HomeMy WebLinkAbout08/20/2002, C9 - CONSULTANT CONTRACT AMENDMENTS FOR THE MARSH STREET PARKING GARAGE EXPANSION PROJECT council W6'Dmc a� j acEnba izepout I..N..6� e9 CITY OF SAN LUIS OBISPO FROM: Michael D. McCluskey, Public Works Director Prepared By: Keith Opalewski,Parking Manager SUBJECT: CONSULTANT CONTRACT AMENDMENTS FOR THE MARSH STREET PARKING GARAGE EXPANSION PROJECT CAO RECOMMENDATION Approve contract amendments for additional materials testing to EarthSystems Pacific ($13,500) and additional archeological services to Applied EarthWorks ($37,500) and authorize the Mayor to award the contract amendments. DISCUSSION The Marsh Street parking structure expansion project continues to work its way towards completion of construction. Currently it is anticipated that the structure will be open by the last week of September 2002. As part of bringing this project to completion, some budgeting and financial items need to be addressed. Materials Testing The required materials testing component for the Marsh Street Garage expansion project is in its final phase. Due to the more significant nature of the material testing services (concrete, steel, etc.) the current budget for materials testing has been depleted and is now over budget. The cost overrun of$13,500 is based on two areas that have significantly exceeded the projected budget amounts for materials testing. The two areas were compression testing of concrete cylinders and sampling of the concrete per code requirements. This additional cost was derived from the specified criteria of sampling and testing a set of cylinders from every caisson, as opposed to a less frequent test series. The original budget anticipated a reduced number of tests during the actual construction, but the structural engineer for the project did not approve this request and adhered to the more extensive testing schedule. As a result of this more stringent standard, the materials testing budget will need to be amended by $13,500 to complete the finish testing and final reports for this phase of the project. Archeological Services Archeological monitoring and fieldwork has been completed at the construction site for the garage expansion. The complete collection of archeological remains is contained in approximately 50 archive boxes, which still need processing and analysis in order to complete the final mitigation report for the project. To date, the current archeological budget has nearly been depleted with much of the laboratory analysis still pending. As with any large-scale eq-1 Council Agenda Report—Consultant.Amendments-Marsh Street Garage Expansion page 2 construction project in the downtown area, the exact magnitude of archeological findings and the corresponding costs to process them is only an estimate until the project is completed. This is the case for the garage expansion, which now has a more precise understanding of what it will cost to finalize the required documentation of the artifacts. As part of the actual field work the archaeologist encountered a series of unknown sites including a significant underground privy that contained many pieces of relics that will need to be examined. As a result of the additional artifacts the archaeological budget will need to be amended by $37,500 to complete the processing and final reports of the project. FISCAL IMPACT The contract amendment of $13,500 for materials testing (EarthSystems) will cover what has already been completed along with final testing and required reports. A minor contingency is also included in this budget to cover any minor unforeseen costs associated with this work. The amendment of$37,500 for archeological services (AppliedEarthworks) will complete the sorting, analyzing and cataloging along with a final report that will discuss required mitigation for the relics. The $51,000 needed for both amendments can be funded out of the $654,000 contingency fund for the project. To date, at 85% completion of the garage expansion, 50% of the contingency remains unencumbered. The remaining $327,000 contingency fund can readily cover the proposed amendments without jeopardizing the completion of the project. The final budgets for the two consultants will be the following: Current Budget Proposed Final Budget EarthSystems $44,271 $13,500 $57,771 Applied EarthWorks $80,298 $37,500 $117,798 ATTACHMENTS Attachment 1---Archaeological Services Amendment Attachment 2— Materials Testing Amendment I.Council Agendareport/2002 Reports/CouncilReportcontractamendsMSS cy z Attachment 1 AMENDMENT NO. 2 AGREEMENT WITH APPLIED EARTHWORKS The AGREEMENT dated May 26, 2000 between the CITY OF SAN LUIS OBISPO, a municipal corporation, hereinafter referred to as "City" and "Applied Earthworks", hereinafter referred to as"Contractor",is hereby amended to as follows: A. DESCRIPTION OF WORK 2. Workscope Provide Cultural Resource Monitoring for the Marsh. Street Garage Expansion project, Specification No. 99684. The amended work, as outlined in Exhibit A, will be performed for additional compensation not to exceed $37,500. All other terns and conditions of the AGREEMENT remain the same. Both CITY and CONTRACTOR do covenant that each individual executing this addendum on behalf of each party is a person duly authorized and empowered to execute Agreements for such part. IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed on this day of , 2002. CITY OF SAN LUIS OBISPO A Municipal Corporation Mayor Allen K. Settle APPROVED AS TO FORM: CONTRACTOR /ItylktfornPrint Name: Cy-3 ILiCAIW_ ctO - Exhibit A 5090 North Fruit Avenue Applied VIA FAX AND FIRST CLASS MAIL suite 101 M1 Fresno,CA 93711-3064 Eorthorks (559)229-1656 FAX(559)229-2019 2 July 2002 City of San Luis Obispo Public Works Department ATTN: Mr. Keith Opalewski 1260 Chorro Street, Suite B San Luis Obispo, CA 93401 RE: Revised Budget Modification Request No. 2 Cultural Resource Monitoring for the Marsh Street Garage Expansion Dear Mr. Opalewski: Since July 2000, Applied EarthWorks, Inc. (AE)has provided technical support to the City of San Luis Obispo during development of the Marsh Street Garage Expansion Project. The work has included background research, consultation and coordination with City staff and construction personnel,preparation of a cultural resources mitigation plan as required by the Project Environmental Impact Report (EIR), on-site construction monitoring, and emergency investigation of archaeological features discovered during construction. Archaeological monitoring began in August 2001 and has continued through February 2002. The initial approved budget for the project included two weeks of cultural resource monitoring, which was completed in mid-August 2001. During the remainder of August lE performed an additional two weeks of monitoring as well as emergency excavations to evaluate the significance of 8 archaeological features and mitigate project impacts to less-than-significant levels. Such work wasrequired by the EIR and cultural resources mitigation plan. In September 2001 the City approved a budget modification to cover the costs of additional work performed during August 2001. Since that time AE has performed additional monitoring and emergency archaeological fieldwork, during which time six additional archaeological features were excavated . The attached budget modification request covers the cost of the laboratory processing, analysis, and reporting required by the EIR and mitigation plan. As we discussed in our most recent meeting in your office, this work involves the following tasks,which are detailed in the cultural resources mitigation plan: (1) Cleaning artifacts and sorting them into gross categories(glass, metal, ceramic, other) (2) Sorting artifacts into functional catagories, and then into object types. (3) Packaging artifacts by type and assigning a unique catalog number. A label, containing provenience information,material type, object type, count, and weight will be placed with each package. (4) Analyzing and cataloging artifacts on paper using AE's standard cataloging sheets. (5) Entering analytic and provenience data into Hs computerized historic artifact database. As (6) Labeling artifacts with ink according to the standards of the facility where collections will be sent for final long-term curation. Most policies require that the site trinomial and the catalog number is inked onto each artifact. Often when large bags of artifact fragments (such as a bag with 100 pieces of glass) occur, only 15 or so pieces will be labeled. (7) Photographing or otherwise illustrating artifacts for the final report (8) Boxing and other preparation of collections for shipment to the curation facility. The complete collection of archaeological remains from the Marsh Street Garage project is contained in approximately 50 archive boxes. The processing and analysis described above requires approximately 29 hours per box, broken down as follows: cleaning and rough sorting— 4.5 hours; fine sorting, counting,weighing, and tagging, and packaging—4 hours; analysis and cataloging— 10 hours; computerized data entry—4 hours; labeling,photographing, and preparation for curation—6.5 hours. For 50 boxes of artifacts, that would require 1450 labor hours. As shown in the attached labor allocation table,we have allocated only 1160 hours for those tasks, a reduction of 20 per cent which reflects work completed to date, boxes which are not completely full, and other cost-saving measures such as discussed below. This time may be shortened further if complete analysis of each feature is not required. This happens when a feature is judged to lack historical significance. Features will be evaluated for significance according to standards set forth in the cultural resources mitigation plan. Features that do not meet these values will be quantified at the rough sort stage, entered into the database, labeled, and prepared for curation. Standard practices do not allow for these items to be discarded, as they may hold potential for future research. At this point, the entire collection has been washed and rough sorted. Although a complete inventory has not been undertaken, we are aware that not all boxes contain large amounts of artifacts. It is not feasible at this time to quantify the number of items in each box to give a time breakdown by box. Any such savings will be reflected as cost reductions at the conclusion of the project. As you know,)E has worked hard to build several cost-saving factors into this final budget. These include: • Reducing labor costs. Distributing as many hours as possible to employees compensated at lower rate categories by using interns and lower-ranked laboratory technicians for as many tasks as possible. • Prioritizing collections. Collections will be prioritized by level of significance, and non-significant features will receive minimal analysis. (At present, prioritization has not occurred, and cannot be figured into the budget, but a cost savings will be realized at the end of the project.) • An aggressive discard policy. Some materials from significant features may be discarded after they have been analyzed, cataloged, counted, and weighed. If items are discarded,this will be noted in the catalog record. Identification of may-S these materials is based on lack of long-term research values, excessive quantity, poor condition, and/or health and safety risks. The discarded types may include window glass; glass lamp chimneys; undiagnostic bottle and bottle glass fragments; nails (after being identified by type and given MNI totals); all leather and textiles (leather requires treatment with potentially hazardous and flammable material in order to be preserved, so only leather artifacts with clear interpretive value would be treated in this way); metal scraps, sheets, strips, and wire; corroded,non-temporally diagnostic ferrous items; slag and amorphous metal and glass; large items for which curation may be a problem (e.g., porcelain toilets). As we discussed,the attached budget does not include costs for final curation of the archaeological collections with an approved repository. Such costs cannot be determined until after an appropriate curation facility is identified and a final box count is made. This will be done after analysis and reporting is completed. Thank you for your assistance in processing this budget modification request. As I will be on vacation for the next two weeks,please contact Wendy Nettles in my office if you require additional information or have any questions on the information supplied herewith. Sincerely, n O Barry A. Price, M.A. Vice President/Principal Archaeologist cc: W. Nettles b it A r Cl) qlr C14 Cl) 0 cli C14 0 W W F W 'yO Y m O < N co 1 r U Q .0 d, Cl)C N . F W Q J �C Cl) C O Y W m U co > E �x LU LU N C m U) Q C H c N O Q co C W C CM � Q W 0 m ~ � O v U �e G IL Lo C o IM W N LO LLI Cl) M O M C N r N N C O R LL O Qa C Cb fit Q f0 N U Q M W W M M Q X O 0 O > N 4 m 2 Q f... F- 99 Z W 0 W Di Z. U S co ~ v — U U O 'C Q' 0 _ — LU W M W 01 0 9. C m 0 F d � Z y p cW O v v LL W a �LOY 0 0 4 a. W o c 'c .00 .� .a cW m .—o� Fi w a W .2 cc 13 z m W c CWa pE`0 'o r IOU o C No`N W Q 0 M Gm'ow O O N a' O C L Q aE U m m mr 2 � WN oE J Q N W d l0 d LL J D Q F of f/J �I AI M' O IOI MI NN N S a g o 0 o a e o 0 L-f REVISED BUDf MODIFICATION#2 G:Warshstrset12002teost mod 2a.gp2 Marsh St. Garay- expansion Project Cultural Resource Monitoring APPLIED EARTHWORKS, INC. 2 July 2002 Labor Category Hrs Rate Code Rate Cost Project Manager BAP 36 003 87.50 $3,150 Senior Historical Archaeologist MCH 013 59.00 Laboratory Director CD 64 026 40.60 $2,598, Staff Archaeolo ist. PE/KW 027 39.40 Staff Archaeolo ist-0T PE/KW 027 59.10 Publications Manager SR 061 39.80 Historical Archaeologist WN 028 38.80 Faunal Analyst SG 028 38.80 Archaeological Monitor AVS 035 31.80 Archaeological Monitor-OT 47.70 Laboratory Technician 1 400 034 33.40 $13,360 Laboratory Technician II 324 035 31.80 $10,303 Field Technician III 039 27.00 Laboratory Trainee 412 082 17.96 $7,400 Draftsperson LM 030 33.60 Word Processing/Data Entry(CB/RB) 055 33.80 Administrative Support M _ 073 28.50 Total Hours/$ 1236 $36,811 E ui ment/Su lies Field/Lab Equipment and Supplies Vehicle Rental weeks 450 Fuel for Rental Vehicle. Travel/Transportation Units Mileage(personal vehicles $0.34 Per Diem (person da $100.00 Lodging (person days) $60.00 Subsistence(person days) $40.00 Outside Services Archive Fees Geos atial Analyst. Other Direct Costs Postage/Duplication Office Communication/Supplies Laboratory Facilities $600 TOTAL LABOR and BENEFITS $36.811 TOTAL EQUIPMENT/SUPPLIES TOTAL TRAVELRRANSPORTATION TOTAL OUTSIDE SERVICES TOTAL ODCs $600 FEE R 10% non-labor $60 TOTAL $37,471 Attachment 2 AMENDMENT NO. 2 AGREEMENT WITH EARTH SYSTEMS PACIFIC The AGREEMENT dated October 10th, 2000 between the CITY OF SAN LUIS OBISPO, a municipal corporation,hereinafter referred to as "City" and "Earth Systems Pacific", hereinafter referred to as "Contractor", is hereby amended to as follows: A. DESCRIPTION OF WORK 2. Workscope Provide additional materials testing and inspection for compaction and concrete testing and grouting as outlined in Exhibit A: Additional work scope will be performed for an amount not to exceed $13,500 for a total contract amount not to exceed $57,771. All other terms and conditions of the AGREEMENT remain the same. Both CITY and CONTRACTOR do covenant that each individual executing this addendum on behalf of each party is a person duly authorized and empowered to execute Agreements for such part. IN WITNESS WHEREOF, the parties hereto have caused this instrument to be executed on this day of .12002. CITY OF SAN LUIS OBISPO A Municipal Corporation Mayor Allen K. Settle APPROVED AS TO FORM: CONTRACTOR ItYA1171 y Print Name: G:/Contracts&RFPs/Marsh Street Expansion/Contract Amendments/Amendment 2—Earth Systems Pacific �j /q 1C�1" Qr2f c�— Exhibit A Harris &Associates TRANSMITTAL Date: June 27, 2002 To: Keith Opalewski City of Sam Luis Obispo From: Mary Jo Bachini— Harris &Associates RE: CITY OF SAN LUIS OBISPO MARSH STREET GARAGE EXPANSION PROJECT Earth Systems Budget An amendment is needed for the Earth Systems Contract for-the Marsh Street Garage Expansion Budget. The additional amount is as follows: April Billing $7609 Balance <7,004.50> May Billing $1383 Balance <8,387.50> Billing through June 23d $2192 Balance <10,579.50> Projected Additional Costs $1500 Balance <12,079.50> (compaction and concrete testing at drive path, grouting) Office Time for Reports $1000 Balance <13,079.50> Contingency on Projected $200 Balance <13,279.50> The overrun is due to the amount of concrete sampling and cylinder breaks, especially with the piers. In September 2001, when amending Earth Systems Pack's budget, the amended amount was based on having the designer team reduce the amount of concrete testing on the piers, see attached memos to PMSM and from PMSM. PMSMMalker did not relax the requirement "due to the importance of the foundation system". If you have any questions or need any additional information, please feel free to contact me at (805) 593-0675. Attachments Harris and Associates P.O. Box 15458, San Luis Obispo, CA 93406 (805) 593-0675 Fax (805) 593-0695 t�/C�