Loading...
HomeMy WebLinkAbout07-10-2018 Item 11 - Silt Removal 2018 Meeting Date: 7/10/2018 FROM: Daryl Grigsby, Director of Public Works Prepared By: Violeta Esparza-Reniere, Engineer III SUBJECT: SILT REMOVAL 2018 RECOMMENDATIONS 1. Approve Plans and Specifications Silt Removal 2018, Specification No. 91523; and 2. Authorize staff to advertise for bids; and 3. Authorize the City Manager to award the construction contract of up to $120,000 to the lowest responsible bidder. DISCUSSION Background The City’s creeks contain locations where sediment collects over time and requires removal to facilitate storm flow. Without proper and routine maintenance, channel flow capacities decrease, and the surrounding properties become more susceptible to flooding. This project consists of the removal of accumulated sediment from Prefumo Creek between Los Osos Valley Road and Laguna Lake. Project Site: Prefumo Creek, in between Los Osos Valley Road and Laguna Lake Prefumo Creek between Los Osos Valley Road and Laguna Lake experiences sediment deposits because the creek slope flattens and water velocity decreases. If addressed early enough, sediment can be removed from the creek prior to migration into Laguna Lake. Therefore, the accumulated sediment needs to be removed periodically to maintain creek capacity and prevent the sediment from migrating into Laguna Lake. Roughly six feet of sediment, or approximately 1,320 cubic yards, was deposited since the last silt removal project completed in 2015. This sediment , as well as exotic invasive vegetation, will be removed by this project . Areas along the creek that are disturbed during construction will be revegetated to reduce erosion and protect the creek banks. All existing trees will be protected. This project will restore Prefumo Creek’s flow capacity and reduce the likelihood of sediment transfer into Laguna Lake. Regulatory Permitting Due to the location of this project within the creek system, work must be scheduled for late summer or early fall – the time of year when the water in the creeks is lowest, and when work can be performed with reduced likelihood of imp acts to adjacent wildlife. As such, scheduling these projects around this limited construction timeline requires advanced planning, design, and regulatory permitting work. Packet Pg. 165 Item 11 The project requires regulatory permits from the California Department of Fish and Wildlife, the California Regional Water Quality Control Board, and the U.S. Army Corps of Engineers. As of June 18, 2018, t he California Department of Fish and Wild life permit is still pending but permits from all of the other listed agencies have been r eceived. Based upon recent correspondence with the City’s environmental consultant, indications are that the remaining permit will be received in time for the scheduled construction start in September 2018. Construction Timing By authorizing this project for advertisement and allowing the City Manager the authority to award a contract up to $120,000, the City may be able to complete this work before the end of 2018. The recommended action will allow the project to be advertised now so that a construction contract may be awarded w ithin the construction window limited by the regulatory permits. Delegating the City Manager authority to award a contract up to $120,000, greater than the Engineer’s Estimate of $82,350, will ensure that if bids are returned higher than the estimate that the project can move forward without delay. If the City is ultimately not successful in obtaining a California Department of Fish and Wildlife permit to allow for construction work to be completed this year, all bids will be rejected, and the project will be rebid next year. ENVIRONMENTAL REVIEW The City’s Community Development Department has issued an Addendum to Initial Studies / Mitigated Negative Declaration ER#1-11 for this project. All required mitigation measures identified in this environmental document have been incorporated into the project specifications. FISCAL IMPACT The 2017-19 Financial Plan, pages E2-18 and E2-19, identifies the silt removal project with a construction budget of $102,000 in 2017-18 and $100,000 in 2018-19 to support this and other silt removal projects. With the 2018-19 allocation, a total of $311,000 will be available in the Silt Removal Master Account . The funding source for this work is provided by the San Luis Obispo County Flood Control and Water Conservation District Zone 9, which will reimburse the City for actual costs incurred up to $311,000, though this silt removal project is not projected to exceed $120,000 Due to the short construction window, the strategy is to allow the City Mana ger to award the contract to the lowest responsible bid up to the amount of $120,000. The total project estimate including contingency cost is $96,100; this request to award up to $120,000 allows for flexibility to accommodate bids that may come in over the engineer’s estimate and still construct during the tight construction window. Packet Pg. 166 Item 11 Total Project Estimate: $82,350 Contingencies:$8,250 Monitoring $5,000 Printing and Misc:$500 Total Project Estimate $96,100 Silt Removal Budget $311,000 Remaining Balance after Project:$214,900 Silt Removal 2018, Specification #91523 ALTERNATIVE Deny authorization to advertise and award. The City Council may choose not to authorize project advertisement. This is not recommended since postponing this project until a later date decrease the capacity of the creek, increase sediment migration into Laguna Lake, and increases the risk of flooding in neighboring residential area. Attachments: a - Council Reading File - 91523 Silt Removal 2018 Plans b - Council Reading File - 91523 Silt Removal 2018 Specifications Packet Pg. 167 Item 11 Page intentionally left blank. Packet Pg. 168 Item 11