HomeMy WebLinkAbout05-07-2019 Item 09 - Contract Amendments for Phase 4 and 5 of the WRRF Department Name: Utilities Cost Center: 6101 For Agenda of: May 7, 2019 Placement: Consent Estimated Time: N/A FROM: Aaron Floyd, Utilities Director Prepared By: David Hix, Deputy Director, Utilities – Wastewater SUBJECT: WATER RESOURCE RECOVERY FACILITY ENGINEERING SERVICES DURING CONSTRUCTION AND PHASE 4 AND 5 PROGRAM MANAGEMENT AND LABOR COMPLIANCE. RECOMMENDATION 1. Approve a contract amendment with CH2M Hill Engineers (Jacobs), for engineering services during construction of the Water Resource Recovery Facility Project, for an amount not to exceed $5,142,138; and 2. Approve a contract amendment with Water Systems Consulting Inc. for program management and labor compliance of Phase 4 and 5 of the Water Resource Recovery Facility Project for an amount not to exceed $2,620,938. DISCUSSION On December 4, 2018, City Council authorized the Water Resource Recovery Facility (WRRF) project to advertise for construction bids after the construction and bidding documents were complete. On March 13, 2019, the WRRF project was advertised, with bids to be received by Monday, May 20, 2019. On May 21, 2019, the City will begin the process of analyzing the bids to determine which contractor provided the most responsive bid. Staff anticipates award of the WRRF construction contract in June or July 2019. The WRRF project will provide additional wastewater treatment to meet the State’s stringent discharge requirements, provide additional capacity to meet the City’s General Plan, replace aging infrastructure, maximize recycled water production and provide a community asset. The WRRF project will utilize technology that will produce exceptional water quality and positions the City to explore potable reuse options in the future. Now that the WRRF project has completed the study and design phase it has officially entered the construction and project close-out phases. As anticipated, for the largest capital improvement project undertaken by the City, during construction, consultant services will be needed to assist in the delivery of the WRRF project. These include Construction Management (CM), Engineering Services During Construction (ESDC), Program Management (PM), and labor compliance. On September 18, 2018, Council awarded a contract to Carollo Engineers to provide the CM services for the WRRF project. The current request is to make awards for ESDC, PM, and labor compliance services. Packet Pg. 97 Item 9 Engineering Services During Construction of the WRRF The plans and specifications for a complicated project such as th e WRRF are very specialized and intricate. Larger projects like the WRRF retain the design engineer s through construction to work with the project team to address the numerous required submittals, provide information and clarifications to the construction contractor, and work closely with the construction manager during construction of the project . Engineering services provide the critical connection between owner, designer, construction manager, and the construction contractor during construction. It is an ticipated that the City will receive over 1,500 submittals, request s for information, and other documentation related to specialized decisions that will need to be made throughout the construction phase of the project. The WRRF designer, Jacobs, has submitted a proposal (Attachment A) to provide construction engineering services required during the construction of the WRRF. Jacobs will provide project management, review, and approval of contractor equipment submittals, on-site engineering services and project close-out services to successfully deliver this project. The City project team and Jacobs have negotiated this agreement to ensure adequate resources to successfully deliver this project and maintain a reasonable budget for construction. The City did not request proposals from other design engineers, because Jacobs possesses specialized and comprehensive knowledge of the design, specifications, schedule and sequencing of the WRRF project. To bring in an outside designer with no or little experience with the project likely would be more expensive, could compromise project quality, and would create delays as the new firm would need to review and/or duplicate work previously completed to comes up to speed with volumes of drawings, specifications and other critical details of the project. Jacobs has been a highly engaged member of the WRRF project team and will continue to bring a dedicated, qualified and communicative team to support the construction of the project and the WRRF team. The Jacobs proposal is approximately 4.6 percent of the estimated construction cost, including a modest technical contingency which is in-line with the industry average for a project of this size and complexity. Program Management (PM) and Labor Compliance Services During Construction of the WRRF On January 21, 2014, City Council awarded a contract to Water Systems Consulting, Inc. (WSC) to provide program management services for the entire Water Resource Recovery Facility (WRRF) project and authorized funding for Phase 1. Since that time, Council authorized funding for Phases 2 & 3 (Preliminary and Final Design) on June 16, 2015. Staff is recommending the authorization to proceed with a contract with WSC for the two last program phases of the project because of WSC’s knowledge of the project and program expertise. WSC has been a valuable partner to the project’s success and changing program management services providers through completion of the project would be financially costly, would compromise project timeliness, quality, and continuity, and would put the City’s timely project delivery, as required by the City’s Time Schedule Order, at risk. Given the size and complexity of this project, City staff alone does not possess the expertise, experience, resources, or time to provide the needed management to ensure a successful project. WSC has provided a proposal (Attachment B) for PM services for construction (phase 4) and close-out (phase 5) of the project. Packet Pg. 98 Item 9 The PM support for these final phases include program planning and management, permitting, funding and financing support, stakeholder engagement and outreach, coordinating and assisting with CM, contactor and designer with plant operations to maintain compliance, start-up and commissioning, and construction close-out. This proposal includes updated public outreach with community workshops, a refreshed website offering frequently updated information, pictures, videos and social media updates as construction progresses. The scope also includes labor compliance provided by Golden State Labor Compliance, a sub consultant to WSC. Golden State specializes in labor compliance and is familiar with Project Labor Agreements and labor codes and the specific requirements outlined in this project’s Community Workforce Agreement (CWA). Like Jacobs, the City and WSC negotiated this agreement to ensure adequate PM resources and maintain a reasonable construction budget. WSC’s proposal is approximately 2.3 percent of the project construction phases, including labor compliance, which is appropriate for these last phases of the project. Next Steps In June or July of this year, staff will provide a recommendation to award the construction contract. Because of the current uncertain nature of the bidding climate, staff anticipates two different scenarios. If the WRRF project, including the Water Resource Center, comes in within the recommended construction budget of $111,600,000, staff will recommend the City Manager award the contract, as authorized in the December 4, 2018, Council agenda report (Attachment C). If the project exceeds the estimated construction budget, staff will return to Council to explain any changes to the scope of the project, budget, and to recommend a path forward. The construction phase of the WRRF will take 44 months, with some additional time after that for project close-out. Below is an updated timeline of the project, including project close-out. Staff believes that a Notice to Proceed can be issued to the selected contractor in August 2019 with major construction activities beginning in October 2019. All required construction permits for this project have been secured. Policy Context The WRRF project upgrade involves several processes to ensure compliance with the City’s stringent requirements for treated wastewater discharge. The project will also increase capacity that aligns with the City’s General Plan and maximizes recycled water production. Packet Pg. 99 Item 9 Public Engagement Public outreach and engagement for the WRRF project and grant funding opportunities began at the first steps of this project. The WRRF project continues engagement activities through the project website http://slowrrfproject.org, updates in the Utilities Department Resource newsletter, tours, presentations, and other events. CONCURRENCE The Public Works Department concurs with the construction services and staff recommendation. ENVIRONMENTAL REVIEW The Environmental Impact Report (EIR) for the WRRF Project was certified by the City Council on August 16, 2016. FISCAL IMPACT Budgeted: Yes Budget Year: 2019-2022 Funding Identified: Yes The construction phase of the WRRF project will primarily be financed through a low-interest State Revolving Fund (SRF) loan administered by the State Water Resources Control Board Water Recycling Funding Program. The construction budget for the bid documents was set at $111,600,000, with construction phase professional services at $16,048,528. In order to adjust to the loan amount available, the project will carry an 11-percent contingency which amounts to $12,351,472. The table below breaks down these services and the costs. Construction phase professional services include construction management, engineering services during construction, labor compliance with the C W A administration, and phase 4 and 5 program management. These services are eligible for reimbursement from the SRF loan. The total construction budget, contingency, and construction phase professional services are provided below. As stated above, the contingency has been adjusted from 12 percent to 11 percent, which is reasonable and adequate for this type of project with a complete and final cost estimate. Construction Phase Professional Services Construction Management– Carollo* *Awarded September 2018 $8,285,452 Program Management – WSC $2,353,188 Engineering Services - Jacobs $5,142,138 Labor Compliance – Golden State $267,750 Total $16,048,528 Packet Pg. 100 Item 9 WRRF Project Budget Construction cost budget $111,600,000 Project contingency / budget allowance (11%) $12,351,472 Construction Phase Professional Services $16,048,528 Total $140,000,000 Maximum SRF Loan Amount $140,000,000 Fiscal Analysis: Funding Sources Current FY Cost Annualized On-going Cost including debt payment Total Construction Cost Sewer Fund $7,763,076 $9,799,114 $140,000,000 State Federal Fees Other: Total $7,763,076 $9,799,114 $140,000,000 The City recently signed the agreement to receive $78,125. from the Integrated Regional Water Management (IRWM) Plan for a planning grant related to value engineering for the WRRF project. Two other grants are in the approval process; CalOES and an IRWM implementation grant. The CalOES grant is still being processed; if awarded, the CalOES grant will provide approximately $2 million in grant funding for flood improvements at the WRRF. Staff recently submitted an IRWM implementation grant application to fund $3.1 million in treatment improvements at the WRRF. Staff believes it has a very competitive IRWM application and is hopeful of some level of funding. The City will be notified if the grant proposal is approved to advance to the funding stage in May at which point staff will return to Council for permission to accept this grant funding. ALTERNATIVES Elect not to approve construction phase professional services or changes scope of agreements. The City Council may elect not to approve these services or change their scope. Staff does not recommend this alternative due to the expertise required to deliver this project. Not approving these agreements or changing their scope may result in delayed construction and completion of the project. Attachments: a - Jacobs Proposal & CH2M Hill Engineers, Inc. Contract Amendment No. 4 b - WSC Phase 4-5 PM Proposal & Amendment No. 4 c - Dec. 4, 2018 Staff Report- WRRF Project Bid Authorization Packet Pg. 101 Item 9 AMENDMENT TO AGREEMENT NO. 4 THIS AMENDMENT TO AGREEMENT is made and entered in the City of San Luis Obispo on ______________________, by and between the CITY OF SAN LUIS OBISPO, a municipal corporation, herein after referred to as City, and CH2M Hill Engineers, Inc., hereinafter referred to as Contractor. WITNESSETH: WHEREAS, on November 23, 2015 the City entered into an Agreement with Contractor for Design Services for the Water Resources Recovery Facility per Specification No. 91363; and WHEREAS, the City desires to amend the scope of services to include Services During Construction for the Water Resource Recovery Facility project. NOW THEREFORE, in consideration of their mutual promises, obligations and covenants hereinafter contained, the parties hereto agree as follows: 1. The scope of services and related compensation is hereby amended as set forth in Exhibit A attached hereto. a. Services During Construction per proposal dated April 2, 2019, at a cost not to exceed $5,142,138 on a time and materials basis. 2. All other terms and conditions of the Agreement remain in full force and effect. IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed the day and year first written above. ATTEST: CITY OF SAN LUIS OBISPO ____________________________________ By: ____________________________________ Teresa Purrington, City Clerk Mayor Heidi Harmon APPROVED AS TO FORM: CONTRACTOR _____________________________________ By: ____________________________________ Christine Dietrick, City Attorney Packet Pg. 102 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC City of San Luis Obispo Water Resource Recovery Facility Project Services During Construction April 2, 2019 Introduction Jacobs agrees to furnish the following construction phase services for the City of San Luis Obispo Water Resource Recovery Facility (WRRF) Project (the Project). Jacobs shall commence work upon receipt of Notice to Proceed for this phase of services from the City of San Luis Obispo (City). The services to be provided during the construction phase are intended to assist the City in administering the construction contract, providing engineering services during construction (SDC), verifying that the Contractor’s work is in substantial compliance with the Contract Documents and design intent, and assisting the City in responding to events that occur during the construction. The following key assumptions were made in the compilation of this Scope of Work and in estimating the level of effort: • The Project will be constructed under a single construction contract issued to the single Construction Contractor (Contractor). • Jacobs’s services are based upon a construction duration of 43.5 months (August 2019 to March 2023). It is expected that the Jacobs support will ramp up at the end of 2019 and ramp down in 2023 during the final completion period (estimated to be 60 calendar days following Substantial Completion). The actual effort is based on a 40-month period of main SDC activity. • The number of submittals is based on 1.00 submittal per design drawing. Jacobs’s submittal review will include up to a 50 percent resubmission rate, with a review time of 50 percent less for a resubmission. The number of Requests for Information (RFIs) is based on 1.2 RFIs per design drawing. Deviations from the anticipated schedule or duration of construction, or increased numbers of submittals and RFIs, may materially affect the scope of these services and Jacobs’s compensation and may constitute additional services. • The City will contract directly with the Contractor and will be actively involved in the construction process to make decisions, provide approvals, and perform other actions necessary for the completion of construction. • The City has contracted directly with a Construction Management (CM) services firm. It is the intent of the City that the CM provide Construction Management, daily on-site inspection for all construction trades, monitor compliance with the contract documents and quality assurance of the work on the Project. The CM shall perform all services described in the Contract Documents as being required by the Resident Project Representative (RPR). • The City team will include the services of the Program Manager, Water Systems Consulting, Inc. • Jacobs will not be responsible for the means, methods, techniques, sequences or Packet Pg. 103 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC procedures of the Contractor, nor shall Jacobs be responsible for the Contractor’s failure to perform in accordance with Contract Documents. Management of these activities will be the responsibility of the City and the CM. • Jacobs will not be responsible for the monitoring or review of the Contractor’s cost and schedule performance during construction. This work shall be performed by the CM. • The CM will establish and administer the document management system (Procore) for managing, tracking and storing relevant documents between the Contractor, CM, Jacobs and the City. Jacobs will utilize the electronic document management system (Procore) exclusively to transmit submittal reviews, RFI responses, correspondence and other project-related documentation. • Jacobs will not be responsible for site coordination including conducting the Pre- Construction Conference, partnering sessions, project site meetings, issuance of field instructions, monthly progress reporting and mobilizing the site team. These services will be provided by the CM. • The CM shall be responsible for confirming the Contractor maintains detailed as- built drawings. • Jacobs will not be responsible for providing construction contract administration including processing of monthly payment requests from the Contractor, Contractor schedule revisions and analysis, providing correspondence to the Contractor, receiving correspondence from the Contractor and maintaining correspondence files. These services will be provided by the CM. • Jacobs will not be responsible for receiving claims and disputes from the Contractor and providing resolution. These services will be provided by the CM. It is anticipated that Jacobs will provide input into claims and disputes with the Contractor. • Jacobs will be promptly notified of any development that affects the scope or timing of Jacobs’s services, or of any defect in the work of Jacobs or the Contractor. • Any labor and expenses required to address non-Jacobs design-based construction changes, unforeseen subsurface conditions or additional construction requested by the Contractor or the City will constitute additional services subject to compensation through the Technical Contingency. Jacobs will not be responsible for any labor and expenses required to address changes or additional construction related to Jacobs’ design that fall within the standard of care of the industry for this type of project. • Any claims resolution or litigation assistance requested of Jacobs by the City will constitute additional services. • Cannon Corporation and MWA Architects will provide review of submittals and Requests for Information (RFIs) related to their design. Subconsultant costs will be marked up 5% by Jacobs. • Jacobs will not be responsible for agency or permitting coordination through the construction phase which may include but not be limited to submission of deferred submittals, agency inspections, test reports, notifications or other follow-up correspondence. These services will be provided by the CM. Packet Pg. 104 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC Health and Safety Jacobs will manage the health, safety and environmental activities of its staff and the staff of its subcontractors (Subs) to achieve compliance with applicable health and safety laws and regulations. Jacobs will coordinate its health, safety and environmental program with the responsibilities for health, safety and environmental compliance specified in the Contract for Construction between the City and the Contractor. Jacobs will coordinate with responsible parties to correct conditions when observed that do not meet applicable federal, state and local occupational safety and health laws and regulations, when such conditions expose Jacobs staff or Subs staff to unsafe conditions. Jacobs will notify affected personnel of any site conditions posing an imminent danger to its staff which Jacobs observes. Jacobs is not responsible for health or safety precautions of the Contractor or its employees, the City, CM or Program Manager. Jacobs is not responsible for the Contractor’s compliance with the health and safety requirements in the Contract for Construction, or with federal, state, and local occupational safety and health laws and regulations. Task 1 Project Management Jacobs will provide Project Management for SDC as defined below: Task 1.01 – Project Administration Jacobs will provide draft and final (incorporating City comments) construction phase services Project Execution Plans to include work planning, staff scheduling, budget control, records management, communication protocols and related functions for management of Jacobs ‘s Project Team for the 43.5-month construction period. The actual effort is based on a 40-month period of main SDC activity. Jacobs will prepare monthly invoices and provide required information for the CM’s Project Monthly Status Report. Jacobs’ monthly report will include a summary of the submittals and RFIs reviewed during the reporting period, the number of meetings attended, utilization of technical contingency, and other key issues. Task 1.02 – Communications Jacobs will provide routine communications with the CM in accordance with the lines of communication set forth in the Construction Management Plan prepared by the CM including proactive issue resolution through phone calls, emails, and/or meeting attendance. Formal communications will be documented through the electronic document control system (Procore), and the CM will be provided a copy of the communication documentation. Jacobs will attend and participate in the 2-hour weekly construction progress meetings during the 40-month construction period along with an estimated six (6) public relations/regulatory meetings. Attendance in the weekly construction progress meetings will be via teleconference for the project manager. The Jacobs resident engineer will attend the weekly construction progress meetings in person for the duration they are assigned to the Project. The Jacobs project manager will attend weekly construction progress meetings after the resident engineer transitions off the Project. Any technical support in the weekly calls shall be covered under the technical contingency. Packet Pg. 105 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC Task 1.03 – Coordination Jacobs will mobilize a resident engineer on-site through the completion of the liquids phase improvements milestone (estimated to be 25 months) to provide site coordination between Jacobs, Contractor, CM and the City. Jacobs will coordinate the activities of its Subs. The costs for this task are included in Task 3.01 and Task 3.02. Task 1.04 – Pre-construction Conference Jacobs will attend the Water Resource Recovery Project pre-construction conference with the Contractor, CM and the City. The purpose of the meeting will be to review the roles and responsibilities, procedures, communication plan, conflict resolution plan, record keeping requirements, and other information pertinent to the execution and completion of the work. It is anticipated that the CM will lead the meeting, prepare the required materials, and prepare and distribute meeting minutes. It is assumed that there will be three (3) attendees from Jacobs for the Pre-Construction Conference Meeting (Project Manager, Assistant Project Manager, and Design Manager). The meeting duration is assumed to be four (4) hours. Task 1.05 – Partnering Jacobs shall attend partnering sessions with the Contractor, CM and the City. Jacobs will attend the initial 4-hour Executive Partnering Workshop and 8-hour Initial Partnering Workshop. Thereafter, Jacobs will participate in eight (8) hour follow-up sessions every three (3) months for a total of twelve (12) sessions, to ensure that the commitments made are updated and being followed by all parties. It is assumed that there will be the following attendees at the workshops from Jacobs • Initial Executive Partnering Workshop – Two attendees (PM and Project Principal) • Initial Partnering Workshop - Two attendees (PM and Resident Engineer) • Partnering meetings for the remainder of the Project – Two attendees (PM and Resident Engineer while assigned to Project) Task 1.06 – Project Management Meetings Jacobs will attend the following project management meetings • The PM will attend monthly CMT meeting (40 total meetings) • The PM and RE (while assigned to Project) will attend monthly Project Management meetings (40 total meetings) The Project Management and CMT meetings will be held on the same day. Task 1.07 – Conformed Documents Jacobs will create a set of conformed documents for use during construction. The conformed set will incorporate all items revised through the Addenda process. Two full size sets of drawings and specifications will be provided along with one electronic file in PDF and one CADD file of the drawings. Packet Pg. 106 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC Task 2 Submittal Review, Requests for Information (RFIs) and Clarifications, Modifications and Document Tracking The following sections apply to the Water Resource Recovery Facility Project. Task 2.01 – Submittal Review Jacobs will assist the CM and the City in reviewing and responding to any Contractor requests for substitution of materials and equipment. Jacobs will review such requests and will advise the CM and the City as to the acceptability of such substitutions. Jacobs will review the Contractor’s shop drawings, samples, and other submittals for general conformance with the design intent and the requirements of the Contract Documents. Jacobs’s review will occur after the CM has confirmed general compliance with the submittal transmittal requirements. Such review by Jacobs, shall not relieve the Contractor from its responsibility for performance in accordance with the contract for construction, nor is such review a guarantee that the work covered by the shop drawings, samples and submittals is free of errors, inconsistencies or omissions. Jacobs’s services are based on an estimated number of submittals shown in the table below, with a review time of 5.7 hours per submittal. Jacobs’s submittal review efforts will include a maximum resubmission rate of 50 percent, with a review time of 2.9 hours per resubmittal. This level of effort includes attendance and participation in pre-submittal and submittal issue resolution meetings as required by appropriate technical staff. BASIS OF EFFORT Contract Number of Drawings Number of Submittals 1 Number of Resubmittals 2 WRRF Project 1000 1000 500 1. Based on 1.0 submittals per drawing 2. Assumes 50 percent resubmission rate Should additional reviews be required, Jacobs shall track these costs to be entitled to additional compensation consistent with the provisions of the Contract Documents. The quantity of submittals assumes that the CM will review a portion of the Contractor’s submittals. Jacobs will not review more submittals than shown under the base scope of work. Jacobs will utilize Adobe Acrobat or Bluebeam Revu, and electronic signatures for processing Web-based submittals. A cover sheet with the stamped review action and a tabulation of the review comments will be included with each submittal review. All submittals are to be in bookmarked PDF electronic format only. All submittal responses will be posted to the electronic document control system (Procore). Task 2.02 – RFIs and Clarifications Jacobs will review and respond to the Contractor’s requests for information (RFIs) and/or contract clarification information requests (CCIRs). Jacobs’s services are based on an estimated number of RFIs shown in the table below, with a review time of 3.0 hours per RFI. Packet Pg. 107 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC BASIS OF EFFORT Contract Number of Drawings Number of RFIs 1 WRRF Project 1000 1200 1. Based on 1.2 RFIs per drawing Should additional RFIs be submitted, Jacobs shall track these costs in order for additional compensation to be considered by the City. Jacobs will only respond to the quantity of RFIs shown under the base scope of work. The level of effort is based on the City and CM reviewing some of the RFIs submitted by the Contractor. Jacobs will coordinate such reviews with the design team and with the CM as appropriate, including participation in meetings to facilitate RFI resolution. Jacobs will coordinate and issue responses to the requests via the electronic document control system (Procore). Task 2.03 – Modifications All work required to implement changes or modifications to the construction Contract Documents for City or Contractor initiated change orders shall be authorized under the technical contingency. Task 3 – On-Site Services Task 3.01 - Site Visits Jacobs will not provide members of the design team to make periodic site visits covering work such as electrical, mechanical equipment placement, architectural, HVAC, site civil and other technical disciplines under the base scope of work. All CM or Owner requests for site visits related to key design issues shall be covered under the technical contingency. Jacobs will only witness the factory witness testing required by the construction Contract Documents including the UV system, membrane equipment system, motor control centers, diesel generator, and programmable logic controllers. All other factory testing will be covered under the technical contingency. Specifically, for the I&C, Jacobs will participate in the factory testing, functional test part 1, functional test part 2, and performance testing. For each site visit, Jacobs will take photographs and will prepare a site visit report that documents the purpose of the site visit, the outcome and results of the site visit, a punch list of outstanding issues or items for correction and ultimately a recommendation as to the pass/failure of the system/equipment based on the criteria outlined during the site visit. The site visit report will be posted to the electronic document control system (Procore). Jacobs will participate in the company of the CM and Contractor in a site visit for the purposes of determining Substantial Completion of the Project Milestones in accordance with the construction Contract Documents. When ready, the Contractor will request the substantial completion site visit. The CM will prepare a list of items to be completed or corrected. Jacobs will review the list for concurrence. This will also include the instrumentation and control system start-up punch lists based on observations during on- site testing. Jacobs will support the commissioning activities associated with the Water Resource Center (WRC). These services include coordination with the third-party commissioning agent and Packet Pg. 108 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC include completion of the commissioning (CXR) certificate of compliance forms. The City will hire the third-party commissioning agent to witness the testing activities required by the construction Contract Documents. Jacobs will attend and participate in all software design workshops, control systems integrator coordination workshops and MCC integration workshops specified in the construction Contract Documents. Jacobs will perform the structural and geotechnical special inspection and observation as required by the construction Contract Documents and applicable codes. Jacobs will prepare the required structural observation and geotechnical special inspection reports and post the documents to the electronic document control system (Procore). Jacobs will attend coordination meetings with PG&E for the new electrical service installation. The assumptions in the following table were used to estimate hours for site visits, factory tests, factory acceptance tests and substantial completion site visits. BASIS OF EFFORT Activity Staff Duration Visits Hr / Visit Factory Acceptance Tests UV Disinfection 3 5 days 1 40 Membrane Equipment System 3 10 days 1 80 Motor Control Centers 2 5 days 3 40 Diesel Generator 1 3 days 1 32 Factory Software Demonstration Testing as described in 40 96 00 – 3.01 1 5 days 3 40 Total Hours 752 Site and Other Testing HVAC and Odor Control Commissioning Support (does not include WRC commissioning) 1 2 days 8 24 Software Design Workshops described in 40 96 00 – 1.06 and Vendor Coordination Workshops for Aeration Blowers, Sludge Thickening, and Solids Loadout described in 40 96 00 – 1.07. Other Vendor Coordination Workshops are covered under the equipment Factory Acceptance Test staff. 1 1 day 9 8 Structural site visits 1 1 day 50 16 Geotechnical site visits 1 1 day 20 16 PG&E Coordination 1 2 days 3 16 Substantial Completion Visits 3 3 days 1 32 Total Hours 1512 Packet Pg. 109 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC Notes: 1. Hours per visit include 8 hours of travel time for Corvallis staff. Travel will be during regular business hours. 2. Structural and geotechnical site visits are based on each facility being ready for inspection independently, one at a time, with multiple trips required per facility for structural. 3. Additional factory tests or any site visits, as requested by the CM, will be performed as Technical Services, entitling Jacobs to additional compensation. Task 3.02 – Resident Engineer Jacobs will provide an on-site senior resident engineer to facilitate Contractor submittal and RFI coordination with Jacobs’s design center as well as other communications between Jacobs and Contractor, CM and the City. Jacobs resident engineer will attend weekly construction progress meetings with the CM, Contractor, and the City. Jacobs will also attend meetings, such as presubmittal, maintenance of plant operation, Joint Test Group, and other meetings as may be required to review and resolve issues. Jacobs’ resident engineer will be assigned to the Project through the completion of the liquids phase improvements milestone (estimated to be 25 months from the effective date of the construction Notice to Proceed). Task 4 Closeout Phase Services Jacobs will assist the City in closing out the Contract for Construction and commencement of the City’s use of the completed Work. Jacobs’s services will include the following. Task 4.01 – Startup and Commissioning Services Jacobs will assist the CM, Contractor and the City in the startup of the new unit processes and auxiliary system, while the City’s Operations Staff will operate the new unit processes during startup. The services under this task will include review and preparation of testing procedures, assistance in trouble shooting, providing testing observation support for the systems integrator work, participation in Joint Test Group meetings as specified in the construction Contract Documents, support to the Joint Test Group, and fine-tuning operation. The City’s Operations Staff will operate the new facilities or unit processes during commissioning and after acceptance in coordination with the Contractor. Startup and commissioning will occur at the individual process unit level and not at the facility level. For estimating purposes, it is assumed that there will be twenty-four (24) different unit processes that will be started up and commissioned, as delineated by the following unit processes: 1. Headworks 2. Flow Equalization 3. Primary Clarification (including primary sludge pumping) 4. Primary Effluent Diversion 5. Primary Effluent Screens Packet Pg. 110 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC 6. Bioreactor Basins 1 & 2 7. Bioreactor Basins 3 & 4 8. Blower Systems 9. Membrane Equipment System and Tanks 10. UV Disinfection 11. Effluent Structure (Cooling and 3W Pump Station) 12. Filtrate Equalization 13. Air Gap Building (1W Pumping) 14. Sodium Hypochlorite System 15. Ferric Chloride System 16. CEPT System 17. Supplemental Carbon System 18. Sludge Blending 19. Sludge Thickening 20. Digesters 1 & 2 (Will be done at separate times) 21. Digester Complex 22. Digested Sludge Storage 23. Dewatering (loadout) 24. Odor Control In addition, auxiliary systems will be tested to support the unit process startup. These include the following systems: 1. SCADA system 2. Electrical Service and Distribution 3. Standby Diesel Generator 4. Building Systems (HVAC, plumbing, etc.) 5. Landscaping 6. Corrosion control 7. Water quality instrumentation 8. Security Systems 9. Fire Protection It is assumed that most of the auxiliary systems will not require support from Jacobs for the testing, except for the electrical motor control centers, SCADA system, and standby diesel generator. It is anticipated that the Contractor will develop and distribute the startup schedule several months ahead of the anticipated time for startup. Jacobs will closely coordinate this activity with the CM. Task 4.02 – WRC Startup Services It is anticipated that the Owner will hire a third-party Commissioning Agent for the startup Packet Pg. 111 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC and commissioning services for the WRC in compliance with the Energy Code. The Jacobs team will provide support for questions related to the design and has budgeted four trips of 16 hours each to the site for WRC startup support. Task 4.03 – Training Jacobs will provide supplemental instruction to the City’s staff in the operation, maintenance, and testing of the equipment provided under this Project. This instruction shall cover both the basic operational concept and actual operation of the systems and components under both normal and abnormal operations that are likely to occur. Jacobs will prepare a training syllabus and training materials to leave with the City staff. The training syllabus and materials will be transmitted to the City for review and comment a minimum of 30 days in advance of the scheduled training date. Jacobs will submit draft and final training materials to the City for each unit process. Training materials will be delivered to the City as an electronic copy and in one (1) hard copy format. For estimating purposes, it is assumed that there will be twenty-four (24) different facilities/processes that will be started up thus requiring up to twenty-four (24) training sessions, as delineated by the following facilities/processes: 1. Headworks 2. Flow Equalization 3. Primary Clarification (including primary sludge pumping) 4. Primary Effluent Diversion 5. Primary Effluent Screens 6. Blower Systems 7. Bioreactor Basins 1 & 2 8. Bioreactor Basins 3 & 4 9. Membrane Equipment System and Tanks 10. UV Disinfection 11. Effluent Structure (Cooling and 3W Pump Station) 12. Filtrate Equalization 13. Air Gap Building (1W Pumping) 14. Sodium Hypochlorite System 15. Ferric Chloride System 16. CEPT System 17. Supplemental Carbon System 18. Sludge Blending 19. Sludge Thickening 20. Digesters 1 & 2 21. Digester Complex 22. Digested Sludge Storage 23. Dewatering (loadout) 24. Odor Control Packet Pg. 112 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC In addition, auxiliary systems will be tested to support the unit process startup. These include the following systems: 1. SCADA System 2. Electrical Service and Distribution 3. Standby Diesel Generator 4. Building Systems 5. Landscaping 6. Corrosion control 7. Water quality instrumentation 8. Security Systems 9. Fire Protection It is assumed that most of the auxiliary systems will not require support from Jacobs for the training, as the training will be provided by the Contractor, Training sessions are assumed to be for a single group with one-day per facility. If multiple sessions are required, this shall be considered a Technical Contingency entitling Jacobs to additional compensation. Each training session will be videotaped by Others. Task 4.04 – Operations and Maintenance Manual Jacobs will develop a Process Operations and Maintenance (O&M) manual describing the operation of the individual unit processes at the WRRF. The O&M Manual will be developed in Microsoft Word and will also be provided in a compiled native PDF format with bookmarks. The format shall be based on the sample City of Henderson O&M Manual that was provided to the City. Manufacturers’ O&M materials will be referenced but not duplicated. The O&M manual will include an update to the existing O&M manual, using the information from the existing sections, for unit processes that are being changed. Those being eliminated will be deleted from the O&M manual. Unit process that are remaining unchanged will not be updated. The O&M manual will generally explain the various primary modes of operation that may be used, including normal operation, peak flow conditions, and emergency operation procedures. The manual will explain the purpose and basic concept of the various processes that are incorporated into the overall plant. Where appropriate, reference will be made to the manufacturers’ detailed O&M submittals. The manual will be suitable for use as an operational tool and to facilitate operator training. The manual will be produced in an electronic format that is consistent with the City’s most recent guide. Sections of the O&M currently identified include: 1. Primary Treatment 2. Primary Sludge Thickening 3. Bioreactors 4. Secondary Treatment (membrane bioreactors) 5. Anaerobic Digestion 6. Digested Sludge Thickening/Dewatering/Storage Packet Pg. 113 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC 7. Biosolids Storage and Loadout 8. Instrumentation and Control (SCADA) 9. Chemical Storage and Feed Systems 10. Odor Control System 11. Disinfection 12. Support Systems (i.e. HVAC, electrical, plant air, service water, etc.) Jacobs will provide draft and final versions of the O&M Manual. Comments provided by the City will be tabulated, and formal responses will be provided in a Microsoft Excel spreadsheet. One electronic copy containing the final compiled PDF O&M Manual, five (5) hard copies of the draft O&M Manual, and six (6) hard copies of the Final O&M Manual will be provided to the City. Task 4.05 – Membrane System Commissioning Period Support Jacobs will provide support during the 180-day membrane system commissioning period including reviewing test result data and providing technical support. The majority of the effort for the commissioning period will be by the City with Suez. Jacobs will review and comment on the Commissioning Period Report prepared by Suez at the conclusion of the membrane systems commissioning period. Jacobs will provide a list of items to be corrected under the membrane system warranty and provide a recommendation regarding final acceptance of the system by the City. An estimate of 16 hours per month for one person is assumed for budgeting for this task along with 24 hours for review and comment to the final report. Task 4.06 – Final Completion Jacobs will participate in a final completion site visit along with the CM, Contractor, and other City staff as appropriate for the purposes of determining that the completed Project has met the requirements of the construction Contract Documents regarding Final Completion. Jacobs will assist the CM in preparing a list of items in which this site visit reveals that the Work is incomplete or defective and will make recommendations to the City concerning acceptance when items on the final punch list have been completed or corrected. Task 4.07 – Closeout Workshop Jacobs shall participate in a closeout workshop. The CM will lead the meeting, prepare the required materials, and prepare and distribute meeting minutes. The meeting duration is assumed to be four (4) hours. Task 4.08 – Record Drawings Jacobs will revise the original design drawings to reflect record information provided by the Contractor, CM and equipment suppliers. 3D models will not be updated for actual equipment installed unless the layout is substantially changed. Jacobs’s services are based on an estimated three (3) hours per drawing. One electronic file in the most current version of AutoCAD, one PDF file, and two hard copies (one full-size set and one half-size set) will be provided to the City. Packet Pg. 114 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC Task 5 Technical Contingency Upon request of the City, Jacobs will provide additional engineering services during construction that are not described herein. A Technical Contingency budget has been established for these services. For any such work, Jacobs will first furnish a written scope and cost estimate that the City shall approve in writing before Jacobs proceeds with the work. Technical Contingency Services may include, but are not limited to, the following: • Technical support during weekly construction progress meetings. • Design work required for Owner, CM, or Contractor initiated changes or modifications. • Site visits for technical support and factory test witnessing not specifically listed under Task 3.01. • Submittals or RFI’s required to be reviewed in excess of the quantity shown. • Additional training sessions. • Claims support and resolution. Compensation Compensation for the tasks as described in the Scope of Work will be on a time and material basis. Labor will be based upon the hourly rate table provided in Attachment B – Per Diem Rate Schedule. The total estimated cost shall not exceed the amount shown in Attachment A without agreement and authorization by both parties. Details on the estimated hours, expenses, and costs are provided in Attachment A – Fee Schedule. Packet Pg. 115 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC Attachment A – Fee Schedule Packet Pg. 116 Item 9 2019 $274 $274 $240 $240 $208 $186 $175 $162 $143 $117 $108 $164 $99 $116 2020 $282 $282 $247 $247 $214 $191 $180 $167 $148 $120 $111 $169 $102 $119 2021 $290 $290 $254 $254 $221 $197 $186 $172 $152 $124 $115 $174 $105 $123 2022 $299 $299 $262 $262 $227 $203 $191 $177 $157 $128 $118 $180 $108 $126 Task 1 Project Management Task Total 1960 $565,426 0 $0 0 $0 200 $50,066 0 $0 40 $7,426 0 $0 0 $0 0 $0 24 $2,801 24 $2,597 80 $13,155 80 $7,893 976 $117,959 3384 $767,324 $54,000 $58,762 $37,740 $96,502 $917,826 1.01 Project Administration Total 160 $46,206 0 $0 0 $0 160 $40,475 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 624 $76,235 944 $162,917 $20,000 $38,762 $27,500 $66,262 $249,179 2019 16 $4,379 $0 $0 16 $3,836 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $5,551 80 $13,766 $5,000 $8,762 $5,000 $13,762 $32,528 2020 48 $13,532 $0 $0 48 $11,854 $0 $0 $0 $0 $0 $0 $0 $0 $0 192 $22,869 288 $48,255 $5,000 $10,000 $7,500 $17,500 $70,755 2021 48 $13,938 $0 $0 48 $12,210 $0 $0 $0 $0 $0 $0 $0 $0 $0 192 $23,555 288 $49,702 $5,000 $10,000 $7,500 $17,500 $72,202 2022 48 $14,356 $0 $0 48 $12,576 $0 $0 $0 $0 $0 $0 $0 $0 $0 192 $24,261 288 $51,194 $5,000 $10,000 $7,500 $17,500 $73,694 1.02 Communications Total 960 $277,239 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 192 $23,222 1152 $300,461 $10,000 $0 $0 $0 $310,461 2019 96 $26,276 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $5,551 144 $31,827 $2,500 $0 $34,327 2020 288 $81,194 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $5,717 336 $86,911 $2,500 $0 $89,411 2021 288 $83,630 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $5,889 336 $89,518 $2,500 $0 $92,018 2022 288 $86,139 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $6,065 336 $92,204 $2,500 $0 $94,704 1.03 Coordination Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 $0 $0 $0 $0 $0 2019 0 $0 $0 $0 0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2020 0 $0 $0 $0 0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2021 0 $0 $0 $0 0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2022 0 $0 $0 $0 0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 1.04 Pre-Construction Conference Total 16 4,379 0 0 0 0 16 3,836 0 0 16 2,971 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 48 $11,186 $2,000 $0 $0 $0 $13,186 2019 16 4,379 0 0 16 3,836 0 16 2,971 0 0 0 0 0 0 0 $0 48 $11,186 $2,000 $0 $13,186 1.05 Partnering Total 160 46,206 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 160 $46,206 $17,000 $0 $0 $0 $63,206 2019 16 $4,379 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 16 $4,379 $2,000 $0 $6,379 2020 48 $13,532 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $13,532 $5,000 $0 $18,532 2021 48 $13,938 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $13,938 $5,000 $0 $18,938 2022 48 $14,356 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $14,356 $5,000 $0 $19,356 1.06 Project Management Meetings Total 640 184,826 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 640 $184,826 $0 $0 $0 $0 $184,826 2019 64 $17,518 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 64 $17,518 $0 $17,518 2020 192 $54,129 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 192 $54,129 $0 $54,129 2021 192 $55,753 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 192 $55,753 $0 $55,753 2022 192 $57,426 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 192 $57,426 $0 $57,426 1.07 Conformed Documents Total 24 6,569 0 0 0 0 24 5,754 0 0 24 4,456 0 0 0 0 0 0 24 2,801 24 2,597 80 13,155 80 7,893 160 $18,502 440 $61,727 $5,000 $20,000 $10,240 $30,240 $96,967 2019 24 $6,569 $0 $0 24 $5,754 $0 24 $4,456 $0 $0 $0 24 $2,801 24 $2,597 80 $13,155 80 $7,893 160 $18,502 440 $61,727 $5,000 $20,000 $10,240 $30,240 $96,967 Task 2. Submittal Review, RFIs and Clarifications, Modifications and Document Tracking Task Total 280 $80,655 0 $0 0 $0 380 $95,949 570 $124,818 630 $122,922 630 $115,898 630 $107,469 1010 $152,140 1274 $156,877 1110 $126,602 0 $0 0 $0 1054 $127,970 7568 $1,211,298 $23,500 $465,530 $85,274 $550,804 $1,785,602 2.01 Submittal Review Total 190 $54,767 0 $0 0 $0 190 $47,974 380 $83,212 380 $74,297 380 $70,051 380 $64,956 760 $114,629 1034 $127,479 760 $86,609 0 $0 0 $0 534 $64,869 4988 $788,844 $16,500 $330,054 $50,034 $380,088 $1,185,432 2019 20 $5,474 $0 $0 20 $4,795 40 $8,317 40 $7,426 40 $7,002 40 $6,493 80 $11,458 80 $9,336 80 $8,657 $0 $0 80 $9,251 520 $78,210 $1,500 $25,000 $5,034 $30,034 $109,744 2020 60 $16,915 $0 $0 60 $14,817 120 $25,701 120 $22,947 120 $21,636 120 $20,062 240 $35,404 300 $36,060 240 $26,750 $0 $0 160 $19,057 1540 $239,351 $5,000 $100,000 $15,000 $115,000 $359,351 2021 60 $17,423 $0 $0 60 $15,262 120 $26,472 120 $23,636 120 $22,285 120 $20,664 240 $36,466 354 $43,827 240 $27,552 $0 $0 160 $19,629 1594 $253,217 $5,000 $100,000 $15,000 $115,000 $373,217 2022 50 $14,955 $0 $0 50 $13,100 100 $22,722 100 $20,287 100 $19,128 100 $17,737 200 $31,300 300 $38,256 200 $23,649 $0 $0 134 $16,932 1334 $218,066 $5,000 $105,054 $15,000 $120,054 $343,120 2.02 RFIs and Clarifications Total 90 $25,888 0 $0 0 $0 190 $47,974 190 $41,606 250 $48,625 250 $45,847 250 $42,512 250 $37,511 240 $29,397 350 $39,993 0 0 0 0 520 $63,100 2580 $422,455 $7,000 $135,476 $35,240 $170,716 $600,171 2019 10 $2,737 $0 $0 20 $4,795 20 $4,159 40 $7,426 40 $7,002 40 $6,493 40 $5,729 30 $3,501 30 $3,246 $0 $0 80 $9,251 350 $54,339 $1,000 $15,476 $5,240 $20,716 $76,055 2020 30 $8,458 $0 $0 60 $14,817 60 $12,850 80 $15,298 80 $14,424 80 $13,375 80 $11,801 80 $9,616 100 $11,146 $0 $0 160 $19,057 810 $130,843 $2,000 $40,000 $10,000 $50,000 $182,843 2021 30 $8,711 $0 $0 60 $15,262 60 $13,236 80 $15,757 80 $14,857 80 $13,776 80 $12,155 80 $9,904 120 $13,776 $0 $0 160 $19,629 830 $137,064 $2,000 $40,000 $10,000 $50,000 $189,064 2022 20 $5,982 $0 $0 50 $13,100 50 $11,361 50 $10,144 50 $9,564 50 $8,868 50 $7,825 50 $6,376 100 $11,825 $0 $0 120 $15,163 590 $100,208 $2,000 $40,000 $10,000 $50,000 $152,208 2.03 Modifications - Moved to technical contingency Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 $0 $0 $0 $0 $0 2019 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2021 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 Task 3 On-Site Services Task Total 0 $0 0 $0 0 $0 0 $0 336 $73,532 460 $89,710 816 $150,554 0 $0 4160 $617,298 0 $0 0 $0 0 $0 0 $0 0 $0 5772 $931,095 $155,000 $82,500 $0 $82,500 $1,168,595 3.01 Site Visits Total 0 $0 0 $0 0 $0 0 $0 336 $73,532 460 $89,710 816 $150,554 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 1612 $313,796 $55,000 $82,500 $0 $82,500 $451,296 2019 $0 $0 $0 $0 48 $9,981 48 $8,912 96 $16,805 $0 $0 $0 $0 $0 $0 $0 192 $35,697 $10,000 $10,000 $10,000 $55,697 2020 $0 $0 $0 $0 96 $20,561 160 $30,596 240 $43,272 $0 $0 $0 $0 $0 $0 $0 496 $94,429 $15,000 $15,000 $15,000 $124,429 2021 $0 $0 $0 $0 96 $21,178 156 $30,726 240 $44,570 $0 $0 $0 $0 $0 $0 $0 492 $96,474 $15,000 $32,500 $32,500 $143,974 2022 $0 $0 $0 $0 96 $21,813 96 $19,476 240 $45,907 $0 $0 $0 $0 $0 $0 $0 432 $87,196 $15,000 $25,000 $25,000 $127,196 3.02 Resident Engineer Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 4160 $617,298 0 $0 0 $0 0 $0 0 $0 0 $0 4160 $617,298 $100,000 $0 $0 $0 $717,298 2019 $0 $0 $0 $0 $0 $0 $0 $0 640 $91,662 $0 $0 $0 $0 $0 640 $91,662 $16,000 $0 $107,662 2020 $0 $0 $0 $0 $0 $0 $0 $0 2080 $306,838 $0 $0 $0 $0 $0 2080 $306,838 $48,000 $0 $354,838 2021 $0 $0 $0 $0 $0 $0 $0 $0 1440 $218,799 $0 $0 $0 $0 $0 1440 $218,799 $36,000 $0 $254,799 2022 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 $0 Task 4 Closeout Phase Services Task Total 24 $7,178 0 $0 0 $0 24 $6,105 48 $10,748 48 $9,454 48 $8,914 0 $0 2936 $452,440 96 $11,885 0 $0 600 $107,812 500 $53,906 120 $14,722 4444 $683,164 $101,500 $131,091 $44,360 $175,451 $960,115 4.01 Startup and Commissioning Services Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 1152 $176,256 0 $0 0 $0 0 $0 0 $0 0 $0 1152 $176,256 $50,000 $84,465 $0 $84,465 $310,721 2020 $0 $0 $0 $0 $0 $0 $0 $0 240 $35,404 $0 $0 $0 $0 $0 240 $35,404 $10,000 $19,465 $19,465 $64,869 2021 $0 $0 $0 $0 $0 $0 $0 $0 412 $62,601 $0 $0 $0 $0 $0 412 $62,601 $20,000 $25,000 $25,000 $107,601 2022 $0 $0 $0 $0 $0 $0 $0 $0 500 $78,251 $0 $0 $0 $0 $0 500 $78,251 $20,000 $40,000 $40,000 $138,251 4.02 WRC Startup Services Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 64 $9,724 0 $0 0 $0 0 $0 0 $0 0 $0 64 $9,724 $2,000 $0 $0 $0 $11,724 2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2021 $0 $0 $0 $0 $0 $0 $0 $0 64 $9,724 $0 $0 $0 $0 $0 64 $9,724 $2,000 $0 $11,724 2022 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 4.03 Training Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 480 $73,491 0 $0 0 $0 0 $0 0 $0 0 $0 480 $73,491 $22,000 $0 $0 $0 $95,491 2020 $0 $0 $0 $0 $0 $0 $0 $0 80 $11,801 $0 $0 $0 $0 $0 80 $11,801 $2,000 $0 $13,801 2021 $0 $0 $0 $0 $0 $0 $0 $0 200 $30,389 $0 $0 $0 $0 $0 200 $30,389 $10,000 $0 $40,389 2022 $0 $0 $0 $0 $0 $0 $0 $0 200 $31,300 $0 $0 $0 $0 $0 200 $31,300 $10,000 $0 $41,300 4.04 Operations and Maintenance Manual Total 0 $0 0 $0 0 $0 24 $6,105 24 $5,294 48 $9,454 48 $8,914 0 $0 120 $18,233 96 $11,885 0 $0 0 $0 0 $0 120 $14,722 480 $74,608 $5,000 $16,873 $0 $16,873 $96,481 2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2021 $0 $0 $0 24 $6,105 24 $5,294 48 $9,454 48 $8,914 $0 120 $18,233 96 $11,885 $0 $0 $0 120 $14,722 480 $74,608 $5,000 $16,873 $16,873 $96,481 2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 4.05 Membrane System Commissioning Period Support Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 120 $18,233 0 $0 0 $0 0 $0 0 $0 0 $0 120 $18,233 $15,000 $0 $0 $0 $33,233 2021 $0 $0 $0 $0 $0 $0 $0 $0 120 $18,233 $0 $0 $0 $0 $0 120 $18,233 $15,000 $0 $33,233 2022 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 4.06 Final Completion Total 24 $7,178 0 $0 0 $0 0 $0 24 $5,453 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 48 $12,631 $2,500 $0 $11,600 $11,600 $26,731 Technician Task Nos.Task/Activity Description Labor Classification Subconsultant Costs ($) Office / ClericalPrincipal in Charge Principal Professional 2 Principal Professional 1 Sr. Professional 2 Sr. Professional 1 TOTAL Estimated Cost ($) MWA Architects Attachment A Detailed Fee Estimate City of San Luis Obispo Water Resource Recovery Facility Project Professional 2Project Manager Process Optimization Subconsultant TotalTotal Labor Hours Total Labor Costs ($) Travel and Other Expenses ($) Cannon Corp. Project Professional 1 Staff Professional 2 Staff Professional 1 Engineering Technician Packet Pg. 117 Item 9 Attachment A Detailed Fee Estimate City of San Luis Obispo Water Resource Recovery Facility 2022 24 $7,178 $0 $0 $0 24 $5,453 $0 $0 $0 $0 $0 $0 $0 $0 $0 48 $12,631 $2,500 $11,600 $11,600 $26,731 4.07 Closeout Workshop Total 8 $2,393 0 $0 0 $0 0 $0 8 $1,818 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 16 $4,210 $1,000 $1,312 $0 $1,312 $6,522 2019 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2020 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2021 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0 2022 8 $2,393 $0 $0 $0 8 $1,818 $0 $0 $0 $0 $0 $0 $0 $0 $0 16 $4,210 $1,000 $1,312 $1,312 $6,522 4.08 Record Drawings Total 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 0 $0 1000 $156,502 0 $0 0 $0 600 $107,812 500 $53,906 0 $0 2100 $318,221 $5,000 $29,753 $32,760 $62,513 $385,734 2022 $0 $0 $0 $0 $0 $0 $0 $0 1000 $156,502 $0 $0 600 $107,812 500 $53,906 $0 2100 $318,221 $5,000 $29,753 $32,760 $62,513 $385,734 Task 5 Technical Contingency Task Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $310,000 5.01 Communications Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $25,000 5.02 Modifications Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $200,000 5.04 Submittals and RFI's Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $75,000 5.05 Additional training Sessions Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $10,000 5.06 Claims Support Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 2264 $653,260 0 $0 0 $0 604 $152,119 954 $209,098 1178 $229,512 1494 $275,366 630 $107,469 8106 $1,221,878 1394 $171,563 1134 $129,199 680 $120,968 580 $61,799 2150 $260,650 21168 $3,592,881 $334,000 $737,883 $167,374 $905,257 $5,142,138TOTAL Packet Pg. 118 Item 9 040219_SLO WRRF SDC SCOPE_FINAL.DOC Attachment B – Per Diem Rate Schedule Packet Pg. 119 Item 9 Attachment B Classification 2019 Rate 2020 Rate 2021 Rate 2022 Rate Project Manager $274 $282 $290 $299 Process Optimization $274 $282 $290 $299 Principal-In-Charge $240 $247 $254 $262 Principal Professional 2 $240 $247 $254 $262 Principal Professional 1 $208 $214 $221 $227 Sr. Professional 2 $186 $191 $197 $203 Sr. Professional 1 $175 $180 $186 $191 Project Professional 2 $162 $167 $172 $177 Project Professional 1 $143 $148 $152 $157 Staff Professional 2 $117 $120 $124 $128 Staff Professional 1 $108 $111 $115 $118 Engineering Technician $164 $169 $174 $180 Technician $99 $102 $105 $108 Office/Clerical $116 $119 $123 $126 EXPENSES Expense Type Estimating Method Auto Mileage Travel Auto Rental Travel Other Travel Travel Equipment Rental Operating Expense Postage/Freight Operating Expense Reprographics Outside Service Subcontractors Outside Service CH2M HILL Professionals and Technicians Hourly Billing Rate Schedule Packet Pg. 120 Item 9 AMENDMENT TO AGREEMENT NO. 4 THIS AMENDMENT TO AGREEMENT is made and entered in the City of San Luis Obispo on _______________________, by and between the CITY OF SAN LUIS OBISPO, a municipal corporation, herein after referred to as City, and WATER SYSTEMS CONSULTING, INC., hereinafter referred to as Contractor. WITNESSETH: WHEREAS, in January 29, 2014 the City entered into an Agreement with Contractor for Program Manager Services per Water Reclamation Facility Upgrade Project, Specification No. 91219 and WHEREAS, the City desires to amend the scope of services to include Phase 4 & 5 Program Manager Services for the Water Resource Recovery Facility Project. NOW THEREFORE, in consideration of their mutual promises, obligations and covenants hereinafter contained, the parties hereto agree as follows: 1. The scope of services and related compensation is hereby amended as set forth in Exhibit A attached hereto. a. Program Manager Services per proposal dated April 2, 2019, at cost not to exceed $2,620,938 on a time and materials basis. 2. All other terms and conditions of the Agreement remain in full force and effect. IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed the day and year first written above. ATTEST: CITY OF SAN LUIS OBISPO ____________________________________ By:____________________________________ Teresa Purrington, City Clerk Mayor Heidi Harmon APPROVED AS TO FORM: CONTRACTOR _____________________________________ By:____________________________________ Christine Dietrick, City Attorney Jeff Szytel, Water Systems Consulting, Inc. Packet Pg. 121 Item 9 Program Manager for the WRRF Project Proposal for Phase 4 and 5 Services 4/2/2019 Prepared for the: Packet Pg. 122 Item 9 City of San Luis Obispo Proposal for Phase 4 and 5 Services Program Manager for WRRF Upgrade Project 4/2/2019 i TABLE OF CONTENTS Scope of Services: Phases 4 and 5 – Construction and Close-Out ............................................................ 1 Introduction .............................................................................................................................................. 1 Task 0.0 Program Planning .................................................................................................................. 1 0.1 Review and Update Program Management Plan (PMP) ........................................................... 1 0.2 Charter Workshop ..................................................................................................................... 2 0.3 Partnering ................................................................................................................................. 2 Task 1.0 Program Management for Phase 4 ....................................................................................... 2 1.1 Program Administration ............................................................................................................ 2 1.2 City Coordination ...................................................................................................................... 3 1.3 Agency Coordination ................................................................................................................. 3 1.4 Consultant Coordination ........................................................................................................... 3 1.5 Document Review ..................................................................................................................... 4 1.6 Quality Assurance ..................................................................................................................... 4 1.7 Program Controls ...................................................................................................................... 4 1.8 Change Management ................................................................................................................ 5 1.9 Risk Management ..................................................................................................................... 5 1.10 Data Management .................................................................................................................... 6 1.11 Program Status Reports ............................................................................................................ 6 1.12 Recurring Meetings ................................................................................................................... 6 1.13 Non-Recurring Meetings ........................................................................................................... 7 Task 2.0 Submittal and Request For Information Review ................................................................... 8 2.1 Submittal and Request for Information (RFI) Review ............................................................... 8 Task 3.0 Permitting Support ................................................................................................................ 8 Task 4.0 Funding and financing Support ............................................................................................. 9 4.1 State Revolving Fund (SRF) Loan Support ................................................................................. 9 4.2 California Office of Emergency Services (CalOES) Grant Funding Support ............................... 9 Task 5.0 Public and Stakeholder Outreach ....................................................................................... 10 5.1 Council and Stakeholder Meetings ......................................................................................... 10 5.2 Community Workshop ............................................................................................................ 10 5.3 Project Website Refresh ......................................................................................................... 10 Packet Pg. 123 Item 9 City of San Luis Obispo Proposal for Phase 4 and 5 Services Program Manager for WRRF Upgrade Project 4/2/2019 ii 5.4 Project Website Maintenance/Updates ................................................................................. 11 5.5 Ribbon Cutting and/or WRRF Recognition Event ................................................................... 11 5.6 Photography and Videography ............................................................................................... 11 Task 6.0 Maintenance of Plant Operation ........................................................................................ 12 6.1 MOPO Document Review ....................................................................................................... 12 Task 7.0 Start-Up and Commissioning .............................................................................................. 12 7.1 Coordination and Document Review ...................................................................................... 12 7.2 Acceptance .............................................................................................................................. 13 Task 8.0 Construction Close-Out ....................................................................................................... 13 8.1 Punch List ................................................................................................................................ 13 8.2 Document Review ................................................................................................................... 13 Task 9.0 Labor Compliance and Community Workforce Agreement Administration ...................... 13 9.1 Labor Compliance and Community Workforce Agreement (CWA) Administration Plan ....... 13 9.2 Labor Compliance ................................................................................................................... 13 9.3 CWA Administration ............................................................................................................... 13 9.4 Monthly Reports ..................................................................................................................... 13 9.5 Close-Out Report ..................................................................................................................... 14 Task 10.0 Phase 5 – Program Close-Out ............................................................................................. 14 10.1 Project Archive ........................................................................................................................ 14 10.2 Close-Out Report ..................................................................................................................... 14 10.3 Funding/Financing Close-Out .................................................................................................. 14 10.4 City Council Presentation ........................................................................................................ 14 Optional Task 1.0 Asset Management Support ....................................................................................... 14 O1.1 Asset Management System Data Management ..................................................................... 14 O1.2 Support New Asset Hierarchy Development .......................................................................... 16 O1.3 Asset Management System Technical Support ...................................................................... 16 Optional Task 2.0 Partnerships ................................................................................................................ 17 O2.1 California Polytechnic State University (Cal Poly) ................................................................... 17 O2.2 One Water Learning Center .................................................................................................... 17 Optional Task 3.0 Maintenance of Plant Operation Coordination .......................................................... 18 O3.1 MOPO Liaison .......................................................................................................................... 18 O3.2 MOPO Coordination Meetings ................................................................................................ 18 Packet Pg. 124 Item 9 City of San Luis Obispo Proposal for Phase 4 and 5 Services Program Manager for WRRF Upgrade Project 4/2/2019 iii O3.3 Document Review ................................................................................................................... 18 O3.4 Revised Operating Procedures ................................................................................................ 18 Recurring Meetings Summary .................................................................................................................... 19 Packet Pg. 125 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 1 Scope of Services: Phases 4 and 5 – Construction and Close-Out INTRODUCTION The City of San Luis Obispo (City) hired the WSC-HDR team (Consultant) in January 2014 as Program Manager for the Water Resource Recovery Facility (WRRF) Project. This proposal is for Phases 4 and 5 of the Program, which are expected to continue through June 2023. Phase Assumed Schedule Phase 1 – Project Planning January, 2014 – June, 2015 Phase 2 – Preliminary Design July, 2015 – June, 2016 Phase 3 – Final Design July, 2016 – July, 2019 Phase 4 – Construction August, 2019 – February, 2023 Phase 5 – Close Out March, 2023 – June, 2023 The scope of work below includes a detailed breakdown of the services anticipated for Phases 4 and 5. Given the nature of the Program, it is anticipated that the tasks will evolve to accommodate changing Program needs. Therefore, the budget allocations provided for each task are estimates only and the City will have the flexibility to reallocate budgets between tasks, as dictated by Program needs and as directed by the City. Throughout the scope both Program Team and Project Team are referenced. Program Team refers to the WSC-HDR program management team. Project Team refers to the larger WRRF project team, which includes the Program Team, Design Engineer, Construction Manager, and the City’s WRRF team. This scope covers Phases 4 and 5 services for construction and Program close-out through June 30, 2023, or a duration of approximately 47 months. TASK 0.0 PROGRAM PLANNING 0.1 Review and Update Program Management Plan (PMP) ➢ Review the following sections of the PMP and update as required, including modifications necessary to align with the Contract Documents: (1) Chapter 3 – Program Administrative Procedures (2) Chapter 4 – Communication Plan (3) Chapter 5 – Data Management (4) Chapter 6 – Change Management (5) Chapter 7 – Risk Management (6) Chapter 8 – Design Standards (7) Chapter 9 – Sustainability Plan (8) Chapter 10 – Quality Assurance/Quality Control (QA/QC) Plan Packet Pg. 126 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 2 ➢ Document revisions in the PMP Revision Log, and distribute updated PMP to all Project Team members, including the Design Engineer and Construction Manager. 0.2 Charter Workshop ➢ Facilitate a structured workshop with the Project Team at the onset of Phase 4 to review the Charter with key team members from the City team, Program Team, Design Team, Construction Manager, and others as determined by the Core Management Team (CMT). The workshop may include new Council members and new staff from the Central Coast Regional Water Quality Control Board (Regional Board). ➢ The goal of the workshop will be to review the Charter, reflect on successes, identify areas for improvement, and develop initiatives going forward. The workshop will also be an opportunity for new project participants to sign onto the Charter. ➢ The scope assumes one (1) 4-hour workshop. 0.3 Partnering ➢ Develop a draft and final scope of work for Partnering Facilitator and assist City in procurement of the Partnering Facilitator. Costs for the Partnering Facilitator’s contract are not included, since it is assumed that the City and/or the General Contractor will contract with the Partnering Facilitator directly. ➢ Coordinate with the Partnering Facilitator in the development of materials for the Executive Partnering Workshop and Initial Partnering Workshop. ➢ Coordinate with the Project Team to plan and schedule Partnering Meetings. It is assumed the Partnering Facilitator will be responsible for documenting the Partnering Meetings and preparing meeting minutes. ➢ Participate in the Executive Partnering Workshop and Initial Partnering Workshop. The assumed duration for the Executive Partnering Workshop is four (4) hours and the assumed duration for the Initial Partnering Workshop is eight (8) hours. Two (2) members of the Program Team will participate in the Executive Partnering Workshop and three (3) members of the Program Team will participate in the Initial Partnering Workshop. Deliverable: Updated Program Management Plan, Partnering Facilitator Scope of Work, Meeting Agendas and Minutes TASK 1.0 PROGRAM MANAGEMENT FOR PHASE 4 1.1 Program Administration ➢ Provide oversight, manage communication, assign resources, and coordinate work efforts of the Consultant team to align with Program priorities and achieve cost-effective performance. ➢ Actively solve problems and address issues, including coordination and collaboration of Program resources. ➢ Administer WSC’s subconsultant agreements and coordinate subconsultant activities. Packet Pg. 127 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 3 ➢ Prepare monthly invoices and monthly progress reports to the City. Monthly progress reports will be limited to a description of the services provided by WSC-HDR during the reporting period. Quarterly Program status reports are included in Task 1.11. 1.2 City Coordination ➢ Engage, collaborate, and coordinate with City staff. ➢ Facilitate and/or participate in impromptu meetings, phone/conference calls, and site visits. ➢ Support and facilitate information sharing and knowledge transfer. ➢ Provide technical expertise when needed to advise the City on key decisions during construction. ➢ Coordinate with the Community Development and Public Works Departments to manage the interface of the Prado Overpass, Regional Transit Authority Bus Facility, Prado Bridge Widening, and Elks Lane Realignment Projects with the WRRF Project. 1.3 Agency Coordination ➢ Serve as primary point of contact and Program lead for the City. Coordinate interactions with jurisdictional agencies, permitting entities, project partners, and other stakeholders directly related to the Program. ➢ Coordinate with Pacific Gas & Electric (PG&E) to facilitate construction of the new WRRF electrical service. WSC’s scope will be limited to PG&E outreach on behalf of the City to facilitate service planning and PG&E system improvements required for the new WRRF electrical service. ➢ Plan, organize, conduct, and document meetings with agencies. ➢ Participate in the City’s ongoing negotiations with agencies and provide technical support to the City to support negotiations with agencies. ➢ A level of effort of 94 hours was assumed due to the uncertainty related to the level of effort for this task. 1.4 Consultant Coordination ➢ Coordinate the work of the City’s consulting firms, including Jacobs, Carollo, Larry Walker and Associates, Somach Simmons & Dunn, the selected Water Resources Center (WRC) commissioning coordinator, and the selected environmental consulting firm. Manage and monitor the work of consultants through construction. ➢ Manage and monitor the work of the environmental consultant through completion. Manage the review of all deliverables. Review consultant’s progress against the project schedule and recommend corrective action as needed. ➢ Develop scope of work and assist City in the procurement of a commissioning coordinator for the WRC to satisfy the California Energy Code requirements regarding building commissioning. Packet Pg. 128 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 4 ➢ Manage and monitor the work of the commissioning coordinator through completion. Manage the review of all deliverables. Review consultant’s progress against the project schedule and recommend corrective action as needed. 1.5 Document Review ➢ Review and provide comments on all deliverables developed by the commissioning coordinator including performance test instructions, test results, systems manual, and commissioning report. 1.6 Quality Assurance ➢ Provide quality assurance to meet the Program’s goals, standards, and quality objectives, including: (1) Meet the intent of the QA/QC Plan, as defined in the PMP; (2) Monitor adherence to the Program standards, as defined in the PMP; (3) Review documents for consistency with Program Charter; (4) Periodically audit QC documentation; (5) Review and update QA/QC Plan as necessary. ➢ Attend the Construction Quality Control Plan Coordination Meeting to discuss development of the General Contractor’s Construction Quality Control (CQC) Plan. ➢ Review the General Contractor’s CQC Plan and provide detailed review comments. ➢ Periodically monitor Construction Manager’s compliance with the procedures and guidelines set forth in the Construction Management Plan (CMP) and the Construction Manager’s Construction QA/QC Plan. ➢ Perform periodic audits of the construction documents in Procore to confirm accurate and comprehensive records are maintained by the Construction Manager and Design Engineer. ➢ In coordination with the Construction Manager, monitor maintenance of the as-built drawings by the General Contractor. ➢ Coordinate with the City’s Community Development Department and the Construction Manager for inspections required by City permits. 1.7 Program Controls ➢ Maintain the MIS to manage Program documentation. ➢ Maintain and monitor the master Program schedule. Develop an updated Program schedule for Phase 4 through project completion and produce updated schedules as required. Incorporate detailed schedules from Project Team members. ➢ Review invoices and progress reports of Project Team members, including the Construction Manager, and recommend approval or rejection of invoice by City. Packet Pg. 129 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 5 ➢ Compile and monitor budget, cost, and cash flow information for the Program. Update Program budget and produce budget and cost projections monthly. ➢ Monitor scope, including tracking approved out of scope work. ➢ In coordination with the Construction Manager, review Schedule of Values prepared by the General Contractor and provide detailed review comments. ➢ Review Preliminary Construction Schedule, Baseline Schedule, monthly Baseline Schedule updates, and other schedules prepared by the General Contractor and provide detailed review comments. 1.8 Change Management ➢ Work closely with the Project Team to proactively manage changes to scope and/or budget of the Program and implement change management procedures as defined by the PMP. ➢ Review documentation developed by the Design Engineer during construction including contract document clarifications and Design Engineer initiated changes for completeness and consistency with the Program Charter and the Final Predesign Report (dated October 2017). Coordinate comments and assist in resolving conflicting comments. ➢ Review and evaluate requests for scope changes during construction and provide recommendations to the City for its action. ➢ Identify and document potential change orders (PCOs) from the Project Team and evaluate options and solutions to address the issue(s), including estimating potential impacts to budget, schedule, and quality (if any). Management of construction-related change orders will be the primary responsibility of the Construction Manager. ➢ Manage PCOs, change order requests (CORs), and contract change orders (CCOs) from consultant teams in Procore. ➢ Support the City in executing CCOs for consultant teams as required. ➢ Review PCOs and CORs prepared by the Construction Manager and General Contractor and recommend approval and incorporation into a CCO or rejection by the City. ➢ In coordination with the Construction Manager, review time impact analyses (TIAs) prepared by the General Contractor and recommend appropriate adjustments to the Contract Time. ➢ Participate in change order negotiations with the City, Construction Manager, and General Contractor and provide recommendations regarding approval or rejection of CORs. 1.9 Risk Management ➢ Identify Program risks and develop mitigation and contingency plans, including risks specifically related to the construction contract. ➢ Characterize, quantify, and prioritize Program risks utilizing the Program risk register, and analyze impacts on Program budget and schedule. Packet Pg. 130 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 6 ➢ Implement risk mitigation measures identified through risk characterization efforts as applicable. 1.10 Data Management ➢ Provide Procore training resources to new Project Team members and training on use of specific Procore modules, as needed. ➢ Maintain project files in electronic format according to structure defined by PMP. ➢ Provide existing information, design criteria, and technical standards to the consulting firms. ➢ Research, compile, and provide other available information requested by consultants to facilitate resolution of issues encountered during construction. 1.11 Program Status Reports ➢ Provide quarterly status updates in a dashboard format that summarize Program performance relative to the baseline Program budget and schedule and summarize activities completed in current quarter and planned for the next quarter. The Quarterly status updates will also discuss alignment with the Program Charter and performance against the Objectives and Guiding Principles. Quarterly status updates will be distributed to the Project Team via email. 1.12 Recurring Meetings ➢ Plan, organize, and conduct monthly CMT meetings (two-hour duration each). CMT meetings are intended to provide a venue to discuss Program level issues. ➢ Plan, organize, and conduct monthly Project Management Meetings with the City, Design Engineer, and Construction Manager (two-hour duration each). Project Management Meetings are intended to provide a venue to discuss construction-specific issues in the absence of the General Contractor. ➢ Plan, organize, and conduct consultant coordination meetings with the City and commissioning coordinator as necessary to facilitate the development of deliverables to the City. ➢ Attend monthly Construction Meetings with the City, the Construction Manager, the Design Engineer, and the General Contractor’s Project Manager. ➢ Attend Weekly Construction Progress Meetings and provide comments on meeting minutes. ➢ Attend Pre-Submittal Meetings with the City, Construction Manager, Design Engineer, General Contractor, and equipment suppliers to expedite the review and approval of long-lead and critical pieces of equipment. ➢ Attend Pre-Installation Meetings with the City, Construction Manager, Design Engineer, General Contractor, and equipment suppliers to discuss the installation of critical pieces of equipment. ➢ Attend Process Instrumentation and Control System (PICS) Coordination Meetings with the City, Construction Manager, Design Engineer, General Contractor, and Control Systems Integrator to discuss the development of the PICS and SCADA graphics. Packet Pg. 131 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 7 ➢ Attend Applications Software Development Meetings with the City, Construction Manager, Design Engineer, General Contractor, and Control Systems Integrator to discuss the development of the Supervisory Control and Data Acquisition (SCADA) System ➢ Attend Underground Task Force Meetings with the City, Construction Manager, Design Engineer, General Contractor, and key subcontractors to discuss utility tie-ins and resolve unforeseen field conditions/constructability issues. ➢ Plan, organize, and conduct monthly WRRF Staff Meetings to present an update on the status of the Program to City Operations staff. ➢ Attend Maintenance of Plant Operation (MOPO) Meetings with the City, Construction Manager, Design Engineer, and General Contractor on an as-needed basis to discuss shutdowns, tie-ins, impacts to plant operations, and maintenance of plant operations. ➢ Participate in Joint Test Group (JTG) Start-Up and Commissioning Meetings with the City, Construction Manager, General Contractor, and key subcontractors to develop the start-up and commissioning plan and schedule start-up and testing activities. ➢ Plan, organize, and conduct Funding, Financing and Cash Flow Meetings on a quarterly basis. ➢ Attend monthly Schedule Review Meetings with the City, General Contractor, and Construction Manager. ➢ Participate in quarterly Partnering Sessions through the course of construction. ➢ Participate in quarterly Joint Administrative Committee (JAC) meetings in accordance with the requirements set forth in the Community Workforce Agreement (CWA). 1.13 Non-Recurring Meetings ➢ Attend Pre-Construction Meeting, provide comments on draft meeting agenda and meeting minutes. ➢ Attend the Pre-Job Conference with the General Contractor, Subcontractors, Building Trades, Community Workforce Coordinator, and the Construction Manager to discuss work assignments and potential jurisdictional issues as required by the CWA. ➢ Attend the Pre-Construction Scheduling Meeting with the City, the Construction Manager, and the General Contractor to discuss the development of the Preliminary Schedule and the Baseline Construction Schedule. ➢ Attend issue-specific meetings on an as-needed basis. Three hundred twenty-one hours have been assumed due to the uncertainty related to the level of effort for this task. Deliverables: Monthly Invoices and Program Management Progress Report, Commissioning Coordinator Scope of Work, Quarterly Status Reports (Electronic PDF via Procore), Meeting Agendas and Minutes (as necessary) Packet Pg. 132 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 8 TASK 2.0 SUBMITTAL AND REQUEST FOR INFORMATION REVIEW 2.1 Submittal and Request for Information (RFI) Review ➢ Review and provide comments on RFI responses prepared by the Design Engineer and the Construction Manager on an as-needed basis. ➢ Review and provide comments on submittals transmitted by the General Contractor and submittal responses prepared by the Design Engineer and the Construction Manager on an as- needed basis. ➢ Coordinate with City staff as necessary to facilitate the review of RFIs and submittals transmitted by the General Contractor. ➢ It is assumed that the Design Engineer and Construction Manager will be primarily responsible for reviewing the General Contractor’s submittals and RFIs. WSC’s review of General Contractor submittals and RFIs and responses from the Design Engineer and Construction Manager will be limited to critical items of equipment, work plans, and issues. TASK 3.0 PERMITTING SUPPORT WSC will provide support to the City and Project Team for compliance with the various permits required for construction of the WRRF Project, including the Construction General Permit (i.e., SWPPP), National Pollutant Discharge Elimination System (NPDES) Permit, City Permits (e.g., Building Permit, Encroachment Permit, Demolition Permit), Air Pollution Control District (APCD) Authority to Construct Permit, and implementation of the Mitigation, Monitoring and Reporting Program (MMRP). The following table summarizes the permitting lead for each permit and WSC’s assumed role. WSC will not lead permit compliance for any permits but will primarily serve in a coordination role and be available as a technical resource. Specific assumptions are listed below; however, due to the uncertainty in level of effort for this task, the scope of work includes 160 hours for permitting support. Permit Lead WSC Role Assumptions Construction General Permit General Contractor; CM provides QA/QC Coordination and meeting participation Environmental Programs Coordinator or other City designee is legally responsible person; Construction dewatering to be included in CGP. NPDES LWA; Legal support from Somach Simmons & Dunn Coordination, meeting preparation and participation, technical support Assumes 8 meetings and technical support for NPDES permit renewal. City Permits General Contractor; CM provides QA/QC Coordination Building Permit ready to issue by Community Development. Field inspection by Public Works inspection staff. Packet Pg. 133 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 9 APCD City Coordination as required APCD Authority to Construct issued prior to start of construction. MMRP Biological Monitoring – City; Cultural Resources – Environmental Consultant Coordination, contract management CM is MMRP coordinator, City to procure environmental consultant through on-call list. Deliverables: Meeting Agendas and Minutes TASK 4.0 FUNDING AND FINANCING SUPPORT 4.1 State Revolving Fund (SRF) Loan Support ➢ Prepare and submit monthly status reports to State Water Resources Control Board (SWRCB) Division of Financial Assistance staff. The status reports are required with each disbursement request. ➢ Prepare and submit monthly disbursement requests to SWRCB on behalf of the City. ➢ Compile Disadvantaged Business Enterprise (DBE) documentation from consultants, General Contractor, and subcontractors to facilitate annual DBE compliance reporting. ➢ Prepare and submit Project Completion Report to the SWRCB at the end of the project. ➢ Provide support to City staff for preparation of legal and financial documents prepared by the City. ➢ Coordinate with the State Water Resources Control Board via email, phone calls, and meetings, as necessary. ➢ It is assumed that the Consultant team and General Contractor will provide the supporting documentation required to prepare the SRF disbursement requests, DBE reporting, and Project Completion Report (e.g., invoices, payment requests, DBE outreach documentation, etc.). WSC will compile the information provided by others into the reporting templates provided by the SWRCB. ➢ Performance of the Single Project or Program Audit as required by the SWRCB funding agreement is not included in this scope of work. 4.2 California Office of Emergency Services (CalOES) Grant Funding Support ➢ Coordinate with CalOES via email, phone calls, and meetings, as necessary. ➢ Provide responses to RFIs from CalOES and Federal Emergency Management Agency (FEMA) staff. ➢ Prepare and submit quarterly progress reports to CalOES as required by the funding agreement. ➢ Prepare and submit disbursement requests on behalf of the City. Packet Pg. 134 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 10 ➢ Coordinate with Design Engineer to prepare any substantiating material required for CalOES disbursement requests. ➢ It is assumed that the Consultant team and General Contractor will provide the supporting documentation required to prepare quarterly progress reports and disbursement requests (e.g., invoices, payment requests, etc.). WSC will compile the information provided by others into the reporting templates provided by CalOES. Deliverables: SWRCB Monthly Status Reports, Monthly Disbursement Requests, Annual DBE Compliance Report, and Project Completion Report; CalOES RFI Responses, Quarterly Progress Reports, and Disbursement Requests TASK 5.0 PUBLIC AND STAKEHOLDER OUTREACH 5.1 Council and Stakeholder Meetings WSC will facilitate information sharing that supports collaboration and decision making with Council and other project stakeholders. ➢ Provide communications support that takes detailed project information and provides tools for effective communication to various audiences. Produce supporting slides and information graphics (approximately 30 base slides and 15 master graphics) for use in both stakeholder and Council presentations. ➢ Prepare for and attend City Council study sessions and/or meetings to update Council on the WRRF Project at key milestones as determined by the CMT. ➢ Assist the City in preparation of the staff reports as requested by the City and prepare the PowerPoint presentation materials. ➢ This task assumes 135 hours of support to prepare content and agendas for the meetings, including presentation slides for key information. 5.2 Community Workshop ➢ Facilitate Community Workshop(s) at milestones determined by the CMT. ➢ The scope assumes City staff will coordinate meeting logistics, notifications, audiovisual equipment, refreshments, and advertisements. ➢ Prepare a handout or posters that support community education and awareness of the details of the Program, benefits, and status, building on content provided in presentations to City Council and stakeholders. ➢ This task assumes 100 hours of support to plan logistics and prepare posters and/or handouts. 5.3 Project Website Refresh ➢ WSC will perform a refresh to the existing slowrrfproject.org website that includes: Packet Pg. 135 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 11 (1) Building out the home page to draw the site visitor in, help the non-technical audiences understand the objective of the WRRF Program, and provide portals to the rest of the site. (2) Reorganizing the site content to reduce the number of subpages, improve ease of navigation, eliminate redundancy of information, and enhance clarity of messaging. (3) Creating two new graphics to 1) show the treatment process in easy-to-understand terms and 2) illustrate the One Water cycle. (4) Overall content polish/rewrites/consolidation of text. (5) Overall design polish, working with the existing WordPress site. (6) Addition of new photos and staff videos throughout to help make the connection between the WRRF and community health and prosperity. ➢ This task assumes 121 hours to refresh the Project website. 5.4 Project Website Maintenance/Updates ➢ Assist the City with updating current content on the WRRF Project website. WSC will prepare updates to be posted on the website at major milestones (assumed to be quarterly). This task assumes 70 hours of support to update website at major milestones. ➢ WSC understands that City WRRF staff will post weekly updates to the website and Facebook. WSC’s budget includes 48 hours of marketing/messaging support to review/edit these updates as needed. 5.5 Ribbon Cutting and/or WRRF Recognition Event ➢ Assist City with the planning for a ribbon cutting or groundbreaking event. ➢ Design invitation/email invitation and support needed outreach to targeted attendees and public. ➢ Support development of talking points and/or slides for event presentation by official(s). ➢ Prepare handout for the event, utilizing the handout/presentation graphics outlined in Tasks 5.1 to 5.3. ➢ Develop branded signs (6) to support education and event presentations. ➢ Develop press release and coordinate with media to draw best coverage of event and project. ➢ It is assumed the City will coordinate meeting logistics, provide audiovisual equipment, lead site tours, and provide refreshments. ➢ Because of the uncertainty related to the level of effort for this task, a level of effort of 114 hours has been assumed. 5.6 Photography and Videography ➢ Provide photography and videography support to continue implementing the Project History Plan. This may include: Packet Pg. 136 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 12 (1) Photography services for key outreach events; (2) Videography of key outreach events, WRRF staff and Project Team to capture the thoughts, ideas and changes as the WRRF Project evolves. Deliverables: Project PowerPoint Slides, Project Master Graphics, Community Workshop Agendas, Project Handouts and Posters, Website Updates, Ribbon Cutting Handout, Press Release, Project Videos, Photo Library TASK 6.0 MAINTENANCE OF PLANT OPERATION The scope assumes the City will serve as the Maintenance of Plant Operation (MOPO) lead and liaison during construction responsible for all internal City coordination. WSC understands the WRRF Chief Plant Operator and/or Chief of Maintenance will serve in this role. WSC assumes the City will have the following responsibilities: • Prepare plans and procedures for each shutdown, tie-in, bypass, or process cutover to accommodate the General Contractor’s scheduled activities and work plan; • Revise Standard Operating Procedures for unit processes to accommodate the General Contractor’s construction activities; • Coordination of internal City and WRRF staff review of General Contractor’s MOPO submittals and compilation of City review comments; • Participation in MOPO Meetings to review and discuss General Contractor’s planned activities, potential impacts to plant operations, and steps required to accommodate General Contractor’s scheduled activities and work plan. WSC’s scope assumes participation in MOPO Meetings as described in Task 1.12 and document review, as described below. 6.1 MOPO Document Review ➢ Review MOPO submittals prepared by the General Contractor. Provide detailed review comments on General Contractor’s MOPO submittals. ➢ One hundred twenty (120) hours have been included in the budget for MOPO support. TASK 7.0 START-UP AND COMMISSIONING 7.1 Coordination and Document Review ➢ Review start-up and commissioning plans prepared by the General Contractor and provide detailed review comments. ➢ Review start-up and commissioning schedule prepared by the General Contractor and provide detailed review comments. ➢ Participate in Joint Test Group meetings as detailed in Task 1.12. ➢ Coordinate with the City, Construction Manager, Design Engineer, and the General Contractor to resolve issues arising during start-up, commissioning, and demonstration testing. Packet Pg. 137 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 13 7.2 Acceptance ➢ Coordinate with the City, Construction Manager, and the Design Engineer to document acceptance of the improvements and beneficial use by the City upon successful completion of start-up and testing activities in accordance with the Contract Documents. TASK 8.0 CONSTRUCTION CLOSE-OUT 8.1 Punch List ➢ Coordinate with the City, Construction Manager, Design Engineer, and the General Contractor to perform final inspections and prepare the final Project punch list. Provide recommendation of Final Acceptance to the City upon completion of all punch list items and transmittal of all contract-required documentation. 8.2 Document Review ➢ Review the Project close-out documentation prepared by the Construction Manager including Notice of Completion, final payment, lien releases, warranty tabulation, and executive summary report. TASK 9.0 LABOR COMPLIANCE AND COMMUNITY WORKFORCE AGREEMENT ADMINISTRATION 9.1 Labor Compliance and Community Workforce Agreement (CWA) Administration Plan ➢ Prepare a Labor Compliance and CWA Administration Plan detailing the procedures to implement a labor compliance program (LCP) and comply with the provisions of the CWA. 9.2 Labor Compliance ➢ Implement a comprehensive LCP including, at a minimum, determination of prevailing wages; review, tracking, and auditing of certified payroll reports (CPRs); compilation of required forms and documents from General Contractor and subcontractors; job site interviews; tracking of training fund contributions; and monitoring of apprentice utilization. ➢ Investigate and resolve labor compliance issues on the project level when applicable and refer violations to the State Division of Labor Standards Enforcement as necessary. 9.3 CWA Administration ➢ WSC’s subconsultant, Golden State Labor Compliance, will serve as the Community Workforce Coordinator as defined in the CWA and administer the CWA on behalf of the City. CWA administration will include, at a minimum, collecting letters of assent, compiling monthly trust fund payments, compiling core employee lists, presenting CWA requirements at the pre-bid meeting, collection and management of craft request forms, management of grievances, and tracking local worker participation. ➢ Participate in JAC meetings as detailed in Task 1.12. 9.4 Monthly Reports ➢ Prepare a monthly report detailing, at a minimum, the status of LCP and CWA documentation from General Contractor and subcontractors of every tier, percentage of hours worked by local residents, and outstanding issues related to labor compliance and CWA requirements. Packet Pg. 138 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 14 9.5 Close-Out Report ➢ Prepare a close-out report tabulating General Contractor and subcontractor compliance with the local worker participation goals; evaluating the ability of craft unions to refer sufficient numbers of local workers; descriptions of disputes among General Contractor, City, unions, and subcontractors, whether formal or informal, and corresponding resolution; description of enforcement actions taken by City; tabulation of prevailing wage, fringe benefit, and apprentice utilization requirements by General Contractor and subcontractors; and description of lessons learned and opportunities for improving labor compliance and CWA administration efforts on future projects. TASK 10.0 PHASE 5 – PROGRAM CLOSE-OUT 10.1 Project Archive ➢ Perform a final audit of the Procore database for completeness. Coordinate with Project Team members to populate missing content in Procore prior to archiving the database. ➢ Prepare and transmit an archive of the Procore Program database. 10.2 Close-Out Report ➢ Prepare a close-out report describing each phase of the Program, summarizing the final Program budget and schedule, and detailing lessons learned. 10.3 Funding/Financing Close-Out ➢ Coordinate with SRF and CalOES as necessary to prepare and submit final reports and close-out the SRF loan and Hazard Mitigation Grant, respectively. 10.4 City Council Presentation ➢ Prepare a PowerPoint presentation for City Council summarizing the Program, highlighting key milestones and accomplishments, and reporting the final budget and schedule. ➢ Assist the City in preparation of a staff report and participate in City Council meeting to present final Program staff report. OPTIONAL TASK 1.0 ASSET MANAGEMENT SUPPORT This scope of work is to support the City in capturing asset attribute data during construction, and loading the collected data into the asset registry of the City’s Infor MP2 computerized maintenance management system (“MP2” or “CMMS”) that includes the City’s asset registry for plants, and is used to issue work orders, schedule preventive maintenance, plan maintenance projects, and capture equipment history. The objective of this effort is to support the City’s implementation of Asset Management best practices in operating and maintaining the newly constructed assets. O1.1 Asset Management System Data Management ➢ Chair one (1) 2-hour task kickoff meeting. Up to four (4) members from the Program Team will be a part of the meeting. Level of effort for this task assumes 30 hours of support. Packet Pg. 139 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 15 ➢ Request existing data and documentation currently used by the City for analysis and preparation for work process workshops. Conduct two (2), 4-hour process workshops to establish data management steps, roles and responsibilities. Up to three (3) members from the Program Management team will be a part of the meeting. Level of effort for this task assumes 80 hours of support. ➢ Produce a work plan that includes workflows and recommended asset attributes to be submitted for new assets. Level of effort for this task assumes 88 hours of support. ➢ Support the compilation of General Contractor’s submittals for loading into the City’s MP2 system during three (3) separate construction phases. It is expected that the Construction Manager will review and approve these submittals for completeness and correctness and that the submitted documentation will be available in a digital form. This documentation will include, but not be limited to, as many of the following as are applicable for each asset: (1) Manufacturers’ Operations and Maintenance Manuals (2) Manufacturers’ Specifications (3) Manufacturers’ Cut Sheets (4) Contract Specifications (5) Electrical Wiring Drawings (6) Lists of Spare Parts supplied and/or recommended (7) Manufacturers’ Recommended Preventive Maintenance Procedures and Frequencies (8) Photographs (9) Other Technical Information and Drawings Level of effort for this task assumes 48 hours of support. ➢ Extend the City’s existing Equipment Summary Sheet (ESS) template spreadsheet to include additional attribute data specified in the City’s standard for each asset type. Level of effort for this task assumes 24 hours of support. (1) It is expected that the City will provide an asset definition defining its policy for the smallest items that will be considered an asset, a list of desired and required attributes to be collected for each asset sub-class, lists of valid entries (or domains) for each attribute and conventions for creating asset IDs and asset naming. ➢ Providing the enhanced ESS spreadsheet to the General Contractor and/or the Construction Manager for entry of the City’s required equipment and asset data as agreed upon in the established workflows. ➢ Performing quality assurance validations and verifications of asset registry data prior to loading into MP2. Level of effort for this task assumes 40 hours of support. Packet Pg. 140 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 16 ➢ At the conclusion of each construction phase, assist the City in Extracting, Transferring, and Loading (ETL) the asset data for that phase into MP2’s asset registry. It is assumed that the City will ETL the asset data and the Program Team will provide technical assistance as needed. Level of effort for this task assumes 72 hours of support. O1.2 Support New Asset Hierarchy Development ➢ Support the City in revising its MP2 asset hierarchy to accurately reflect equipment installed and replaced during the three phases of the project. Two (2) 4-hour workshops will be conducted to support this task. Level of effort for this task assumes 56 hours of support. ➢ For the new assets documented during the project as well as existing equipment, an asset hierarchy will be designed to reflect: (1) Hierarchical (i.e., parent/child) relationships for equipment installed during the three construction phases, including assets that are new, retired, repurposed, moved, replaced, and unchanged (2) Plant management’s operational and reporting needs (3) City’s standards for asset hierarchies in MP2 Level of effort for this task assumes 40 hours of support. ➢ The Program Team will produce a technical memorandum summarizing its asset hierarchy recommendations. O1.3 Asset Management System Technical Support ➢ Provide technical support to the City for all other aspects of the City’s implementation of its Asset Management System not identified in Tasks O1.1 and O1.2. The Program Team will inform the City if the requested support is expected to exceed the budgeted hours and will not exceed this budget without City approval. Level of effort for this task assumes 132 hours of support. Exclusions and Assumptions The scope and budget developed for this task assumes the following: • MP2 is the target asset data repository and provides an automated method of batch loading asset data. City will provide this format as part of the initial analysis. • Assets are part of a plant or similar facility with hierarchical asset structure. Linear assets (e.g., pipes) are a minor component and do not require any integration with a geographic information system. • The City has a current work process for managing and loading data. The focus of this effort will be to improve and refine the process. • City has sufficient technical resources to perform the bulk of the data loading into MP2. The Program Team will provide the data tools, define the processes and data templates, and provide as-needed support. Packet Pg. 141 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 17 • Assets will be managed in three phases consistent with the construction schedule and only for new assets. Data loading will occur during each phase. • Scope does not include research or development efforts to identify and populate missing data in data submittals. Any data research and development will be performed by City staff. This includes any data submittals that need to be converted into digital form. • Parts and maintenance requirements are not included. • Contract updates or updated submittal requirements are not included. Deliverables: Meeting Agendas and Minutes, Enhanced ESS Entry Template for Asset Data Entry, Asset Data Management Work Plan, Establishing Asset Hierarchy Technical Memorandum OPTIONAL TASK 2.0 PARTNERSHIPS O2.1 California Polytechnic State University (Cal Poly) ➢ Collaborate with the City to identify potential strategies to enhance the City’s partnership with Cal Poly. ➢ Support the City in developing a research partnership with Cal Poly, including coordinating and attending meetings as required. ➢ A budget of 120 hours was assumed due to the uncertainty related to the level of effort for this task. O2.2 One Water Learning Center ➢ Identify and pursue potential partnerships, including public-private partnerships, that could support the build-out of the One Water Learning Center. ➢ Coordinate, prepare for, and attend meetings as required. ➢ This task does not include procurement of a design-builder to design and construct the exhibits in the One Water Learning Center. ➢ A budget of 120 hours was assumed due to the uncertainty related to the level of effort for this task. Deliverables: Meeting Agendas and Minutes Packet Pg. 142 Item 9 City of San Luis Obispo Scope of Services: Phases 4 and 5 – Construction and Close-Out Program Manager for WRRF Upgrade Project 4/2/2019 18 OPTIONAL TASK 3.0 MAINTENANCE OF PLANT OPERATION COORDINATION At the City’s request, WSC can provide a MOPO Liaison to coordinate with City Operations staff and minimize the impacts of construction on WRRF operations. The MOPO Liaison will engage with City Operations staff to facilitate the implementation of the General Contractor’s outage requests, tie-in plans, bypass pumping operations, and process cutovers. The MOPO Liaison will attend MOPO Meetings with the Construction Manager and General Contractor and will chair internal MOPO Coordination Meetings with City Operations staff to develop operational strategies and revised operating procedures to accommodate the General Contractor’s construction activities. O3.1 MOPO Liaison ➢ Provide a liaison to coordinate potential impacts to the WRRF operation between the General Contractor and City Operations staff. ➢ Maintain a log of planned and completed shutdowns and construction activities that could potentially impact current plant operations. ➢ Participate in site walks with City Operations staff, the Construction Manager, and the General Contractor to aid in the development of MOPO submittals. O3.2 MOPO Coordination Meetings ➢ Plan, organize, and conduct MOPO Coordination Meetings with City Operations staff on a semi- monthly basis to review MOPO log and discuss planned shutdowns, tie-ins, and other impacts to plant operations. MOPO Coordination Meetings are intended to include the majority of the WRRF Operations staff and provide a forum to update staff on the status of construction activities that may impact WRRF standard operating procedures. In addition, MOPO Coordination Meetings will be used to discuss specific strategies and procedures to be employed by WRRF Operations to accommodate the General Contractor’s work plan. O3.3 Document Review ➢ Coordinate review of General Contractor’s MOPO submittals by City Operations staff and compile review comments from City reviewers. O3.4 Revised Operating Procedures ➢ Develop revisions to WRRF standard operating procedures as required to accommodate extended shutdowns and process changes anticipated during construction (e.g., chemically- enhanced primary treatment, sludge co-thickening, etc.). Deliverables: Meeting Agendas and Minutes, Revised Operating Procedures Packet Pg. 143 Item 9 City of San Luis Obispo Recurring Meetings Summary Program Manager for WRRF Upgrade Project 4/2/2019 19 Recurring Meetings Summary The following table summarizes the recurring meetings and workshops for Phases 4 and 5. For efficiency and cost-effectiveness, meetings will be combined when possible. ATTENDEES Meeting Name Purpose Duration (hours) Frequency Number City WSC/HDR Jacobs Carollo Contractor Other CMT Meeting Discuss Program level issues with the Core Management Team 2 Monthly 44 X X X X Project Management Meeting Discuss construction-specific issues with the CMT in the absence of the General Contractor. 2 Monthly 44 X X X X Consultant Coordination Meeting Facilitate the development of deliverables and the delivery of consultant scopes of work. 2 As-Needed 4 X X Env. Consultant, Cx. Coord. Construction Meeting Discuss status of construction and key issues with the CM, Design Engineer, and General Contractor. 2 Monthly 44 X X X X X Progress Meeting Discuss project status, schedule, and key issues. 2 Weekly 191 X X X X X Key subcontractors Pre-Submittal Meeting Review specification requirements and discuss key considerations in advance of formal transmittal of key equipment submittals. 2 As-Needed 10 X X X X X Key subs and suppliers Pre-Installation Meeting Discuss the installation of critical pieces of equipment. 2 As-Needed 10 X X X X X Key subs and suppliers Process Instrumentation and Control System Coordination Meeting Discuss the development of process control system. 4 As-Needed 6 X X X X X Systems integrator Applications Software Development Meeting Discuss development of the SCADA applications software and SCADA/HMI graphics. 4 As-Needed 8 X X X X X Systems integrator Underground Task Force Meeting Discuss planned utility tie-ins and resolve unforeseen field conditions in a timely manner. 2 As-Needed 28 X X X X X WRRF Staff Meeting Present an update on the status of the WRRF Project to City Operations staff. 1 Monthly 44 X X MOPO Contractor Meeting Discuss shutdowns, tie-ins, impacts to plant operations, and proposed plan to maintain plant operations during interim operating conditions. 1 Semi-Monthly (As-Needed) 44 X X X X X Joint Test Group Meeting Collaborate with the General Contractor, Design Engineer, subcontractors, and key suppliers to advise and assist with the development of the start-up and commissioning plan and testing activities. 2 Semi-Monthly (As-Needed) 88 X X X X X Integrator, key subs and suppliers Funding, Financing and Cash Flow Meeting Discuss status of outside funding sources and review Program cash flow. 2 Quarterly 12 X X Schedule Review Meeting Discuss monthly Baseline Construction Schedule update. 2 Monthly 44 X X X X Partnering Discuss project status, dispute resolution, shared risk registry, and success of partnering efforts. 4 Quarterly 14 X X X X X Key subcontractors Joint Administrative Committee Meeting Discuss status of the CWA, compliance with local worker participation goal, grievances, and outstanding issues. 3 Quarterly 14 X X Unions, CWA Coordinator Packet Pg. 144 Item 9 City of San Luis ObispoProgram Management Phases 4 and 5 ‐ Water Resource Recovery FacilityCost Proposal4/2/2019WSC Labor HoursWSC FeeLabor Hours  Labor Fee   Labor Fee   Labor Fee  Total Fee0 Program PlanningSUBTOTAL 60 15,435$           36 8,295$             ‐$                 ‐$                  23,730$          1 Program ManagementSUBTOTAL4621 1,142,824$     3762640,713$       ‐$                 ‐$                  1,783,537$     2 Submittal and RFI ReviewSUBTOTAL8020,040$          609,923$            ‐$                 ‐$                  29,963$          3 Permitting SupportSUBTOTAL8020,968$          8013,230$         ‐$                 ‐$                  34,198$          4 Funding and Financing SupportSUBTOTAL8821,056$          35258,212$         ‐$                 ‐$                  79,268$          5 Public and Stakeholder OutreachSUBTOTAL548 101,780$        406,615$            ‐$                 5,250$             113,645$        6 Maintenance of Plant OperationSUBTOTAL8017,920$          406,615$            ‐$                 ‐$                  24,535$          7 Start‐Up and CommissioningSUBTOTAL5613,988$          18036,912$         ‐$                 ‐$                  50,900$          8 Construction Close‐OutSUBTOTAL163,968$              162,646$            ‐$                 ‐$                 6,614$             9 Labor Compliance and CWA AdministrationSUBTOTAL11228,076$          12019,845$         267,750$        ‐$                 315,671$        10 Program Close‐OutSUBTOTAL6616,872$          10417,199$         ‐$                 ‐$                  34,071$           COLUMN TOTALS 5,807 1,402,927$     4,790 820,204$       267,750$        5,250$              2,496,131$      TECHNICAL CONTINGENCY 124,807$         TOTAL 2,620,938$     1Optional Tasks:OT 1 Asset ManagementAsset Management TOTAL8017,920$          584 187,425$       ‐$                 ‐$                 205,345$        OT 2 PartnershipsPartnerships TOTAL24058,312$          0‐$                ‐$                 ‐$                  58,312$          OT 3 Maintenance of Plant Operation SupportMaintenance of Plant Operation Support TOTAL950 192,556$        0‐$                ‐$                 ‐$                 192,556$        OPTIONAL TASKS TOTAL1,270 268,788$        584187,425$       ‐$                 ‐$                 456,213$        Task No. Task DescriptionALL FIRMSWSC Golden State  SlotographyHDRPacket Pg. 145Item 9 Department Name: Utilities Cost Center: 6101 For Agenda of: December 4, 2018 Placement: Business Estimated Time: 30 minutes FROM: Carrie Mattingly, Utilities Director Prepared By: David Hix, Deputy Director Utilities Lianne Westberg, Assistant WRRF Program Manager, Water Systems Consulting, Inc. SUBJECT: WATER RESOURCE RECOVERY FACILITY PROJECT - AUTHORIZATION TO BID RECOMMENDATION 1.Approve plans and specifications (Reading File) for the Water Resource Recovery Facility Project, Specification No. 91620; and 2.Authorize staff to advertise for construction bids pending City Engineer’s approval of the bid set; and 3.Authorize the City Manager to award the contract if the lowest responsible bid is within the project construction budget of $111,600,000; and 4.Approve amended WRRF Project-specific Construction Contract Change Order policy Attachment A) and authorize the Utilities Director to be responsible for construction contract change orders (CCOs) for the WRRF Project in any amount with the limitation that the sum total of all CCOs not exceed the contingency budget amount of $13,390,000; and 5.Authorize the Utilities Director to substitute an Enhanced Local Outreach Program Attachment C) in the WRRF bid documents if a fully executed Community Workforce Agreement (Reading File) by all Trades Council affiliates is not received by December 4, 2018 at 5:00 p.m. in a final form acceptable to the City Attorney. DISCUSSION The Water Resource Recovery Facility (WRRF) Project has reached the 95% design milestone. Completion of the WRRF Project will allow the City to meet stringent mandatory State water quality requirements, replace old and aged infrastructure, maximize recycled water production, and ensure wastewater capacity to meet the City’s 2035 General Plan. All plans and specifications are near completion with minor quality assurance and quality control items pending. These documents are available for review in the City Clerk’s office, 990 Palm Street . Packet Pg. 159 Item 13 Packet Pg. 146 Item 9 Project Costs and the Bid Package Based on the 95% design, the cost estimate reflects increases associated with the more detailed design and thorough estimation process. The design engineer provided low, median, and high cost estimates for the project. The range of cost estimates are provided below: WRRF Project Cost Estimate Design Milestone Low Median High 95% Design $102,960,000 $ 114,400,000 $131,560,000 This estimate captures recent price increases in concrete, steel, and electrical components, as well as increases in several unit processes including the membrane bioreactor. Cost savings of $7 million from value engineering are also reflected in this estimate. Because of the uncertain bidding climate, the Water Resource Center is an ‘additive alternate’ in the bid package. This approach preserves maximum flexibility for the City by allowing this portion of the project to be separated out if necessary due to funding constraints. Effective communication is the key to this project’s success and that communication is laid out in the bid package’s contract documents. The organization and formatting of these documents is in the language of the construction industry providing a means of communication between the owner, contractors, subcontractors, suppliers, bidders, and building officials. City staff and the WRRF team have paid meticulous attention to the contract documents to make this project clear to administer and fair for all parties involved. The bid package will not be released for advertising until after it is approved by the City Engineer. This ensures that all City conditions and requirements will be met , and the project is consistent with the City’s development guidelines. Revised Contract Change Order Policy The City’s Contract Change Order (CCO) policy is appropriate and useful for its typical CIP projects. For a project the size of the WRRF Project, the largest undertaken in City history, a project -specific contract change order policy has been prepared for Council’s consideration and approval (Attachment A). While the goal is to keep change orders to a minimum, unknowable project conditions will inevitably surface with cost potential over $100,000 highly likely. Streamlin ing CCO approvals and avoiding idling manpower and equipment will save the project time and money and assist with minimizing schedule impacts, an important project outcome related to regulatory requirements. Expertise from the WRRF project team and City Engineer were used to identify appropriate thresholds for the proposed project -specific CCO Policy. The revised policy is consistent with other public agencies that have completed similar projects. The proposed policy authorizes the Utilities Director to approve all CCOs of any amount as long as the running total of all approved CCOs does not exceed the total authorized contingency amount of $13,390,000. Packet Pg. 160 Item 13 Packet Pg. 147 Item 9 The Project Manager will have the authority to approve CCOs under $100,000 with concurrence from the Utilities Director. The proposed project -specific CCO Policy stipulates when the sum of all CCOs reaches 75% of $13,390,000 ($10,042,500), the Utilities Director will inform the City Manager and Finance Director of project status and the sufficiency of funding to complete the project . WRRF Project Phases and Milestones The WRRF Project is divided into five phases. The bid package will be released at the end of January 2019 with construction expected to begin in May. A detailed milestone schedule is provided as Attachment B. Work Efforts Recently Completed: Construction Management and Inspection Services Agreement. On September 18, 2018, Council awarded a contract to Carollo Engineers to provide Construction Management and Inspection Services for the WRRF Project. Carollo brings extensive experience and expertise in construction management and inspection services particularly with Membrane Bioreactors (MBR) and Ultraviolet (UV) disinfection that will be utilized at the WRRF. Building Permit Review. The Community Development Department building division review is near completion and will be integrated into the plan and specifications. This effort involved the coordination and collaboration with the Community Development, Fire, and Public Works Departments to ensure that the project meets City development standards. These improvements include, frontage improvements, traffic and parking, onsite stormwater management, and flood modeling. Community Workforce Agreement. On November 13, 2018, Council agreed to enter into a Community Workforce Agreement (CWA) between the City and the Building and Construction trades. This agreement allows the prioritization of local hires, preserves the construction management and inspection services already under contract by the City, maintains opportunities for local contractors to participate in the project and will not unduly affect the cost, schedule, or quality of the WRRF Project. The proposed actions include a contingent action to authorize the Utilities Director to substitute an Enhanced Local Outreach Program should a fully executed copy of a CWA Packet Pg. 161 Item 13 Packet Pg. 148 Item 9 not be delivered to the City by December 4, 2018 at 5:00 pm. This timing is critical in order for the City to continue progress towards bidding and commencement of construction. Enhanced Local Outreach Program. The draft Enhanced Local Outreach Program (Attachment C) will need to be finalized (based on Council feedback) in coordination with the City Attorney and incorporated into the WRRF bid documents. The program will include outreach to local contractors and local residents and will culminate in the development of a database with contact information for interested parties. This database will be provided to prospective bidders. Prospective bidders will be required to solicit subcontract bids from local contractors and notify local residents of potential employment opportunities on the WRRF Project. The bidders’ compliance with the enhanced local outreach program will be evaluated as a part of the City’s bid review process. Bidders who do not comply with the enhanced local outreach program would be subject to disqualification. Execution of the State Revolving Fund Agreement for Funding. On November 13, 2018, Council approved a Clean Water State Revolving Fund loan agreement of up to $140 million at an interest rate that is half the State’s General Obligation Bond interest rate or 1.8 percent. This agreement ensures a funding stream for the project including $4 million of principal forgiveness from green project reserve funding. Contractor Prequalification. On April 17, 2018, Council approved a Request for Statements of Qualifications for general and sub-contractors for the WRRF Project and authorized the City Manager to approve the final list. Prequalification allows the City to assess a contractor’s experience, past performance, and financial status on work like the WRRF project to better ensure qualified bidders. Five General Contractors and two Control System Integrators have been prequalified while a determination regarding Electrical sub-contractors is pending. Staff believes this will be completed in December 2018. Upcoming WRRF Project Items: Phase 4 Program Management Services, Engineering Services During Construction, Labor Compliance, CWA administration. City staff will return to Council with requests for these services. Program services will assist the City in managing the numerous contracts, agreements, permits and requirements during construction while engineering services will assist the construction manager and review and manage the numerous engineering and construction submittals, reviews and tasks during construction. Labor compliance and CWA administration are necessary services to ensure compliance with State labor requirements and the CWA. Policy Context The City’s National Pollutant Discharge Elimination System permit for WRRF operations requires the facility processes meet more stringent requirements. The WRRF Project will accomplish this when it is complete. The WRRF Project includes a capacity component that aligns with the City’s 2035 General Plan build-out population. Packet Pg. 162 Item 13 Packet Pg. 149 Item 9 Public Engagement Extensive public engagement occurred as the first step of this project; prior to the beginning of Facility Plan which informed the final design. There is a WRRF Project website and routine updates included in the Utilities Department Resource newsletter, along with a special, project - specific direct mailing. Bidders on the WRRF Project have been pre-qualified through a robust process that included extensive personal outreach by the Project Team. Public engagement will continue throughout the project. CONCURRENCE Utilities has collaborated with the Public Works Department and Community Development. Community Development concurs with the environmental review findings. The Public Works Department and Community Development have reviewed the Building Permit Submittal. Comments will be incorporated into t he Bid Set, and the City Engineer will provide final approval. ENVIRONMENTAL REVIEW The Environmental Impact Report (EIR) for the WRRF Project was certified by Council on August 16, 2016. Packet Pg. 163 Item 13 Packet Pg. 150 Item 9 FISCAL IMPACT Budgeted: Yes Budget Year: 2019-2022 Funding Identified: Yes The WRRF Project will primarily be financed through a low -interest SRF loan administered by the State Water Resources Control Board (SWRCB) Water Recycling Funding Program. The City will receive a maximum loan of 140 million dollars, with four million dollars of principal forgiveness. Thus, the principal to be repaid over 30 years will be 136 million dollars. Payments from the City to the SWRCB will start one year after construction completion. At 1.8 percent interest, the annual payment to the SWRCB will be $5,906,675. The Sewer Fund long-range fund analysis has programmed sufficient revenues and adequate cash flow to meet the terms of the agreement including the maintenance of one year of payments in reserve and a 12 percent City-he ld contingency. Construction phase professional services include construction management, engineering services during construction, labor compliance, CWA administration and phase 4 and 5 program management. These services are eligible for reimbursement fro m the SRF loan. The construction budget is provided below. WRRF Project Construction Budget Construction cost budget $111,600,000 Project contingency / budget allowance (12%) $13,390,000 Construction Phase Professional Services $15,010,000 Total $140,000,000 Maximum Loan Amount $140,000,000 The sewer fund is positioned to cover the long-term debt service and on-going operations and maintenance after project completion. Operations and maintenance costs will require some adjustment s as more accurate estimates become available and the upgraded WRRF comes on line. The annualized on-going costs shown below are the 2018-19 WRRF operating budget and the SRF loan payment . Fiscal Analysis: Funding Sources Current FY Cost Annualized On-going Cost Total Construction Cost Sewer Fund $3,892,439 State $5,906,675 $ 140,000,000 Federal Fees Other: Total $9,799,114 $ 140,000,000 Two grants are in the approval process (CalOES /FEMA and Integrated Regional Water Management Plan). If the grants are successful through their respective processes, they are expected to total about $3 million. Packet Pg. 164 Item 13 Packet Pg. 151 Item 9 ALTERNATIVES Deny or defer approval to advertise. The City Council may choose to deny or defer the approval to advertise this project. If Council decides to defer advertising, staff could come back to Council early next year to obtain approval to advertise. However delaying authorization beyond this year could impact the project schedule resulting in possible additional costs. If Council elects to defer for a long period of time or deny the project, staff could continue to operate the WRRF with its existing processes and in its existing condition (to the extent possible), however the City would not meet water quality requirements set by the Central Coa st Regional Water Quality Control Board and subject to enforcement action, and possible penalties and fines. AVAILABLE FOR REVIEW IN THE CITY CLERK’S OFFICE Plans, Specifications and Cost Estimate for the Water Resource Recovery Facility Project, Specification No. 91620. November 13, 2018 Community Workforce Agreement Attachments: a - Revised Change Order Policy-WRRF Project b - WRRF Project Timeline c - Local Contractor Good Faith Outreach Requirements_20180907 Packet Pg. 165 Item 13 Packet Pg. 152 Item 9 CityofSanLuisObispo, PublicUtilities, 879MorroStreet, SanLuisObispo, CA, 93401-2710, 805.781.7215, slocity.org CONSTRUCTION CONTRACT CHANGE ORDERS FOR THE WATER RESOURCE RECOVERY FACILITY PROJECT Financial Management Manual – Section 225 – Revised for Referenced Project Section CONSTRUCTION CONTRACT CHANGE ORDERS OVERVIEW When the City awards a construction contract, the need for contract change orders (CCO’s) is not unusual. CCO’s are required whenever the scope of work changes from that in the original contract or an unknown condition of the site requires a change in the scope of work. Usually a contingency amount is established when the project budget is finalized upon contract award to accommodate limited CCO’s. The purpose of this policy is to establish limits of authority for approving construction project CCO’s. GOALS 1. Ensure appropriate authority and accountability in the approval of change orders. 2. Minimize the time needed to approve a CCO in order to avoid project delays. 3. Establish a system under which the organizational level at which approval is given is commensurate with the size of CCO and size of project. 4. Eliminate the potential for approval of a CCO when cont ingency funds are insufficient. POLICIES Conditions for Approval of CCO's by Staff 1. Sufficient contingency funds are budgeted and available in order for the Public Works Director or City Manager (approved designees) Utilities Director to approve a CCO. 2. The nature of work in the CCO is not significantly different from that in the contract. 3. Authorization limits are based on an individual CCO amount, not the or aggregate amount of all CCO’s. 4. Authorization limits apply to CCO’s for increases in contract amounts only. Packet Pg. 166 Item 13 Packet Pg. 153 Item 9 5. When the aggregate amount of CCO’s reaches 75% of the contingency, the awarding authority the City Manager and Finance Director shall be informed of the status of the project and the sufficiency of funding to complete the project. 6. Work will not be broken up into multiple CCO’s in order to circumvent this policy. 7. All CCO's must be in writing and approved by the appropriate contract part ies consistent with the authorized limits established in this policy. 8. A copy of each approved CCO will be transmitted promptly to the Finance Division. 9. The Purchasing Authority may grant approval of CCO's in excess of $100,000 under the following circumstances (all three factors must be present): a. Immediate approval of the CCO is necessary to avoid delay. b. The CCO is an integral and mandatory component of the project. c. The costs associated with delay of the project would be excessive. The Project Manager Utilities Director is responsible for carrying out this policy. 10. The Purchasing Authority is also authorized to approve CCO’s in excess of $100,000 related to Job Order Contract Task Orders. Authorization Limits 1. Public Works Director/ Designee Project Manager - Not to exceed $100,000 2. Utilities Director – None on individual; CCO’s with the Cumulative approved CCO total, limited to approved project budget . Purchasing Authority (City Manager/Designee) Not to exceed $100,000 3. City Council Greater than contract or $100,000 approved project budget. See circumstances above where the Purchasing Authority may approve CCO’s in excess of $100,000. Originally Approved by the Council on August 3, 1993; Revised by the Council on April 15, 2003 and June 2, 2015 Approved by the Council on December 4, 2018 for the Water Resource Recovery Facility Project, Specification 91620, Exclusively Packet Pg. 167 Item 13 Packet Pg. 154 Item 9 Packet Pg. 168 Item 13 Packet Pg. 155 Item 9 LOCAL BUSINESS ENTERPRISE GOOD FAITH EFFORT OUTREACH REQUIREMENTS WRRF UPGRADE PROJECT) Specification No.: ____________ 1. POLICY. The City of San Luis Obispo’s Local Business Enterprise Outreach and Opportunities Program (LBEP) is designed to maximize participation of diverse, qualified, local contractors, consultants, and material suppliers seeking to do business on City of San Luis Obispo projects. Effective implementation of LBEP is a requirement of the project and award of a contract will be determined, in part, by the Contractor’s demonstrated good faith efforts in conducting effective outreach to local contractors. Failure to comply with the requirements herein shall render the bid as non-responsive. 2. DEFINITIONS. a) For the purposes of this program, a Local Business Enterprise (“LBE”) means a business that is a firm or dealer with fixed offices located in and having a street address within the County of San Luis Obispo and holds a valid business license issued by either the County or a city within the County for at least six months prior to the date upon which a request for sealed bids or proposals is issued. b) Vendor/Material Supplier: An individual, partnership, corporation or other legal entity that provides equipment, materials or supplies under an executed contract. c) Written Communication: Any handwritten or typed correspondence delivered by e- mail, fax, or U.S. mail. e) Outreach Forms: 1) Schedule A-1, Designation of All Subcontractors/Vendors/Service Providers 2) Schedule A-2, Subcontracting Opportunities and Contact Log 3. OUTREACH RESOURCES PROVIDED BY THE CITY. a) Outreach materials provided by the City shall be the primary source of outreach activity. Contractors are encouraged to supplement but not replace the City provided materials. City-provided outreach materials include: 1) LBEP List: This list shall be used as the primary source for outreach activity and consists of potential subcontractors and vendors/material suppliers specific to the project. Packet Pg. 169 Item 13 Packet Pg. 156 Item 9 a. The bidder will use the LBEP List through the following website: [need to create website based on RFQ]. b. For each category of work identified by the bidder as a subcontracting opportunity in schedule A-2, the bidder will contact each LBE listed and shall comply with the outreach requirements in Section 4 below. 4. OUTREACH ACTIVITY REQUIREMENTS AND EVIDENCE OF FULFILLMENT. a) The bidder shall conduct pre-bid outreach activities to provide equal opportunity to all firms, including LBEs, to participate on the project. Outreach solicitations shall occur prior to submission of the bid to be considered good faith outreach efforts. The following table outlines the outreach activity requirements and evidence of fulfillment . Outreach activities identified with an “M” on the left hand column are mandatory outreach efforts; outreach activities identified with a “R” are strongly recommended, but are not mandatory: Outreach Activity Requirements Description M Identify Work that can be Subcontracted. Evidence of Fulfillment : i) Complete and submit Schedule A-2 by entering: A description of each item of work solicited from subcontractors; Estimated cost of work, materials or services; Percent of total fee; and Whether or not a subcontractor or vendor was selected, and the reason for selection/non-selection. M Notify firms on LBEP List of subcontracting opportunities for each category listed on Schedule A-2. Notifications must occur no fewer than 14 calendar days prior to the bid due date. One contact must be written (mail, email, or fax) and one contact must be verbal (telephone or personal meeting). Notification shall name the City as project owner; identify work available to subcontractors; bid due date; contact information including but not limited to telephone number, e-mail and name of contact; and, all available times and locations where plans, specifications and bid documents can be viewed or copied. Evidence of Fulfillment i) Provide copies of letter and written communication (including e-mail or fax) sent to firms on the LBEP List. If other sources were identified by the bidder, provide copies of letter and written communication (including email or fax) on those other sources. Packet Pg. 170 Item 13 Packet Pg. 157 Item 9 ii) Complete and submit Schedule A-2 to document contact with small contractors, including: Name and title of each person contacted; Fax, e-mail, and phone number of the company; Whether the firm submitted a bid to the contractor, and If bid submitted to contractor, reason the firm was not selected to work on the project. M The bidder negotiated in good faith with the LBEs and did not unjustifiably reject as unsatisfactory bids prepared by any LBEs as determined by City. Evidence of Fulfillment: Copies or list of all bids and a spreadsheet listing all bids with firm name, contact person, bid items(s), bid price, LBE classification, and comments re- selection or rejection LBE bids accepted and included in bid response R The bidder advertised, not less than ten (10) calendar days before the date the bids are opened, in one or more local daily or weekly newspapers, trade association publications, minority or trade-oriented publications, or trade journals for LBEs that are interested in participating in the project. Evidence of Fulfillment : Copy of advertisements, certified letters, successfully completed faxes and/or other notices to LBEs with selected specific items identified. R The bidder followed up initial solicitations of interest by contacting the enterprises to determine with certainty whether the enterprises were interested in performing specific items of the project. Evidence of Fulfillment : Copy of published advertisements, letters, successfully completed faxes, etc. with LBE name/contact information including the required information or directions on how to obtain it and the date the information was provided Agenda, meeting notes, etc. including specific topics discussed, LBE firm names and contact persons in attendance that received information, and the location and date information was provided 5. OUTREACH RESULTS: REPORTING REQUIREMENTS. Upon completion of the outreach activity requirements and as requested by the City, bidders shall submit the following items no later than the close of two business days after the bid opening. Packet Pg. 171 Item 13 Packet Pg. 158 Item 9 Within two (2) days of written request from the City, the two responsible bidders with the lowest responsive bids must submit to the Project Manager the following: Required Forms Included Completed Schedule A-1. Completed Schedule A-2 Letters of Intent to all Subcontractors Evidence of Contact with LBEs on the LBEP List (examples: dated e-mail, fax or letter). Evidence of Fulfillment information described in Section 4 above. 6. SUBCONTRACTOR SUBSTITUTION. a) Written authorization from the City is required prior to substitution of any subcontractor. Subcontractors may be substituted based on the criteria below: 1) For any reason stated in California Public Contract Code Section 4107 which are incorporated herein. 2) For reasons, which the City in its judgment, deems to be in the best interests of the City, except where prohibited by law. 7. AWARD OF AGREEMENT. The Contractor’s good faith outreach efforts will be reviewed by the City’s Director of Utilities or his/her designee, prior to the award of a contract, to determine whether good faith outreach efforts requirements, if applicable, were met. 8. POST-AWARD MONITORING. a) To ensure compliance with Contractor stated commitments, the City will monitor subcontracting activity throughout the duration of the contract. To comply with post -award monitoring the bidder shall: 1) Ensure that subcontractors and suppliers perform the type of work and the quantity of work as specified in Schedule A-1. 2) Provide the City with any additional reports, subcontracts, or other information deemed necessary for determining Contractor’s compliance with its subcontracting commitment. 3) Maintain all reports and corresponding information for a period of no less than three years after the completion of the project, or until such time a program audit has been completed on the project by the City, whichever occurs first. 9. LBEP NONCOMPLIANCE. a) Failure by the Contractor to fulfill any of the Program guidelines constitutes brea ch of a contractual obligation and may result in City-imposed sanctions on the Contractor. Upon Packet Pg. 172 Item 13 Packet Pg. 159 Item 9 determining that a Contractor is not in compliance with Program guidelines, the City may seek, without limitations, the following remedies: 1) Withholding progress payments until the City deems the Contractor to be in compliance. 2) Withholding an amount equal to the unmet portion of the amount contracted to the subcontractor, vendor, or supplier in question. Packet Pg. 173 Item 13 Packet Pg. 160 Item 9 Page intentionally left blank. Packet Pg. 174 Item 13 Packet Pg. 161 Item 9 Packet Pg. 162 Item 9 Packet Pg. 163 Item 9 Packet Pg. 164 Item 9 Packet Pg. 165 Item 9 Page intentionally left blank. Packet Pg. 166 Item 9