HomeMy WebLinkAbout05-01-2018 Item 02 Roadway Sealing and Laurel Lane Complete Streets 2018
Meeting Date: 5/1/2018
FROM: Daryl R. Grigsby, Director of Public Works
Prepared By: Hai Nguyen, Engineer II
SUBJECT: ROADWAY SEALING AND LAUREL LANE COMPLETE STREETS 2018
PROJECT, SPECIFICATION NO. 91630
RECOMMENDATION
1. Approve plans and specifications for the Roadway Sealing and Laurel Lane Complete
Streets 2018 Project, Specification Number. 91630; and
2. Authorize staff to advertise for bids; and
3. Authorize the City Manager to award the construction contract including the Base Bid and
Additive Alternatives if the lowest responsible bid is within the publicly disclosed Funding
Amount of $1,629,002.
DISCUSSION
Background
The City’s Pavement Maintenance Plan (Pavement Plan) was adopted by the City Council on
April 14, 1998. The Pavement Plan was updated to provide additional emphasis on arterial street
maintenance in 2009. A key element of the Pavement Plan is the establishment of a rotating and
methodical approach to ensuring all areas of the City receive regular preventative or corrective
maintenance. Most recent practice is to perform maintenance in two neighborhood Pavement
Areas one year, then focus on critical arterial street work the following year, alternating between
neighborhood areas and arterials each year. Last summer, available streets maintenance funding
was used for arterial street reconstruction and maintenance to Madonna Road and Los Osos
Valley Road. In summer 2016, neighborhood Pavement Areas 1 and 8 were completed.
This year, program funding is planned to be used to seal neighborhood streets with additional
arterial complete streets work to Laurel Lane predicated upon resulting project bid prices. This
additional work is identified as Additive Alternates A, B, and C to the contract. The base bid and
additive alternates are described in more detail below.
Roadway Sealing (Base Bid)
The Base Bid portion includes slurry seal maintenance for Area 2 & 3 Local and Collector
streets, and several streets in Area 8 that were not completed in 2016. Orcutt Road from Johnson
to Tank Farm is also included in the base bid. Orcutt Road was identified by staff for slurry seal
maintenance this year to prevent deterioration while still being in good condition.
In anticipation of this year’s roadway sealing project, the City’s Street Maintenance Program has
performed pavement repairs and crack sealing in pavement maintenance Areas 2 and 3. This
preparatory work increases the slurry seal application’s long-term effectiveness and reduces overall
construction costs. Slurry seal is a mixture of asphalt emulsion, aggregates and water. Slurry seal
is a cost-effective treatment that extends pavement life up to 8 years. The intent of this project is
Packet Page 69
Item 2
to prevent more expensive maintenance work in the future. Preventative and ongoing maintenance
is less costly and more environmentally beneficial than street re-paving.
Completion of roadway sealing will enable the City to make progress towards the Council’s
established goal to maintain at least 70% of streets in good condition and have no less than 7% of
the City’s streets in bad condition. This project also helps implement multimodal improvements,
a Major City Goal, due to bicycle improvements, which include buffered bike lanes and green
bike lanes.
Laurel Lane Complete Streets (Additive Alternates A, B, & C)
Complete Streets is a national movement that began years ago to create street networks that
provide safe travel options for pedestrians, cyclists, transit users and vehicles. The 2015 Traffic
Safety Report identified the intersection of Laurel Lane and Southwood Drive as the highest-
ranking intersection for pedestrian collisions on City of San Luis Obispo maintained streets. The
report recommendation included investigation of a lane reduction, or “road diet” for Laurel Lane
(one lane in each direction and center turn lane) and bulb out modifications to the sidewalk at
Laurel/Southwood and Laurel/Augusta intersections. These intersection improvements would
reduce the number of conflict points and reduced crossing distances for pedestrians at
intersections. The City Council adopted the 2015 Traffic Safety Report in September 2016 and
City staff began efforts to analyze Laurel Lane for feasibility of a “road diet.” The ‘road diet’
options anticipated for Laurel Lane constitute a ‘Complete Street’ project.
In general, the Complete Streets project on Laurel Lane would include the following elements:
1. Reduce travel lanes to one in each direction
2. Install two-way center turn lane
3. Install buffers between the travel lane and bicycle lane
4. Add on-street parking where width allows
5. Stripe the existing crosswalks as high-visibility crosswalks
6. Sidewalk bulb outs at the intersections of Laurel/Southwood and Laurel/Augusta
Existing Section
Packet Page 70
Item 2
Proposed Section
Laurel Lane meets safety and operational criteria established in the Federal Highway
Administration Road Diet Information Guide as a very feasible candidate to go from four lanes
to three (the middle lane being a two-way-center turn lane). Both existing conditions and General
Plan full buildout conditions were analyzed, concluding that this type of lane configuration on
Laurel Lane would be unlikely to affect congestion along the corridor, whereas providing
additional safety features such as shortening crossing distances at intersections and buffered
bicycle lanes would improve the walking and biking environment along the corridor.
Two community meetings were held in the neighborhood to discuss the Complete Streets project
as well as traffic safety throughout the neighborhood. Additionally, City staff has worked
directly with neighbors to create a comprehensive design addressing traffic safety on Laurel
Lane. The top priorities from the community is pedestrian safety and street lighting. The top
remaining concern from residents is that the proposed project is not enough to adequately
address the safety issues.
The additive alternatives include additional pavement repairs and Complete Street improvements
on Laurel Lane. While improvements in excess of roadway striping revisions are not typically
included with annual roadway maintenance work, in order to address safety needs and
community priorities Laurel Lane complete streets work improvement work is included with this
maintenance project.
Additive Alternative A includes pavement repairs, slurry sealing, and striping modifications to
Laurel Lane reducing the number of travel lanes from two in each direction to one with a
common two-way center turn lane. Additive Alternative A is the first priority alternative to
construct since it will have the greatest safety benefit for all users of the corridor.
Additive Alternative B includes construction of four bulb outs and landscape improvements at
the intersection of Laurel Lane and Southwood Drive. Additive Alternate B is the second priority
alternative as the intersection of Laurel and Southwood was identified in the 2015 Traffic Safety
Report as having the highest pedestrian collision rate of intersections under City jurisdiction.
Packet Page 71
Item 2
Additive Alternative C includes construction of four bulb outs and landscape improvements at
the intersection of Laurel Lane and Augusta Drive. Additive Alternate C is the third priority
alternate. While this intersection was not identified in the Traffic Safety Report, it is nearly
identical in physical features as well as vehicle, pedestrian and bicycle volumes as Laurel at
Southwood. The existing challenges pedestrians face crossing Laurel at Augusta and Laurel at
Southwood are the same.
ENVIRONMENTAL REVIEW
This project is categorically exempt from environmental review pursuant to section 15301 of the
CEQA Guidelines (Existing Facilities) since it is a maintenance and replacement project. A
Notice of Exemption has been filed through the Community Development Department.
FISCAL IMPACT
The project is structured with a Base Bid and three Additive Alternatives to maximize the scope
of project within the available funding. The strategy is to award the contract with the Base Bid
and as many of the Additive Alternatives as funding will allow, up to the Publicly Disclosed
Funding amount of $1,648,345 in compliance with Public Contract Code Section 20103.8C.
There is currently a balance of $849,000 in the Street Reconstruction and Resurfacing Master
Account (Specification Number 90346). Additional funding of $1,600,000 will be available on
July 1, 2018 bringing the funding available balance in the Street Reconstruction and Resurfacing
Master Account to $2,499,000. It is anticipated that $670,169 will be used for the Concrete
Streets & Accessibility Improvement Project and $1,778,861 will be available to support this
project. While the construction estimate for this project is estimated at $1,562,000, staff is
requesting authorization to award a contract up to $1,629,002 to complete this work.
Other sources of funding include Bicycle Transportation Implementation Account ($174,141),
Bicycle Facility Improvements Account ($158,498), Water Distribution System Improvements
Master Account ($3,739,272), and the Collections System Improvement Master Account
($2,753,269). These funding sources support striping improvements for bicycle safety,
adjustment of water and sewer facilities to the new pavement elevations, and installation of bulb
outs along Laurel Lane.
This project is 99% funded through the City’s Local Revenue Measure approved by the City’s
residents.
Packet Page 72
Item 2
Estimated Project Cost by Funding Sources
Street R& R
Master
Account
(90346)
Distribution
System Imp.
(90227)
Sewer
Collection
System
Imp.
(90239)
Bicycle
Facility
Impr.
(90572)
Bicycle
Trans.
Implement.
(91373)
Total
Base Bid Estimate:$1,549,159 $12,841 $1,562,000
Add Alt A Estimate:$203,098 $10,000 $12,000 $77,159 $81,556 $383,813
Add Alt B Estimate:$146,825 $146,825
Add Alt C Estimate:$120,092 $120,092
Total Project Estimate:$2,019,174 $10,000 $12,000 $90,000 $81,556 $2,212,730
Contingencies (12%):$265,528 $265,528
Material Testing:$6,000 $6,000
Printing:$500 $500
Total for Project (including
additive alternatives):$2,291,202 $10,000 $12,000 $90,000 $81,556 $2,484,758
Current Fund Balance:$849,000
Concrete Streets & Access.
Improvements Project ($670,139)
2017-19 Financial Plan Funding
(Available after July 1, 2018):$1,600,000
Total funding available after
July 1, 2017 $1,778,861 $10,000 $12,000 $90,000 $81,556 $1,972,417
Total Contingencies, Materials
Testing, Printing Costs:$162,700
Publically Disclosed Funding
Amount $1,629,002
ROADWAY SEALING AND LAUREL LANE COMPLETE STREETS 2018
Packet Page 73
Item 2
ALTERNATIVES
1. Deny authorization to advertise. The City Council may choose not to authorize project
advertisement. This is not recommended since summer is the best time to pave and seal
streets.
2. Authorize Advertisement of only the Base Bid. The City Council may choose to construct
only the base bid and remove the pavement rehabilitation and road diet work proposed for
Laurel Lane.
3. Authorize Advertisement of only the Base Bid and Additive Alternate A. The City Council
may choose to construct the base bid and the pavement rehabilitation and road diet to Laurel
Lane, but with the option of not including either of the intersections with proposed bulb outs.
4. Authorize Advertisement of the Base Bid and Additive Alternate A, and either Additive
Alternative B or Additive Alternative C. The City Council may choose to construct the base
bid and the pavement rehabilitation and road diet to Laurel Lane, but with the option of
including one of the intersections with proposed bulb outs. This option would allow for
removal of bulb outs construction work from the total project, located at either Laurel and
Southwood (Add Alt B) or Laurel and Augusta (Add Alt C).
Attachments:
a - Pavement Area Map
b - Vicinity Map
c - Council Reading File - 91630 Plans
d - Council Reading File - 91630 Specifications
Packet Page 74
Item 2
Packet Page 75
Item 2
Page intentionally left
blank.
Packet Page 76
Item 2
THE
Newspaper of the Central Coast
RECEIVED
APR 2 5 2018
SLO CITY CLERK
3825 South Higuera • Post Office Box 112 - San Luis Obispo, Califo
In The Superior Court of The State of California
In and for the County of San Luis Obispo
AD 43624725
CITY OF SAN LUIS OBISPO
OFFICE OF THE CITY CLERK
STATE OF CALIFORNIA
ss.
County of San Luis Obispo
I am a citizen of the United States and a resident of the
County aforesaid; I am over the age of eighteen and not
interested in the above entitled matter; I am now, and at
all times embraced in the publication herein mentioned
was, the principal clerk of the printers and publishers of
THE TRIBUNE, a newspaper of general Circulation,
printed and published daily at the City of San Luis
Obispo in the above named county and state; that notice
at which the annexed clippings is a true copy, was
published in the above-named newspaper and not in any
supplement thereof — on the following dates to wit;;
APRIL 21, 2018 that said newspaper was duly and
regularly ascertained and established a newspaper of
general circulation by Decree entered in the Superior
Court of San Luis Obispo County, State of California, on
June 9, 1952, Case #19139 under the Government Code
of the State of California.
I certify (or declare) under the penalty of perjury that the
foregoing is true and correct.
(Sign ure of Principal Clerk)
DATE: APRIL 21, 2018
AD COST: $373.52
00,, crff op
SIMLWOEMWO
SAN LUIS OBISPO CITY COUNCIL
NOTICE OF PUBLIC HEARING
The San Luis Obispo City Council invites
all interested persons to attend a public
hearing on Tuesday, May 1, 2018, at 4:00
p.m. in the City Hall Council Chamber,
990 Palm Street, San Luis Obispo, Cali-
fornia, relative to the following:
1) REVIEW OF A COMMON INTEREST
VESTING TENTATIVE TRACT MAP NO.
3111 TO CREATE 30 RESIDENTIAL
LOTS AND AN HOA LOT ON THE
PRATT PROPERTY, PARCEL 2 OF
VESTING TENTATIVE PARCEL MAP
SLO-17-0127, WITHIN THE ORCUTT
AREA SPECIFIC PLAN WITH A STATU-
TORY EXEMPTION FROM ENVIRON-
MENTAL REVIEW IN ACCORDANCE
WITH GOVERNMENT CODE SECTION
65457 (3750 BULLOCK LANE).
A public hearing to consider the Planning
Commission's recommendation to adopt a
resolution to approve a Vesting Tentative
Tract Map, No. 3111
3750 Bullock Lane
(SBDV-1226-2017)
For more information, you are invited to
contact Rachel Cohen of the City's Com-
munity Development Department at (805)
781-7574 or by email atrcohen@slocity.
orn.
2) ROADWAY SEALING AND LAUREL
LANE COMPLETE STREETS 2016 PROJ-
ECT, SPECIFICATION Na. 91630, RE-
DUCING LAUREL LANE FROM TWO
LANES IN EACH DIRECTION, TO ONE
LANE WITH BUFFERED BIKE LANES IN
EACH DIRECTION AND ENHANCING PE-
DESTRIAN CROSSINGS.
so
RUU� p
SQIJ
O�
ORCUTT
A public hearing to consider approval of
pians and specifications for the roadway
sealing and Laurel Lane Complete Streets
2018 project, Specification No. 91630, and;
authorizing staff to advertise for bids; and
authorizing the City Manager to award the
Construction contract including the base
bid and additive alternatives if the lowest
responsible bid is within the publicly dis-
dosed funding amount of $1,629,002.
For more information, you are invited to
contact Jake Hudson of the City's Public
Works Department at (805) 781-7255 or by
email at ihudson@slocity.orq
The City Council may also discuss other
hearings or business items before or after,
the items listed above. If you challenge the
proposed project in court, you may be limit-
ed to raising only those issues you or
someone else raised at the public hearing
described in this notice, or in written corre-
spondence derivered to the City Council at,
or prior to, the public hearing.
Reports for this meeting Will be available
for review in the City Clerk's Office and on-
line at www.slocity.org on Wednesday,
April 25, 2018. Please call the City Clerk's
Office at (805) 781-7100 for more informa-
tion. The City Council meeting will be tele-
vised live on Charter Cable Channel 20
and live streaming on www.slocifV.org.
Teresa Punington,
City Clerk
City of San Luis Obispo
ApN 21.2018 3624725
5/1/2018
1
Laurel Lane Complete Streets
Resealing Project 2018
City Council, May 1, 2018
Presenter:
Jennifer Rice, Transportation Planner-Engineer
• Background
• Road Diet Feasibility Study
• Components of the Project
• Public Engagement
• Staff Recommendation
Background
2015 Traffic Safety Report
Resealing 2018 CIP
Staff Presentation - Item #2
5/1/2018
2
What is a “Road Diet”?
Benefits of a Road Diet
Pedestrian improvements
Staff Presentation - Item #2
5/1/2018
3
Benefits of a Road Diet
Motorist safety improvements
Benefits of a Road Diet
Bicycle improvements
Staff Presentation - Item #2
5/1/2018
4
Road Diet Feasibility Study
Road Diet Feasibility Study
0
5000
10000
15000
20000
25000
Johnson to Augusta Augusta to Southwood Southwood to Orcutt
Average Daily Vehicle Volumes
Staff Presentation - Item #2
5/1/2018
5
Road Diet Feasibility Study
0
100
200
300
400
500
600
700
800
900
1000
AM PM AM PM AM PM
Laurel Lane:
Johnson to Augusta
Laurel Lane:
Augusta to Southwood
Laurel Lane:
Southwood to Orcutt
Peak Hour Volumes Per Direction
NB
NB NB
NB
NB
NB
SB SB
SB
SB
SB SB
Typical Cross Sections
What is proposed for Laurel Lane?
Staff Presentation - Item #2
5/1/2018
6
Typical Intersection
Typical Segment
What is proposed for Laurel Lane?
Typical Intersection
What is proposed for Laurel Lane?
Staff Presentation - Item #2
5/1/2018
7
Laurel and Orcutt
What is proposed for Laurel Lane?
Community Outreach
2 Community Meetings
One-on-one meetings with residents and
neighborhood groups
Top priorities: pedestrian safety, street lighting
Remaining concerns:
Proposed efforts may not enough to adequately address
the safety issues
Can the City install flashing lights to warn drivers when
pedestrians are crossing the roadway?
Staff Presentation - Item #2
5/1/2018
8
Prioritization
1.Additive Alternative A: Laurel Lane Striping
Reconfiguration
Greatest impact to improve safety along the corridor for
all modes of transportation
2.Additive Alternative B: Bulbout at Laurel/Southwood
2015 TSR-highest ranking pedestrian collision rate
3.Additive Alternative C: Bulbout at Laurel/Augusta
Identical features as Laurel/Southwood (physical
configuration, vehicle, pedestrian, bicycle volumes,
accessibility to transit, elementary school, senior housing)
Staff Recommendation
1.Approve the Plans and Specifications for the Roadway Sealing
and Laurel Lane Complete Streets 2018, Specification Number
91630; and
2.Authorize staff to advertise for bids; and
3.Authorize the City Manager to award the construction contract
including the Base Bid and Additive Alternatives if the lowest
responsible bid is within the publicly disclosed Funding Amount
of $1,629,002.
3.Direct staff to return to Council with the 2018-19 Budget Supplement with those projects identified; and
4.Authorize the City Manager to award the construction contract
including the Base Bid and staff recommended Additive
Alternatives if the lowest responsible bid is within the available
project funding as identified in the 2018-19 Budget Supplement.
Staff Presentation - Item #2