6/20/2017
FROM: Daryl R. Grigsby
Prepared By: Bryan Wheeler and Matt Crisp
SUBJECT: MONTEREY/OSOS TRAFFIC SIGNAL INSTALLATION,
SPECIFICATION NO. 91377
RECOMMENDATION
1. Approve Plans and Specifications for the “Monterey/Osos Traffic Signal Installation Project,
Specification No. 91377,” and authorize staff to advertise for construction bids; and
2. Authorize the City Manager to award a contract if the total of the bid plus contingency is
within the available project at time of award; and
3. Approve the transfer of $191,000 from various Public Works Transportation accounts to the
Monterey/Osos Traffic Signal Installation Project account.
DISCUSSION
Background
The annual Traffic Safety Report (“Report”) identified the intersection of Monterey and Osos as
a high collision rate intersection with correctable measures available. Red light violations in all
directions was the pattern of collision identified at the intersection and the Report recommended
signal mast arms to enhance visibility.
The initial CIP funding for the project, as requested in the 2015-2017 Financial Plan, did not
anticipate significant street work necessary for the project. During the design phase of this
project, all four corners of the intersection were identified for replacement particularly to address
tree root intrusion on one corner. Utility conflicts and limited space at the corners of the
intersection require the antiquated signal and streetlight pole foundations to be removed and new
signal pole foundations to be installed in the same locations. Each corner must then be
reconstructed. This practice is not commonly used because space is usually utilized adjacent to
existing foundations that does not require significant disruption of the corner. State and Federal
standards for pole placement and existing underground conflicts limit the poles to their existing
locations. The existing signal poles and foundations cannot be utilized, as they are well older
than current standards, and cannot be upgraded in their current configuration.
This increase in estimated project cost reflects increases in labor and materials for the project.
The project also includes ADA improvements on the southeast corner of the intersection. A
Ficus tree has created significant vertical displacement of the sidewalk. This disruption is
identified as problematic by the Engineering Department and requires temporary fixes to reduce
trip hazards. The Tree Committee approved the removal of the 36” box size Ficus tree located
near the intersection on January 26, 2016. The public notice requirement was followed and there
Packet Pg 143
11
was no appeal of the committee’s decision. The removal was conditional upon the reinstallation
of a 36” box size Ficus tree near the same location which is being proposed with this project.
CONCURRENCES
The Monterey and Osos Traffic Signal upgrades have been identified as a mitigation measure to
address the collision rates at the intersection in the Traffic Safety Reports completed in 2013,
2014, and 2015. The project is also identified in the 2015-17 Financial Plan.
ENVIRONMENTAL REVIEW
The project is Categorically Exempt from environmental review pursuant to CEQA Guidelines
Section 15304(i) (Class 2 – Replacement or reconstruction; replacement or reconstruction of
existing structures and facilities where the new structure will be located on the same site as the
structure replaced and will have substantially the same purpose and capacity as the structure
replaced). Upon approval of this item, and before bid solicitation, a Notice of Exemption will be
filed through the Community Development Department.
Packet Pg 144
11
FISCAL IMPACT
The Monterey and Osos Traffic Signal Installation project is identified in the 2015-17 Financial
Plan, Capital Improvement Plan, on Page F-29. This project is a Local Revenue Measure funded
project. The original budget request was in the amount of $225,000. There is currently a balance
of $217,600 remaining in the construction phase available for this project. Staff recommends the
transfer of funds from various completed project and transportation accounts in the amount of
$191,000, the estimated project cost of $375,000.
The project’s estimated construction costs are shown below:
Monterey/Osos Traffic Signal Installation, Specification No. 91377
Construction Costs $375,000
Construction Contingencies $33,000
Total for Construction $408,000
Available Funding $217,600
Funding difference -$191,000
The increase in construction costs are due to constraints discovered during the design of the
project. A communications vault and fiber optic line was discovered in the area during survey of
the intersection. Additionally, adjacent buildings on two corners have basements located
underneath the city sidewalk. These obstructions prevent the new signal poles to be in others
areas except for the existing streetlight pole locations. The process to remove the existing
streetlight pole foundation and install a new signal pole and foundation is longer than a normal
signal installation, resulting in increased contractor time and cost.
Additionally, as part of the project, several ADA upgrades are being performed to bring the
sidewalks within acceptable accessibility conditions. The southeast corner of the project must be
completely reconstructed with this signal installation, due to extensive tree root damage in the
sidewalk area.
Staff recommends the transfer of funds to the project’s construction account. A Budget
Amendment Request will transfer $191,143 from various Public Works – Transportation (50500)
accounts to the Monterey/Osos Traffic Signal In stallation project account. The project accounts
that funds are being transferred from are completed projects or master accounts for which the
projects identified have been completed. These transfers provide sufficient funding to support
project construction and of an 8% construction contingency. A fiscal impact summary of funding
sources is provided below. Several of these accounts are Local Revenue Measure accounts, and
are also indicated below.
Fiscal Impact Summary
Fund Account Phase Balance (to transfer) Account
101 90398 953 $7,508.94 Safety Report Implementation
(Measure G) 400 90398 953 $12,536.96
405 90398 953 $210.00
Packet Pg 145
11
400 91321 953 $277.20 Downtown Lighted Crosswalks
400 91321 954 $3,500.00
401 90872 953 $48,477.00 General Traffic Signal Improvements
(Measure G)
400 90849 953 $35,000.00 Sidewalk and Tree Replacement
401 91295 952 $83,633.06 Traffic Safety and Operations
(Measure G)
Costs By Type
ALTERNATIVES
1. Deny Authorization to Advertise and direct staff to redesign the project within the available
existing budget. This is not recommended as the ADA curb ramp upgrades must also occur at
the location.
2. Deny authorization to advertise. The City Council may choose not to authorize project
advertisement. This is not recommended since the project has been identified as a necessary
project in the Traffic Safety Report.
Attachments:
a - Council Reading File - Plans 91377
b - Council Reading File - Specials 91377