HomeMy WebLinkAbout20. ScreencheckFEIR311PublicSe 3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-1
Final EIR
3.11 PUBLIC SERVICES
The following section describes existing and planned public services, and evaluates the
operation and capacity of these services with the development of the Project. Public
services utilized during construction and operation of the Project include police and fire
protection, schools, and parks. The following agencies provide public services for the
Project site:
Table 3.11-1. Public Services Serving the Project Vicinity
Public Services Serving Avila Ranch
Fire Protection City of San Luis Obispo Fire Department
Law Enforcement City of San Luis Obispo Police Department
Public Schools San Luis Coastal Unified School District
Public Parks City of San Luis Obispo Department of Parks and Recreation
For information regarding public utilities such as water, wastewater, solid waste, and
energy utilities, please refer to Section 3.13, Utilities, and for public transportation and
parking, please refer to Section 3.12, Transportation and Traffic.
Development of the Project site with residential and commercial uses would increase
demand on City of San Luis Obispo (City) services, including fire protection, police
protection, and other City supported public services; however, the City has a system of
developer impact fees and required dedications or exactions established to address direct
demand for new facilities (e.g., park land), while potential increases in property tax revenue
associated with valuation of new homes, businesses, and other revenues (e.g., sales tax)
would help offset the increased ongoing cost of provision of public services to new
residents and commercial uses.
Information in this section was derived from the 2014 Land Use and Circulation Elements
Update EIR (LUCE Update EIR), as well as contacts with the San Luis Obispo Police
Department (SLOPD), San Luis Obispo City Fire Department (SLOFD), California
Department of Forestry and Fire Protection (CALFIRE), and the San Luis Coastal Unified
School District (SLCUSD).
3.11.1 LUCE Update EIR
The LUCE Update EIR analyzed the impacts of increased demand for public services
associated with development of the Project site related to the adoption of land use
designations in the 2014 LUCE Update. The LUCE Update EIR noted that the Project site
3.11 PUBLIC SERVICES
3.11-2 Avila Ranch Development Project
Final EIR
is located beyond the City Fire Department’s 4-minute travel time area and recommended
adding a fifth fire station to improve response time in southern areas of the City in order to
address potential fire safety impacts. The LUCE Update EIR concluded that increased
demand for police services resulting from additional population associated with buildout
allowed under the LUCE Update would not require expanded law enforcement facilities
that would have the potential to result in significant environmental impacts.
With regard to schools, the LUCE Update EIR found that while generation of additional
school-age children from total LUCE buildout could potentially contribute to over-capacity
conditions of local schools and the need for facilities expansion, it is unlikely that the
expansions would result in significant adverse environmental impacts.
The LUCE Update EIR parks and recreation analysis determined that although the City’s
existing per capita parkland standard is not currently achieved, the LUCE buildout would
provide additional acres of parkland within the City and a slightly improved parkland per
capita ratio when compared to existing conditions. On a Citywide basis, the LUCE buildout
would result in an increase in the existing per capita parkland area and, therefore, less than
significant environmental impacts related to parks and recreation facilities.
3.11.2 Environmental Setting
Figure 3.11-1 shows the key existing public facilities operated by the City, which are
located in the vicinity of the Project.
3.11.1.1 Police Services
The San Luis Obispo Police Department (SLOPD) provides a variety of law enforcement
and community services. The City operates out of one main police station which is located
at 1042 Walnut Street at the intersection of Santa Rosa (Highway 1) and U.S. Highway
101. The building was constructed in 1969 and is currently at full occupancy and in need
of rehabilitation and growth. Full-time Police Department staff includes 85.5 employees,
60 of whom are sworn police officers who provide law enforcement, supervision, and
management duties. The SLOPD is divided into two police bureaus, with a Police Captain
commanding each. The Operations Bureau includes Patrol Services, Traffic Safety,
Downtown bike officers, homeless services through a Community Action Team, Special
Enforcement Team, and Neighborhood Services, while the Administration Bureau includes
Administrative Services, Investigative Division, Communications Division, and the
Records Unit (SLOPD 2015).
CF
CF
F
F
F
F
HP
P
HP
Los RanchosLos Ranchos
Elementary SchoolElementary School
LagunaLaguna
Middle SchoolMiddle School
Los Ranchos
Elementary School
San Luis
High School
Laguna
Middle School
San LuisSan Luis
ObispoObispo
CalCal
PolyPoly
San Luis
Obispo
Cal
Poly
Bishop
Peak
101
101
227
1
JESPERSON ROADJESPERSON ROADLOS OSOS VALLEYLOS OSOS VALLEY ROAD ROADO’CONNER
WAYO’CONNER
WAYORCUT
T
RO
ADORCUT
T
RO
AD
TANK FATANK FARM ROADRM ROAD
HIGUERA STREETHIGUERA STREETSUBURBANSUBURBAN
ROADROADLOS OSOS VALLEY ROADBUCKLEY ROAD
JESPERSON ROADTANK FARM ROAD
HIGUERA STREETSUBURBAN
ROADO’CONNER
WAYORCUT
T
RO
AD
San Luis Obispo City Fire Station
CalFire Station
San Luis Obispo City Police Station
California Highway Patrol Office
Park/ Open Space
School
Incorporated City
San Luis Obispo County
F
CF
P
HP
0 5,000
SCALE IN FEET
N
Public Services within the Region 3.11-1
FIGURE
LEGEND
Project site
3.11-3
3.11 PUBLIC SERVICES
3.11-4 Avila Ranch Development Project
Final EIR
According to the Safety Element of the City’s General Plan, the SLOPD has a 30 percent
available-time objective for patrol response and the current ratio of officers to 1,000 people
in the City is 1.27 (City of San Luis Obispo 2014b). Available time is the portion of total
time that a patrol unit is not previously assigned or otherwise unavailable for response to a
new emergency call for service. Potential changes in needs for the SLOPD staffing plan
are considered as part of overall City budget priorities. Additionally, equipment
enhancement programs exist and are also considered in the context of the City budget
process and available grants.
In 2015, police officers took 31,924 calls for service (CFS) with a permanent population
of 45,950 and a daily service population of approximately 90,000. A 5-year average of CFS
and permanent population equates to each resident requiring a CFS at a rate of 0.67 CFS
per resident per year. One officer takes on an average of 925 calls per year. Each increase
of 1,400 permanent residents would require an addition of one officer, not including
investigations personnel, communications, records, property, or admin staff. Additionally,
approximately 15 percent of police officer shift time is spent in the Downtown area, and
CFS that are outside of that area will naturally increase response times. Any increase in
population in the City will have a negative impact on police services (City of San Luis
Obispo, comm. with Keith Storton 2016).
3.11.1.2 Fire Protection Services
The Project site is located in a Moderate Fire Severity Zone. Moderate wildfire hazards
within the Project area are associated with open grasslands and scattered trees, but not
highly flammable chaparral habitats. The site is currently undeveloped and has been
historically used for cultivated agriculture and pasture to support grazing. Much of the
Project site is typically plowed to facilitate cultivation, minimizing vegetative growth.
Tank Farm Creek traverses the site diagonally from the northeast to southwest and supports
a riparian corridor of approximately 10 to up to 100 feet in width. The lack of dense brush,
presence of a moist riparian corridor factors, and frequent cultivation all reduce existing
onsite wildfire hazards.
San Luis Obispo City Fire Department (SLOFD) provides emergency and non-emergency
fire, rescue, and medical services, with support from CALFIRE through mutual aid
agreements, as described below. Emergency services include fire response, advanced life
support (“paramedic”) emergency medical response, hazardous materials response,
technical rescue response, and public assistance. All City engine companies include
paramedic staff and equipment capabilities. Non-emergency services include fire and life
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-5
Final EIR
safety inspections, building inspections, fire code investigations, code compliance, and
public education. The SLOFD currently operates four fire stations with a total of 54 full-
time employees. Four of these employees are administrative personnel, two are vehicle and
equipment mechanics, six are fire prevention and educational staff, and the remaining 42
are firefighters with emergency response capabilities (SLOFD 2015a).
Fire Station One: Constructed in 1996, this station is located south of Downtown at 2160
Santa Barbara Avenue. This is the newest firehouse in the City and it houses the Fire
Administrative staff, the Fire Prevention Bureau, the department’s apparatus maintenance
shop, the City’s Emergency Operations Center, as well as emergency response personnel
and apparatus. On the emergency response side, this station is staffed by a Battalion Chief
and a four-person paramedic company which responds on a 100-foot tillered quint ladder
truck. Also housed at this station is a Type VI wildland response vehicle (Patrol 1), a non-
transport medical response unit (Squad 1), and the reserve ladder truck (a 1993 75-foot
Quint).
Fire Station Two: Constructed in 1954, this station is located near the California
Polytechnic State University (Cal Poly) campus at 126 North Chorro Street. This is the
oldest station in the City and it is staffed with a three-person paramedic engine company
(Type I pumper/fire engine). Additional equipment housed at Fire Station 2 includes a
state-owned Type I pumper/fire engine and a four-wheel-drive pickup truck for Open
Space rescue support.
Fire Station Three: Constructed in 1960, this station is located at 1280 Laurel Lane and is
the only fire station on the east side of the Southern Pacific Railroad line. The station is
staffed with a three-person paramedic engine company (Type I pumper/fire engine).
Additional equipment housed at Fire Station 3 includes the reserve Type I pumper/fire
engine.
Fire Station Four: Constructed in 1978, this
station is the western-most station and is
located in the area of Laguna Lake at 1395
Madonna Road and is the closest station to the
Project site. The station is staffed with a three-
person paramedic engine company (Type I
pumper/fire engine). Additional equipment
housed at Fire Station 4 includes an unstaffed
Type III fire apparatus.
Fire Station Four is located at 1395 Madonna
Road and is the closest station to the Project
site.
3.11 PUBLIC SERVICES
3.11-6 Avila Ranch Development Project
Final EIR
Existing SLOFD Response Times
According to the City of San Luis Obispo’s General Plan Safety Element, sufficient Fire
Department resources should be deployed to facilitate a travel time of emergency response
apparatus to all City emergencies requiring the use of lights and siren of 4 minutes or less,
95 percent of the time. In 2016, the City Council directed staff to adopt the more recognized
standard of a travel time of 4 minutes or less 90 percent of the time. Fire Station Four is
located at 1395 Madonna Road, approximately 2 miles west of the Project site. According
to the City Geographic Information System (GIS) analysis, the response time for
emergencies to the Project site are outside of the General Plan Safety Element minimum
travel time goal of 4 minutes or less of travel time (SLOFD 2015b).
The lack of 4‐minute response time coverage in the southern portion of the City was
identified in the 2009 Fire Department Master Plan and the LUCE Update EIR, which both
recommended adding a fifth fire station and crew to improve response time in southern
areas of the City (City of San Luis Obispo 2014a; SLOFD 2009). In addition, existing City
department daily firefighter staffing is not adequate as an initial force to extinguish serious
fires without help from CALFIRE. The Fire Department Master Plan determined that each
shift for SLOFD would require a minimum of 14 personnel on duty at any given time;
however, in order to adequately address calls for service, daily staffing would need to be
increased to 16 personnel per day. The Fire Department Master Plan finds that the addition
of a fifth fire station in the southern area of the City would address this need for additional
firefighting personnel to address a major event. The Fire Department Master Plan
determined that increasing firefighter staffing at existing City fire stations alone would not
improve response times in the Project area nor allow simultaneous emergency calls to be
covered by a proposed fifth unit in the event a CALFIRE unit is not available (SLOFD
2009).
The City does not currently have an established development impact fee program to fund
development of new fire department facilities. However, the City is currently in the process
to consider establishing an impact fee program to fund a fifth SLOFD fire station to serve
the southern portion of the City (SLOFD 2015c). While the City is currently undergoing
this process, the timing for adoption of the new fee program has not been determined and
the timing of actual fire station site acquisition and development cannot be accurately
forecasted (SLOFD 2015c).
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-7
Final EIR
Mutual Aid Agreements between SLOFD and CALFIRE
In California, virtually all fire departments are signatories to the California Master Mutual
Aid Agreement. SLOFD has current interagency plans in partnership with CALFIRE and
is a participant in the California Master Mutual Aid Agreement within Mutual Aid Region
1.The California Master Mutual Aid Agreement establishes a formal process where
jurisdictions can give and receive fire or emergency assistance to other members within
their mutual aid region when it is needed. CALFIRE Fire Station 21 would be the
jurisdictional station to provide responses for the Project site. Fire Station 21 is located
approximated 3.5 miles to the east and would have a 6- to 8-minute response time to the
Project site (CALFIRE 2016a).
CALFIRE Fire Station 21: This station is located at San Luis Obispo Regional Airport on
4671 Broad Street and is one of the newest fire service facilities located in San Luis Obispo
County (County). This fire station is staffed with a two-person basic life support engine
company and a single-person airport crash rescue truck. This station does not provide
advanced life support (paramedic) services. This station provides other reserve and non-
staffed apparatus. The station is also staffed by a Paid Call Fire Company (non-full time)
to service the rescue and water tender (CALFIRE 2016b).
3.11.1.3 Schools
The San Luis Coastal Unified School District (SLCUSD) provides educational services for
the City, the City of Morro Bay, and a portion of the unincorporated areas of the County.
The SLCUSD operates a variety of educational programs and schools, which include 10
elementary schools, 2 middle schools, 2 high schools, 1 continuation school, and 1 adult
school (SLCUSD 2015a). The closest schools to the Project site are Los Ranchos
Elementary School (3.5 miles southeast), Laguna Middle School (3.4 miles northwest), and
San Luis High School (4.6 miles north). Table 3.11-2 summarizes existing capacity and
enrollment at SLCUSD schools from the 2014 to 2015 school year.
3.11 PUBLIC SERVICES
3.11-8 Avila Ranch Development Project
Final EIR
Table 3.11-2. Existing Capacity and Enrollment at SLCUSD Schools (2014-2015)
School Capacity Enrollment % Utilization1 Remaining
Capacity
Elementary
Baywood Elementary 432 352 81 80
Bellevue-Santa Fe Charter 154 154 100 0
Bishop’s Peak/Teach
Elementary
542 427 79 115
Del Mar Elementary 477 443 93 34
Hawthorne Elementary 390 310 79 80
Los Ranchos Elementary 460 463 101 -3
Monarch Grove
Elementary
470 347 74 123
Pacheco Elementary 528 541 102 -13
Sinsheimer Elementary 467 359 77 108
C.L. Smith Elementary 452 418 92 34
Total 4,624 4,372 3,996 3,814 86 87 558
Middle School
Laguna Middle School 1,118 688 62 430
Los Osos Middle School 1,073 583 54 490
Total 2,191 1,271 58 920
High School
San Luis High School 2,034 1,431 70 603
Morro Bay High School 1,400 867 62 533
Total 3,574 3,434 2,362 2,298 66 67 1,136
1 For elementary schools at or above 90 percent capacity – In 2014/2015, SLCUSD did not load three or more classrooms
at each elementary school site due to enhanced programs. Therefore, if additional capacity were needed, these programs
could potentially be moved to different spaces (with the exception of Bellevue-Santa Fe Charter which will remain at
100 percent due to programming).
Source: SLCUSD 2015b.
SLCUSD currently provides intra-district open enrollment, which allows parents a request
to enroll their children at any district school; the district approves requests on a space-
available basis. The ideal utilization of an elementary school site is 90 percent, and 85
percent for a middle school site (SLCUSD 2015b). According to the SLCUSD Enrollment
Projections Capacity Analysis 2014/15 Update, the majority of these schools currently
have the capacity to accept additional students; however, three elementary schools are
operating either at or over capacity, including Los Ranchos Elementary, the closest
elementary school to the Project site (see Table 3.11-2; SLCUSD 2015b).
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-9
Final EIR
3.11.1.4 Parks
The San Luis Obispo Parks and Recreation Department is responsible for providing the
community with park facilities, recreational programs, planning new park facilities, and
managing City open space that is accessible to the public. There are 21 parks and sports
facilities located throughout the City in
addition to 10 designated Natural
Reserves and open spaces (City of San
Luis Obispo 2015a). There are three
parks located in the general Project
vicinity, including Islay Hill Park (3.1
miles northeast), Las Praderas Park (1.5
miles northwest), and French Park (2.6
miles northeast) (City of San Luis
Obispo 2012). In addition, the Johnson
Ranch and Irish Hills Natural Reserve
open space areas and associated hiking
trails lie approximately 1.5 miles west of the Project site across U.S. Highway 101.
The City General Plan, Parks and Recreation Element, Policy 3.13.1 requires that
neighborhood and community park facilities be provided at a ratio of 10 acres of parkland
per 1,000 persons in expansion areas, of which, 5 acres should be neighborhood parks.
Under existing conditions, the City Parks Department maintains a total of 151.65 acres of
parks, landscape areas, and open spaces, of which 33.53 acres are neighborhood parks. This
results in approximately 3.32 acres of total parkland per 1,000 residents, and 0.72 acres of
neighborhood parks per 1,000 residents. Based on existing population and parks acreage
conditions, the City needs an additional 303 acres of park land to serve existing residents,
of which 195 acres should be neighborhood parks, to meet its per capita parkland standard
(City of San Luis Obispo 2012).
3.11.3 Regulatory Setting
3.11.3.1 Federal
No federal public service regulations or policies would be applicable to the Project.
Islay Hill Park is located 3.1 miles northeast of the
Project site and provides passive recreation
opportunities (i.e., trails).
3.11 PUBLIC SERVICES
3.11-10 Avila Ranch Development Project
Final EIR
3.11.3.2 State
California Code of Regulations Sections 17620 and 65995
California Code of Regulations (CCR) Section 17620 authorizes school districts to levy a
fee, charge, dedication, or other requirement against any construction of new residential,
commercial, and industrial uses within their boundaries to fund the construction of new
schools or school facilities. CCR Section 65995 limits the maximum fee that school
districts can assess. Section 65996 designates Section 17620 of the Education Code and
Section 65970 of the Government Code to be the exclusive method for considering and
mitigating development impacts on school facilities.
Senate Bill 50 (SB 50) (1998)
This bill requires that cities and counties mitigate impacts to school facilities as a condition
of approving new developments. SB 50 also authorizes school districts to levy statutory
developer fees at levels which may be significantly higher than previously permitted. To
levy fees higher than permitted, the school district must conduct a Needs Analysis and a
Fee Justification Study which address the justification of the levying of developer fees.
This legislation also stipulates that school impact fees are the sole and exclusive method
of mitigation for school enrollment impacts.
Quimby Act (1975)
The Quimby Act gives cities and counties the authority, by ordinance, to require the
dedication of land or payment of in‐lieu fees, or a combination of both, for park and
recreation purposes as a condition of approval of a tract map or parcel map. The Quimby
Act allows fees to be collected for up to 5 acres of parkland per 1,000 residents to serve
the needs of residents of the subdivision and the greater public residing in the City.
3.11.3.3 Local
City of San Luis Obispo General Plan
The City of San Luis Obispo is the provider of emergency protection services to residents
of the City. Applicable regulations that would affect the provision of public services are
based on local policies and other regulations that place requirements on the level of service
that must be provided. Established policies and regulations that would apply to the Project
are contained in the plans and policies section of the following General Plan Elements.
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-11
Final EIR
Parks and Recreation Element
Policy 3.13.1. The Parks System. The City shall develop and maintain a park system at a
rate of 10 acres of parkland per 1,000 residents. Five acres shall be dedicated as a
neighborhood park. The remaining five acres required under the 10 acres per 1,000
residents in the residential annexation policy may be located anywhere within the City’s
park system as deemed appropriate.
Policy 3.15.1 Neighborhood Parks. San Luis Obispo residents shall have access to a
neighborhood park within 0.5 to 1.0 mile walking distance of their residence.
Policy 3.15.3 Neighborhood Parks. All residential annexation areas shall provide
developed neighborhood parks at the rate of five acres per 1,000 residents.
Policy 3.15.4 Neighborhood Parks. In neighborhoods where existing parks do not
adequately serve residents, mini-parks may be considered.
Safety Element
Policy 3.0 Adequate Fire Service. Development shall be approved only when adequate fire
suppression services and facilities are available or will be made available concurrent with
development, considering the setting, type, intensity, and form of the proposed
development.
Policy 9.3 Program: Response Performance Standards. The following response-time
programs are intended to apply to recurrent types of emergencies, not rare, area-wide
disasters.
a)The Fire Department has set a response-time objective of four minutes. (The Fire
Department’s standard of coverage recommends that a three-person engine
company, with paramedic, meet this standard 95 percent of the time.)
b)The Police Department has set a 30-percent available-time objective for patrol
response. (“Available time” is the fraction of total time that a patrol unit is not
previously assigned or otherwise unavailable for response to a new emergency call
for service.)
c)The City will evaluate fire-flow capacities and identify deficiencies through testing
and modeling of the water system. For identified deficiencies, the Utilities
Department will propose remedies to meet recommended service levels based on
Insurance Service Organization ratings and other objective criteria.
3.11 PUBLIC SERVICES
3.11-12 Avila Ranch Development Project
Final EIR
Policy 9.21 Program: Development Review. City fire, police, public works, and utilities
personnel will review applications for subdivisions and development projects, for
consistency with safety objectives.
Airport Area Specific Plan
Policy 7.9.1 Adequate Fire Suppression Services and Facilities. The City shall provide
adequate fire suppression services and facilities to the Airport Area, consistent with the
Safety Element of the General Plan, by completing area transportation improvements, co-
locating City fire services with existing CALFIRE facilities located on Broad Street, and/or
establishing a permanent facility within the Airport Area.
Policy 7.9.2 Fire Station Location and Site Dedication. During the first phase of
development of the Chevron Tank Farm site, property that is suitable for the development
of a new fire station shall be deeded to the City, to the approval of the Fire Chief.
Policy 7.9.3 Interim Safety Improvements. Until a permanent facility is developed that
enables the City to achieve its response time objectives, new development in the Airport
Area may be required to finance other improvements that will contribute to alleviating
current deficiencies, as identified in the San Luis Obispo Fire Department Master Plan
(2009). This policy will be implemented on a case by case basis through conditions of
approval when project specific fire and life safety impacts are identified.
3.11.4 Environmental Impact Analysis
3.11.4.1 Thresholds of Significance
The thresholds of significance listed below are based on Appendix G of the California
Environmental Quality Act (CEQA) Guidelines, as well as the General Plan Safety
Element, AASP, and SLOFD guidelines for response times. The effects of the Project on
public services would be considered a significant impact if:
a)Police protection services to the Project site were inadequate, police staffing would be
inadequate to support the Project or if the Project demand for such services would
indirectly affect existing levels of such services for City residents;
b) Fire protection services response times to the Project site did not meet established
requirements (e.g. less than 4 minutes), or if the firefighter/population ratio would
decline for existing residents, or if firefighter staffing or equipment would be
inadequate to support the Project;
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-13
Final EIR
c)The Project increased demand for schools and park services beyond current capacity,
with potential impacts to the adequacy of services to existing City and future Project
residents;
d)Substantial adverse physical impacts would occur associated with provision of new or
physically altered governmental facilities; or
e)The Project would create the need for new or physically altered governmental facilities,
the construction of which could cause significant environmental impacts, in order to
maintain acceptable service ratios, response times, or other performance objectives.
3.11.4.2 Impact Assessment Methodology
This section evaluates the adequacy of existing police and fire protection services, public
schools, and parklands to serve the Project, including any planned improvements to these
services. The analysis identifies Project created increases in demand for such services, the
adequacy of existing and planned services or facilities to meet such demand and the
possible indirect effects on existing residents of such increases in demand. Finally, this
section reviews whether Project increases in demand for such services would create a need
for new or physically altered facilities, the construction of which could cause significant
environmental impacts.
In order to assess impacts on public service systems, existing and forecast capacities of
service providers were obtained from SLCUSD, SLOFD and SLOPD management
personnel and General Plan documents. Project increases in population were assessed to
identify increased demand for public services. The goals and policies of the City’s General
Plan, Safety Element and Parks and Recreation Elements, as well as those in the AASP,
provided additional information used to establish levels of significance for public services.
SLOFD and SLOPD also provided guidelines for determining potential impacts to police
and fire protection services, specifically staffing and service demands.
3.11.4.3 Project Impacts and Mitigation Measures
The proposed Project would result in the following public services impacts.
3.11 PUBLIC SERVICES
3.11-14 Avila Ranch Development Project
Final EIR
Table 3.11-3. Summary of Project Impacts
Public Service Impacts Mitigation Measures Residual Significance
PS-1 Implementation of the Project would
potentially increase demand on the SLOPD
for police protection services.
MM PS-1 Significant but Mitigable
PS-2 Project implementation would increase
the demand for SLOFD fire protection
services, create potential declines in
firefighter to resident ratios, be located
outside of accepted response time
performance area and necessitate
construction of an additional fire protection
facility, with potential for secondary
environmental impacts.
MM PS-2 Significant but Mitigable
PS-3 Development of 720 new homes as part
of the Project would generate increases in
enrollment at public schools (Los Ranchos
Elementary, Laguna Middle, and San Luis
High).
None required Less than Significant
PS-4 Implementation of the Project would
potentially increase the demand for park
services public parks beyond current
capacity.
None required Less than Significant
Impact PS-1 Implementation of the Project would potentially increase demand on
the SLOPD for police protection services (Significant but Mitigable).
The Project would result in development of 720 multiple and single family homes, 15,000
sf of commercial space concentrated in the Town Center, and 71.30 acres of open space
and parks. At full buildout, the Project site would support a population of 1,649 residents
as well as patrons or users of the 15,000 sf of commercial space. New residential and non-
residential development as part of the Project would increase City population by
approximately 3.5 percent, incrementally increasing demand for SLOPD police protection
services and responses to incidents such as burglary, domestic or neighborhood disputes,
traffic violations, noise complaints and other similar incidents. Because the Project would
be implemented in six phases over approximately 10 years, increases in call volumes for
SLOPD services would occur incrementally over time. Without additional resources, such
increases in call volumes could incrementally affect levels of service to both future Project
residents and existing City residents.
Existing SLOPD staff levels are adequate to meet the City’s Safety Element standard of 30
percent available-sworn officer time objective for patrol response. According to SLOPD
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-15
Final EIR
response records, SLOPD staff has exceeded this standard and has achieved a 32-24
percent available-sworn time objective for patrol response (SLOPD 2016). Project-created
increases in population may necessitate a need to hire additional officers or purchase new
police equipment to maintain adequate response time objectives. As estimated in the LUCE
Update EIR, with the Project’s projected population increase of 1,649 residents, the
SLOPD would need two additional police officers to maintain the current ratio of 1.27
police officers per 1,000 residents, which would constitute a 3.3 percent increase in the
number of sworn officers working for the City. However, hiring of two additional police
officers would not necessitate police station expansion or construction.
For long-term police staff planning, the SLOPD and the City Council would address
departmental budget, staffing, and equipment needs as part of the annual budgetary
process. This review allows for SLOPD to determine any increases in police resources and
equipment if needed. The SLOPD is funded through general fund revenues generated by
property, sales, and transient occupancy taxes, all of which are expected to increase in
proportion to new development within the City. Such increases in revenues could be used
to hire additional officers and purchase equipment to maintain or improve SLOPD service
levels over time to meet changing demands, if determined appropriate by the City Council.
While changes in police staffing would largely address this impact, recruiting and hiring
additional sworn officers requires allocation of funding and would need to be implemented
in a timely manner during Project construction over the next decade. Measures to decrease
Project demand for police protection services, and indirect impacts to City residents
associated with such increased demand, would help reduce demand for such services and
allow more flexibility for City allocation of resources. In addition, proposed amendments
to the AASP as part of the Project indicate that “the City shall facilitate formation of a
Community Facilities District (CFD)” that “shall provide for the equitable assessment of
the cost of construction and operation of public safety facilities” (Policy 7.9.1). Preparation
and implementation of an onsite security plan would help minimize increased demand for
police services. Therefore, with incorporation of MM PS-1 below, impacts to police
protection services would be significant but mitigable.
Mitigation Measures
MM PS-1 The Applicant shall prepare and implement a brief Security Plan for the
Project site. The Security Plan shall be prepared in consultation with the
SLOPD and address public safety concerns in common or public spaces,
parks, bike paths and open space areas, the commercial center, and parking
3.11 PUBLIC SERVICES
3.11-16 Avila Ranch Development Project
Final EIR
lots. The Security Plan shall set forth lighting requirements, security
recommendations for parks, open space and trails (e.g., visibility, lighting,
etc.), and establish rules for use of the public areas. Any private security
patrol service established as part of this development shall be coordinated
with the SLOPD.
Requirements and Timing. The Security Plan shall incorporate and
address all required and recommended SLOPD security measures and shall
be subject to review and approval by the SLOPD. Review and approval of
the Security Plan may occur prior to or subsequent to acceptance of the final
Development Plan recordation of the final Vesting Tentative Tract Map
(VTM). The Applicant shall demonstrate incorporation of SLOPD
recommended security measures into the Development Plan prior to the
issuance of grading and construction permits for each phase.
Monitoring. The City and SLOPD shall review the final Development Plan,
Security Plan, and construction plans for each Project phase to ensure
implementation of recommendations.
Residual Impact
Implementation of the above mitigation measure, in combination with the ability to
consider increases in future police staffing, would reduce demand on SLOPD police
protection services. Therefore, residual impacts would be less than significant.
Impact PS-2 Project implementation would increase the demand for SLOFD fire
protection services, create potential declines in firefighter to resident
ratios, be located outside of accepted response time performance area
and necessitate construction of an additional fire protection facility,
with potential for secondary environmental impacts. (Significant but
Mitigable).
Project development of approximately 720 residential units with an estimated 1,649 new
residents, as well as additional employees and patrons of new commercial-retail
development would alter existing firefighter-to-population ratios.
Fire protection for this new development would be provided by the SLOFD and CALFIRE.
In addition, new development would be subject to the SLOFD standards and California
Fire Code in all proposed buildings, including installation of fire hydrants, building
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-17
Final EIR
sprinklers, provision of adequate water supply and pressure, placement of fire
extinguishers, provision of adequate fire access to buildings, and other requirements.
According to the SLOFD, AASP, and Safety Element of the General Plan, response times
(travel times) to urban development should be a maximum of 4 minutes, 90 percent of the
time under Safety Element Policy 9.3(A), and, as stated in the AASP, the SLOFD should
maintain a firefighter-to-population ratio of approximately 1 fire fighter to every 1,000
citizens. New residential development within the Project site would increase demand for
fire protection services in an area currently outside of 4-minute safe response (travel) time
objective. In addition, such increased demand could cause the firefighter to resident ratio
stipulated in the AASP to gradually decline over time, absent provision of new service
capacity. Further, construction of new fire protection facilities has potential to cause
secondary physical environmental impacts from construction and operations.
At full buildout in 2030, the Project would require approximately 1.7 new firefighters with
required supporting equipment in order to maintain existing service ratios. In terms of
response times, the closest SLOFD fire station (Station Four) is located at 1395 Madonna
Road, approximately 2 miles west of the Project site across U.S. Highway 101, with access
to the site slowed by distance, roadway configurations, geographical factors, and
congestion. According to the SLOFD, the response time for emergencies to the Project site
would be between 4 and 5 minutes, marginally outside of the SLOFD response time
objective of 4 minutes or less travel time (SLOFD 2015b). While the City has a mutual aid
agreement with CALFIRE which allows for additional fire or emergency assistance when
needed, CALFIRE Fire Station 21 is located approximated 3.5 miles to the east and would
have a 7-minute response time to the Project site.
Therefore, the Project has the potential to adversely impact fire protection services in
conflict with adopted City policies. However, the Project would construct an Interim Fire
Station at the intersection of Earthwood Land/Venture Drive. This station is currently
proposed to support two firefighters or emergency responders after 50 percent buildout of
the Project site (approximately 360 units). Under current phasing, this would occur during
Phase 3 of Project development in year 2024. In addition, proposed amendments to the
AASP as part of the Project indicate that “the City shall facilitate formation of a
Community Facilities District (CFD)” that “shall provide for the equitable assessment of
the cost of construction and operation of public safety facilities (Policy 7.9.1). Further,
AASP policy 7.9.3 notes that “the Avila Ranch Project may provide an interim fire and/or
emergency response substation at the intersection of Earthwood Lane and Venture Drive”.
Until completion of the Interim Fire Station, units within Phases 1 and 2 may temporarily
3.11 PUBLIC SERVICES
3.11-18 Avila Ranch Development Project
Final EIR
experience fire protection response times greater than 4 minutes and City residents may
experience an incremental short-term decline in the firefighter to resident ratio. However,
these impacts would be short-term and, after construction of Phase 3, the Interim Fire
Station would provide coverage to the Project site and surrounding areas until the City’s
fifth fire station is constructed and operational. The 2016 San Luis Obispo Fire Department
Master Plan also requires construction of a permanent station when the entire southern area
of the City reaches 90 percent buildout.
The City is currently in the review process to consider establishing an impact fee program
to pay for acquisition and construction of a new fire station in the southern area of the City.
SLOFD staff will work with the City Manager and the City Council to review and adopt
financing options for a fifth fire station given competing City general fund needs over the
estimated decade or more that development of the Project site and other areas in the
southern City is expected to occur. Given that this impact fee program study is not yet in
place and it would likely require at least 5 to 10 years to acquire sufficient funds and to
plan for building a new long-term fire station, it is unlikely that such a facility would be
operational at Project buildout (SLOFD 2015c; 2016). The timing of opening a fifth fire
station in the southern area of the City would be dependent on both collection of impact
fees and ongoing revenue growth, as the expansion areas in the southern City would likely
not develop in time to provide sufficient funding for the station in the short-term (SLOFD
2016). However, provision of the CFD as envisioned in the proposed amendments to the
AASP could provide an interim financing vehicle, at least for construction and operation
of the interim fire station. The following mitigation measure would be implemented in
order to reduce the potential fire service impacts of the Project. With installation of the
Interim Fire Station, which would be operational until the City’s fifth fire station is
constructed, impacts to fire protection services associated with the Project would be
significant but mitigable.
Mitigation Measures
MM PS-2 Fair Share Contribution. The Applicant shall agree to pay a fair share
contribution to a future citywide or area-wide fire protection service
protection development impact fee program. Additionally, the AASP should
be amended to include a fee program to fund the City’s fifth fire station
and/or integrate such fair share fee programs into the proposed Community
Facilities District (CFD).
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-19
Final EIR
Requirements and Timing. The City shall review and approve a fee
program within the AASP or as part of the CFD to fund the new SLOFD
fifth fire station and staffing. The Applicant shall pay development impact
fees prior to recordation of the final VTM or enter into a binding written
agreement with the City to pay a fee appropriate to the amount and size of
Project development based upon the amounts set forth in the new fire
protection development impact fee program.
Monitoring. The City shall ensure full payment of development impact fees
and/or formation of the CFD.
Residual Impact
Construction of an Interim Fire Station would serve the Project site until the fifth fire
station becomes operational. Further, implementation of MM PS-2 would ensure that the
Project contributes its fair share to the costs of constructing the fifth fire station. Therefore,
residual impacts associated with adequate fire protection services would be less than
significant throughout operation of the Project.
As described in the LUCE Update EIR, construction and operation of the fifth fire station
has the potential to result in additional secondary environmental impacts such as
incremental increases in traffic and air quality impacts due to increased emissions, noise
from operation of engines, sirens, and loudspeakers and any site specific impacts such as
site grading, erosion and sedimentation or possible impacts to biological or cultural
resources; however, such site specific effects cannot be known at this time. Due to these
potential additional impacts, as also described in the LUCE Update EIR, the new fire
station would also likely be required to go under environmental review under CEQA before
it is approved.
Impact PS-3 Development of 720 new homes as part of the Project would generate
increases in enrollment at public schools (especially Los Ranchos
Elementary, Laguna Middle, and San Luis High) (Less than
Significant).
The Project would result in the development of approximately 720 residential units,
consisting of 410 single‐family dwellings and 310 multi‐family units. Based on SLCUSD
student generation rates used in the SLCUSD Enrollment Projections Capacity Analysis
2014/15 Update, it is estimated that Project development would generate approximately
256 additional school‐age children (see Table 3.11-4).
3.11 PUBLIC SERVICES
3.11-20 Avila Ranch Development Project
Final EIR
Table 3.11-4. Project Student Generation
Grade Level
Generation Rates Proposed Units
Additional
Students Single-Family
Units (students
per unit)
Multi-Family
Units (students
per unit)
Single-
Family
Units
Multi-
Family
Units
K-6 0.302 0.116 410 310 159.78
7-8 0.064 0.032 410 310 36.16
9-12 0.119 0.066 410 310 69.25
TOTAL (K-12) 0.485 0.214 410 310 256.19
Source: SLCUSD 2015b.
While schools within the region currently have remaining capacity, development of the
Project could increase elementary school enrollment by up to 160 students, which could
contribute to over-capacity at Los Ranchos Elementary School and may require increased
classroom space, new teachers, and additional equipment at the school serving the Project
area (City of San Luis Obispo 2014a). However, enrollment and capacity has the potential
to vary by school year. As previously discussed, in 2014/15, the SLCUSD did not load
three or more classrooms at each elementary school site, which could allow for additional
capacity if needed. Further, the district currently accepts intra-district open enrollment, so
students could be accommodated at other district schools upon request and availability.
Pending closure of the Diablo Canyon Power Plant, a significant source of revenue and
funding for the SLCUSD, local schools are currently facing additional challenges in
securing future funding for local schools. However, despite closure of the Diablo Canyon
Power Plan and this loss of tax revenues, the SLCUSD has noted that primary and
secondary school facilities within the district are currently adequate and capable of serving
the proposed Avila Ranch development and managing future facility needs (refer to
Comment Letter 7 in Section 8.0, Response to Comments).
In addition, consistent with applicable legislation, the SLCUSD currently requires all new
residential and commercial development to pay developer fees to offset potential impacts
of increased enrollment on City facilities through improvements to school facilities
(Government Code Section 65996), which under the law is considered to be full mitigation
for potential impacts. SLCUSD currently collects developer fees as authorized by SB 50
(Government Code Section 65970) to mitigate increased demand for school facilities.
These fees are currently assessed at $3.36 per square foot of residential development and
$0.54 per square foot of commercial development (SLCUSD 2015a), which would be
estimated when building plans and sizes are finalized, but it is estimated to be $3.5 million.
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-21
Final EIR
Given district-wide capacity and the payment of impact fees for school facilities, impacts
on school facilities associated with the Project would be considered adverse but less than
significant.
Impact PS-4 Implementation of the Project would potentially increase the demand
for public parks beyond current capacity (Less than Significant).
The Project would result in the development of approximately 720 residential units,
consisting of 410 single‐family dwellings and 310 multi‐family units with 1,649 new
residents, including 256 school age children. Based on the population anticipated for the
Project site, at least 16.49 acres of parkland would be required to meet City standards, of
which 8.25 acres would need to be a neighborhood park. To address this demand, the
Project intends to provide 16.0 acres of developed parkland, including a 9.8-acre
neighborhood park, several mini-parks, and an onsite pocket park. The size of the 9.8-acre
neighborhood park would be consistent with Policy 3.15.3 of the Parks and Recreation
Element, and would be consistent with Policy 3.15.1 due to its location within 0.5 mile
from most proposed residential neighborhoods. In addition, the Project is proposing to
provide a contribution or fee equal to 1.5 acres to the City for community park space or
community facilities. This payment of in-lieu fees for an additional 1.5 acres of parkland
would allow the Project to meet/exceed the total 16.49-acre City requirement for the
Project.
The Project site would comply with the City General Plan, Parks and Recreation Element
by providing a total of 16.0 acres of parkland as well as a contribution or fee equal to 1.5
acres to the City for community park space or community facilities. Therefore, the Project
site would result in less than significant impacts to parks.
3.11.4.4 Cumulative Impacts
Public services within the City of San Luis Obispo are primarily provided by the City of
San Luis Obispo, supplemented by interagency mutual aid agreements for fire protection
services. Cumulative impacts to public services are largely related to citywide population
growth. Please refer to Section 3.10, Population and Housing for a detailed growth forecast
and the LUCE Update EIR for cumulative impacts to public services.
In addition to resident population growth, new employment, commercial, retail, and
recreational uses would increase daytime populations and visitation with associated
demand for public services. Planned and pending development in the City includes multiple
mixed-use commercial and residential projects. These projects are also expected to expand
3.11 PUBLIC SERVICES
3.11-22 Avila Ranch Development Project
Final EIR
residential space and contribute to additional population increases in the City, thereby
increasing demand for the City’s public services.
The Project, in conjunction with approved, pending, or proposed development projects in
the City, proposed land use changes under the LUCE, along with associated population
growth, would incrementally increase overall demand for public services including fire
protection, police protection, schools, and parks. The Project’s contribution to potential
cumulative impacts to public services is described below.
Police Protection
New development proposed as part of the Project site would contribute to cumulative
citywide population growth and associated increases in demand for police protection
provided by the SLOPD. Overall growth within the City is anticipated to cause an increase
in demand for police services that may decrease officer to resident ratios and conflict with
General Plan available time goals response goals.
Existing SLOPD staffing levels are adequate to meet the 30 percent available-time
objective for patrol response, as described in the Safety Element of the City’s General Plan.
Per the LUCE Update EIR, if no additional police officers were hired by the City’s General
Plan buildout year of 2035, cumulative growth and increased population would decrease
the ratio of officers to 1,000 people in the City from the existing ratio of 1.27 to a ratio of
1.03. To meet increased demand for police protection services while maintain the existing
1.27 officers per thousand residents ratio would require a total of 74 officers, an increase
of 17 officers or a 28 percent increase in sworn officers. The Project would contribute
approximately 12 percent of this potential increase in demand for added police staffing.
However, as noted above, the City Council would address SLOPD departmental budget,
staffing, and equipment needs as part of the annual budgetary process. This review allows
for SLOPD to determine any increases in police resources and equipment if needed. The
SLOPD is funded through general fund revenues generated by property, sales, and transient
occupancy taxes, all of which are expected to increase in proportion to new development
within the City. Such increases in revenues could be used to hire additional officers and
purchase equipment to maintain or improve SLOPD service levels over time to meet
changing demands, if determined appropriate by the City Council. Therefore, the Project’s
contribution towards cumulative impacts would be less than significant for police services.
3. 11 PUBLIC SERVICES
Avila Ranch Development Project 3.11-23
Final EIR
Fire Protection
Per the LUCE Update EIR, development proposed under the Project would contribute to
cumulative citywide population growth and associated increases in demand for fire
protection services provided by the SLOFD from the four existing fire stations. As a
number of future developments in the City would be located in the vicinity of the Project
area, additional demands would be placed on the SLOFD and the mutual aid agreement
with CALFIRE. As indicated by the Fire Department Master Plan, a fifth fire station in the
southern portion of the City would be required if developments, such as the Project, are to
be consistent with the General Plan, Safety Element Policy 3.0. The Interim Fire Station
would be implemented by the Project at the intersection of Earthwood Lane and Venture
Drive within the Airport Area, and would be subject to the City’s approval and consistent
with the General Plan’s Safety Element. This fire station would remain operational until
establishment of the City’s fifth fire station to serve the southern region of the City.
Inclusion of this Interim Fire Station would counteract any cumulative impacts of the
Project on the City’s existing fire services.
Upon development of the fifth fire station, cumulative impacts to fire protection services
would continue to be less than significant.
Schools
Per the LUCE Update EIR, the total estimated enrollment generation that would result from
LUCE buildout, based on development of approximately 4,904 new dwelling units (2,420
single‐family dwellings and 2,484 multi-family units), is projected to be 911 new students.
Land use changes anticipated to occur under the Project could add up to approximately 270
new school-aged residents, contributing to future over-capacity at certain schools and
potentially requiring increased classroom space, new teachers, and additional equipment at
the schools serving the Project area. Thus, the Project and other projected growth in the
City would contribute incrementally to increased enrollment within the SLCUSD.
SLCUSD estimates that one or possibly two additional school sites will be needed to serve
planned residential growth in the southern part of the City. The Orcutt Area Specific Plan
is expected to include a potential elementary school site. Due to district budget constraints,
new dwellings will have serious adverse consequences for school staffing, facilities, and
programs unless new development adequately mitigates the adverse impact on school
facilities. Mitigation is in the form of development fees ($3.36 per square foot of residential
development and $0.54 per square foot of commercial development) assessed with
3.11 PUBLIC SERVICES
3.11-24 Avila Ranch Development Project
Final EIR
issuance of construction permits. School district fees are collected by the City and used by
the district to fund school infrastructure needs (City of San Luis Obispo 2015b). In
addition, school bond Measure D was passed in November 2014, allocating $177 million
to address longstanding facility, technology, and infrastructure needs throughout the
district, including classroom construction and renovation, facilities updates and upgrades,
and infrastructure energy efficiency improvements (SLCUSD 2015a). Given the payment
of developer fees for school facilities under the Project (which constitutes full mitigation
pursuant to SB 50), cumulative impacts would be less than significant.
Parks and Recreation
The Project would contribute to increased demand for park and recreational due to
approved, pending or proposed citywide development and associated population growth
(Table 3.0-1). Implementation of cumulative development projects in combination with the
Project, would result substantial increased use of, and demand for, park and recreation
facilities.
The City General Plan, Parks and Recreation Element requires that neighborhood and
community park facilities be provided at a ratio of 10 acres of parkland per 1,000 persons.
Under existing conditions, the City Park Department maintains a total of 151.65 acres of
parks, landscape areas, and open spaces (City of San Luis Obispo 2012), significantly less
than what is required under City standards to support current estimated City population of
46,456 (U.S. Census Bureau 2015). In addition, 572 acres of parkland would be required
to support the projected future population of 57,200 individuals as projected under
development of land uses permitted under the LUCE, which would result in a projected
need of 420.5 acres of additional parkland. However, the Project would not contribute to
cumulatively considerable impacts as the Project would provide adequate parkland under
City standards along with payment of development impact fees to accommodate the park
and recreation needs of the 1,649 future Project residents. Therefore, the Project would not
result in substantial deterioration of these facilities or service levels and this impact would
be less than significant.