FROM: Michael D.McCluskey, Public Works Directorm- v
PREPARED BY: Lawrence S. Tolson
SUBJECT: ADDITIONAL APPROPRIATION FOR RENOVATIONS AT JACK
HOUSE
CAO RECOMMENDATION:
Appropriate an additional $20,000 from the unappropriated balance of the General Fund to the
Jack House Renovation project account
DISCUSSION
Originally budgeted in the Jack House Renovations project account was $61,100 for three
proj ects:
1) Repainting exterior surfaces of the main house at an estimated cost of$20,000
2) Building a foundation for the carriage house at an estimated cost of$21,100
3) Replacing floor coverings in the main house at an estimated cost of$20,000
The City Administrative Officer recently awarded the exterior repainting contract at a cost of
$32,900 plus $7,100 for contingencies. The contingencies level is somewhat high because of the
uncertainty involved with associated renovation work. The overall repainting cost is
substantially higher (twice the original estimate) because a) the original estimate was calculated
in 1995 b) two additional buildings have been included and c) there are high levels of lead which
require expensive removal and disposal techniques.
In order to proceed with the repainting project in a timely manner and complete the project prior
to the rainy season, the contract was awarded using funds set aside for the other projects. The
Jack House Committee concurred with this decision. The Jack House Committee felt that the
painting project was more important and that replacing the floor covering could wait until the
next two-year budget cycle, if necessary.
The City Administrative Officer felt, however, that the City should continue to pursue the floor
covering project in a timely manner. Therefore, staff recommends we appropriate $20,000 to
restore funding for the carpeting project.
CONCURRENCES
The Jack House Advisory Committee concurs with the recommendation, but is willing to
postpone the flooring replacement until 2001-02 if necessary should the Council decide not to
make this appropriation at this time.
C6-1
1.
Council Agenda Report—Jack House Appropriations
Page_2
FISCAL IMPACT
Exterior Repainting(Contract.Cost plus Contingencies) $40,000
Carriage House Foundation Construction(Estimated Cost) 20,100
Floor Covering Replacement(Estimated Cost) 20,000
Subtotal $80,100
Less Current Budget 60,100
Additional Appropriation Needed $20,000
Based on interim results for 1998-99, adequate reserves are available to fund the additional
appropriation-and retain the General Fund balance at policy level.