HomeMy WebLinkAbout06/16/1998, C2 - REAL PROPERTY ACQUISITION - 879 MORRO STREET council ne
June 16 1998
acEnOA IZEpont 't=Nh.
CITY OF SAN LUIS OBIS.PO
FROM: John Moss, Director of Utilities"
SUBJECT: Real Property Acquisition- 879 Morro Street
CAO RECOMMENDATION
1. Approve the purchase of property located at 879 Morro Street for the price of$468,034.
2. Authorize preparation of letter of friendly condemnation.
3. Authorize CAO to sign purchase documents and deed.
DISCUSSION
On April 21, 1998 Council authorized staff to enter into negotiation with Tom Copeland for the
purchase of the property located at 879 Morro Street. The proposed use of the property after
acquisition would be for office space for Utilities Department Administration and Conservation
staff. Council also authorized staff to contract with a local architect to obtain a refined
rehabilitation and construction cost estimate for remodel of the building to accommodate its
proposed use. This report recommends that Council approve the purchase of the property at 879
Morro Street for the negotiated amount of $468,034 which is within the negotiating amount
authorized by Council. In Council's consideration of this recommendation, Council should also
review the refined construction cost estimate provided in the attached report provided by Fraser
and Seiple Architects, which identifies the additional costs for seismic retrofit, fire sprinklers and
remodel of the structure required before use as City office space.
Previous staff reports have presented the need for additional office space for the Utilities and
Public Works Departments. In short, it was identified that in order to meet the growing demands
being placed on both departments and accommodate existing and future staffing requirements,
additional office space would be needed. The property under consideration meets the identified
space needs for Utilities as well as other important considerations such as adjacency to City Hall
and potential future value for enhancement of the Palm Street parking structure. The anticipated
minimum utilization of the property as office space for the Utilities Department is 15 +years.
The appraised value of$450,000 was established by Rollie McCormack,MIA, of the San Luis
Obispo firm of Schenberger, Taylor, McCormick, and Jecker, Incorporated and provided an
initial point of negotiations. High and low estimates for acquisition, construction and furnishing,
including seismic safety improvements were provided in the April 21, 1998 staff report to
Council and are summarized in the following table.
Council Agenda Report-Property Purchase-879 Morro Street
Page 2
Preliminary Cost Estimate
879 Morro Acquire and Remodel Project
Low High
Acquisition $450,000 $495,000
Strengthen and remodel(plus 10%contingency) 250,800 308,000
Design&Study services(estimated at 15%to 20%) 39,600 61,600
Acquisition and Construction Subtotal $740,400 5864,600
Furnishings 66,000 80,000
Total $806,400 $944,600
Based on the negotiated purchase price of$468,034 and the refined construction cost estimate of
$317,756 provided by Fraser and Seiple Architects,the revised acquisition and construction cost
projections as shown in the following table are within the previous high and low estimate
provided in the April 21, 1998 staff report. Additional costs have been added in the following
table to those provided in the previous staff report to cover miscellaneous escrow closing costs
and construction management services.
Refined Cost Estiniare
879 Morro Acquire and Remodel Project
Acquisition $468,034
Strengthen and remodel(plus 15%contingency) $317,800
Furnishings(high estimate) $ 80,000
Total $865,834
Additional Costs
Miscellaneous closing costs $ 11,966
Construction management $ 30,000
Design& Study services(estimated at 20%) $ 63,600
Acquisition and Construction Total $971,400
A Phase I Environmental Assessment of the building was performed by ATC Associates of
Marina, California, and found no evidence of Recognized Environmental Conditions (RECs).
Their conclusion was that no further evaluation was warranted. However, before construction,
ATC recommended a comprehensive asbestos survey to evaluate the type and condition of any
suspect materials. The samples taken in the phase 1 assessment showed no asbestos, but this is
not conclusive. The cost of such a survey would be between $2,500 and $3,000, depending on
the number of samples required. The survey will be completed after Council approves the
acquisition of the property and any conditions requiring special handling will be identified in the
preparation of the plans and specifications for improvements and included in the final
construction cost estimate for the remodel project.
Council Agenda Report-Property Purchase-879 Morro Street
Page 3
CONCURRENCES
The Public Works Director concurs with the recommended action.
General Plan Consistency
The Planning Commission considered the City's acquisition of this building on May 27, 1998
and found it to be in conformance with the General Plan.
FISCAL IMPACT
The negotiated purchase price for the property is $468,034. There will also be some
miscellaneous expenses associated with closing escrow. The needed funds were recommended
and considered for appropriation, as a part of the water and sewer enterprise fund analysis and
included as a 1998-99 Capital Improvement Plan Request, at the June 2, 1998 meeting of the
City Council and are anticipated to be approved with the remainder of the City's 1998-99 Budget
on June 16, 1998. The requested appropriation includes funds for all aspects of the project,
including furnishings. It is anticipated that escrow will close in August of 1998. The refined
total cost estimate for acquisition and construction is $971,400.. Based on the fund analyses and
revenue projections presented at the June 2, 1998 Council meeting, sufficient working capital in
the Water and Sewer Fund is available to support the project. Staff recommends that the Water
and Sewer Funds pay 68% and 32% respectively of the project costs. This is based on the duties
of the staff to be located in the office space, many of whom are charged full time to water
activities.
ALTERNATIVES
Do not purchase the property. This alternative is not recommended as the options available for
meeting the growing space needs of the Public Works and Utilities Departments are very limited
and opportunities which also meet longer term goals of the City such as enhanced parking are
even more limited.
SUMMARY
Next Steps. An estimated schedule of activities to follow the recommended action is as shown
below:
Staff prepares RFP for Architectural and Design Services June 1998
Solicit Proposals July 1998
Award Design Contract August 1998
Complete Design and Plans and Specs December 1998
Advertise for Construction Jan.-Feb. 1999
Award Construction Contract March 1999
Complete Construction and Move-in Summer 1999
��•3
Council .genda.Report=Property PurchAse='879 Morro Street.
Page 4
Attachments
Refined Construction Cost Estimate- Fraser•and Seiple Architects.
Vicinity Map
Purchase Agreement(Copy avail'atile in the Council Reading File)
�n
S� �r`� p
May 18, 1998 LUIS OBISPO
PUBLIC WORKS/UTILITIES
John Moss
Public Works Department
City of San Luis Obispo
955 Morro Street
San Luis Obispo, CA 93401
RE: Estimate Refinement, Improvements to 879 Morro Street
Dear John:
Subsequent to the preliminary estimate I transmitted last week I've received our electrical
engineers analysis, reviewed heating,ventilating and air conditioning requirements with our
mechanical engineer and have refined several other components of our estimate.
Among our additional findings are the following:
1. The spaces inside the building are generally suitable for the Utility Division offices. Only
the perimeter walls and the hallway/stairway walls perpendicular to Morro Street are load-
bearing, so both floors can be reconfigured from reasonably well proportioned rectangles.
2. The second floor attic is about 24"tall and well configured for the routing of new ducts,
conduits, and related installations. This allows us to reduce our estimate for duct routing.
3. Much of the work of electrical remodeling is subtractive, but a lot of modernization still
needs to be done. The electrical estimate has been upgraded per Bill Thoma's input and
amounts have been added for data/communications and alarms.
4. It is unlikely that any of the existing roof mounted air conditioning equipment can be
efficiently re-used. Most of these units were installed to address specific equipment
requirements and would not suit general office areas. The estimate for mechanical
systems assumes a complete new installation.
5. The estimate for seismic upgrades has been reduced to compensate for the fact that the
original engineers estimate included its own overhead/bond/profit multipliers, which
we've applied to the overall estimate.
6. We've corrected a couple of mistakes in the preliminary estimate. The line item for fire
sprinklers was left out and we had a math error in the total.
9. i 0305 Street
Son Luis Cb;sDo
(0H0rn:s 93»01
is6 5;= ;,15s n�
5/18/98
John Moss
Page 2
These factors affect our 5/11/98 preliminary estimate as follows:
Seismic Upgrades:
Devaney Co. 11/21/94 estimate,with 42 mo. inflation
@ 4%per year. 73,814.00 X 1.14= 84,148.00
Interior Remodeling and Finishes:
Allowance: 3,923 g.s.f. X$25.00/s.f.= 13,652.00
Exterior Street Elevation Improvements:
Allowance: 880 s.f.X$15.00/s.f. = 13,200.00
Other Exterior Remodeling and Finishes:
Allowance: 1,760 s.f. X$6.00/s.f.= 10,560.00
Roofing:
Built-up membrane: 19 sq. X$149.38= 2,838.00
Plumbing:
13 new fixtures X$1,257.70= 16,350.00
Mechanical:
New equipment and ducting: 3,923 g.s.f.X$7.50= 29,423.00
Fire Sprinklers:
Complete system: 3,923 g.s.f.X$2.50= 9,808.00
Electrical:
Reconfigure power, new lighting(per engineer)= 41,935.00 .
Data/Communications:
Upgrade to Category 5 cabling (per engineer)= 12,000.00
Alarms:
Allowance(per engineer) = 5.000.00
SUBTOTAL 238,914.00
General Contractor Overhead, Profit, Bonds: 18%= 43,005.00
Contingency: 15%= 35.837.00
TOTAL: $317,756.00
C��•L
5/18/98
John Moss
Page 3
Attached here is the report Bill Thoma prepared describing electrical system upgrades.
I will be out of the area through Wednesday, June 3. I'll get back in touch with you or Sue
Baasch at that point to review what additional level of analysis is appropriate to complete this
effort.
.4
Sincerely,
Bruce Douglas Fraser, AIA
Principal
FRASER SEIPLE ARCHITECTS
attachment
UQ/1/./ba tut i-I:U0 1-.AA 61,10 043 "Zkf LKU31A hI&CIMIC INC LIM 001
ELECTRIC CO.
May 12.. 1998
Bruce Fraser Architect
971 Osos St
San Luis Obispo, CA 93401
Re: 879 Morro Street
Dear Bruce
As you have asked,we have visited the site and considered the conversion of this building for the
purposes of expanding into City office use. The following observations should be noted based on
our very brief sire observation conducted on 5/4/98.
1. The building is currently fed by (2) 200amp 120/240volt single phase services (several
separate meters however total capacity of 400amps). Thcre is no 3phase available in the
building.
2. Currently there are two emergency generators servicing telecommunication equipment.
One on the roof and one on a trailer located immediately behind the building. Both units
are likely to be removed when the current user vacates the property.
3. There is a tremendous amount of conduit subpancls, and branch circuit wiring that has
been added over many years of the existing user's telecommunication system growth.
Most of this infrastructure is likely to be removed because it is of little value to the Citv
for their purpose.
4. There are 5 or 6 HVAC units on the roof with(3)priniarily feeding the equipment rooms
on the first level. It appears that possibly two units are conditioning the upstairs offices..
5. There is likely to be some fairly radical re-arran.-enient of the main electrical incoming
sen,ice from its current condition, however most of this work is demolition and possibly
re-establishing a new meter for the south half of the building near the existing one at the
front north cast comer near the driveway on Morro St. and a new sub-panel for branch
circuiting to consolidate Circuits to one or two locations.
6. The upstairs has been converted to offices from being apaitnents. There will likely be a
need to add more outlets especially for anticipated computer applications (although
previous user was also using computers in these area
7. The two original "Trurnbell" panels (likely 1940's vintage panels) are still being used on
the second floor for power to receptacles and lighting. These should be re-fed with new
.... ��. JV ♦ul. i, .0l'.�. Du.! J1J JOLJ 1KU./li tLG1.1K11. ll\V. 40002
feeders and new panels or possibly one new larger panel. There will likely be a need for
isolated ground circuits and dedicated circuits.
S. The Fire Alarm System is likely to require upgrade to accommodate ADA requirements.
There are heat detectors and smoke detectors in most areas of the building since the
building is not fire spnnklcred. This system is likely to be required to remain or a new
fire sprinkler system installed, which would also trigger a newer style panel with ADA
provisions and monitoring of the fire sprinklers..
9. The lighting in the space except for the lower floor, north side, is in need of significant
improvement. Light levels are not at office levels and should be retrofitted with newer
lighting as well as addition lighting. The equipment rooms are lighted with task lighfing
that will be inappropriate when the equipment is removed (mostly bare lamp or strip
type).
10. Telecommunications and data system cabling is likely to be necessary, either surface
mounted in conduit or wiremold raceway. The building has more communication
service that could ever be necessary unless it is being removed when the current tenant
moves out. The only issue here :s getting the right cables to the right location in the
building.
11. The attic is quite accessible with approximately 24" clearance from roof to ceiling joist
except where flex duct for HVAC units are routed.
12. It appears that most electrical systems are run in "B3:", flexible conduit,or EMT.
The following is my very rough order of magnitude cost for various major items:
i. Demo (mainly equipment areas) $1,000.00
2. Install new 200annp meter/main $3,000.00(for south side)
3. Install new 200amp sub-panel $1,500.00(associated %v/112)
4. Upstairs office lighting (Qa$3.00 sq.ft.
5. Upstairs additional power @$1.50 sq.ft.
6. Downstairs Lighting ion sq.ft.(no attic)
7. Downstairs Power @ S5.00 sq.ft. (no attic)
8. HVAC units hooked up (x3$750.00 each(9 unknown)
9. Replacement of feeders and panels at 2"d floor $2,500.00 each(2 units)
10. New Category 5 computer cable&telephone $12,000.00
11. Fire Alarm panel with ADA devices $5,000.00(if required)
I hope these comments and assessments have been of some help. Please feel free to call if you
have questions or wish to pursue any one issue further. Thank you for considering our firm for
this project.
Sincerely,
William A. Thoma
Thoma Electric.Inc.
Morrost.doc
L;�4-9
Vicinity Map
r r
1 J t r
J r
1 r \ r
J /
` J
\ `
` r
\ r
♦� , ; r r
\ � r
r 1 r l
! �r
` J
r
1 J r
J � r
t t r r
J � r
r
1 r A
1 r r 1 J J \
37] \ r r \
r
J r l 87
9 M orm J r \t s
� r
l
r r
r , r
r ` J
J \
fi
° J
J
r J
\ l r J 1 r