HomeMy WebLinkAbout02/16/1999, C5 - ABANDONMENT OF STENNER CANYON HYDROELECTRIC PLANT Dft
council Feb
Feb. 16 1999
j ac en oa Repoin F-R� 71
CITY O F SAN LUIS O B I S P O
FROM: John Moss, Utilities Director t '
Prepared By: Gary Henders , Water Division Manager 4w*"
SUBJECT: Abandonment of Stenner Canyon Hydroelectric Plant
CAO RECONEAENDATION
Authorize staff to request an abandonment of the Federal Energy Regulatory Commission's
granted conduit exemption order for operation of the Stenner Canyon Hydroelectric Plant.
DISCUSSION
Background
The Stenner Canyon Hydroelectric Plant was constructed in the mid-1980's at the old water
treatment plant site adjacent to Reservoir #2. The facility utilized the raw water supplied from
Salinas Reservoir to generate power which is sold back to Pacific Gas and Electric Company
(PG&E). The plant was designed to generate 640 kilowatts per hour (kwh) but only achieved
approximately 520 kwh maximum output due to pipeline losses and other system constraints.
During the construction of the facility, the City entered into a power purchase contract with
PG&E for the energy produced from the facility. The original agreement required the City to
supply the full rated capacity of the hydroplant during the peak energy period of May through
October between the hours of noon and 6:00 p.m. In 1995, PG&E contacted the City and
informed staff that we were not providing adequate power as defined under the terms of our
agreement. Since the Salinas Reservoir can not always supply water, as was the case during the
drought, and due to operational constraints, the City entered into discussions with PG&E to
resolve the contractual problem. In 1995, the City executed a new power purchase agreement
with PG&E which doesn't require energy production at specific times. The downside of the new
power purchase agreement is that payment for the power produced went from approximately
$.08/kwh to about $.02/kwh.
Operational Changes
Since the original construction of the power generation facility, several changes have occurred
which have an impact on the operations of the hydroplant. The water treatment plant underwent
a major upgrade during 1994. The major water treatment process change was the use of ozone as
the primary disinfectant as opposed to chlorine. Ozone must be produced onsite and requires
electricity to produce ozone (03) gas. The process is very sensitive to power interruptions and
surges and is easily "knocked" off-line in these situations. A loss of the ozone generators
requires a plant shutdown and then a restarting of the plant processes by the operator(s). The
C5-1
Council Agenda Report—Abandonment of Stenner Canyon Hydroelectric Plant
Page 2
operation of the hydroelectric plant can cause power fluctuations in the area which would likely
result in additional plant shutdowns and have potential water quality or other impacts. In
addition, if the hydroelectric plant "trips" off-line, staff would have to travel up the canyon to
restart the facility which will have impacts on the water plant operations and maintenance.
During many night shifts, only one operator is overseeing the water plant operations which
would not allow for operation of the hydroelectric plant while still providing full-time oversight
of the treatment plant processes.
In 1995, construction of the State Water Project resulted in modifications to the Cuesta Tunnel
which delivers mw water from Salinas Reservoir to the City of San Luis Obispo. During
construction, the telemetry control equipment for the hydroelectric plant was removed and
subsequently damaged. The City was compensated for the equipment at the tunnel site as well as
equipment at the hydroplant building since the old equipment was no longer available (the
control system requires compatible equipment at each site). The control equipment was to be
reinstalled by City staff following the end of the construction work at the tunnel. The equipment
has not been installed due to the many factors and concerns raised in this report. In addition,
modifications at the tunnel raise questions as to whether the system can still be operated to run
the hydroelectric plant.
Since completion of the water treatment plant upgrade and the State Water Project, the
hydroelectric facility has not been operational and therefore has not been generating power.
Federal Energy Regulatory Commission
In June of 1998, the City was notified by the Federal Energy Regulatory Commission (FERC)
that maintenance and operation of the facility has not been performed for several years. FERC is
responsible for licensing and oversight of hydroelectric facilities and places requirements for
their continued operation. The correspondence states; "Periodic maintenance work must be
performed on the power plant to keep it in an operable condition. If the power plant is no longer
going to be operated, you may voluntarily surrender the conduit exemption order granted by the
Federal Energy Regulatory Commission."
Maintenance
Maintenance of the facility requires professional technical expertise in high voltage and electric
generation equipment. In the past, a local individual provided these services and the annual costs
were on the order of $5,000 per year. The individual is no longer available to provide the
maintenance services and a professional from out of the area would have to be identified to
provide these services which will significantly increase ongoing maintenance costs. In addition,
since the facilities have not been operated for over 5 years and with the increasing age of the
facilities, maintenance costs can be anticipated to be substantial in the future.
C5-2
Council Agenda Report—Abandonment of Stenner Canyon Hydroelectric Plant
Page 3
Safety Concerns
The Water Treatment Plant Operators have been concerned for many years with the operation of
the hydroelectric plant. While staff are highly trained in the technical skills necessary for the
proper operation and treatment of water at the plant, they do not have the same skills relative to
operation of the hydroelectric plant. In addition, the water supply line which serves the
hydroplant requires staff to enter a confined space for operation of valves to divert water to the
facility. The access to this valve vault now requires additional resources and precautions that
were not required in the past. The pipeline pressures at the valve vault are approximately 300 psi
which results in significant vibration and noise during operation of this valves. If a break in the
pipeline were to occur while staff were operating the valves, serious injury or death could occur
to our employees.
Projected Revenues vs. Expenditures
Based on the operational limitations and reduced power payments which are discussed above,
revenues from operation of the hydroelectric facility would be estimated to be approximately
$20,000 per year. Ongoing maintenance costs could be on the order of$10,000 annually and
initial costs for installing the telemetry equipment and providing startup maintenance and
training would likely be significantly more than $10,000 for the first year. Therefore, ongoing
net revenue from operation of the facility would not be expected to exceed$10,000 annually.
Summary
Based on the operational constraints, safety related issues, reduced revenue projections and
increased maintenance costs since the original construction of the hydroelectric facility, staff
would recommend that the FERC conduit exemption order for operation of the Stenner Canyon
Hydroelectric Plant be surrendered. In addition, staff will prepare a CIP request as part of the
upcoming 1999/01 budget process to properly abandon the facility, relocate the pipeline around
the hydroplant building and surplus the turbine generator and associated equipment.
FISCAL IIdPACT
As identified above, net revenue estimates for continued operation of the hydroelectric plant
would be approximately $10,000 annually. The budgets and water rate analyses for the past four
years have not assumed any revenue relative to the operation of this facility. Therefore, no water
rate impacts would be associated with the abandonment of the facility.
ALTERNATIVES
♦ Initiate Actions to Reinstate Operation of the Hydroelectric Plant. This would require
staff to search for qualified technicians to provide the maintenance necessary to place the
facility back in service. In addition, City staff would have to acquire and install the necessary
telemetry control systems for the operation of the plant. It is uncertain whether the facility
C5-3
Council Agenda Report—Abandonment of Stenner Canyon Hydroelectric Plant
Page 4
can be operated as it has in the past due to modifications at the tunnel which serves as the
control point for the hydroplant operation. Based on the operational, safety and other
constraints and the limited revenue potential, staff does not recommend pursuing this
alternative.
♦ Defer any actions relative to the hydroplant. This is essentially what has been done for the
past several years. The FERC will require that the City provide maintenance of the facility or
abandon the license granted by FERC for the continued operation. Staff does not recommend
this alternative.
C5-4